ISSA TEST NO. 

DESCRIPTION 

SPECIFICATION 

 

@ 30 Minutes Minimum (Set) 

12 kg-cm Minimum 

 

@ 60 Minutes Minimum 

(Traffic) 

20 kg-cm or Near Spin Minimum 

ISSA TB-100 

Wet-Track Abrasion Loss 

 

 

One-hour Soak 

540 g/m

2

 Maximum 

 

Six-day Soak 

800 g/m

2

 Maximum 

ISSA TB-147 

Lateral Displacement 

5% Maximum 

 

Specify Gravity after 1,000 

Cycles of 55 kg 

2.10 Maximum 

 

 

 

ISSA TB-109 

Excess Asphalt by LWT Sand 

Adhesion 

540 g/m

2

 Maximum 

ISSA TB-144 

Classification Compatibility 

11 Grade Points Minimum (AAA, BBA) 

*ISSA 

– International Slurry Surfacing Association  

3.5.2.4  Composition of Mixture  

The Owner shall approve the design mix and all Micro Surfacing materials and methods prior to use 
and shall designate the proportions to be used within the following limits: 

  Residual Asphalt: 5.5% to 10.5% by dry weight of aggregate 

  Mineral Filler: 0% to 3% by dry weight of aggregate 

  Polymer Based Modifier: Shall be a minimum of 3% solids content 

  Water (Potable): As required to provide proper consistency 

3.5.2.5  Construction Requirements 

a.  Equipment 

The machine shall be specifically designed and manufactured to apply Micro Surfacing. The material 
shall be mixed by an automatic-sequenced, self-propelled Micro Surfacing mixing machine. It shall 
be  a  continuous-flow  mixing  unit  that  accurately  delivers  and  proportions  the  mix  components 
through  a  revolving  multi-blade,  double-shafted  mixer.  Sufficient  storage  capacity  for  all  mix 
components is required to maintain an adequate supply to the proportioning controls. 

When specifying continuous machinery to minimize transverse joints, the specified machine must be 
capable of loading materials while continuing to apply Micro Surfacing. The continuous-run machine 
shall be equipped to provide the operator with full control of the forward and reverse speeds during 
application. It shall be equipped with opposite-side driver stations to assist in alignment. The self-
loading  device,  opposite-side  driver  stations,  and  forward  and  reverse  speed  controls  shall  be  of 
original-equipment-manufacturer design. 

b.  Spreading Equipment 

The mixture shall be agitated and spread uniformly in the surfacing box by means of twin shafted 
paddles or spiral augers fixed in the spreader box. A front seal shall be provided to insure no loss of 
the  mixture  at  the  road  contact  point.  The  rear  seal  shall  act  as  a  final  strike-off  and  shall  be 
adjustable. The spreader box and rear strike-off shall be so designed and operated that a uniform 
consistency is achieved and a free flow of material is provided to the rear strike-off. The spreader 
box  shall  have  suitable  means  provided  to  side  shift  the  box  to  compensate  for  variations  in  the 
pavement geometry. 

Each mixing unit to be used in the performance of the work shall be calibrated in the presence of the 
Engineer  prior  to  the  start  of  the  project.  Previous  calibration  documentation  covering  the  exact 
materials  to  be  used  may  be  acceptable,  provided  that  no  more  than  60  days  have  lapsed.  The 
documentation shall include an individual calibration of each material at various settings that can be 
related  to  the  machine  metering  devices.  Any  component  replacement  affecting  material 
proportioning requires that the machine be recalibrated. No machine will be allowed to work on the 
project until the calibration has been completed and/or accepted. ISSA Inspector’s Manual describes 
a method of machine calibration. ISSA contractors and/or machine manufacturers may also provide 
methods of machine calibration. 

d.  Lines

Care shall be taken to insure straight lines along kerbs and shoulders. No runoff on these areas will 
be permitted. Lines at intersections shall be kept straight to provide a good appearance. 

e.  Handwork

Approved hand squeegees, with burlap drags, shall be used to spread Micro Surfacing in areas not 
accessible  to  the  Micro  Surfacing  spreader  box.  Care  shall  be  exercised  in  leaving  no  unsightly 
appearance from handwork. 

f.  Curing

Areas receiving Micro Surfacing will be allowed to cure from one to three hours or until the treated 
pavement will not be damaged by traffic. The Contractor will protect the area with suitable barricades 
or markers for the full curing period. Areas which are damaged within 24 hours of application of Micro 
Surfacing,  or  prior  to  moving  to  new  work  locations,  shall  be  repaired  by  the  Contractor  at  his 
expense. 

g.  Surface Preparation

Immediately prior to applying the Micro Surfacing, the surface shall be cleared of all loose material, 
oil  spots,  vegetation  and  other  objectionable  material.  Any  standard  cleaning  method  will  be 
acceptable.  If  water  is  used,  cracks  shall  be  allowed  to  dry  thoroughly  before  Micro  Surfacing. 
Manholes, valve boxes, drop inlets and other service entrances shall be protected from the Micro 
Surfacing  by  a  suitable  method.  The  Engineer  shall  approve  the  surface  preparation  prior  to 
surfacing. 

h.  Weather Limitations

Micro  surfacing  shall  not  be  applied  if  either  the  pavement  or  air  temperature  is  below  10°C  and 
falling, but may be applied when both pavement and air temperatures are above 7°C and rising. No 
Micro Surfacing shall be applied when there is the possibility of freezing temperatures at the project 
location within 24 hours after application. The Micro Surfacing shall not be applied when weather 
conditions prolong opening to traffic beyond a reasonable time. 

i.  Notification

All homeowners and businesses affected by the paving shall be notified 24 hours in advance of the 
surfacing. Suitable tow-away signs may be posted prior to the surfacing. Should work not occur on 
the specified day, a new notification will be distributed. The notification shall be in a form of written 
posting, stating the time and date that the surfacing will take place. 

j.  Traffic Control

Suitable methods shall be used by the contractor to protect the Micro Surfacing from damage from 
all  types  of  vehicular  traffic.  Opening  to  traffic  does  not  constitute  acceptance  of  the  work.  The 
Engineer shall be notified of the methods to be used. In areas that are subject to an increased rate 
of  sharp-turning  vehicles,  additional  time  may  be  required for  a  more  complete  cure  of  the  Micro 

k.  Clean Up

All areas, such as man-ways, gutters and intersections, shall have the Micro Surfacing removed as 
specified by the Engineer. The Contractor shall remove any debris associated with the performance 
of the work on a daily basis. 

3.6  Miscellaneous Pavement Items 

3.6.1 Coloured Bituminous Pavement 

3.6.1.1  Description 

This work  consists of supplying and applying coloured bituminous pavement surfaces  of the type 
and  colour  as  shown  in  the  Contract  plans  or  as  included  in  the  Particular  Specifications.    This 
Specification provides the requirements for the following types of coloured pavement: 

1.  Coloured  bituminous  paving  final  top  course,  where  the  colour  additives  are  added  to  the

bituminous mixture at time of mixing in the batch plant. 

2.  Colour additives included in the emulsified asphalt used for surface treatment.

3.  Coloured surface coatings.

3.6.1.2  Materials 

a.  Contractor Submittals

Contractor shall prepare and submit to the Engineer for approval trial pavement samples of the type 
and colours as shown on the  Contract plans or as included in the Particular  Specifications.  Trial 
sample sizes, numbers and methods shall be agreed with the Engineer prior to preparation which 
may require a full size trial section for final approval by the Owner.   

For coloured bituminous paving final course and surface treatments the submittal shall include the 
pigment  manufacturers  name,  pigment  name  and  number  and  details  of  the  final  mix,  stipulating 
where this mix deviates from the approved wearing course final layer bituminous pavement mix or 
surface treatment materials.  Details shall include such items as quantity of the pigment added and 
mixing  time,  any  use  of  clear  asphalt,  any  use  of  coloured  aggregate,  and  associated  details  as 
needed to supply a consistent and Owner accepted coloured pavement surfacing. 

The Contractor submittals for coloured surface coatings shall meet the requirements of Article 8.2.2.8 
of Chapter 8, Traffic Marking and Signs, of these Standard Specifications. 

b.  Bituminous Mixes

Materials for coloured top course bituminous mixes shall meet the applicable requirements in Section 
3.3.2 with the addition of a pigment (colorant) that is usually added at the time of the asphalt mixing 
in  a  powder  or  pelletized  form.    Replacement  of  the  bitumen  binder  with  a  clear  binder  or  the 
aggregate  with  coloured  aggregate  may  be  necessary  to  achieve  the  require  colour  tint.    Such 
replacement shall be done with materials of similar properties as otherwise specified and approved 
by the Engineer.  Application rates of the pigment and mixing requirements shall be made as per the 
initial suggestions of the pigment supplier or manufacture, and then adjusted as necessary to meet 
the final approved colour tint, as approved by the Engineer. 

Materials  for  coloured  surface  treatments  shall  meet  the  requirements  of  Article  3.5.1.2  with  the 
addition of an approved colour pigment pre-mixed with the bitumen prior to application.  Replacement 
of the bitumen binder with a clear binder or the aggregate with coloured aggregate may be necessary 
to achieve the require colour tint.  Such replacement shall be done with materials of similar properties 

 

 

 

as  otherwise  specified  and  approved  by  the  Engineer.    Application  rates  of  the  pigment  to  the 
bitumen shall be made as per the initial suggestions of the pigment supplier  or manufacture, and 
then adjusted as necessary to meet the final approved colour tint, as approved by the Engineer. 

c.  Coloured Surface Coatings 

Materials for coloured surface coatings shall meet the requirements of Article 8.2 of Chapter 8, Traffic 
Marking and Signs, of these Standard Specifications. 

3.6.1.3  Construction Requirements 

Installation  of  coloured  top  course  bituminous  pavement  shall  meet  the  requirements  of  Section 
3.3.3.  Installation of coloured bituminous surface treatment shall meet the requirements of  Article 
3.5.1.4.  Installation of coloured epoxy surface coatings shall meet the requirements of Section 8.2 
of Chapter 8, Traffic Marking and Signs, of these Standard Specifications.  

3.6.2 Speed humps 

3.6.2.1  Description 

 Work consists of construction of speed humps, or installation of temporary speed humps, as shown 
in the Contract plans, specified in the Particular Specifications, and as approved by the Engineer. 

3.6.2.2  Materials 

a.  Asphalt Concrete 

Asphalt concrete shall meet the requirements of either Sub-article a) of Article 3.3.2.5 or Paragraph 
of Sub-article b of Article 3.3.2.5 as defined for wearing course layers for hot mix asphalt. 

b.  Tack Coat 

Tack coat shall meet the requirements of Article 3.4.3.2. 

c.  Temporary Speed Humps 

Temporary speed humps to be provided by the Contractor shall be new prefabricated rubber product 
in  accordance  with  traffic  calming  safety  standards  and  specifications  outlined  by  Institute  of 
Transportation Engineers (ITE), that are capable of being removed and reinstalled numerous times 
without  showing  signs  of  excessive  wear  and  tear.    Type  of  temporary  speed  humps  shall  be  as 
shown on the Contract plans or described in the Particular Specifications, and as approved by the 
Engineer. 

d.  Striping 

Striping  for  speed  humps  shall  be  white  plastic  preformed  permanent  pavement  marking  tape 
material  meeting  the  requirements  of  Article  8.2.2.11  or  a  white  Thermoplastic  marking  material 
meeting  the  requirements  of  Article  8.2.2.5,  or  of  type  as  shown  on  the  Contract  plans  and  as 
approved by the Engineer .   

Temporary  speed  humps  will  normally  be  pre-striped  by  the  manufacture,  and  if  not,  the  striping 
material shall meet the requirements of this Specification Section. 

e.  Signing 

Signing  for  speed  humps  shall  be  the  type  and  size  shown  on  the  Contract  plans  meeting  the 
applicable  requirements  of  Section  9.5,  of  Chapter  9,  Traffic  Control  System,  of  these  Standard 
Specifications. 

 

 

 

3.6.2.3  Construction Requirements 

a.  General 

Contractor  shall  submit  a  method  statement  to  the  Engineer  for  approval  prior  to  the  start  of 
construction  of  speed  humps.    Method  statement  shall  include  schedule,  timing,  construction 
methods and details including type and number of equipment to be used, material to be used with 
the necessary material approval submittals, and detailed traffic management plan. 

If construction of speed humps is on existing streets where no other construction work having traffic 
detours is already in place, Contractor shall apply for and provide to the Engineer proof of acceptance 
that the necessary street traffic closure has been approved by the concerned authorities.  Closures 
shall be temporary, with work performed during the day and the street reopened to traffic by the end 
of the normal work day,  all as approved by the Engineer. 

Speed humps shall be constructed at the locations and to the shapes and configurations shown in 
the Contract plans.  Speed humps are to be constructed of asphalt top (wearing) course, across and 
60 cm narrower than width of existing pavement, leaving 30 cm wide open area between outer most 
edge of speed hump and pavement edge for drainage purposes.  

Use any method necessary to form parabolic shape and to achieve proper height of speed hump. 
One such proven method for forming a parabolic shape of speed hump is to construct template from 
minimum 5 m long wooden board, with centre portion of bottom of template cut into basic parabolic 
shape of speed hump, leaving 60 cm flat area at each end of template. To stiffen template and to 
minimize  any  bending  of  template,  attach  aluminium  or  steel  channel  section  to  top  portion  of 
template.  

After initial placement of asphalt (before compaction and while asphalt is still fresh and pliant) form 
asphalt  surface  into  basic  parabolic  shape  using  template.    With  flat  ends  of  template  resting  on 
abutting pavement surface, drag or shimmy template across asphalt surface forming basic parabolic 
shape of speed hump. During compaction it may be necessary to remove excess asphalt material, 
or place additional asphalt material. Repeat template operation until speed hump is fully compacted 
and has achieved its proper height and shape.  

Do not perform final rolling operation until required parabolic shape of each speed hump has been 
approved by the Engineer 

Pavement markings and striping are to be installed per the layout and configurations shown on the 
Contract plans and per the requirements included in Section 8.2.3 of Chapter 8, Pavement Marking 
and Signs, for the respective approved striping materials.  Signing shall be installed as shown on the 
Contract plans and per the appropriate signing types as included in Section 9.5.3 of Chapter 9, Traffic 
Control System, of these Standard Specifications. 

b.   Installation of Speed Humps on Existing Pavement 

Construct keyway 60 cm wide in shape of speed hump and across existing pavement where speed 
hump is to be installed. Keyway is to be constructed by saw cutting existing pavement minimum of 
38 mm deep along outer most edge of speed hump, then milling on bias to 0 mm at inner edge of 
keyway. Thoroughly clean pavement surface, and apply tack coat making sure to completely cover 
surface area. Tack coat must be applied before placement of any new asphalt material, and between 
any and all subsequent asphalt courses. 

c.  Installation  of  Speed  Humps  as  Part  of  New  Pavement  Laying  or  Pavement 

Resurfacing Work 

Finish paving street with asphalt top course up to outer most limits of speed hump before constructing 
speed hump. Take extra steps to ensure that portion of asphalt top course placed within 30 cm wide 
open area between outer most edges of speed hump and pavement edge is properly compacted. 
Speed hump is to be constructed on top of the asphaltic base course. Thoroughly clean pavement 
surface,  and  apply  tack  coat  making  sure  to  completely  cover  surface  area.  Tack  coat  must  be 

If Contractor elects to, or inadvertently, paves the entire street without making allowances for speed 
hump  construction,  speed  hump  is  to  be  constructed  in  accordance  with  Sub-article  b  of  Article 
3.6.2.3. 

d.  Installation of Temporary Speed Humps

Speed hump warning signs are to be installed minimum of 10 calendar days in advance of installation 
of temporary speed humps.  Speed hump warning signs are to be installed on sign posts at each 
temporary  speed  hump  location.    Speed  hump  warning  signs  are  to  be  covered  until  temporary 
speed humps have been installed.  

Temporary speed hump is to be installed across and 60  centimetre shorter than width of existing 
pavement,  leaving  30  centimetre  wide  open  area  between  outer  most  edge  of  temporary  speed 
hump  and  pavement  edge  for  drainage  purposes.  Prior  to  installation  of  temporary  speed  hump, 
existing pavement area is to be thoroughly cleaned. Installation of temporary speed humps is to be 
in  accordance  with  manufacturer’s  instructions.  Maintain  temporary  speed  humps,  making  any 
adjustments  or  re-installation  necessary  to  ensure  that  temporary  speed  humps  remain  properly 
situated.  

If temporary speed humps do not come pre-striped, pavement markings are to be installed using 
methods described in Sub-article a) of Article 3.6.2.3. 

For Owner supplied speed humps, Contractor shall obtain the temporary speed humps including all 
appurtenances and mounting hardware from the Owners stores and otherwise install as required in 
this  Specification  Section.    Contractor  shall  supply  any  additional  mounting  equipment,  hardware 
and bonding agent as may be needed to properly install the Owner supplied temporary speed humps 
as recommended by the manufacturer. 

Contractor shall remove any temporary speed humps and hardware when directed by the Engineer 
within the project limits, permanently restore existing pavement, filling in all holes necessitated for 
installation of temporary speed hump anchoring system.  

Removed temporary speed humps will remain the property of the Contractor to be removed from the 
site, except where required in the Contract Documents that they remain the property of the Owner. 
Contractor shall protect, package and deliver to Owner store yards as directed by the Engineer, all 
temporary speed humps and hardware that are to remain the property of the Owner.  Any materials 
to remain the property of the Owner, that are damaged beyond repair, are to be replaced with new 
materials. 

3.6.3   Sand asphalt for foot path 

3.6.3.1  Introduction 

When bituminous materials are being applied, the surface of all structures, foot path, wheel guards, 
guard rail, kerbs and gutters, and other, roadway appurtenances shall be protected in an approved 
manner to prevent them from being splattered with bituminous material. The contractor shall at his 
own expense, remove all the trace of bituminous material, and repaired all the damage, and leave 
the appurtenance in an approved condition. 

3.6.3.2  Material and Mix Design 

a.  Aggregate

Aggregate should be crushed rock or gravel. Aggregate gradation for sand asphalt concrete is shown 
in the following table: 

Table 3-47:  Sand Asphalt Gradation 

Percent passing by weight 

9.5 

100 

4.75 

80 

– 100 

2.36 

65 

– 100 

1.18 

40 

– 80 

0.600 

25 

– 65 

0.300 

– 40 

0.150 

– 20 

0.075 

– 10 

Asphalt Binder by weight of total mix 

– 12 % 

b.  Bitumen grade

The binder shall be normal black bitumen (penetration grade 40 

– 50) 

c.  Design criteria

Marshall Method of mix design (Asphalt Institute Manual series MS 

– 2) will be used in designing the 

asphaltic concrete mix. The contractor proposed mix design shall be cross checked prior to approval. 

The mix design for the sand asphalt shall be as follows:    

Table 3-48:  Sand Asphalt Mix requirements 

3.6.3.3  Construction Requirements 

a.  Laying of sand asphalt

The sand asphalt shall be laid by paving machine unless otherwise approved by the Engineer. 

b.  Trial area

The  contractor  shall  prepare  trial  area  2  meter  wide  by  10  meter  long  as  part  of  acceptance 
procedure of the mix.  

c.  Weather limitation for paving operations

  Hot bituminous mix shall be placed when weather is not dusty, fogy, or rainy and when the

existing surface is free from moisture. Bituminous mix shall not be placed during sand storms. 

 

Prime and tack coat should only be applied when ambient temperature 16˚C.

  No paving operation shall be started if rain is imminent.

Properties 

Sand Asphalt Mix 

Marshall Stability (kgf) 

900 Min 

Flow (mm) 

– 5 

Percentage air voids (VIM) 

– 18 

Design Binder Content 

– 12 

3.6.4.1  Scope 

This specification provides the minimum requirements for the inclusion of recycled asphalt 
pavement to replace a percentage of the raw materials in new hot mix asphalt. 

3.6.4.2  Description 

Recycled asphalt pavement (RAP) shall consist of a blend of clean, hard, durable crushed 
rock, sand, filler and bitumen which is available from pavement rehabilitation or rejected and 
surplus asphalt production. 

It generally comprises 3 to 5% bitumen by mass with the balance generally consisting of 
clean hard durable aggregate. RAP is used as aggregate and bitumen in new asphalt 
pavement layers.  

RAP is typically recovered by milling or excavating existing asphalt pavements or as waste 
from asphalt production. RAP that is recovered by milling or as plant waste is generally clean 
RAP with no contaminants. RAP that is recovered to full depth by conventional excavation 
can become contaminated during the removal process and is not normally suitable for reuse 
in new asphalt. 

3.6.4.3  Materials 

a.  Stockpile Management Plan

The contractor/supplier shall prepare a Stockpile management plan for the RAP to ensure a 
consistent quality product is achieved. The management plan shall be submitted to the 
Engineer for acceptance, before the RAP can be used on the project  

The Stockpile Management Plan shall detail the stockpiling, processing, storage and testing 
requirements of each Lot and should be in place at each RAP processing / storage facility.  

Each stockpile shall be defined as a Lot to ensure traceability. 

b.  Processing and Storage

1. 

RAP shall be maintained in a separate stockpile prior to processing for use in asphalt.
RAP shall be crushed and screened so that the maximum aggregate size is not greater 
than the aggregate size of the asphalt mix being produced. The processed RAP shall 
be a well-graded, free-flowing and consistent product.  Where the stored RAP is not 
free flowing it shall be screened and/or crushed again. 

2. 

Processed RAP shall be stored in conical or longitudinal stockpiles. Processed RAP
must not be agglomerated or be allowed to congeal in large stockpiles. 

c.  Unacceptable Materials

1. 

The contactor shall ensure that RAP delivered to the stockpiles is devoid of
construction contaminants including amongst others, crushed gravel, timber, concrete 
and other building waste.  

2. 

RAP shall be free of tar and/or asbestos.

3. 

RAP shall be free from any metal contamination.

d.  Sources of Materials

The contractor shall distinguish the RAP sources as either combined or single source RAP. 

RAP that is won from a single source by milling shall be stockpiled individually to ensure it 
remains uncontaminated. Testing shall be carried out as indicated to determine the 
representative properties of the stockpile. 

Combined source RAP 

RAP that is combined from different projects should be blended to construct a uniform 
stockpile prior to additional processing including crushing, screening or fractionating.  Testing 
of the blended samples is required to determine the representative properties and variability 
of the RAP.  

e.  Moisture Management

The RAP stockpile areas shall be well drained and laid to falls to prevent build-up of 
moisture. The contractor shall take adequate precautions to keep the stockpile dry to ensure 
that unnecessary moisture is not incorporated into the mix. 

The moisture of the hot mix asphalt produced shall not exceed 0.5% by dry mass 
immediately after manufacture.  

The moisture of the completed asphalt layer shall not exceed 0.30% by dry mass when cores 
are extracted using dry ice coring (for bit cooling). 

f. Quantity of RAP to be Included

RAP may be added to the mix so that the contribution of the RAP binder does not exceed 
15% of the mix design binder content by mass.  

3.6.4.4  Physical Requirements 

RAP aggregate after extraction of bitumen shall conform to the physical requirements 
described in the following sections of the Standard Construction Specifications: 

 

Superpave mix design materials: Paragraph 1 of Sub-article a of Article 3.3.2.5; OR

 

Marshall mix design materials: Paragraph 4 of Sub-article b of Article 3.3.2.5

3.6.4.5  Minimum Testing Requirements of RAP 

Characterisation testing shall be carried out on completed stockpiles to determine the 
stockpile characteristics as listed in Table 5-1 below. Samples shall be taken from at least 
ten random locations around the stockpile. The individual samples from different parts of the 
stockpile shall not be combined, as tests need to be performed on individual samples to 
assess uniformity. A minimum of ten samples is required to allow statistical analysis of the 
stockpile.   

For continuously replenished stockpiles the stockpile sampling regime shall be continued at a 
frequency of one per 1,000 tons of RAP. 

Table 3: Minimum Testing Requirements for Static Stockpiles 

Test 

Method 

Frequency 

Gradation 

AASHTO T30 

1 per 1000 tons (min 10) 

Asphalt binder content 

AASHTO T164 

1 per 1000 tons (min 10) 

Bulk specific gravity 

AASHTO T308 then 

1 per 1000 tons (min 10) 

Method 

Frequency 

AASTHO T84 and T85 

Aggregate properties1  

See  Standard  Construction 
Specifications  

1 per 5000 tons (min 2) 

Moisture content 

AASHTO T110-03 

3 per 1000 tons (min 2) 

Foreign material 

Table 3-14 Standard 
Construction Specifications 

1 per 5000 tons (min 2) 

Aggregate properties evaluation testing includes: 

  Los Angeles abrasion

  Magnesium sulfate soundness loss of coarse and fine aggregate

  Sodium sulphate soundness

  Fractured faces

  Fine aggregate angularity

  Flat and elongated particles, 3 to 1 ratio

  Flakiness

  Abrasion loss

  Sand equivalent value

  Water absorption of coarse aggregate

a.  Environmental Testing

The contactor or stockpile owner shall take a representative sample of every 10,000 tons of 
unprocessed RAP and conduct a Toxicity Characteristic Leaching Procedure (TCLP) test to 
analyse the specific contamination concentration (SCC) and the leachable concentrations for 
the following pollutants: 

 

Polycyclic aromatic hydrocarbons(PAHs); and

 

Heavy Metals: Barium, Cadmium, Chromium, Lead, Nickel, Arsenic, and Mercury.

The testing will be undertaken by a laboratory approved by Abu Dhabi Quality and 
Conformity Council (ADQCC) or accredited with Emirates Standardisation and Metrology 
Authority (ESMA). 

The results will be compared against the 

Threshold Values for Specific Contaminant and 

Leachable Concentrations

 listed in Annex 1 of the Environment Agency Abu Dhabi (EAD) 

2016, 

Waste Classification Technical Guideline

 (EAD-EQ-PR-TGD-01). 

If contaminants of interest reported SCC and TCLP concentrations below threshold limits, the 
material will be congruent with being non-hazardous waste, which once milled will become a 
reusable construction product.  

3.6.4.6  Acceptance of RAP 

a.  Statistical Evaluation

The Contractor shall summarise the results of the testing in a spreadsheet which includes the 
stockpile name/description and date of sampling and submitted with the job-mix formula. The 

 

 

 

spreadsheet shall calculate the average and standard deviation for each property. The 
allowable variation for key properties is shown in Table 3.  

b.  Exceedance of Statistical Deviation 

Where the standard deviation exceeds the maximum allowable standard deviation the 
material source shall be rejected until such time as additional processing improves the 
variability to within the allowable limit.   

c.  Acceptance Criteria for RAP 

The Contractor shall ensure that the processed RAP complies with the maximum standard 
deviation limits in Table 3. 

Table 3: RAP Stockpile Maximum Variability 

RAP Property 

Maximum  Standard  Deviation 
(%) 

AASHTO Test Methods 

Asphalt Binder Content 

0.5 

T 164 

%  Passing  Median  Sieve 
(2mm) 

5.0 

T-30 

% Passing 0.075 mm Sieve 

1.5 

T-30 

Bulk specific gravity (Gsb) 

±50 kg /m3 

T 84 and T 85 

 

3.6.4.7  Mix Design Requirements 

A separate job-mix design shall be prepared for each RAP stockpile. The average asphalt 
binder content, gradation and specific gravity of the nominated RAP stockpile shall be used 
in the mix design. 

Grading and Marshall characteristics of the mixture shall be in compliance with the Standard 
Construction Specifications Part- 1- Roads. 

The procedure outlined in the latest edition of Asphalt Institute MS-2 under sub title 
"Recycled Asphalt Materials in the Mix Design Process" shall be used for laboratory mix 
design.  

a.  Plant mix trials 

  Trial mixes shall be carried out by manufacturing small quantities in the plant at three 

different binder contents, targeting the optimum binder content found in the laboratory mix, 
as well as at bitumen contents 0.2% above and below the optimum. 

  The results of tests on these trial mixes shall be examined, to identify any shift in properties 

between mixes produced in the laboratory compared to those manufactured full-scale.  

  The Contractor shall make final adjustments to the plant to ensure the job mix properties 

obtained from laboratory testing are achieved.  

  The Contractor shall check the moisture content of the final product to ensure that the mix 

complies with maximum moisture requirements. 

a.  RAP Cold Feed

The Contractor shall provide a separate cold feed bin for each RAP stockpile required by the 
mix design. The cold feed bins shall be equipped with accurate mechanical means for 
feeding the aggregate uniformly into the plant in the proportions required for the finished mix 
to maintain uniform production and temperature. Oversized RAP shall be prevented from 
being incorporated into the completed mixture by the use of a grizzly or grid over the RAP 
bin; in-line roller or impact crusher; screen; or other suitable means. If oversized RAP 
material appears in the completed recycled mix, the appropriate corrective action shall be 
taken immediately. 

During asphalt production the recycled mix shall be sampled and tested daily as summarised 
in Table 3. Where testing indicates that the recycled mix fails to meet the job-mix formula 
within the tolerances specified plant operations shall be stopped.  

b.  RAP Heating and Blending

RAP shall be heated through indirect heat only with no exposure of the RAP to naked flame. 

c.  Production Testing

The contractor shall carry out production testing as scheduled in the Standard Construction 
Specifications and as specified in Table 3. 

Table 3 Production Testing 

Test 

AASHTO Method 

Frequency 

Tolerances 

Retained  4.75  mm 
sieve and larger 

T 30 

1 per day 

± 5.0 % 

Passing  4.75  mm 
and  retained  75  mm 
sieves 

T 30 

1 per day 

± 4.0 % 

Passing 75 mm sieve  T 30 

1 per day 

± 1.5 % 

Asphalt 

binder 

content 

T 164 

1 per day 

± 0.2 % 

Moisture content 

T 110-03 

2 per day 

<0.15% 

3.7  Bituminous Pavement Repairs 

3.7.1 Description 

This work consists of performing all operations and furnishing all materials, labor, tools, equipment 
and appurtenances that may be required for the various pavement repair items.  This work is required 
to  correct  structural  failures,  grade  elevations,  drainage  and  deterioration  and/or  to  prepare  the 
existing pavement surface prior to placing asphaltic concrete overlays or seal coats  as shown on 
the Contract plans, as specified herein and/or in the particular specifications and included in the bills 
of quantities.  

The materials required for the various pavement repair items shall be as specified and shall be in 
accordance with the requirements of Sections 3.3 through 3.5.  

3.7.3 Construction Requirements 

3.7.3.1  Equipment 

Contractor shall be responsible to supply all the equipment and labor necessary to perform the work 
described for the various types of pavement repair items in accordance with these specifications and 
as directed by the Engineer.  Major equipment shall conform to Sub-article (a) of Article 3.2.2.3. 

3.7.3.2  Pavement Repair Types 

a.  Repair  of  Potholes  (isolated holes in asphaltic concrete pavements  of less than

one square meter) using hot asphalt mixture 

Contractor shall perform the following: 

1.  Saw  cut  the  failed  pavement  0.3  to  1.0  meter  beyond  the  perimeter  of  the  failed  area  as

directed by the Engineer.  Make the cut square or rectangular with faces straight and vertical. 
One pair of faces shall be at right angles to the direction of traffic 

2.  Remove and dispose the cut pavement and loose unsuitable material in compliance with the

requirements  of  Section  2.3.2  of  Chapter  2,  Earthworks,  of  these  Standard  Specifications 
and as directed by the Engineer. 

3.  If base material is removed, fill the excavat

ion with a Gradation ‘C’ (sand-gravel), which has

been premixed to optimum moisture content.  Place the material in 150 mm lifts and compact 
each  lift  to  at  least  95  %  modified  Proctor  density  (AASHTO  T  180)  with  mechanical 
compactors; same treatment is to be applied to subgrade before filling the excavation with 
sand-gravel 

4.  Wire broom clean the cut edges of the pavement and paint with bituminous emulsion

5.  Prime the compacted soil or the upper surface of the sand-gravel with a light coating of MC-

70 when directed by the Engineer.  Place Type II wearing course of hot asphaltic concrete 
mix with minimum thickness as the existing pavement and compact in lifts not exceeding 70 
mm to the same level as the adjacent surface. Vibratory compactors shall be used to compact 
the hot asphalt concrete 

6.  Check level of the patch with a straight edge and make corrections as required

b.    Repair  of  potholes  (Isolated  holes  in  asphaltic  concrete  pavement)  Using  Cold
Emulsion Asphalt Mixtures 

1. 

Description

This work shall consist of performing all operations and furnishing all materials, labour, tools, 
and equipment that may be required for the asphalt pavement repair of potholes and similar 
works. This work shall be performed during any season of the year and as specified herein 
or as directed by the Engineer. 

2. Materials

The materials of the cold mixture are obtained by blending dense crushed fine and coarse 
aggregate,  bitumen  emulsion  with  bio  oil  to  give  the  mixture  the  required  workability.  The 
mixture  shall  be  a  homogeneous  distribution  of the  binder  on the aggregate  and  provides 
excellent coating properties, easy, long lasting workability, and good immediate mechanical 
performance. The grading and binder content of this mixture shall be as follows: 

 

 

 

Property 

                               Ranges 

Percent Passing 2.0mm 

                             30 to 50 

                   Percent Passing 0.08mm 

                              4 to 8 

          Residual binder content, ppc 

                               4-6 

 

The mixture is manufactured in cold mix plant or by using mixers adapted to the quantities 
manufactured. The mixture shall be a storable cold mix ready for use, available in bags ideal 
for roadway maintenance work and shall have certification from ADQCC or Equivalent. 

 

3. Mixture Performance 

      The cold mixture shall have the following properties: 

 Test Characteristics  

 Test Method 

  Specification 

Marshall Stability  

AASHTO T245 

       Min 500 kg f 

Marshall Flow 

AASHTO T245 

         1-3 mm 

Stiffness 

Stability/Flow 

          250kgf/mm 

Loss of Marshall 

stability  

 

Submerging 

specimens in water at 

60 C for 24 hours as 

compared to stability 

measured after 

submersion in water at 

60 C for 30 minutes 

(max. % loss) 

 

            30% 

 

4

. Construction Requirements 

i. Equipment 

Contractor  shall  be  responsible  to  supply  all  the  equipment  and  labour  necessary  to                
perform the work described for patching potholes in accordance with these specifications and 
as directed by the Engineer. 

ii. Repair of potholes  

             Contractor shall perform the following: 

  Clean  the  cavity  by  removing  any  water  present  and  all  unbound  items  

(fines, stones, topsoil, etc.) to ensure good adhesion of the asphalt mix to the support. 

  place  cold  asphalt  mixture manually  into the  cavity  by  distributing  evenly in  layers. 

Establish an additional thickness on the surface. 

 

 

 

  Compact  with  a  hand-held  tamper  or  a  vibrating  plate  for  larger  areas.  A  small 

cylinder, used in either smooth or vibrating mode, is also suitable. This operation is 
essential to accelerate the increase in cohesion and sealing of cold asphalt mixture 
and to ensure waterproofing of the surface. 

  If the level of the repaired area after compaction is lower than that of the road, scarify 

the  already  compacted  surface  and  add  the  emulsion  cold  mixture,  and  compact 
again. The level of the repaired area must be the same as that of the pavement. 

  After  compaction,  the  cold  asphalt  mixture  shall  provide  a  closed  surface,  limiting 

rainwater seepage into repaired potholes. 

  A  primer  is  recommended  when  the  fill  thickness  is  thin,  or  when  the  ambient 

temperature is low 

iii. Re-open the road to traffic immediately after compaction is completed 

iv. During traffic, any sticking of asphalt emulsion cold mixture to vehicle tires can be 
avoided by a light surface sanding 

 

c.  Repair of Failed Pavement (deep patch) 

Contractor shall perform the following: 

1.  Saw cut the failed pavement 1 meter beyond the perimeter of the failed area as directed by 

the Engineer. Make the cut square or rectangular with faces straight and each asphalt layer 
stepped back from the one below it by a step width at least equal to the layer thickness.  One 
pair of faces shall be at right angles to the direction of traffic 

2.  Remove the cut pavement and excavate the underlying soil to a depth of not less than 300 

mm.    Engineer  may,  when  deemed  necessary,  order  substantially  greater  depths  of 
excavation payable at daily works schedule rates.  Remove and dispose the cut pavement 
and loose unsuitable material in compliance with the requirements of Section 2.3.2 of Chapter 
2, Earthworks, of these Standard Specifications and as directed by the Engineer. 

3.  Thoroughly  compact  the  subgrade  soil  with  mechanical  compactors  to  at  least  95  %  of 

modified Proctor density 

4.  Place aggregate 

base course meeting Gradation ‘B’, which has been premixed to optimum 

moisture content to the bottom of asphalt concrete.   Place the material in 150 mm lifts and 
compact each lift to at least 95 % modified Proctor density (AASHTO T 180) with mechanical 
compactors; same treatment is to be applied to subgrade before filling the excavation with 
sand-gravel 

5.  Wire broom clean the cut edges of the pavement and paint with bituminous emulsion 

6.  Lightly prime the compacted sand-gravel with MC-70 when directed by the Engineer 

7.  Place and compact a Type II wearing course of asphaltic concrete in the excavation in 70 

mm lifts to the same level as the adjacent surface. Thoroughly and uniformly compact the 
pavement by rolling.  Lower lift shall be compacted with a vibratory compactor and the top lift 
shall be compacted with a steel wheel roller by first compacting the hot asphaltic concrete 
150 mm from the two traffic edges and then by rolling in the direction of traffic.  Drive wheel 
of the roller shall be in a forward position.  Use of an asphaltic concrete pavement finisher 
will depend on the size of the area being patched. 

 

 

 

 

 

 

d.  Repair of Depressed Pavement (skin patch) 

In cases where the pavement has depressed but the asphaltic concrete has not fractured and the 
pavement appears stable, the Contractor shall perform the following: 

1.  Mill the upper 50 mm of the pavement starting just in back of the depression.  Dispose the 

milling  in  accordance  with  the  requirements  of  Section  2.3.2  of  Chapter  2,  Earthworks,  of 
these Standard Specifications and as directed by the Engineer. 

2.  Wire broom clean the surface and lightly tack the surface and paint the edges of the cut with 

bituminous emulsion at the rate of 0.25 to 0.50 kg/m

2

 of tack coat as shown on the Contract 

plans or as directed by the Engineer. 

3.  Place wearing course hot mix asphaltic concrete and compact with a steel wheel roller by 

first compacting the hot asphaltic concrete 150 mm from the two traffic edges and then by 
rolling in the direction of traffic. Drive wheel of the roller shall be in the forward position. 

4.  Check the level of the patch with a straight edge and make corrections as required. 

e.  Repair of Utility Cuts (open pavement and depressed pavement)   

Contractor shall perform the following: 

1.  In cases where the asphaltic concrete pavement is broken or cracked: 

i.  Saw  cut  the  pavement  1  m  beyond  the  perimeter  of  the  failed  area.  Make  the  cut 

rectangular with faces straight and each asphalt layer stepped back from the one below 
it  by  step  width  at  least  equal  to  the  layer  thickness.    One  pair  of  faces  shall  be 
approximately parallel to the utility cut. 

ii.  Remove the cut pavement and excavate the underlying soil to a depth of not less than 

300 mm.  Engineer may, when deemed necessary, order substantially greater depths 
of excavation payable at daily works schedule rates.  Dispose the excavated material 
in accordance with the requirements of Section 2.3.2 of Chapter 2, Earthworks, of these 
Standard Specifications and as directed by the Engineer. 

iii.  Thoroughly  compact  the  subsoil  with  mechanical  compactors  to  at  least  95  %  of 

modified Proctor density. 

iv.  If base material is removed, fill the excavati

on with a Gradation ‘B’ (table 3-6 of clause 

3.2.2), which has been premixed to optimum moisture content.  Place the material in 
150 mm lifts and compact each lift to at least 95 % modified Proctor density (AASHTO 
T 180) with mechanical compactors; same treatment is to be applied to subgrade before 
filling the excavation with sand-gravel. 

v.  Wire broom clean the cut edges of the pavement and paint with bituminous emulsion. 

vi.  Prime the compacted sand-gravel with a light coating of MC-70 when directed by the 

Engineer. 

vii.  Place wearing course of asphaltic concrete in the excavation in 70 mm lifts to the same 

level  as  the  adjacent  surface.  Thoroughly  and  uniformly  compact  the  pavement  by 
rolling.  Lower lift shall be compacted with a vibratory compactor and the top lift shall 
be compacted with a steel wheel roller by first compacting the hot asphaltic concrete 
150 mm from the two traffic edges and then by rolling in the direction of traffic.  Drive 
wheel of the roller shall be in a forward position.  Use of an asphaltic concrete pavement 
finisher will depend on the size of the area being patched.  Use of a vibratory compactor 
on the top lift shall be only with the approval of the Engineer. 

viii.  A vibratory plate compactor shall be used to compact the hot asphaltic concrete against 

kerbing and inlets, catch basins or gullies. 

 

 

 

 

 

 

 

 

 