Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 2 - ROAD STRUCTURES, 2020) - page 8

 

  Index      Manuals     Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 2 - ROAD STRUCTURES, 2020)

 

Search            copyright infringement  

 

   

 

   

 

Content      ..     6      7      8      9     ..

 

 

 

Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 2 - ROAD STRUCTURES, 2020) - page 8

 

 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-4 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

AASHTO 
Designation 

ASTM 
Designation 

Title 

 

ASTM F714 - 
12e1 

Standard Specification for Polyethylene (PE) Plastic 
Pipe (DR-PR) Based on Outside Diameter 

 

ASTM G14-88 
(1996)e1 

 Standard Test Method for Impact Resistance of 
Pipeline Coatings (Falling Weight Test) 

 

ASTM B117 - 11 

Standard Practice for Operating Salt Spray (Fog) 
Apparatus 

 

ASTM A90/ 
A90M - 11 

Standard Test Method for Weight [Mass] of Coating on 
Iron and Steel Articles with Zinc or Zinc-Alloy Coatings 

 

ASTM D2657 - 
07  

Standard Practice for Heat Fusion Joining of Polyolefin 
Pipe and Fittings 

AASHTO M 85-12 

ASTM C150/ 
C150M - 12 

Standard Specification for Portland Cement 

AASHTO T 
106M/T 106-12 

ASTM C109 / 
C109M - 11b 

Standard Test Method for Compressive Strength of 
Hydraulic Cement Mortars (Using 2-in. or [50-mm] 
Cube Specimens) 

 

ASTM D1505 - 
10 

Standard Test Method for Density of Plastics by the 
Density-Gradient Technique 

 

ASTM D1238 - 
10 

Standard Test Method for Melt Flow Rates of 
Thermoplastics by Extrusion Plastometer 

 

ASTM D790 - 10 

Standard Test Methods for Flexural Properties of 
Unreinforced and Reinforced Plastics and Electrical 
Insulating Materials 

 

ASTM D638 - 10 

Standard Test Method for Tensile Properties of Plastics 

 

ASTM D1639 - 
90(1996)e1 

Standard Test Method for Acid Value of Organic 
Coating Materials 

 

ASTM D2837 - 
11 

Standard Test Method for Obtaining Hydrostatic Design 
Basis for Thermoplastic Pipe Materials or Pressure 
Design Basis for Thermoplastic Pipe Products 

 

 

 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-5 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

Table 22-2: Designations and titles for BS and BS EN standards that apply to prestressing 

steel works 

BS 
Designation 

BS EN Designation  Title 

BS 4486: 
1980 

 

Specification for hot rolled and hot rolled and processed 
high tensile alloy steel bars for the prestressing of 
concrete 

BS EN 197-
1:2011 

 

Cement. Composition, specifications and conformity 
criteria for common cements 

 

BS EN 1008:2002 

Mixing water for concrete. Specification for sampling, 
testing and assessing the suitability of water, including 
water recovered from processes in the concrete industry, 
as mixing water for concrete 

 

BS EN 12390-
1:2000 

Testing hardened concrete. Shape, dimensions and 
other requirements for specimens and moulds 

 

BS EN 12390-
2:2009 

Testing hardened concrete. Making and curing 
specimens for strength tests 

BS 
5896:2012 

 

High tensile steel wire and strand for the prestressing of 
concrete. Specification  

 

BS EN ISO 
9001:2015 

Quality management systems. Requirements  

BS 5075-
1:1982 

 

Concrete admixtures. Specification for accelerating 
admixtures, retarding admixtures and water reducing 
admixtures  

BS 5075-
3:1985 

 

Concrete admixtures. Specification for superplasticizing 
admixtures  

 

EN 10138 

Prestressing Steel 

 

BS EN ISO 527-
1:2012 

Plastics. Determination of tensile properties. General 
principles  

 

BS EN ISO 4892-
2:2006+A1:2009 

Plastics. Methods of exposure to laboratory light sources. 
Xenon-arc lamps  

22.4 

Prestressing Quality Assurance 

Prestessing work shall comply with the requirements for quality assurance outlined in this section. 

22.4.1 

Qualifications of Prestressing Subcontractor 

The  subcontractor  who  performs  prestressing  work  on  the  Project  shall  meet  the  qualifications 
outlined in this section. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-6 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

22.4.1.1 

Precast Prestressed Girder 

Before a precast, prestressed girder subcontract is awarded, the  Contractor shall submit the pre-
qualification document of the proposed organisation or subcontractor to the Engineer for approval 
for the performance of the prestressing works. 

Each proposed organisation to perform the prestressed concrete works under these specifications 
shall  be  certified  by  the  Precast/Prestressed  Concrete  Institute  (PCI),  Plant  Certification  program 
prior to start of production of works. 

The  subcontractor  approval  by  the  Engineer  for  the  performance  of  the  prestressing  work  as 
specified in these specifications shall not relieve the Contractor of overall responsibility for such work. 

If the subcontractor cannot perform the prestressing work in a manner acceptable to the Engineer, 
the Contractor shall replace such subcontractor in accordance with the Contract documents. This 
alternate subcontractor and the Contractor shall comply with paragraphs 1, 2, and 3 of this section. 

22.4.1.2 

Post-tensioned Concrete 

If  the  Contractor  proposes  to  perform  the  post-tensioned  concrete  work  with  its  own  forces,  the 
Contractor shall submit all details of  its qualifications, as specified herein, and as required by the 
Engineer, for approval by the Engineer of the Contractor to perform the work. 

If  the  Contractor  cannot  provide  acceptable  and  adequate  information  on  its  qualifications  and  is 
rejected  by  the  Engineer  for  the  post-tensioned  concrete  work,  the  Owner  shall  require  the 
Contractor to subcontract such work. 

The  Owner  shall  require  the  Contractor  to  submit  the  following  information  regarding  its 
qualifications, or those of the proposed subcontractor, to the Engineer for review and approval:  

a.  For the performance of post-tensioned concrete work, the Contractor shall submit the pre-

qualification document of the proposed organisation or subcontractor, along with a complete 
and detailed description of its qualifications and experience.  

b.  Acceptable  evidence  shall  be  submitted  by  the  proposed  organisation  or  subcontractor 

proving to the Engineer that the organisation or subcontractor is experienced in the field of 
prestressing systems. Further, the Contractor or proposed subcontractor shall submit data 
acceptable to the Engineer that it has, within the last five years, performed construction work 
comparable to the post-tensioned concrete work as specified in these standard specifications 
and indicated in the Contract plans. This experience shall be confirmed by the Contractor by 
citing a minimum of two comparable projects that have been successfully accomplished.  

c.   Approval  of  the  Contract

or’s  organisation  or  the  subcontractor  by  the  Engineer  for  the 

performance of the post-tensioned concrete work shall not relieve the Contractor of overall 
responsibility for such work. 

d.  If,  after  the  approval  by  the  Engineer,  the  Contractor 

—  or  an  approved  subcontractor  — 

demonstrates  an  inability  to  perform  the  work  as  specified  in  this  section,  the  Engineer 
reserves the right to rescind such approval and require the Contractor to submit the name of 
another  subcontractor  to  perform  the  work.  All  resubmittals  shall  comply  with  the 
requirements specified herein and in the Contract documents. 

22.4.1.3 

Supervision of Prestressing Operations 

Prestressing  and  grouting  operations  shall  be  under  the  charge  of  a  supervisor  with  appropriate 
knowledge, training and experience in carrying out similar operations. That person shall be present 
during all procedures and shall be responsible for all safety precautions relating to the operations. 
The  Contractor  shall  employ  this  supervisor  and  ensure  that  he  is  aware  of  the  required  tendon 
loads,  order of stressing, extensions, allowance for  losses and all other particulars relating to the 
operations. 

The appointment of the responsible person shall be subject to the approval of the Engineer. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-7 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

The supervisor and all operatives shall be certified under a recognized certification scheme as having 
the necessary qualifications such as CARES Product Installation Certification. 

In addition, for each jacking operation, one technical representative of the approved post-tensioning 
system  as  per  Article  22.7.1.1  shall  be  present  through  the  whole  prestressing  installation  and 
operation process. The technical representative shall provide guidance during the installation of the 
ducts, anchorages, anchorage reinforcement, and actual post-tensioning operation. The technical 
representative  shall  sign  all  post-tensioning  loading,  stressing,  and  elongation  records  with  the 
Contractor’s supervisor and the Engineer. 

22.5 

Supplementary Drawings 

Supplementary  drawings  including  working  drawings,  shop  drawings  and  composite  placement 
drawings shall meet the requirements outlined in this section. 

22.5.1 

Working Drawings 

Where the Contract documents do not include complete details of the prestressing system and its 
method  of  installation,  or  when  complete  details  are  provided  in  the  Contract  plans  and  the 
Contractor wishes to propose changes, the Contractor shall prepare and submit working drawings 
of  the  prestressing  system  proposed  for  use  to  the  Engineer.  Fabrication  or  installation  of 
prestressing material shall not begin until the Engineer has approved the working drawings. 

Working  drawings  of  the  prestressing  system  shall  show  complete  details  and  substantiating 
calculations  of  the  method  and  materials  proposed  by  the  Contractor,  including  any  additions  or 
rearrangement of reinforcing steel and any revision in concrete dimensions from that shown in the 
plans. Such details shall outline the method and sequence of stressing and shall include complete 
specifications and details of the prestressing steel and anchoring devices; working and anchoring 
stresses; stress-strain curves of the prestressing steel; anticipated gauge pressures; cable profiles; 
elongation of prestressing cables; and type of ducts and all other data pertaining to the prestressing 
operation, including the proposed arrangement of the prestressing steel in the members. 

The working drawing shall include as well erection and handling procedures and sequence for all 
precast members. 

Designs  shall  be  prepared  by  a  Specialty  Engineer  who  has  been  approved  in  advance  by  the 
Engineer. 

Working drawings shall be submitted four weeks in advance of the start of the affected work to allow 
time for review by the Engineer and correction by the Contractor of the drawings without delaying 
the work. 

Where required by the Contract plans, or in the Contract documents, the Contractor shall prepare 
composite placement drawings for all items embedded in the concrete. If this provision includes a 
requirement for additional engineering or design detailing, these requirements shall be clearly stated, 
as noted in Section 22.2.  

22.5.2 

Shop Drawings 

The  Contractor  shall  submit  shop  drawings  to  the  Engineer  for  approval  in  accordance  with  the 
requirements of the Contract documents and as specified herein. 

The  shop  drawings  shall  indicate  the  complete  fabrication,  profile,  and  placement  details  for  all 
tendons and strands, including types, locations, anchorages, couplings and methods of support, as 
well  as,  computations  for  the  prestressing  of  each  post-tensioned  tendon  or  all  pre-tensioning 
strands. The shop drawings shall also show, in addition to the tendons and strands, the placement, 
sizes, and details of the reinforcement steel in the prestressed concrete work. Shop drawings shall 
be prepared showing formwork and method and types of bracing. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-8 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

All shop drawings shall be submitted for review and approval in accordance with the requirements 
specified herein. Prints of the final approved shop drawings shall be furnished by the Contractor for 
the Engineer's use. 

The  shop  drawings  and computations shall  be checked  by the  Contractor  before  submittal  to the 
Engineer. All shop drawings, computations and related data shall be accompanied by design data 
confirming that the forces indicated on the  Contract plans are obtainable and that all prestressing 
hardware  is  adequate  to  transmit  these  forces.  All  shop  drawings  and  computations  shall  be 
approved by the Engineer before commencing any fabrication or delivery of material. No deviations 
from the approved shop drawings shall be made by the Contractor without written approval of the 
Engineer. Any fabrication by the Contractor without such written approval shall be at the Contractor's 
risk. Any girders not fabricated in accordance with approved shop drawings will be rejected by the 
Engineer. 

The  Engineer's  approval  of  any  proposed  methods,  materials,  or  equipment  shall  not  relieve  the 
Contractor of full responsibility for the successful completion of all work specified in these Standard 
Specifications and all related Contract documents. 

Shop  drawings  for  post-tensioning  and  other  embedments  and  attachments,  such  as  expansion 
joints, bearings, and anchor bolts submitted by suppliers, shall be reviewed for conformance with 
the design concept and compliance with the Contract plans and specifications; and then approved 
by  the  Engineer.  Where  the  Contract  document  information  on  the  post-tensioning  system  is 
modified  by  the  Contractor,  or  where  the  Contract  plans  do  not  provide  detailed  dimensional 
information  on  the  post-tensioning  system,  it  is  the  Contractor's  responsibility  to  coordinate  the 
placement of the post-tensioning system with other embedments, and to correct any interferences 
created  by  the  Contractor-supplied  post-tensioning  system  or  other  substitutions.  Post-tensioning 
layouts shall govern the layout of the secondary nonprestressed reinforcement. Where necessary, 
location  of  nonprestressed  reinforcement  should  be  adjusted  to  clear  tendons,  subject  to  the 
Engineer

’s approval. 

22.5.3 

Composite Placement Drawings 

Where  required  by  the  Contract  documents,  in  addition  to  all  required  working  drawings,  the 
Contractor shall prepare composite placement drawings to scale and in sufficient detail to show the 
relative  positions  and  depths  of  all  items  embedded  in  the  prestressed  concrete  portions  of  the 
structure.  Such  embedded  items  shall  include  the  prestressing  ducts,  vents,  anchorage 
reinforcement and hardware, reinforcing steel, anchor bolts, earthquake restrainers, deck joint seal 
assemblies, drainage systems, and utility conduits. These drawings shall ensure that the planned 
positions of embedded items do not conflict with one another and that concrete cover is adequate. 
Working  drawings  shall  be  developed  and  prepared  by  the  Contractor  for  embedded  items  or 
proposed  changes  in  the  dimensions  of  the  post-tensioning  systems  work 

—  as  required  by  the 

Contract. This will eliminate conflicts and provide proper cover wherever conflicts arise with or due 
to the post-tensioning system. Resolution of the conflicts should follow the provision of Section 22.2. 
Before  work  can  begin  on  any  affected  item,  the  Engineer  shall  approve  any  revision.  All  costs 
involved  with  the  preparation  of  drawings  and  with  making  necessary  modifications  to  the  work 
resulting there from shall be borne by the Contractor. This will require composite placement drawings 
to be detailed to a scale and sufficient quality to show double-line reinforcement and post-tensioning 
tendon details in either 2D or in complete 3D drawings. 

22.6 

Submittals 

The Contractor shall submit the supplementary drawings to the Engineer for approval in accordance 
with  the  requirements  of  Section  22.5.  In  addition,  submittals  shall  comply  with  the  requirements 
outlined in this section. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-9 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

22.6.1 

Qualification Details 

Experience records  and qualification  details  of the Contractor’s key  structural  design, fabrication, 
installation,  and  quality  control  (QC)  personnel  who  will  work  on  the  prestressing  and  concrete 
operations shall be submitted by the Contractor. Once approved, the Contractor shall not change or 
substitute any of the personnel without the Engineer’s prior approval. 

22.6.2 

Working Drawings 

Working drawings of the proposed prestressing system shall be submitted by the Contractor to the 
Engineer for review and approval. For the initial review, six sets of such drawings shall be submitted. 
One approved set or one set with corrections and modifications shall be returned by the Engineer. 
After modification,  six  sets  of the  drawings  and  their  associated  calculations,  if  any,  showing  any 
required  corrections  shall  be  submitted  for  final  approval.  Working  drawings  shall  be  submitted 
sufficiently in advance of the start of the affected work to allow time for review and correction without 
delaying the approved programmed commencement of the work. Such time shall be proportional to 
the complexity of the work but, in no case, shall be less than two months. 

Approval  of  working  drawings  and  other  submittals  does  not  absolve  the  Contractor  of  the 
responsibility for any contractual obligations. No additional payment will be made to the Contractor 
for changes required as a result of reviews or approvals. Proper material submittals shall be made 
as per Section 1.15, Submittal Procedures, outlined in Chapter 1, General Requirements, of these 
standard specifications, for all materials involved. 

22.6.3 

Certificates 

Certificates from the manufacturer, in quantities as directed by the Engineer, shall be furnished to 
the Engineer certifying that the materials and equipment to be provided comply with the requirements 
of these Standard Specifications, referenced codes and standards and approved shop drawings. 

22.6.4 

Test Reports 

The Contractor shall furnish to the Engineer six (6) copies of test reports and certificates as specified 
herein, unless otherwise directed by the Engineer. 

22.7 

Materials for Prestressing Operations 

Materials  for  prestressing  operations  shall  comply  with  the  requirements  outlined  in  this  section. 
Samples shall be submitted in the quantities as directed by the Engineer. Sampling and testing shall 
be in general compliance with provisions of PCI MNL-117-77. After the Engineer has approved the 
shop drawings, a full sized sample shall be prepared for the precast members for final approval of 
the Engineer. 

22.7.1 

Prestressing System Materials 

Materials for a prestressing system shall comply with the requirements outlined in this section.  

22.7.1.1 

Post-tensioning Systems 

The post-tensioning system shall comply with latest international standards and the requirements of 
these  standard  specifications,  and  shall  be  produced  under  a  permanent  system  of  factory 
production control which shall ensure the same level of confidence in the conformity of the finished 
product, whatever the manufacturing process.  

The post-tensioning system shall subject to an official certification such as BS EN ISO 9001:2015 
and CARES certificate relating to factory production control and product conformity. 

Except  as  otherwise  specified  herein  or  specifically  approved  by  the  Owner,  the  post-tensioning 
system  including  strands,  ducts,  anchorages,  couplers,  installation  machines,  wedges,  stressing 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-10 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

jacks  and  pump  machine,  gauges,  grouting  equipment,  etc.  shall  be  one  of  the  following 
manufacturers or systems or equivalent: 

1.  Bureau BBR Ltd. 

2.  DYWIDAG System Int. 

3.  Freyssinet System 

4.  VSL Corporation 

5.  Tensacciai System 

6.  CLL System 

7.  VLM System 

Where a specific item of one of the manufacturers or systems is indicated on the Contract plans or 
specified in these standard specifications or the particular specifications, comparable items of other 
manufacturers are acceptable, if proven to be of internationally recognized types acceptable to the 
Owner/Engineer. The Owner/Engineer shall be the sole judge as to whether or not any proposed 
alternative system of post-tensioning is comparable and equal to the specified systems. 

22.7.1.2 

Prestressing Steel and Anchorage 

Prestressing  reinforcement  shall  be  high-strength  seven-wire  strand,  high-strength  steel  wire,  or 
high-strength  alloy  bars  of  the  grade  and  type  called  for  in  the  Contract  plans  or  in  a  particular 
specification; and, shall conform to the requirements of the following specifications. 

a. 

Strands 

Strands shall be uncoated, seven-wire, high-tensile, cold-drawn, stress-relieved low relaxation steel 
conforming  to  the  requirements  of  AASHTO  M  203M/M  203-12  (ASTM  A416/  A416M  -  12), 
Supplement  S1  (low  relaxation)  Grade  1860  MPa,  or  BS  5896:2012  Grade  1770  MPa.  Unless 
otherwise specified, the Contractor shall furnish 12.7 mm or 12.5mm diameter strands for all pre-
tensioned members, and 15.24 mm or 15.7 mm diameter strands for all post-tensioned members. 
Prestressing strand, however manufactured, shall be in coils of a large enough diameter to ensure 
that the strand pays off straight. 

Prior to shipment of the strands from the  Manufacturer's plant, the Contractor shall submit typical 
stress-strain curves obtained from the mill 

— or approved independent laboratory — based on test 

performance of the strands proposed for use for approval by the Engineer. For each lot of maximum 
10-ton, or fractions thereof, of strands produced specifically for this Contract, certified copies of the 
Manufacturer's test reports shall be submitted to the Engineer. In addition to the mill certificates, for 
every three coils or reels, one set of three specimens, as selected by the Engineer, shall be tested 
for  tensile  strength  and  elongation  at  a  laboratory  approved  by  the  Engineer.  Upon  building 
confidence in the quality of the delivered strength, the Engineer may relax the aforementioned testing 
requirement. This testing including samples shall be performed by the Contractor at no cost to the 
Owner. Specimens may be cut from the starting end of any length of strand or wire by the Contractor. 

All  strands  accepted  and  approved  shall  have  affixed  to  each  coil,  reel,  or  reel-less  pack  a  tag 
certifying that it has been tested and/or approved by the Engineer. 

b. 

Wires 

Uncoated stress-relieved low relaxation steel wires shall conform to the requirements of AASHTO M 
204M/M 204-06 (2010) (ASTM A421/ A421M - 10). Unless otherwise agreed by the Engineer, low 
relaxation wires shall be in coils of sufficiently large diameter to ensure that the wire pays off straight. 
The  quality  requirements  performed  on  strands  shall  be  applied  on  the  wires  to  be  used  in  the 
Project. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-11 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

c. 

Bars 

Bars  shall  be  Grade  1035  MPa  uncoated  high-strength  bars  conforming  to  the  requirements  of 
AASHTO  M  275M/M  275-08  (ASTM  A722/  A722M  -  12)  or  BS  4486:  1980.  Bars  with  greater 
minimum  ultimate  strength,  but  otherwise  produced  and  tested  in  accordance  with  AASHTO  M 
275M/M  275-08  (ASTM  A722/  A722M  -  12),  may  be  used  provided  they  have  no  properties  that 
make  them  less  satisfactory  than  the  specified  material.  Prestressing  bars  shall  be  straight  upon 
delivery. Three randomly selected samples, per size of bar, per heat of steel with a minimum of one 
sample per shipment shall be tested for tensile strength and elongation at a laboratory approved by 
the Engineer. 

d. 

Assemblies 

Anchorage assemblies, jacks, gauges, grout fittings, and other related equipment and accessories 
shall be standard with the system’s Manufacturer and approved by the Engineer. Post-tensioning 
ducts shall be as approved by the Engineer. 

22.7.1.3 

Post-tensioning Anchorage and Couplers 

Anchorage  assemblies  shall  be  cast  units  that  are  standard  with  the  prestressing  Manufacturer's 
system for the intended purpose (type of anchorages) and to the approval of the Engineer. 

All anchorages and couplers shall develop at least 96 percent of the actual ultimate strength of the 
prestressing  steel,  when  tested  in  an  unbonded  state,  without  exceeding  anticipated  set.  The 
coupling of tendons shall not reduce the elongation at rupture below the requirements of the tendon 
itself.  Couplers,  or  coupler  components,  shall  be  enclosed  in  housings  long  enough  to  permit 
necessary movements. Couplers for tendons shall be used only at locations specifically indicated or 
approved by the Engineer. Couplers shall not be used at points of sharp tendon curvature. 

Anchorages and couplers shall be handled and used strictly in accordance with the Manufacturer's 
instructions and recommendations. 

a. 

Bonded System 

Bond transfer lengths between anchorages and the zone where full prestressing force is required, 
under  service  and  ultimate  loads  shall  normally  be  sufficient  to  develop  the  minimum  specified 
ultimate  strength  of  the  prestressing  steel.  When  anchorages  or  couplers  are  located  at  critical 
sections under ultimate load, the ultimate strength required of the bonded tendons shall not exceed 
the  ultimate  capacity  of  the  tendon  assembly,  including  the  anchorage  or  coupler,  tested  in  an 
unbonded state. 

Housings  shall  be  designed  so  that  complete  grouting  of  all  of  the  coupler  components  will  be 
accomplished when grouting the tendons. 

b. 

Unbonded System 

For  unbonded  tendons,  a  dynamic  test  shall  be  performed  on  a  representative  anchorage  and 
coupler specimen and the tendon shall withstand, without failure, 500,000 cycles from 60 percent to 
66  percent  of  its  minimum  specified  ultimate  strength,  and  also  50  cycles  from  40  percent  to  80 
percent of its minimum specified ultimate strength. The period of each cycle involves the change 
from the lower stress level to the upper stress level and back to the lower. The specimen used for 
the  second  dynamic  test  need  not  be  the  same  used  for  the  first  dynamic  test.  Systems  utilising 
multiple strands, wires, or bars may be tested utilising a test tendon of smaller capacity than the full-
sized tendon. The test tendon shall duplicate the behaviour of the full-sized tendon and generally 
shall not have less than 10 percent of the capacity of the full-sized tendon. Dynamic tests are not 
required on bonded tendons, unless the anchorage is located or used in such manner that repeated 
load applications can be expected on the anchorage. 

Anchorages for unbonded tendons shall not cause a reduction in the total elongation under ultimate 
load of the tendon to less than 2 percent measured in a minimum gauge length of 3 metres. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-12 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

All  the  coupling  components  shall  be  completely  protected  with  a  coating  material  prior  to  final 
encasement in concrete. 

c. 

Special Anchorage Device Acceptance Test 

1.  Test Block Requirements 

Test  blocks  shall  be  a  rectangular  prism  and  shall  contain those  anchorage  components  that  will 
also  be  embedded  in  the  structure's  concrete.  Their  arrangement  must  comply  with  the  practical 
application  and  the  supplier

’s  specifications.  Test  blocks  shall  contain  an  empty  duct  of  an 

appropriate size for the maximum tendon size that can be accommodated by the anchorage device. 

2.  Test Block Dimensions 

Dimensions for the test block perpendicular to the tendon in each direction shall be the smaller of 
the minimum  edge  distance  or the  minimum  spacing  specified  by  the  anchorage  device  supplier; 
with  the  stipulation  that  the  cover  over  any  confining  reinforcing  steel  or  supplementary  skin 
reinforcement be appropriate for the particular application and environment. The length of the block 
along the axis of the tendon shall be at least two times the larger of the cross section dimensions. 

3.  Local Zone Reinforcement (Anchorage Zone) 

The confining reinforcing steel in the local zone shall be the same as that specified by the anchorage 
device supplier for the particular system.  

4.  Skin Reinforcement 

In addition to the anchorage device and its specified confining reinforcement steel, supplementary 
skin  reinforcement  may  be  provided  throughout  the  specimen.  This  supplementary  skin 
reinforcement shall be specified by the anchorage device supplier. Similar reinforcement in the actual 
structure shall be furnished to achieve an equivalent action. 

5.  Concrete Strength 

The concrete strength at the time of stressing shall be greater than the concrete strength of the test 
specimen at time of testing. 

6.  Test Procedure 

Any of the following three test procedures described below is acceptable: 

  Cyclic loading 

  Sustained loading 

  Monotonic loading 

Loads specified for the tests are given in fractions of the ultimate load, or 

F

pu

, of the largest tendon 

that the anchorage device is designed to accommodate. Specimens shall be loaded in accordance 
with  normal  usage  of  the  device  in  post-tensioning  applications,  except  that  load  can  be  applied 
directly to the wedge plate or equivalent area. 

7.  Cyclic Loading Test 

In a cyclic loading test, the load shall be increased to 0.8 

F

pu

, and then cycled for not less than 10 

cycles  between  0.1  Fpu  and  0.8  Fpu  until  crack  widths  stabilize.  Crack  widths  are  considered 
stabilized  if  they  do  not  change  by  more  than  0.025  mm  over  the  last  three  readings.  Upon 
completion of the cyclic loading the specimen shall be preferably loaded to failure or, if limited by the 
capacity of the loading equipment, to at least 1.1 

F

pu

.  

Crack widths and crack patterns shall be recorded at the initial load of 0.8 

F

pu

 at least at the last 

three  consecutive  peak  loadings  before  termination  of  the  cyclic  loading,  and  at  0.9 

F

pu

.  The 

maximum load shall also be reported. 

8.  Sustained Loading Test 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-13 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

In a sustained loading test, the load shall be increased to 0.8 

F

pu

 and held constant for not less than 

48 hours until crack widths stabilize. Crack widths are considered stabilized if they do not change by 
more than 0.025 mm over the last three readings. After sustained loading is completed, the specimen 
shall be preferably loaded to failure or, if limited by the capacity of the loading equipment, to at least 
1.1 

F

pu

Crack widths and crack patterns shall be recorded at the initial load of 0.8 

F

pu

 at least three times at 

intervals  of  not  less  than  four  hours  during  the  last  12  hours  before  termination  of  the  sustained 
loading, and during loading to failure at 0.9 

F

pu

. Maximum loads shall also be reported. 

9.  Monotonic Loading Test 

In a monotonic loading test, the load shall be increased to 0.9 

F

pu

 and held constant for one hour. 

Specimen  shall  then  be  preferably  loaded  to  failure  or,  if  limited  by  the  capacity  of  the  loading 
equipment, to at least 1.2 

F

pu

.  

Crack widths and crack patterns shall be recorded at 0.9 

F

pu

 after the one-hour period, and at 1.0 

F

pu

. Maximum loads shall also be reported. 

10. Anchorage Zone Requirement 

Anchorage zone strengths must exceed the following: 

  Specimens tested under cyclic or sustained loading: 1.1 

F

pu

 

  Specimens tested under monotonic loading: 1.2 

F

pu

 

Maximum  crack  width  criteria,  specified  below,  must  be  met  for  moderately  aggressive 
environments: 

  No cracks greater than 0.25 mm at 0.8 

F

pu

 after completion of the cyclic or sustained loading, 

or at 0.9 

F

pu

 after the one-hour period for monotonic loading  

  No cracks greater than 0.4 mm at 0.9 

F

pu

 after completion of the cyclic or sustained loading, 

or at 1.0 

F

pu

 for monotonic loading 

For high-aggressive environments the crack width criteria shall be reduced by at least 50 percent. 

11. Test Series Requirement 

A test series shall consist of three test specimens. Each specimen must meet the acceptance criteria. 
If  one  of  the  three  specimens  fails  to  pass  the  test,  a  supplementary  test  of  three  additional 
specimens is allowed. The three additional test specimen results must meet all acceptance criteria 
of Paragraph 10 of Sub-article c.  

For a series of similar special anchorage devices, tests are only required for representative samples, 
unless tests for each capacity of the anchorages in the series are required by the Engineer. 

12. Records of the Anchorage Device 

Records of the anchorage device acceptance test shall include the following: 

  Dimensions of the test specimen 

  Drawings and dimensions of the anchorage device, including all confining reinforcing steel 

  Amount and arrangement of supplementary skin reinforcement 

  Type and yield strength of reinforcing steel 

  Type and compressive strength at time of testing of concrete 

  Type of testing procedure and all measurements required in Paragraphs 7 through 10 of sub-

article c for each specimen 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-14 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

22.7.2 

Grout 

The  properties  of  the  grout  made  with  the  materials  and  proposed  plant  and  personnel  shall  be 
assessed by the Contractor for suitability for the intended purpose sufficiently in advance of grouting 
operations to enable adjustments to be made in use of materials or plant or personnel. All retrials 
shall be at the Contractor's expense. 

The materials assessment shall consist of the preparation of the grout, made with the materials and 
using the plant and personnel proposed for use on site, and the testing of it in accordance with Article 
22.8.8.12. The preparation shall be carried out under conditions of temperature expected on site. If 
grouting operations are likely to cover different seasons, the assessment shall include the range of 
expected temperatures. 

The  sources  of  materials  and  procedures  approved  as  a  result  of  satisfactory  trials  shall  not  be 
departed from without the written approval of the Engineer. 

Unless otherwise instructed or agreed by the Engineer as a result of grouting trials, the grout shall 
consist  only  of  Portland  cement  complying  with  BS  EN  197-1:2011  Class  42.5N,  admixtures 
complying with Article 22.8.8.13 and water complying with BS EN 1008:2002. 

The age, chemical composition, fineness and temperature of the cement shall be subject to close 
control. 

The materials used shall be such that the chloride ion content of the grout shall not exceed 0.06% 
chlorides by mass of the cement. 

The post-tensioning grout shall meet the grout physical properties stated in Article 22.7.2.3, Grout 
Physical Properties. Grouts may be either a unique design for the Project or supplied in a prebagged 
form by the grout Manufacturer. For uniquely designed grouts, the cement and admixtures utilised 
in the laboratory trial batches of the proposed grout shall not be changed during construction without 
retesting. Cement freshness shall be in accordance with AASHTO M 85-12 (ASTM C150/ C150M - 
12), except as specified herein. Daily field testing of the grout for the following properties shall be 
required: 

  Fluidity 

  Bleed at three hours 

  Volume change test 

Prebagged  grout  supplied  by  a  grout  manufacturer  shall  be  prebagged  in  plastic-lined  or  plastic-
coated containers and stamped with date of manufacture, lot number, and mixing instructions. Any 
change of materials or material sources shall require retesting and certification of the conformance 
of the grout with the physical properties requirements. Grout suppliers shall provide the Contractor 
with a copy of the QC data sheet for each lot number and shipment sent to the jobsite; these data 
shall also be furnished to the Engineer. Materials with total time from manufacture to usage in excess 
of six months shall be removed from the jobsite and replaced.  

22.7.2.1 

Approval 

Manufacturers  of  post-tensioning  grout  shall  submit  certified  test  reports  from  an  independent 
cement and concrete laboratory for approval. These tests shall show that the material meets all the 
requirements specified herein. 

22.7.2.2 

Mixing 

Materials shall be mixed in accordance with the manufacturer's recommendations. Water used in 
the grout shall be potable, clean, and free of injurious quantities of substances known to be harmful 
to Portland cement or prestressing steel. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-15 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

22.7.2.3 

Grout Physical Properties 

Grouts shall achieve a nonbleeding characteristic. Grout shall contain no aluminium powder or gas-
generating  system  that  produces  hydrogen,  carbon  dioxide,  or  oxygen.  Cementitious  grout  shall 
meet  or  exceed  the  specified  physical  properties  stated  herein,  as  determined  by  the  following 
standard ASTM test methods.  

Grout classes shall be taken as specified in Table 22-3, general grout properties 

for the Engineer’s 

approval in principle shall be as specified in Table 22-4, and field testing of grout for quality control 
shall be as per Article 22.8.8.12. 

a. 

Fluidity 

The fluidity of the grout during the injection period shall be high enough for it to be pumped effectively 
and adequately to fill the duct, but low enough to expel the air and any water in the sheath.  Field 
testing of grout fluidity for quality control shall be as per  Article 22.8.8.12. The fluidity at  the duct 
outlets shall not exceed that of the injected grout by more than 10%. 

b. 

Bleeding 

The bleeding of the grout shall be sufficiently low to prevent excessive segregation and settlement 
of  the  grout  materials.  Field  testing  of  grout  bleeding  for  quality  control  shall  be  as  per  Article 
22.8.8.12. The bleeding shall be less than 2% of the initial volume of the grout and the average of 
four successive results shall be less than 1%. The water shall be reabsorbed by the grout during the 
24 hours after mixing. 

c. 

Volume Change 

The volume change assessed may be either an increase or decrease. Field testing of grout volume 
change for quality control shall be as per Article 22.8.8.12. The volume change of the grout shall be 
within the range 0% to +5%. For grouts with expanding agents there shall be no decrease in volume. 

d. 

Strength 

The compressive strength of 100mm cubes made of the grout shall exceed 27 MPa at 7 days and 
at least 62 MPa after 28 days. Cubes shall be made, cured and tested in accordance with BS EN 
12390-1:2000 and BS EN 12390-2:2009 or AASHTO T 106M/T 106-12. 

e. 

Sieve Test 

The grout shall contain no lumps. This shall be verified by checking the sieving medium on the fluidity 
test cone. 

 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-16 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

 

 

 

First Edition -January 2018 

 

Table 22-3: Grout classes 

Class 

Exposure 

Constituent materials 

Cement 

kg 

Fly ash 

(type F) 

 percent 
ª 

Slag 

 percent 
ª 

Silica 

fume 

(dry) 

 
percentª 

Water 

to 

cementitious 

material ratio 

[W/(c+m)] 

High-range 

water 
reducer

b

 

(type F or G) 
gm/kg 

Calcium 

nitrite

kg/m 

Other 

admixtures

Required 
testing 

Nonaggressive: 
Indoor 

or 

outdoor 

100 

0.45 max 

Article 
22.7.2.3 

Aggressive: 
Subject  wet  or 
dry 

cycles, 

marine environ. 

100 

0 min 

25 max 

0 min 

55 max 

0 min 

15 max 

 

0.45 max 

0 min 

29 max 

0 min 

25 max 

As 

per 

Manufacturers 
recommendation 

Article 
22.7.2.3 

Prepackaged 

Aggressive 

or 

nonaggressive 

0.45 max 

Article 
22.7.2.3

 

Special 

Determined by the Engineer 

 

Article 
22.7.2.3 

Notes:  

a.  Percent of cement substitute. 

b.  Types D and E admixtures may be permitted with approval of the Engineer. 

c.  Alternate corrosion inhibitors may be used. 

d.  Other admixtures, such as anti-bleed admixtures, pumping aids, and air-entraining agents.

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-17 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

Table 22-4: General grout properties 

Property 

Test value 

Test method 

Total chloride ions 

Max.0.06 percent by weight of 
cementitious material 

ASTM C1152/ C1152M - 
04e1 

Fine aggregate (if utilised) 

Max. Size <No. 50 Sieve 

ASTM C33 / C33M - 11a 

Volume change at 28 days 

Min. 0.0 percent at 24 hours 
and 28 days 

ASTM C1090 - 10 

Expansion 

≤2.0 percent for up to 3 hours 

ASTM C940 

– 10a 

Initial set of grout 

Min. 3 hours 

Max. 12 hours 

ASTM C953 - 10 

Fluidity test 

Efflux time from flow cone 
immediately after mixing 

30 minutes after mixing with 
remixing for 30 seconds 

At duct outlet time 

 

Min. 11 seconds                  
Max. 30 seconds 

                                             
Max. 25 seconds 

≥ 10 seconds 

 

ASTM C 939 

– 10 

 

Bleeding at 3 hours 

Max. 0.0 percent 

ASTM C940 

– 10a 

Rapid chloride permeability at 
28 days 

Max. 2,500 coulombs at 30 
volts for 6 hours 

AASHTO T 277-07(2011) 
(ASTM C1202 - 12) 

22.7.3 

Ducts for Prestressing Operations 

Ducts  used to provide holes or voids in the concrete for the placement of post-tensioned bonded 
tendons may be either formed with removable cores or may consist of rigid or semi-rigid ducts that 
are cast into the concrete. 

Ducts  formed  with  removable  cores  shall  be  formed  with  no  constrictions  that  could  block  the 
passage of grout. All coring materials shall be removed. 

Ducts  formed  by  sheaths  left  in  place  shall  be  a  type  that  will  not  permit  the  intrusion  of  cement 
paste. They shall transfer bond stresses, as required, and shall retain their shape under the weight 
of  the  concrete  while  having  sufficient  strength  to  maintain  their  correct  alignment  without  visible 
wobble during concrete placement.  

The  system  of  ducts,  duct  connectors  grouting  connections,  vents,  vent  connections,  drains, 
transitions  to  anchorage  and  caps  for  anchorages  shall  form  a  complete  air  and  water-tight 
encapsulation for the tendons. Ducts shall be of corrosion resistant durable material such as high 
density corrugated polyethylene or polypropylene. Galvanized ferrous metal ducts will be permitted. 
Ducting which may degrade or corrode during the expected life of the structure in the presence of 
contaminants  permeating  the  surrounding  concrete  is  not  permitted.  The  system  shall  be  fully 
compatible with the prestressing anchorages, and other details.  

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-18 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

22.7.3.1 

Metal Ducts for Prestressing 

Sheathing for ducts shall be metal, except as provided herein. Such ducts shall be galvanized ferrous 
metal and shall be fabricated with either welded or interlocked seams. Galvanizing of welded seams 
will not be required. Rigid ducts shall have smooth inner walls and shall be capable of being curved 
to the proper configuration without crimping or flattening. Semi-rigid ducts shall be corrugated and, 
when tendons are to be inserted after the concrete has been placed, their minimum wall thickness 
shall be as follows: 

  0.45 mm for ducts less than or equal to 66.7 mm in diameter  

  0.60 mm for ducts greater than 66.7 mm in diameter 

When bar tendons are preassembled with such ducts, the duct thickness shall not be less than 0.25 
mm. 

22.7.3.2 

Plastic Ducts for Prestressing 

For  locations  in  saltwater  environment,  plastic  duct  material  shall  be  considered  and  is 
recommended. 

Corrugated  plastic  duct  completely  embedded  in  concrete  shall  be  constructed  from  either  high 
density  polyethylene  or  polypropylene.  The  minimum  acceptable  radius  of  curvature  shall  be 
established by the duct supplier, according to standard test methods. The duct shall have a thickness 
as shown in Table 22-5.  

Ducts  shall have a  white coating on the outside or  shall be of white material with ultraviolet (UV) 
stabilizers  added.  Polyethylene  duct  shall  be  fabricated  from  resins  meeting  or  exceeding  the 
requirements of ASTM D3350 - 12, with a cell classification of 345464A.  

Polypropylene duct shall be fabricated from resins meeting or exceeding the requirements of ASTM 
D4101 - 11, with a cell classification range of PP0340BI4541 to PP0340B67884.  

Resin  containing  antioxidants  with  a  minimum  oxidation  induction  time  (OIT)  of  not  less  than  20 
minutes, in accordance ASTM D3895 - 07, shall be used. OIT tests shall be performed on samples 
taken from the finished product. 

Rigid, smooth, black polyethylene ducts used where the tendon is not embedded in concrete shall 
be rigid pipe manufactured from 100 percent virgin polyethylene resin meeting the requirements of 
ASTM  D3350  -  12,  with  a  minimum  cell  class  of 344464C.  A  resin  containing  antioxidants  with a 
minimum OIT of not less than 40 minutes shall be used in accordance with ASTM D3895 - 07. OIT 
tests shall be performed on samples taken from the finished product. Ducts shall be manufactured 
with a dimensional ratio (DR) of 17, as established by either ASTM D 3350 - 12 or ASTM F714 

– 

12e1, and as appropriate for the manufacturing process used. 

Table 22-5: Ducts thickness 

Duct shape 

Duct diameter (mm) 

Duct thickness (mm) 

Flat 

any size 

2.0 

Round 

23 

2.0 

Round 

60 

2.0 

Round 

75 

2.5 

Round 

85 

2.5 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-19 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

Duct shape 

Duct diameter (mm) 

Duct thickness (mm) 

Round 

100 

3.0 

Round 

115 

3.5 

Round 

130 

4.0 

Round 

145 

4.0 

22.7.3.3 

Duct Area 

The provisions of Article 5.4.6.2, Size of Ducts, of the AASHTO LRFD Bridge Design Specifications, 
latest edition, shall apply. 

22.7.3.4 

Duct Fittings 

Coupling  and  transition  fittings  for  ducts  formed  by  sheathing  shall  be  of  either  ferrous  metal 
polyolefin (polyethylene or polypropylene), and shall be air- and watertight and of sufficient strength 
to prevent distortion or displacement of the ducts during concrete placement and tendon grouting. 

All ducts or anchorage assemblies shall be provided with pipes or other suitable connections at each 
end of the duct for the injection of grout after prestressing. As specified in Sub-article a, Duct Inlets 
and  Outlets,  of  Article  22.8.4.2,  ducts  shall  be  provided  with  ports  for  venting  or  grouting  at  high 
points and for draining at intermediate low points. 

Vent and drain pipes shall be at least 20 mm in diameter for strand and at least 12 mm in diameter 
for single-bar tendons and three- or four-strand flat-duct tendons. Connection to ducts shall be made 
with  metallic  or  plastic  structural  fasteners.  Vents  and  drains  shall  be  mortar  tight,  taped  as 
necessary,  and  constructed  with  either  mechanical  or  shrink-wrap  connections.  Vents  and  drains 
shall provide means for injection of grout through the vents and for sealing to prevent leakage of 
grout. 

22.8 

General Prestressing Requirements 

A skilled technician supervisor experienced in the prestressing system as required in Article 22.4.1.3 
and  specified  herein  shall  be  employed  by  the  Contractor.  This  technician  supervisor  shall  be 
capable  of  directing  operations  and  of  providing  aid  and  instruction  in  the  use  of  tensioning  and 
grouting equipment. This assistance shall be available as long as necessary to assure satisfactory 
results in all phases of the tensioning and grouting work. 

Prestressing may be accomplished by pre- and post-tensioning, or by combining the two methods 
— as specified in the Contract documents, in the approved working drawings, or approved in writing 
by the Engineer. 

Prestressing steel shall be tensioned by hydraulic jacks so as to produce the forces shown in the 
Contract documents or on the approved working drawing with appropriate allowances for all losses. 
Losses to be provided for shall be as specified in Article 5.9.5, Loss of Prestress, of the AASHTO 
LRFD Bridge Design Specifications, latest edition. 

For  post-tensioned  work,  the  losses  shall  also  include  the  anchor  set  loss  appropriate  for  the 
anchorage system employed, and actual wobble and friction losses of ducts. 

For pretensioned members, the strand stress prior to seating (jacking stress), shall not exceed 80 
percent of the minimum ultimate tensile strength of the prestressing steel (0.8 fs'). This allowable 
stress  slightly  exceeds  the  values  allowed  in  Article  5.9.3,  AASHTO  LRFD  Bridge  Design 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-20 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

Specifications, and it may be permitted to offset seating losses and to accommodate compensation 
for temperature differences specified in Article 22.8.3.1, Pre-tensioning Requirements. 

For post-tensioned members, the standard stress prior to seating (jacking stress) and the stress in 
the steel immediately after seating shall not exceed the values allowed in AASHTO LRFD Bridge 
Design Specifications, Article 5.9.3, and the Road Structures Design Manual (ADQCC TR-516). 

The method of tensioning employed shall be one of the following as specified or approved: 

1.  Pre-tensioning;  in  which  the  prestressing  strand  or  tendons  are  stressed  prior  to  being 

embedded  in  the  concrete  placed  for  the  member.  After  the  concrete  has  attained  the 
required  strength,  the  prestressing  force  is  released  from  the  external  anchorages  and 
transferred, by bond, into the concrete. 

2.  Post-tensioning; in which the reinforcing tendons are installed in within the concrete and are 

stressed and anchored against the concrete after the development of the required concrete 
strength. As a final operation under this method, the voids or ducts are pressure-grouted. 

3.  Combined  Method;  in  which  part  of  the  reinforcement  is  pre-tensioned  and  part  post-

tensioned. 

Under this method all applicable requirements for pre-tensioning and for post-tensioning shall apply 
to the respective reinforcing elements using these methods. 

During strand stressing, individual wire failures may be accepted by the Engineer, provided not more 
than one wire in any strand is broken and the area of broken wires does not exceed 2 percent of the 
total area of the prestressing steel in the member. 

22.8.1 

Concrete Strength 

Prestressing forces shall not be applied or transferred to the concrete until the concrete has attained 
the  strength  specified  for  initial  stressing.  The  Contractor  shall  cast  and  test  sufficient  cubes  to 
demonstrate  this  to  the  approval  of  the  Engineer.  Additionally,  for  bridges  not  constructed 
segmentally, cast-in-place concrete shall not be post-tensioned until at least 10 days after the last 
concrete  has  been  placed  in  the  member  to  be  post-tensioned,  and  the  minimum  required  cube 
strength gained for post tensioning. 

22.8.2 

Prestressing Equipment 

Hydraulic jacks used to stress tendons shall provide and sustain the necessary forces and shall be 
equipped  with  either  a  pressure  gauge  or  a  load  cell  for  determining  the  jacking  stress.  Jacking 
systems shall provide an independent means by which the tendon elongation can be measured. The 
pressure gauge shall have an accurately reading dial at least 150 mm in diameter or a digital display, 
and each jack and its gage shall be calibrated as a unit with the cylinder extension in the approximate 
position that it will be at final jacking force, and shall be accompanied by a certified calibration chart 
or curve. The load cell shall be calibrated to an accuracy within ± 2 percent and checked at intervals 
to  the  approval  of  the  Engineer;  and  shall  be  provided  with  an  indicator  by  means  of  which  the 
prestressing force in the tendon may be determined. The range of the load cell shall be such that 
the lower 10 percent of the manufacturer's rated capacity will not be used in determining the jacking 
stress. When approved by the Engineer, calibrated proving rings may be used in lieu of load cells. 

Recalibration  of  gauges  shall  be  repeated  at  least  annually  and  whenever  gauge  pressures  and 
elongations indicate materially different stresses. 

22.8.2.1 

Cutting 

Only oxygen flame or mechanical cutting devices shall be used to cut wire, strands, or bars after 
installation  in  the  member  or  after  stressing.  All  cutting  shall  be  carried  out  using  either  of  the 
following:  

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-21 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

a.  A  high-speed  abrasive  cutting  wheel  or  friction  saw  at  not  less  than  1  diameter  from  the 

anchor, or any other mechanical method approved by the Engineer. 

b.  An oxy-acetylene cutting flame, using excess oxygen to ensure a cutting rather than a melting 

action, not less than 75 mm from the anchor. Temperatures of the tendon adjacent to the 
anchor shall not be greater than 200 degrees Celsius. Care shall be taken that neither the 
flame nor splashes come into contact with the anchorages or tendons. 

Electric arc welders shall not be used. 

22.8.2.2 

Sequence of Stressing 

When the sequence of stressing individual tendons is not specified in the Contract documents, or in 
the  approved  working  drawings,  the  stressing  of  post-tensioning  tendons  and  the  release  of 
pretensioned tendons shall be done in a sequence that produces a minimum of eccentric force in 
the member. 

22.8.2.3 

Measurement of Stress 

A  record  of  gauge  pressures  and  tendon  elongations  for  each  tendon  shall  be  provided  by  the 
Contractor for review and approval by the Engineer. Elongations shall be measured to an accuracy 
of  1.5  mm.  The  corresponding  wobble  and  friction  coefficients  of  ducts  shall  be  calculated 
accordingly to verify the assumed coefficients used in the design. Stressing tails of post-tensioned 
tendons shall not be cut until the stressing records and elongation calculation have been approved. 
A facility to measure any movement of the tendon in the gripping devices shall also be provided. 

Stresses in the tendons during tensioning shall be determined by the gage or load-cell readings and 
shall be verified with the measured elongations. Calculations of anticipated elongations shall utilise 
the modulus of elasticity, based on nominal area, as furnished by the manufacturer for the lot of steel 
being tensioned, or as determined by a bench test of strands used in the work. 

All tendons shall be tensioned to a preliminary force, as necessary, to eliminate any take-up in the 
tensioning system before elongation readings are started. This preliminary force shall be between 5 
percent  and  25  percent  of  the  final  jacking  force.  The  initial  force  shall  be  measured  by  a 
dynamometer,  or  by  other  approved  method,  so  that  its  amount  can  be used  as a  check  against 
elongation 

— as computed and as measured. Each strand shall be marked prior to final stressing to 

permit measurement of elongation and to ensure that all anchor wedges set properly. 

It is anticipated that there may be discrepancy in indicated stress between jack gage pressure and 
elongation. In such event, the load used, as indicated by the gage pressure, shall produce a slight 
overstress rather than understress. When a discrepancy between gage pressure and elongation of 
more than 5 percent in tendons more than 15 m long or 7 percent in tendons of 15 m or less in length 
occurs,  the  entire  operation  shall  be  carefully  checked  and  the  source  of  error  determined  and 
corrected  before  proceeding  further.  When  provisional  ducts  are  provided  for  the  addition  of 
prestressing  force  in  event  of  an  apparent  force  deficiency  in  tendons  more  than  15  m  long,  the 
discrepancy between the force indicated by gage pressure and elongation may be increased to  7 
percent before investigation into the source of the error. 

22.8.3 

Pretensioned Members 

Pretensioned members of concrete structures shall comply with the requirements and specifications 
outlined in this section. 

22.8.3.1 

Pre-tensioning Requirements 

Stressing  shall  be  accomplished  by  multiple-strand  stressing  method  subject  to  approval  by  the 
Engineer. Tensioning of an individual strand is not permitted unless approved by the Engineer. Pre-

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-22 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

tensioning shall comply with PCI MNL-116 requirements. The amount of stress to be given to the 
strands shall be as shown in the Contract documents or in the approved working drawings. 

All strands to be stressed in a group (multiple-strand stressing) shall be brought to a uniform initial 
tension prior to  a full  pre-tensioning. The amount  of the initial tensioning force shall be within the 
range specified in Article 22.8.2.3, Measurement of Stress, and shall be the minimum required to 
eliminate all slack and to equalise the stresses in the tendons as determined by the Engineer. The 
amount of this force will be influenced by the length of the casting bed and the size and number of 
tendons in the group to be tensioned. 

When straight tendons are used in the long-line method of pre-tensioning, sufficient locator plates 
shall  be  distributed  throughout  the  length  of  the  bed  to  ensure  that  the  wires  or  strands  are 
maintained in their proper position during concreting. Where a number of units are made in line, they 
shall be free to slide in the direction of their length and thus permit transfer of the prestressing force 
to the concrete along the whole line.  

In the individual mould system, the moulds shall be sufficiently rigid to provide the reaction to the 
prestressing force without distortion. 

Draped pretension tendons shall either be tensioned partially by jacking at the end of the bed and 
partially by uplifting or depressing tendons, or they shall be tensioned entirely by jacking, with the 
tendons being held in their draped positions by means of rollers, pins, or other approved methods 
during the jacking operation. 

Approved low-friction devices shall be used at all points of change in slope of tendon trajectory when 
tensioning draped pretension strands, regardless of the tensioning method used. For single tendons 
the deflector in contact with the tendon shall have a radius of not less than  five times the tendon 
diameter for wire or 10 times the tendon diameter for strand, and the total angle of deflection  shall 
not exceed 15 degrees. 

If the load for a draped strand, as determined by elongation measurements, is more than 5 percent 
less than that indicated by the jack gages, the strand shall be tensioned from both ends of the bed, 
and the load as computed from the sum of elongation at both ends shall agree within 5 percent of 
that indicated by the jack gages. 

When  ordered  by  the  Engineer,  prestressing  steel  strands  in  pretension  members,  if  tensioned 
individually, shall be checked by the Contractor for loss of prestress not more than three hours prior 
to  placing  member  concrete.  Methods  and  equipment  for  checking  the  loss  of  prestress  shall  be 
subject to approval by the Engineer. All strands that show a loss of prestress in excess of 3 percent 
shall be retensioned to the original computed jacking stress. 

Stress  on  all  strands,  including  hold-down  and  hold-up  forces  shall  be  maintained  between 
anchorages  until  the  concrete  has  reached  the  compressive  strength  required  at  the  time  for  the 
transfer of stress to concrete, which shall take place slowly to minimize shock. 

When  prestressing  steel  in  pretensioned  members  is  tensioned  at  a  temperature  more  than  14 
degrees Celsius lower than the estimated temperature of the concrete and the prestressing steel at 
the  time  of  initial  set  of  the  concrete,  the  calculated  elongation  of  the  prestressing  steel  shall  be 
increased to compensate for the loss in stress due to the change in temperature, but in no case shall 
the  jacking  stress  exceed  80  percent  of  the  specified  minimum  ultimate  tensile  strength  of  the 
prestressing steel. 

Strand splicing methods and devices shall be approved by the Engineer. When single-strand jacking 
is used, only one splice per strand will be permitted. When multi-strand jacking is used, either all 
strands shall be spliced or no more than 10 percent of the strands shall be spliced. When more than 
a  strand  are  spliced,  the  splice  location  should  be  staggered.  Spliced  strands  shall  be  similar  in 
physical properties, from the same source, and shall have the same twist or lay. All splices shall be 
located outside of the prestressed units. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-23 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

Side  and  flange  forms  that  restrain  deflection  shall  be  removed  before  release  of  pre-tensioning 
reinforcement. 

Except when otherwise shown in the Contract documents, all pretensioned prestressing strands shall 
be cut flush  to the end of the member and the exposed ends of the strand. A  25-mm strip of the 
adjoining concrete shall be cleaned and painted. Cleaning shall be by wire brushing or abrasive blast 
cleaning to remove all dirt and residue that is not firmly bonded to the metal or concrete surfaces, 
which shall be coated with one thick coat of zinc-rich paint conforming to the requirements of U.S. 
Military Specification MIL-P-24441/20. Paints shall be thoroughly mixed at the time of application, 
and shall be worked into any voids in the strands. 

22.8.3.2 

Placement of Prestressing Steel 

Prestressing steel that resides in a stressing bed shall be protected from corrosion if the stressing 
bed is to be exposed to weather for more than 36 hours before encasement in concrete. 

Anchor  plates  and  anchorages  shall  be  accurately  located  and  securely fastened to  the forms  or 
held in place by approved methods; they shall  be of such nature that strands will not kink, break 
down, or be otherwise damaged; and such anchorages shall ensure proper distribution of the load 
to  the  concrete-bearing  surfaces  between  anchorages.  Concrete  shall  be  perpendicular  and 
concentric with the strands and the line of action of the pre-tensioning. Moulding lengths, as indicated 
in the approved shop drawings, shall be verified and recorded for each strand after anchorages are 
met. Anchorage devices shall hold the pre-tensioning steel without slip of more than 3 mm at a load 
equal to the applied load of the strands at pre-tensioning. If grip type anchorages are used, provisions 
shall be made for observation of possible slip. Strands shall be allowed to extend beyond anchorages 
at an amount sufficient to permit retensioning before placement of concrete. 

Strands shall be carefully handled when removed from storage, uncoiled, placed, and protected from 
damage or the intrusion of foreign material. 

All strands shall be tensioned according to Article 22.8.3.1. Strands shall not be allowed to unwind 
more  than  one  turn.  Jacking  force  records  and  elongation  measurements  shall  be  kept  after  the 
strands are tensioned to 20 percent of final jacking force. 

Prestressing steel shall be tensioned to the required stress. Elongation computations shall include 
strand anchorage slippage, splice slippage, in place horizontal movement of the structural member 
during  prestressing  operations,  and  prestressing  steel  temperature  changes  between  the  time  of 
tensioning and the time when the concrete takes its initial set. All computations must be prepared by 
a Professional Engineer. 

Prestress  bed  forms,  strands,  and  reinforcement  bar  temperatures  shall  be  maintained  by  the 
Contractor within 15 degrees Celsius of the temperature of the concrete to be placed in the forms. 
Strands shall be supported with rollers at points of direction change when strands are tensioned in 
a draped position. Free-running rollers with minimal friction shall be used. Initially, when strands are 
tensioned and then pulled into the draped position, the Contractor shall tension to no more than the 
required tension minus the increased tension due to forcing the strand to a draped profile. If the load 
in  a  draped  strand  at  the  dead  end,  as  determined  by  elongation  measurements,  is  less  than  95 
percent of the jack load, the strand shall be tensioned from both ends of the bed. The load shall be 
made, as computed from the sum of elongations produced by jacking at both ends, agree within 5 
percent of the jack load. 

Within three hours before placing concrete, the tension on the prestressing strands shall be checked. 
The method and equipment for checking the loss of prestress shall be subject to approval by  the 
Engineer. If strands are tensioned individually, each strand shall be checked for loss of prestress. 
Strands that show a loss of prestress in excess of 3 percent shall be retensioned by the Contractor 
to the original computed jacking stress. If strands are tensioned in a group, the entire group for total 
loss of prestress shall be checked. If the total prestress shows a loss in excess of 3 percent, or if any 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-24 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

individual stand appears significantly different from the rest of the strands in a group, the Contractor 
shall release and retension the entire group. 

22.8.3.3 

Releasing of Prestressing Steel 

Transferring of prestressing force from the strands to the concrete shall be performed simultaneously 
and in a controlled manner, as approved by the Engineer. Releasing the force by cutting individual 
prestressing strands shall not be permitted. No bond stress shall be transferred to the concrete, nor 
shall end anchors be released, until the concrete has attained a compressive strength as indicated 
by standard cubes made and cured identically with the members, of at least the minimum strength 
indicated in the approved shop drawings or in the specifications for such transfer of load. Elements 
shall be cut or released in such an order that lateral eccentricity of prestress will be a minimum. 

In cases where several beams cast in one continuous line and stressed at one time, elements shall 
be cut or released in such an order that lateral eccentricity of prestress will be a minimum. 

22.8.4 

Post-tensioned Members 

Post-tensioned  members  of  concrete  structures  shall  comply  with  the  requirements  and 
specifications outlined in this section. 

22.8.4.1 

Post-tensioning Requirements 

Prior  to  post-tensioning  any  member,  the  Contractor  shall  demonstrate  to  the  satisfaction  of  the 
Engineer that the prestressing steel is free and unbonded in the duct. 

All strands in each tendon, except for those in flat ducts with not more than four strands, shall be 
stressed simultaneously with a multi-strand jack. Tensioning shall be accomplished so as to provide 
the forces and elongations specified in Article 22.8.5.1, Pre-tensioning tendons. 

Except as provided herein, or when specified in the Contract documents, or in the approved working 
drawings, tendons in continuous post-tensioned members shall be tensioned by jacking at each end 
of the tendon. For straight tendons, and when one end stressing is shown in the Contract documents, 
tensioning may be performed by jacking from one end or both ends of the tendon at the option of the 
Contractor. 

Deflectors in contact with tendons shall have a radius of not less than 50 times the diameter of the 
tendon, and the total angle of deflection shall not exceed 15 degrees unless otherwise agreed by 
the Engineer.  

Stressing shall continue until the required extension and tendon load are reached or are approved 
by the Engineer.  

After the tendons have been anchored, the force exerted by the jack shall be decreased gradually 
and steadily so as to avoid shock to the tendon or the anchorage. Full records shall be kept of all 
tensioning  operations,  including  the  measured  extensions,  pressure gauge,  or  load-cell  readings; 
and the amount of anchors set at each anchorage. Copies of these records shall be supplied to the 
Engineer within 24 hours of each tensioning operation.  

Unless  otherwise  agreed  by  the  Engineer,  tendons  shall  not  be  cut  less  than  three  days  after 
grouting. 

22.8.4.2 

Placement of Ducts 

Internal and external surfaces of ducts shall be clean and sound at the time of incorporation in the 
work. 

Ducts shall be rigidly supported at the proper locations in the forms by ties to reinforcing steel, which 
are  adequate  to  prevent  displacement  during  concrete  placement.  Supplementary  support  bars 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-25 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

epoxy coated shall be used, where needed, to maintain proper alignment of the duct. Hold-down ties 
shall be used when the buoyancy of the ducts in the fluid concrete will lift the reinforcing steel.  

Polyethylene duct and metal duct for longitudinal or transverse post-tensioning in the flanges shall 
be supported at intervals not to exceed 600 mm. Polyethylene duct in webs for longitudinal post-
tensioning shall be tied to stirrups at interval not to exceed 600 mm and metal duct for longitudinal 
post-tensioning in webs shall be tied to stirrups at interval not to exceed 1.2 metres. 

Joints between sections of duct shall be coupled with positive connections that do not result in angle 
changes at the joints and will prevent the intrusion of cement paste. 

After placing that ducts and reinforcement and forming is complete, an inspection shall be made to 
locate possible duct damage. 

All unintentional holes or openings in the duct must be repaired prior to concrete placing. 

Grout  openings  and  vents  must  be  securely  anchored  to  the  duct  and  to  either  the  forms  or  to 
reinforcing steel to prevent displacement during concrete placing operations. 

After installation in the forms, the ends of ducts shall be at all times covered, as necessary, to prevent 
the entry of water or debris. 

During concrete placement for precast segments, mandrels shall be used as stiffeners in each duct 
and  shall  extend  throughout  the  length  of  the  segment  being  cast  and  at  least  0.6  m  into  the 
corresponding  duct  of  the  previously  cast  segment.  The  mandrels  shall  be  of  sufficient  rigidity  to 
maintain the duct geometry within the tolerances shown in Table 22-6. 

Table 22-6: Duct position tolerances 

Tolerances 

Vertical position 
(mm) 

Lateral position 
(mm) 

Horizontal tendons in slabs or in slab regions of 
larger members 

±6 

±12 

Longitudinal draped superstructure tendons in 
webs 

Tendon over supports or in middle third of span 

±6 

±6 

Tendon in middle-half of web depth 

±12 

±6 

Longitudinal, generally horizontal superstructure  

Tendons usually in top or bottom of member 

±6 

±6 

Horizontal tendons in substructures and 
foundations 

±12 

±12 

 

Longitudinal Position 
(mm) 

Transverse Position 
(mm) 

Vertical tendons in webs 

±6 

±6 

Vertical tendons in pier shafts 

±6 

±6 

Additionally, the following shall apply: 

  In all other cases, locate tendons within ±6 mm in any direction. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-26 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

  Entrance and exit angles of tendon paths at anchorages or at faces of concrete shall be within 

±3 degrees of desired angle measured in any direction and any deviations in the alignment 
are accomplished with smooth transitions without any kinks. 

  Angle changes at duct joints shall not be greater than ±3 degrees in any direction and must 

be accomplished with smooth transitions without any kinks. 

  Locate anchorages within ±6 mm of desired position laterally and ±25 mm along the tendon 

except that minimum cover requirements shall be maintained. 

  Position anchorage confinement reinforcement in the form of spirals, multiple V-shaped bars, 

or links, to be properly centred on the duct and to start within 12 mm of the back of the main 
anchor plate. 

  If  conflicts  exist  between  the  reinforcement  and  post-tensioning  duct,  position  the  post-

tensioning duct and adjust the reinforcement locally with the Engineer's approval. 

a. 

Duct Inlets and Outlets 

All ducts for continuous structures shall be supplied with outlets at the high and low points of the 
duct profile, except where the profile changes are small, as in continuous slabs, and at additional 
locations, as specified the Contract documents. Low-point outlets shall remain open until grouting is 
started. 

b. 

Proving of Post-tensioning Ducts 

Upon completion of concrete placement, the Contractor shall prove that post-tensioning ducts are 
free and clear of any objections or damage and can accept the intended post-tensioning tendons by 
passing a torpedo through the duct. The torpedo shall have the same cross-sectional shape as the 
duct, and 6 mm smaller than the clear nominal inside dimensions of the duct. No deductions shall 
be made to the torpedo section dimensions for tolerances allowed in the manufacture or fixing of the 
ducts. For straight ducts, a torpedo at least 0.6 m long shall be used. For curved ducts, the length 
shall be determined so that when both ends touch the outermost wall of the duct, the torpedo is 6 
mm clear of the innermost wall. If the torpedo will not travel completely through the duct, the Engineer 
shall reject the member, unless through workable repairs the torpedo shall pass through the duct 
easily, by hand, and without resorting to excessive effort or mechanical assistance. 

c. 

Duct Pressure Field Test 

Before stressing and grouting internal or external tendons, the Contractor shall install all grout caps, 
inlets, and outlets  and test  the  duct  with  compressed  air to  determine  if  duct  connections require 
repair. In the presence of the Engineer, the duct shall be pressurized to 345 kPa and the outside air 
source shall be locked off. Pressure loss shall be recorded for one minute. A pressure loss of 170 
kPa is acceptable for ducts that are 45 metres or shorter and a pressure loss of 100 kPa is acceptable 
for  ducts that  are  longer  than  45 metres. If the  pressure  losses  exceed  allowable  thresholds,  the 
Contractor shall repair leaking connections using methods approved by the Engineer and then test 
duct pressure again. 

22.8.4.3 

Placement of Concrete 

Where the end of a post-tensioned assembly will not be covered by concrete, the Contractor shall 
recess the anchoring devices so that the ends of the prestressing steel and all parts of the anchoring 
devices are at least 51 mm inside the end surface of the members. 

Before  placing  concrete,  the  Contractor  shall  demonstrate  that  all  ducts  are  unobstructed. 
Immediately after concrete placement, the Contractor shall blow out the conduit with compressed, 
oil-free  air  to  break-up  and  remove  all  mortar  in  the  conduit  before  it  hardens.  Approximately  24 
hours  after  the  concrete  placement,  the  Contractor  shall  flush  the  conduits  with  water  that  may 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-27 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

contain lime or calcium oxide, or slaked lime or calcium hydroxide, in the amount of 12 gm per liter. 
Water shall be blown out with compressed, oil-free air. 

For post-tensioned members that are to be steam cured, the Contractor shall not install prestressing 
steel until curing is complete. 

22.8.4.4 

Placement of Post-tensioning Steel 

Unless otherwise directed by the Engineer, prestressing steel installed in members prior to placing 
and curing of the concrete, is not acceptable.  

When accepted by the Engineer, all prestressing steel preassembled in ducts and installed prior to 
the placement of concrete shall be accurately placed and held in position during concrete placement. 
Locations and support of each tendon shall be within a tolerance of ±6 cm. Tendons shall be securely 
tied in place or supported to prevent their dislocation during the concreting operation. 

When  the  prestressing  steel  is  installed  after  the  concrete  has  been  placed,  the  Contractor  shall 
demonstrate  to  the  satisfaction  of  the  Engineer  that  the  ducts  are  free  of  water  and  debris 
immediately prior to installation of the steel. At this point, the total number of strands in an individual 
tendon may be pulled into the duct as a unit, or individual strands may be pulled or pushed through 
the duct. 

Anchorage devices or block-out templates for anchorages shall be set and held so that their axis 
coincides with the axis of the tendon and anchor plates are normal in all directions to the tendon. 

Prestressing steel shall be distributed so that the force in each girder stem is equal or as required 
by the Contract plans, except as provided herein. For box girders with more than two girder stems, 
at  the  Contractor's  option,  the  prestressing  force  may  vary  up  to  5  percent  from  the  theoretical 
required force per girder stem provided the required total force in the superstructure is obtained and 
the force is distributed symmetrically about the centre line of the typical section. 

a. 

Protection of Steel After Installation 

When prestressing steel, used in post-tensioned concrete members, is installed prior to placing and 
curing of the concrete and is not grouted within the time limit specified below, a corrosion inhibitor 
placed in the ducts or directly applied to the steel may only be used when directed by the Engineer 
to continuously protect the prestressing steel against rust or other corrosion  until grouted or encased 
in concrete. Otherwise, removal, replacement and reinstallation of strands may be required at the 
direction of the Engineer. 

Prestressing steel installed and tensioned in members after placing and curing of the concrete and 
grouted within the time limit specified below will not require a corrosion inhibitor, as described herein. 
Rust that may form during the interval between tendon installation and grouting will not be cause for 
rejection of the steel. 

Permissible intervals between tendon installation and grouting without use of a corrosion inhibitor for 
various exposure conditions shall be as follows: 

  Very damp atmosphere or over saltwater (Humidity >70 percent): 7 days 

  Moderate atmosphere (Humidity from 40 percent to 70 percent): 15 days 

  Very dry atmosphere (Humidity <40 percent): 20 days 

After tendons are placed in ducts, the openings at the ends of the ducts shall be sealed to prevent 
entry of moisture. 

When steam curing is used, steel for post-tensioning shall not be installed until the steam curing is 
completed. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-28 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

Such tendons shall be protected against corrosion by means of a corrosion inhibitor placed in the 
ducts or on the steel, or shall be stressed and grouted within seven days after steam curing. 

Whenever  electric  welding  is  performed  on  or  near  members  containing  prestressing  steel,  the 
welding  ground  shall  be  attached  directly  to  the  steel  being  welded.  All  prestressing  steel  and 
hardware shall be protected from weld spatter or other damage. 

b. 

Protection of Tendons 

Within four hours after stressing and prior to grouting, tendons shall be protected against corrosion 
or harmful effects of debris by temporarily plugging or sealing all openings and vents; cleaning rust 
and other debris from all metal surfaces that will be covered by the grout cap; and placing the grout 
cap, including a seal, over the wedge plate until the tendon is grouted. 

22.8.4.5 

Placement of Anchorage 

Proper  placement  of  all  materials  shall  be  the  responsibility  of  the  Contractor,  according  to  the 
Contract documents, and the requirements stipulated by the anchorage device supplier. Due care 
and  attention  shall  be  exercised  by  the  Contractor  in  the  placement  of  anchorage  hardware, 
reinforcement, concrete, and consolidation of concrete in anchorage zones. Modifications to the local 
zone  details,  verified  under  provisions  of  Article  5.10.9.7.3  of  the  AASHTO  LRFD  Bridge  Design 
Specifications  and  Sub-article  c,  Special  Anchorage  Device  Acceptance  Test,  of  Article  22.7.1.3, 
shall  be  approved  by  both  the 

Contractor’s  supervisor  and  the  technical  representative  of  the 

approved post-tensioning system. 

22.8.4.6 

Record of Stressing Operation 

A record of the following post-tensioning operations shall be kept for each tendon installed: 

  The Project name and number 

  The Contractor and/or subcontractor  

  Tendon location, size, and type  

  Date tendon was first installed in ducts  

  Coil or reel number for strands or wires and heat number for bars and wire  

  Assumed and actual cross-sectional area 

  Assumed and actual modulus of elasticity  

  Date stressed 

  Jack and gage numbers per end of tendon  

  Required jacking force 

  Gage pressures 

  Elongations, anticipated and actual 

  Anchor sets, anticipated and actual  

  Stressing sequence, including tendons before and after this tendon 

  Stressing mode, such as one end, two ends, simultaneous 

  Witnesses to stressing operation, the Contractor and inspector  

  Date grouted, days from stressing to grouting, grouting pressure applied, and injection end 

  Record any other relevant information, including pour back and bitumastic installation dates 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-29 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

A complete copy of all stressing operations, and the jack calibration forms, shall be provided to the 
Engineer. 

22.8.5 

Identification and Testing 

All wire, strand, or bars shipped to the site shall be assigned a lot number and tagged for identification 
purposes.  Anchorage  assemblies  shall  be  likewise  identified.  Each  cable  shall  be  tagged  with  its 
number from which the coil numbers of the steel used can be identified. 

Cables shall not be kinked or twisted. Individual wires and strands for which extensions are to be 
measured  shall  be  readily  identifiable  at  each  end  of  the  member.  No  strand  that  has  come 
unravelled shall be used. 

Each  lot  of  wire  or  bars  and  each  reel  of  strand  reinforcement  shall  be  accompanied  by  a 
manufacturer's certificate of compliance, a mill certificate, and a test report. The mill certificate and 
test report shall include the following: 

  Chemical composition, not required for strands 

  Cross-sectional area 

  Yield and ultimate strengths  

  Elongation at rupture 

  Modulus of elasticity 

  Stress strain curve for the actual prestressing steel intended for use 

All values certified shall be based on test values and nominal sectional areas of the material being 
certified. 

Samples  described  in  the  following  subsections  selected  from  each  lot  shall  be  furnished  by  the 
Contractor  to  the  Engineer  for  verification  testing.  Selection  of  samples  shall  be  made  at  the 
manufacturer’s plant by the inspector, if ordered by the Engineer. 

All samples submitted to the Engineer shall be accompanied by a certification from the supplier or 
subcontractor certifying that the samples were taken from, and are representative of, the lot of reels 
to be furnished. In the case of wire or strand, samples shall be taken from the same master roll. 

Actual strengths of the prestressing steel shall not be less than specified by the applicable ASTM or 
British standard, and shall be determined by tests of representative samples of the tendon material 
in conformance with ASTM or British standards. 

If it is proposed to use super strand complying with BS 5896: 2012 Table 6 or other than the lowest 
strength 3, 4, 5, 6 or 7mm diameter wires complying with BS 5896: 2012 Tables 4 and 5, reels will 
only  be  accepted  if  both  the  breaking  load  and  the  0.1%  proof  load  of  the  sample  exceeds  the 
specified characteristic loads given in the above Tables 4 or 6. In the case of Table 5 this requirement 
shall apply to the breaking load and the load at 1% elongation.  

The Contractor shall employ the services of an independent testing laboratory to design the concrete 
mixes and test the cement and aggregates, concrete, reinforcing steel, pre-stressing steel, and such 
other materials as directed by the Engineer. All of the materials specified for testing shall be furnished 
free of cost and shall be delivered in time for tests to be made well in advance of anticipated time of 
use. 

22.8.5.1 

Pre-tensioning Strands 

For each certificate furnished for pretensioned strands, one sample at least 5 m long near ends of 
fittings  shall  be  furnished  in  accordance  with  the  requirements  of  paragraph  9.1  of  AASHTO  M 
203M/M 203-12 (ASTM A416/ A416M - 12). 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-30 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

22.8.5.2 

Post-tensioning Tendons 

The following lengths shall be furnished for each 10,000 kg, or portion thereof, lot of material used 
in the work: 

  For wires not requiring heading-sufficient length to make up one parallel-lay cable, 1.5 m long 

consisting of the same number of wires as the cable to be furnished. 

  For strands to be furnished with fittings, 1.5 m between near ends of fittings. 

  For bars to be furnished with threaded ends and nuts, 1.5 m between threads at ends. 

22.8.5.3 

Anchorage Assemblies and Couplers 

One specimen of each size of the prestressing tendon, including couplings, at the selected type, with 
end fittings and anchorage assembly attached, shall be furnished by the Contractor for strength tests 
only.  These  specimens  shall  be  1.5  m  in  clear  length,  measured  between  ends  of  fittings.  If  the 
results  of  the  test  indicate  the  necessity  of  check  tests,  additional  specimens  shall  be  furnished 
without cost. 

When dynamic testing is required, the Contractor shall perform the testing and shall furnish certified 
copies of test results that indicate conformance with the specified requirements prior to installation 
of anchorages or couplers. Costs of such testing shall be borne by the Contractor. 

For  prestressing  systems  previously  tested  and  approved  on  projects  having  the  same  tendon 
configuration, the Engineer may not require complete tendon samples, provided there is no change 
in the material, design, or details previously approved. Shop drawings or prestressing details shall 
identify the Project on which approval was obtained; otherwise testing shall be conducted. 

22.8.6 

Protection of Prestressing Steel 

All  prestressing  steel  shall  be  protected  against  physical  damage  and  rust  or  other  results  of 
corrosion  at  all  times  from  manufacture  to  grouting.  Prestressing  steel  shall  also  be  free  of 
deleterious material, such as grease, oil, wax, or paint. Prestressing steel that has sustained physical 
damage at any time shall be rejected. Development of pitting or other results of corrosion, other than 
rust stain, shall be cause for rejection. 

Prestressing  steel  shall  be  stored  clear  of  the  ground  and  be  protected  from  the  weather,  from 
splashes from any other materials, and from splashes from the cutting operation of an oxyacetylene 
torch  or  arc  welding  activity.  In  no  circumstances  shall  prestressing  steel,  after  manufacture,  be 
subjected to any welding operation, or heat treatment or metallic coating, such as galvanising. This 
does not preclude cutting as described in Article 22.8.2.1. 

Prestressing steel shall be packaged in containers or shipping forms for the protection of the strand 
against  physical  damage  and  corrosion  during  shipping  and  storage.  A  corrosion  inhibitor  that 
prevents  rust  or  other  results  of  corrosion  shall  be  placed  in  the  package  or  form,  or  shall  be 
incorporated  in  a  corrosion  inhibitor  carrier  type  packaging  material.  When  permitted  by  the 
Engineer, a corrosion inhibitor  may  also be applied directly to the steel. Corrosion inhibitors shall 
have  no  deleterious  effect  on  the  steel,  concrete,  or  bond  strength  of  steel  to  concrete  or  grout. 
Packaging  or  forms  damaged  from  any  cause  shall  be  immediately  replaced  or  restored  to  their 
original condition. 

Shipping packages or forms shall be clearly marked with a statement that the package contains high-
strength prestressing steel, and the type of corrosion inhibitor used, including the date packaged. 

All pre- or post-tensioning steel shall be satisfactorily stored and protected from excessive rust or 
other corrosion prior to placing. Such steel shall be free from deleterious substances when placed. 
Ample protection shall also be provided for all exposed steel at the ends of prestressed concrete 
bridge members to prevent deterioration by rust and corrosion. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-31 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

All anchorages, end fittings, couplers, and exposed tendons, which will not be encased in concrete 
or grout in the completed work, shall be permanently protected against corrosion. 

22.8.7 

Corrosion Inhibitor 

Corrosion  inhibitors  shall  consist  of  a  vapour-phase  inhibitor  (VPI)  powder  conforming  to  the 
provision of Federal Specification MIL-P-3420F-87 or as otherwise approved by the Engineer.  

Corrosion  inhibitors  shall  only  be  used  at  the  direction  of  the  Engineer.  When  approved,  water-
soluble oil may be used on prestressing steel as a corrosion inhibitor. 

22.8.8 

Grouting 

The  Contractor  shall  undertake  grout  trials  in  accordance  with  the  details  described  in  Article 
22.8.8.11.  The  trials  are  required  to  demonstrate  that  the  grouting  methods  and  procedures 
proposed  by  the  Contractor  will  ensure  that  grout  completely  fills  the  ducts  and  surrounds  the 
prestressing steel. 

The Contractor shall submit at least 4 weeks before on-site trials a detailed method statement or 
grouting  operation  plan  covering  proposed  materials,  duct,  anchorage  and  vent  arrangements, 
personnel, equipment grouting procedures and quality control for the approval of the Engineer. 

When the post-tensioning method is used, the prestressing steel shall be provided with permanent 
protection and shall be bonded to the concrete by completely filling the void space between the duct 
and the tendon with grout. Grout should be injected from low points pumping toward the high-point 
vent. For segmental, span-by-span construction, grout shall be injected through a grout inlet at mid-
span. 

All grouting operations shall be carried out by experienced superintendents and foremen that have 
received  instructional  training  and  have  at  least  three  years  of  experience  on  previous  projects 
involving grouting of similar type and magnitude. 

A  grouting  operation  plan  shall  be  submitted  for  approval  at  least  45  days  in  advance  of  any 
scheduled grouting operations. Written approval of the grouting operation plan by the Engineer shall 
be required before any grouting of the permanent tendons in the structure takes place. 

Tendons shall be grouted at not less than  eight hours to 12 hours, but within the number of days 
specified  in  Article  22.8.4.4  after  tendon  installation.  The  tendons  shall  be  protected  against 
corrosion by a plug at each end to prevent the passage of air, and such plugs shall be left in place 
until the tendon is grouted. 

At a minimum, the following items shall be provided in the grouting operation plan: 

1.  Provide names, and proof of training and experience records for the grouting crew and the 

crew supervisor in conformance with this specification 

2.  Type, quantity, and brand of materials used in grouting including all required certifications 

3.  Type of equipment furnished, including capacity in relation to demand and working condition, 

as well as back-up equipment and spare parts 

4.  General grouting procedure 

5.  Duct pressure test and repair procedures 

6.  Method to be used to control the rate of flow within ducts 

7.  Theoretical grout volume calculations 

8.  Mixing and pumping procedures 

9.  Direction of grouting 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-32 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

10. Sequence of use of the inlets and outlet pipes 

11. Procedures for handling blockages 

12. Procedures for possible post grouting repair 

13. Grout trials 

Before grouting operations begin, a joint meeting of the Contractor, grouting crew, and the Engineer 
shall  be  conducted.  At  the  meeting,  the  grouting  operation  plan,  required  testing,  corrective 
procedures, and any other relevant issues shall be discussed. 

22.8.8.1 

Preparation of Ducts 

Each duct shall be air-pressure tested prior to the installation of the prestressing steel into the ducts. 
If leaks are indicated during the test, the duct shall be repaired to eliminate the leakage or minimize 
the consequences of the leakage. 

All ducts shall be clean and free of deleterious materials that would impair bonding or interfere with 
grouting procedures. 

Ducts with concrete walls, or cored ducts, shall be flushed to ensure that the concrete is thoroughly 
wetted. Metal ducts shall be flushed, if necessary, to remove deleterious material. 

Water used for flushing ducts may contain slack lime or calcium hydroxide, or quicklime (or calcium 
oxide, in the amount of 0.012 kg/L. 

After flushing, all water shall be blown out of the duct with oil-free compressed air. 

22.8.8.2 

Equipment 

Grouting  equipment  shall  include  a  high-speed  shear  mixer  capable  of  continuous  mechanical 
mixing,  which  will  produce  a  grout  free  of  lumps  and  undispersed  cement;  a  storage  reservoir;  a 
grout pump with all the necessary connection hoses, valves, measuring devices for water, cement 
and  admixtures  and  testing  equipment;  and  stand-by  flushing  equipment  with  water  supply.  The 
equipment shall pump the mixed grout in a manner that will comply with all requirements. 

Accessory equipment that will provide for accurate solid and liquid measures shall be provided to 
batch all materials. 

The mixing equipment shall be capable of producing a grout of homogeneous consistency and shall 
be capable of providing a continuous supply to the injection equipment. 

The capacity of the equipment shall be such that the duct can be filled and vented without interruption 
and at the required rate of injection. 

The injection equipment shall be capable of continuous operation with little variation of pressure and 
shall include a system for recirculating the grout while actual grouting is not in progress. 

The equipment shall have a constant delivery pressure of less than 1 MPa, it shall be equipped with 
a pressure gauge and shall prevent pressures above 2 MPa. The pressure gage shall be placed at 
some  point  in the grout  line  between  the  pump  outlet  and the  duct  inlet. Pumps shall  have  seals 
adequate to prevent introduction of oil, air, or other foreign substance into the grout, and to prevent 
loss of grout or water. All piping to the grout pump shall have a minimum number of bends, valves 
and changes in diameter and shall incorporate a sampling Tee with stop cock. 

The equipment shall be capable of maintaining pressure on completely grouted ducts and shall be 
fitted with a valve that can be locked off without loss of pressure in the duct. 

Grouting equipment shall contain a screen having clear openings of 3.35 mm maximum size to filter 
the grout prior to its introduction into the grout pump. If a grout with a thixotropic additive is used, a 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-33 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

screen opening of 4.75 mm is satisfactory. This screen shall be easily accessible for inspection and 
cleaning. 

Grouting equipment shall utilise gravity feed to the pump inlet from a hopper attached to and directly 
over it. Hoppers must be kept at least partially full of grout at all times during the pumping operation 
to prevent air from being drawn into the post-tensioning duct. 

Under  normal  conditions,  the  grouting  equipment  shall  be  capable  of  continuously  grouting  the 
largest tendon on the Project in no more than 20 min. 

During the grouting operation, the Contractor shall provide adequate flushing-out plant to facilitate 
complete  removal  of  the  grout  in  the  event  of  a  breakdown  of  the  grouting  equipment  or  other 
disruption  before  the  grouting  operation  has  been  completed  and  shall  demonstrate  that  this 
equipment is in full working order. 

All equipment shall be kept free from build-up of adhering materials by washing as required. 

22.8.8.3 

Batching and Mixing of Grout 

All materials shall be batched by weight except the mixing water and liquid admixtures which may 
be batched by weight or volume. The accuracy of batching shall be: 

  ± 2% for cement and admixtures 

  ± 1% for mixing water 

of the quantities specified. The mixing water shall include the water content of liquid admixtures. 

Depending upon environmental or materials influence (e.g. temperature, configuration of the tendon 
and properties of the cement used), the water/cement ratio shall be kept as low as possible having 
regard to the required plastic properties of the grout. 

The maximum w/c ratio shall be 0.40. The material shall be mixed to produce a homogeneous grout 
and kept in slow continuous agitation until pumped into the duct. Water shall be added to the mixer 
first, followed by the cement and admixtures. The batch quantities of cement and admixture may be 
added as a whole or in part in sequence until the total quantities are added. The minimum mixing 
time determined from grouting trials shall be adhered to. 

The temperature of freshly mixed grout shall be between 5°C and 25°C. 

Grout shall be mixed in accordance with the manufacturer's instructions using a colloidal mixer to 
obtain homogeneous mixture. A fluidity test shall be performed on the mixed grout prior to beginning 
the injection process. Target flow rates, as a function of mixer type used and ambient temperatures, 
shall be obtained from the grout manufacturer. The grouting process shall not be started until the 
proper grout properties have been obtained. 

Mixing shall be of such duration as to obtain a uniform, thoroughly blended grout, without excessive 
temperature increase or loss of expansive properties of the admixture. Grout shall be continuously 
agitated until it is pumped. 

Water shall not be added to increase grout flow, which has been decreased by delayed use of the 
grout. 

22.8.8.4 

Injection of Grout 

Grouting  operations  shall  be  carried  out  by  operatives  with  appropriate  knowledge,  training  and 
proven experience in carrying out similar operations and certified under an approved scheme. 

A check shall be made to ensure the ducts, vents, inlets and outlets are capable of accepting injection 
of the grout. This shall be done by blowing through the system with dry, oil-free air and proving each 
vent in turn. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-34 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

Where there is water in the duct, it shall be removed through outlets at the lowest points. Dry, oil-
free compressed air may be used for this purpose. 

Grouting of the ducts shall be carried out as soon as is practicable after the tendons in the ducts 
have been stressed and the Engineer's written agreement to commence has been obtained. All grout 
vents shall be opened before grouting starts. Injection and ejection vents with positive shut-offs shall 
be  provided.  Grout  shall  be  allowed  to flow from  the first  injection  vent  until  any  residual flushing 
water or entrapped air has been removed prior to closing that vent. Remaining vents shall be closed 
in sequence in the same manner. Injection shall be continuous, and it shall be slow enough to avoid 
producing segregation of the grout. Unless otherwise agreed by the Engineer, grout injection shall 
be at the rate of between 10 and 15 metres of duct per minute as per CEB-FIP Model Code1990.  

Pumping  pressure  at  the  injection  vent  should  not  exceed  1  MPa.  Normal  operations  shall  be 
performed at approximately 0.5 MPa. If the actual grouting pressure exceeds the maximum allowed, 
the injection vent shall be closed and the grout shall be injected at the next vent that has been, or is 
ready  to  be,  closed;  as  long  as  a  one-way  flow  is  maintained.  Grout  shall  not  be  injected  into  a 
succeeding vent from which grout has not yet flowed. 

The method of injecting grout shall ensure complete filling of the ducts and complete surrounding of 
the  steel.  Grout  shall  be  allowed  to  flow  from  each  vent  and  the  free  end  of  the  duct  until  its 
consistency is equivalent to that of the grout injected and no visible slugs of water or air are ejected. 
Following  this,  a  further  5  litres  at  each  vent  shall  be  vented  into  a  clean  receptacle,  tested  in 
accordance with Article 22.8.8.12 and then discarded. The opening shall be firmly closed. All vents 
shall  be  closed  in  a  similar  manner  one  after  another  in  the  direction  of  the  flow  except  that  at 
intermediate crests the vents 400mm downstream shall be closed before their associated crest vent. 

The  injection  tubes  shall  then  be  sealed  off  under  pressure.  A  pressure  of  0.5  MPa  shall  be 
maintained for at least one minute. 

Grout vents at high points shall be reopened 10 minutes after completion of grouting and any escape 
of air, water or grout recorded and reported immediately to the Engineer. A further pumping of grout 
may be required at this stage to expel bleed water and/or entrapped air. This shall be carried out 
with only the high points open one at a time sequentially in the direction of grouting. 

The filled ducts shall not be subjected to shock or vibration within 24 hours of grouting. 

Not less than 48 hours after grouting, the level of grout in the injection and the vent tubes shall be 
inspected, all defective grout shall be removed from the vent and the level topped up as necessary 
with freshly mixed grout. 

Not  less  than  48  hours  after  grouting,  the  end  caps  at  anchorages  shall  be  removed  and  a 
photographic record taken, clearly identified. 

If, in the opinion of the Engineer, there is cause for doubt that the ducts are completely filled with 
grout, the Engineer may require non-destructive testing to be carried out. 

The Contractor shall keep full records of grouting for each duct including the date each duct was 
grouted,  the  proportion  of  the  grout  and  any  admixtures  used,  the  pressure,  details  of  any 
interruptions  and  topping  up  required,  and  the  records  shall  be  in  accordance  with  the 
recommendations  of  the  certification  scheme.  Copies  of  these  records  shall  be  supplied  to  the 
Engineer within 24 hours of grouting. 

Grout vents shall be positively sealed to be waterproof on completion of grouting so as to maintain 
the encapsulation to the tendons by a means separate from the concrete waterproofing. 

The fluidity test shall be performed on each tendon in accordance with Article 22.8.8.12, measuring 
the grout fluidity from the discharge outlet. Measured grout efflux times shall not be faster than the 
efflux  time measured  at the  inlet  or the  minimum  efflux  time  established  in  Article 22.7.2.3. If  the 
grout efflux time is not acceptable, additional grout shall be discharged from the discharge outlet. 
Grout efflux time shall be tested. This cycle shall continue until acceptable grout fluidity is achieved. 

S

TANDARD 

C

ONSTRUCTION SPECIFICATIONS

 

 

PART 

2

 

 

R

OAD 

S

TRUCTURES

 

 

 

Page 22-35 

C

HAPTER 

22:

 

P

RESTRESSING 

S

YSTEMS

 

 

First Edition -January 2018 

 

To ensure that the tendon remains filled with grout, the ejection and injection vents shall be closed 
in sequence, respectively, under pressure when the tendon duct is completely filled with grout. The 
positive shut-offs at the injection and ejection vents shall not be removed or vents opened until the 
grout has set. 

22.8.8.5 

Grouting During Adverse Weather 

a. 

Hot Weather 

Grouting in conditions where the shade air temperature exceeds 30

o

 C will only be permitted when 

the Contractor's proposals for ensuring that the grout quality will not be impaired have been accepted 
by the Engineer. 

During  hot  weather,  the  Contractor  shall  ensure  that  the  constituent  materials  of  the  grout  are 
sufficiently  cool  to  prevent  the grout from  stiffening  in  the  interval  between  its  discharge from the 
mixer  and compaction in its final position. Cement  shall not be allowed to come into contact with 
water at a temperature greater than 40°C. 

Notwithstanding the above recommendations grouting shall not be carried out when the shade air 
temperature exceeds 40° C or during "ghibli" conditions. 

b. 

Cold Weather 

When the ambient temperature may be expected to fall below 5°C, accurate temperature records 
shall be kept covering maximum and minimum air temperatures, and temperatures of the structures 
adjacent to the ducts to be grouted.  

No grout shall be placed when the temperature of the structure adjacent to the ducts is below 5°C, 
or  is likely to fall below  5°C during the following 48 hours, unless the member is heated so as to 
maintain the temperature of the placed grout above 5°C for at least 48 hours. Methods of heating 
shall be to the approval of the Engineer. 

Ducts shall not be warmed with steam. 

22.8.8.6 

Vertical Grouting 

In  lieu  of  a  positive  shut-off,  vertical  or  near  vertical  tendon  ducts  for  grouting  shall  terminate  in 
reservoirs at the upper-most point. The reservoir shall have sufficient capacity to store excess grout 
and bleed water. Visible grout levels shall be maintained in the reservoirs, which shall be maintained 
until the grout has set.  

Grout shall be injected at a rate of 5 m of duct per minute. 

22.8.8.7 

Post-grouting Inspection 

Vacuum  grouting  shall  be  used  to  fill  any  voids  that  expose  strands  discovered  in  the  grouting 
process. 

Where  possible,  all  anchorages  and  high-point  vents  shall  be  drilled  and  probed  48  hours  after 
grouting, until the Engineer is assured that no bleed water or subsidence, such as settlement, voids 
exist. After the Engineer is assured that voids do not exist, only one or two anchorages per span 
shall  be  drilled  and  probed  to  ensure  quality  grouting.  Any  voids  discovered  should  be  filled 
immediately with the approved grout. 

22.8.8.8 

Finishing 

The following requirements apply: 

a.  Valves, caps, and vent pipes shall not be removed or opened until the grout has set. 

 

 

 

 

 

 

 