ix.  Check the level of the patch with a straight edge and make corrections as required. 

2.  In cases where the utility cut has been patched and the patch is depressed but the pavement 

is not fractured and the asphaltic concrete appears stable, perform the following: 

i.  Mill  and  remove  the  upper  30  mm  of  the  pavement  starting  just  in  back  of  the 

depression.  Dispose of the removed pavement in accordance with the requirements 
of  Section  2.3.2  of  Chapter  2,  Earthworks,  of  these  Standard  Specifications  and  as 
directed by the Engineer. 

ii.  Wire broom clean the surface and lightly tack the surface and paint the edges of the 

cut with bituminous emulsion at the rate of 0.25 to 0.50 kg/m

2

 of tack coat as shown on 

the Contract plans or as directed by the Engineer. 

iii.  Place wearing course of asphaltic concrete in the excavation in 70 mm lifts to the same 

level  as  the  adjacent  surface.  Thoroughly  and  uniformly  compact  the  pavement  by 
rolling with a steel wheel roller  by first compacting the hot asphalt concrete 150 mm 
from the two traffic edges and then by rolling in the direction of traffic.  Drive wheel of 
the roller shall be in a forward position 

iv.  Check the level of the patch with a straight edge and make corrections as required. 

f.  Sealing Cracks in Asphaltic Concrete Pavement   

Depending on the type & nature of Cracks, appropriate method shall be applied to seal the cracks 
with approved sealant which, as a minimum, shall comply with requirements specified herein. The 
contractor shall be required to carry out a thorough site investigation identifying the exact location of 
different type of cracks and shall submit to the Engineer for his approval, full details of the proposed 
crack  sealant  along  with  manufactures  brochure,  a  method  statement  &  a  track  record  of 
performance of the product  in UAE or  under similar  climatic condition. Acceptance of the sealant 
shall  be  subject  to  satisfactory  site trials.  The  manufacturer  shall  provide  a  guarantee  letter  for  a 
minimum  of  5  years  performance  when  the  material  is  applied  on  site  as  per  his  recommended 
method  statement.  The  applicator  shall  have  adequate  experience  and  be  familiar  with  the 
application process of the product as recommended by the manufacturer.  

This sealant shall be hot pourable, polymer modified bituminous binder with the characteristics of 
good adhesion, high ductility with high elastic recovery and shall meet the following requirements: 

                

Test 

Specification 

Test method designation 

Cone Penetration @ 25 °C 

45 dmm max. 

ASTM D 

– 5329 

Softening point, °C, min 

99 min. 

ASTM D 

– 36 

Ductility @ 25 °C, min 

30 cm. min. 

ASTM D 

– 113 

Resilience @ 25 °C, 

30% min. 

ASTM D 

– 5329 

Flow @ 60 °C 

3 mm max. 

ASTM D 

– 5329 

Viscosity  

100 poise max. 

Brookfield Viscometer 

Note:  Manufacturer's  recommendation  shall  be  followed  for  cleaning  of  the  cracks  as  well  as 
preparation & application of sealant. However a general requirement is outlined hereunder.  

- Cracks shall be thoroughly cleaned by hot air compressor. 

-  The  sealant  shall  be  heated  in  a  pre-heater  unit  provided  with  agitation  paddles  to  the 
recommended temperature. 

 

 

 

- The heated material shall be transferred to a bucket & hand drawn screed box or a specialized 
applicator having a direct connecting pressure hose type extruding device with nozzles shaped for 
insertion into the pre-warmed crack. Manufacturer's recommended temperature for application shall 
be maintained. 

- Where instructed by the Engineer the crack shall be chased out using a mechanical router and the 
hole shall be cleaned free of all dust, dirt, and dampness by the use of hot compressed air lances 
prior to the application of the heated sealant. 

- Every attempt shall be made to avoid application of excess sealant. However, if any, the surface 
shall be scrapped to avoid formation of ridges & the sealant being picked up by the traffic.    

- It is to be noted that any crack sealant other than those specified above can be proposed by the 
Contractor for Engineers review and consideration. Following site trial if the material appears to serve 
the purpose for which it is intended the Engineer with Client’s concern may approve the material on 
condition that a five (5) years performance guarantee provided by the manufacturer is endorsed by 
the main Contractor.  

g.  Restoration of Kerbing 

Contractor shall perform the following: 

1.  Remove pavement and tiles adjacent to the kerbing and break the mortar joint between the 

sound kerbstone and the kerbstones to be removed or reset. 

2.  Remove  all  broken  and  loose  kerbstones  and  rubble  and  chisel  off  the  mortar  from  the 

exposed edges of the sound kerbstones. 

3.  Excavate the soil in back of the kerb to the depth of the kerb foundation. 

4.  Clean and reinstate the kerb foundation as required.  This may require raising a maximum 

height of 150 mm.  If so, the contractor shall raise the foundation using Class C15 concrete, 
unreinforced, mixed with maximum aggregate size of 19 mm and formed the same width as 
the existing foundation and to the required height.  No separate payment will be made by the 
department for this work.  

5.  Wet the kerb foundation and set and grout the replacement kerbstones to proper alignment 

allowing 10 mm for mortar joints and 10 mm for expansion joints. 

6.  Wet the joints and fill with a cement and sand mortar of 1:2 mix, clean, point and cure with a 

liquid curing compound as directed by the Engineer. 

7.  Fill the expansion joints with bituminous preformed joint filler conforming to AASHTO M-33. 

8.  Form  and  cast  a  100  x  150  mm  Portland  cement  concrete  toe  against  the  front  of  the 

kerbstone using a Class C15 unreinforced concrete, mixed with maximum aggregate size of 
19 mm.  Cure with a liquid curing compound and as directed by the Engineer. 

9.  Cast a 200 x 200 mm Portland cement concrete haunching of Class C15 concrete to the back 

of the kerbstone and cure it with a liquid curing compound as directed by the Engineer. 

10. Expansion joints shall be constructed each 10 meters in the new kerbing and in between new 

or reset kerbstone and existing kerbstone. 

11. Strip all forms from the concrete and fill the excavation in back of the kerbstone with soil to a 

depth 100 mm below the top of the kerbstone. 

12. Paint bituminous emulsion on the face of the concrete and kerbstone which will be in contact 

with the asphaltic concrete. 

13. Reinstate the asphaltic concrete pavement and tiles adjacent to the repair. 

 

 

 

h.  Restoration of Sidewalk Tiles 

Contractor  shall  restore  all  sidewalk  tiles  removed,  damaged  or  otherwise  disturbed  by  his 
construction operations. Unless otherwise directed by the Engineer, such tile shall be restored on a 
base and shall match existing adjacent surfaces. 

Where  existing  concrete  sidewalk  tiles  are  to  be  restored,  and  unless  otherwise  directed  by  the 
Engineer, the sidewalk tiles shall be installed as follows: 

1.  Remove carefully the existing sidewalk tiles, clean, chisel off the mortar from the exposed 

faces, protect, load, transport and unload the sound and unbroken tiles at a location approved 
by the Engineer.  Removal of the existing tiles shall be by hand, so as to preserve the tiles; 
cart away and dispose of the remainder of the tiles at a location approved by the Engineer.  
Break, remove and cart away the mortar or any base, including concrete base laid below the 
tiles, to the approved location. 

2.  Excavate  the  foundation  soil  to  a  depth  of  50  mm.    Dispose  the  excavated  material  at  a 

location approved by the  Engineer.  Level, sprinkle with water, fill as required to bring the 
level of the soil to the required depth below the top level of the new tiles.  In the event fill is 
required, add water too.  Turnover and mix the soil thoroughly.  Compaction operations shall 
achieve a minimum of 90 % of the standard Proctor (AASHTO T 99) density.  Contractor shall 
take into consideration that the leveling of the natural ground surface shall be done according 
to the proposed grades and slopes.  Any objectionable material and unsuitable soil shall be 
removed from the site and disposed of by the Contractor in accordance with the requirements 
of Section 2.3.2 of Chapter 2, Earthworks, of these Standard Specifications or as directed by 
the Engineer. 

3.  A layer of clean sand, average thickness 80 mm, shall be spread and water shall be added 

in order to obtain the proper grades and levels before placing the concrete tiles. 

4.  Precast concrete tiles shall be placed directly on the sand layer without using any cement 

mortar. 

5.  In placing concrete tiles, care must be exercised so that no spaces shall be left between tiles.  

Sides of tiles shall be touching each other as closely as possible. 

6.  Tiles shall be secured in place using light compactors in order to achieve the proposed levels 

and grades. 

7.  A thin layer of sand shall be utilized as filler between tiles.  Water shall be sprayed to flush 

the sand into the voids. 

8.  Placing  of  tiles  shall  be  carried  out  in  lengths  not  exceeding  10  meters  separated  by 

expansion joints according to the instructions of the Engineer.  Expansion joint filler shall be 
10 mm thick bituminous preformed joint filler conforming to AASHTO M-33. 

9.  Concrete tiles shall be placed in a proper pattern, no tiles or any part thereof shall be cast in-

situ. 

10. An additional or substitute pattern, if needed, may be used for laying tiles only after a written 

approval from the Engineer is obtained by the Contractor. 

11. Where existing quarry tile sidewalks are to be restored, and unless otherwise directed by the 

Engineer, the sidewalk tiles shall be reinstated to original condition. 

12. Where other types of existing sidewalks are to be restored, and unless otherwise directed by 

the Engineer, the installation shall be as specified in these specifications. 

i.  Adjust,  or  Demolish  and  Reconstruct  Existing  Inlets,  Manholes,  or  Service 

Facilities to New Pavement Elevations 

Contractor shall adjust, or demolish and reconstruct to finished pavement grade or level all existing 
service facilities including, but not by way of limitation, all utility or service vaults, valve boxes, inlets, 
manholes, jointing boxes, sewerage house connection service chambers used as restaurant grease 

 

 

 

traps and similar structures within the limits of the Contract as specified herein and as directed by 
the Engineer or as required by the respective utility agency.  Contractor shall perform the work per 
the following: 

1.  Adjust existing inlets, manholes or service facilities to new pavement elevation:  At locations 

where there is a minor level difference between the new pavement elevation and the cover 
level of existing inlets, manholes or service facilities, the Contractor shall adjust these existing 
facilities  to the  cover  grade  and  level matching the  new  pavement  level and  slopes.   This 
work consists of, but is not limited to, the removal of frames and covers, placing or removal 
of  minor  amounts  of  concrete  and  reinforcement  as  necessary  to  raise  or  lower  the  inlet, 
manhole or service facility to match new pavement levels and slopes, refixing the frames and 
covers and all associated works, except the supply of covers and frames, as specified herein, 
as per the following items:   

i.  Contractor shall reuse the removed covers and frames unless otherwise directed by the 

Engineer.  If the  Contractor is required to replace the existing cover and frame with a 
new cover and frame,  separate measurement and payment will be made as specified 
herein for the items, remove and transport the existing cover and frame and replace with 
new covers and frames. 

ii.  When an existing utility manhole requires level adjustment, prior to commencement of 

the  works  specified  herein,  the  Contractor  shall  contact  the  applicable  utility  authority 
and request their field supervision and approval for the work.  Contractor shall provide 
necessary temporary protection as approved by the utility authority and the Engineer to 
insure safety of existing utility lines while executing the works specified herein. 

iii.  Contractor shall perform the following items: 

a)  Submit shop drawings for approval by the Engineer prior to start of the work, which 

show  how  the  Contractor  intends  to  proceed  with  the  work  for  each  site  including 
traffic routing.  The shop drawing shall also indicate the existing structure portion and 
how  the  height  is  to  be  adjusted  showing  additional  height  construction  details 
including  the  portion  to  be  removed,  reinforcement,  construction  joints,  frame  and 
cover  type,  attachment  method  for  the  frame,  and  pavement  base  replacement 
method around the chambers. 

b)  Barricade the immediate work site to protect workmen and motorists without closing 

the entire roadway lane to traffic. 

c)  Cut and remove sufficient asphalt pavement and concrete from the edges of the inlet 

frame or manhole to permit removal of the frame from the gully or manhole without 
damaging the reinforcing steel and cart away and dispose of the rubble in accordance 
with the requirements of Section 2.3.2 of Chapter 2, Earthworks, of these Standard 
Specifications and as directed by the Engineer. 

d)  Position the frame of the inlet, manhole or other service facility at the proper elevation 

and  cast  it  in  place  with  Class  C25  concrete  using  Type  V  Portland  cement  with 
additives approved by the Engineer to accelerate the set of the concrete.  All concrete 
and  reinforcement  for  the  work  shall  comply  with  the  requirements  of  Chapter  4, 
Concrete works, and Chapter 5, Reinforcing Steel, of these Standard Specifications. 

e)  Paint the exposed concrete surface with bituminous emulsion after the initial set but 

never later than twenty minutes after placing the concrete.  Curing period shall be as 
approved by the Engineer 

f)  Clean the inside of the inlet or manhole and replace the inlet grate or manhole cover 

2.  Demolish  and  reconstruct  existing  inlets,  manholes  or  service  facilities  to  new  pavement 

elevation:  At locations where the level difference between the new pavement level and the 
covers  for  existing  inlets,  manholes  or  service  facilities  is  beyond  the  scope  of  minor 
adjustments  and  requires  major  level  adjustment,  the  contractor  shall  demolish  and 
reconstruct these facilities to match the new pavement level and slopes. Respective utility 

 

 

 

owner and the Engineer will determine, on site, the requirement to demolish and reconstruct 
the existing inlet, manhole or service facility.  Contractor shall perform the work as follows: 

i.  Demolition  of  existing  inlets,  manholes  or  other  service  facilities  shall  meet  the 

requirements of Section 2.3.2 of Chapter 2, Earthworks, of these Standard Specifications 
and as directed by the Engineer.  New inlets, manholes, or other service facilities at these 
locations shall be similar to those demolished unless otherwise directed by the Engineer 
or  required  by  the  utility  owner.    Shop  drawings  for  the  construction  of  new  inlets, 
manholes  and  service  facilities  shall  include  all  details  necessary  to  construct  these 
proposed items.  Shop drawings for utility manholes will be approved by applicable utility 
authority. 

ii.  Contractor shall reuse the removed cover and frame for the reconstruction work unless 

otherwise directed by the Engineer.  If the Contractor is required to use a new cover and 
frame, separate measurement and payment will be made as specified herein under the 
items, remove and transport the existing cover and frame and replace with new cover 
and frame. 

iii.  Contractor  shall  construct the  new  inlets,  manholes  or  service facilities in  accordance 

with all applicable requirements as specified herein to adjust the top levels of these items 
including, but not limited to, the reuse of covers and frames, and the submittal of shop 
drawings indicating the proposed construction materials and procedures for approval by 
the utility owner. 

3.  Remove and transport existing covers and frames and replace with new covers and frames 

for inlets, manholes and service facilities in pedestrian areas.  When covers and frames for 
existing inlets, manholes or service facilities in pedestrian areas, except for sewerage house 
connection chambers, require replacement with new covers and frames, the Contractor shall 
furnish new medium duty ductile iron covers and frames with appropriate service description.  
Engineer and the respective utility owner will determine, on site, the requirement to replace 
the existing covers and frames with new ones. When an existing sewerage house connection 
chamber used as a restaurant grease trap requires a new cover, the Contractor shall furnish 
a new lightweight ductile iron cover and inner GRP cover as shown on the Contract plans.  
Medium  duty  and  light  weight  ductile  iron  covers  and  frames  shall  comply  with  the 
requirements of and be of the type as described in Section 12.3.2 of Chapter 12, Storm water 
Drainage, or as shown on the Contract plans or as directed by the Engineer.  Contractor shall 
clean, load, transport unload and place in store yard where designated by the Engineer all 
removed covers and frames. 

4.  Remove and transport existing covers and frames and replace with new covers and frames 

for inlets, manholes and service facilities in traffic areas:  When covers and frames for existing 
or reconstructed inlets, manholes or service facilities in traffic areas such as service roads 
parking  areas  and  main  roads,  require  replacement  with  new  covers  and  frames,  the 
Contractor  shall furnish new  heavy  duty  ductile  iron  covers  and  frames.  Engineer  and  the 
respective utility owner will determine, on site, the requirement to replace the existing covers 
and frames with new ones.  Heavy duty ductile iron covers and frames shall comply with the 
requirements of and be the type as described in Section 12.3.2 of Chapter 12, Storm water 
Drainage,  or  as  shown  on  the  drawings  or  as  directed  by  the  Engineer.    Contractor  shall 
clean,  load,  transport,  unload  and  place  all  removed  covers  and  frames  in  a  store  yard 
designated by the Engineer. 

3.8  Portland Cement Concrete Pavement 

3.8.1 Description   

This  Work  shall  consist  of  furnishing  concrete  mix,  transporting,  and  constructing  jointed  plain 
concrete pavement on a prepared base course in accordance with the specifications, in conformity 
with the lines, grades, thickness and typical cross-sections shown on the plans or established by the 
Engineer and included in the bills of quantities. 

 

 

 

This  work  also  includes  pavement  rehabilitation  consisting  of  full-depth,  full-width  removal  and 
reconstruction of rigid pavement.   

3.8.2 Materials 

Concrete  pavement  shall  meet the  material  requirements  as  specified  herein.    Concrete  pavement 
shall  meet  the  composition  requirements  shown  in  Table  3-49.  All  Portland  cement  concrete 
pavements shall incorporate 1000 g/m

3

 of approved polypropylene fiber in the concrete mix to avoid 

the risk of shrinkage cracking. 

Table 3-494:  Rigid pavement composition 

Water/cement 

ratio (maximum) 

Temperature 

of concrete 

Slump 

Air content 

(%) 

Aggregate 

size 

(AASHTO M 

43) 

28-day compressive 

strength 

(minimum) 

0.45 

20 ±10 º C 

40 ±20 mm 

2 max. 

No. 57 or 67 

45 mPa 

3.8.2.1  Aggregates 

Aggregates shall meet the applicable requirements of Section 4.3.7 of Chapter 4, Concrete Works, 
and the following: 

a.  Reactivity.    Aggregate  shall  be  free  of  substances  that  are  deleteriously  reactive  with  the 

alkalies in the cement in an amount sufficient to cause excessive expansion of the concrete.  
Acceptable aggregate shall be based on satisfactory evidence furnished by the Contractor 
that the aggregate is free from such materials.  This evidence shall include service records 
of  concrete  of  comparable  properties  under  similar  conditions  of  exposure  and/or  certified 
records of tests by a testing laboratory that meets the requirements of ASTM C1077.  Tests 
shall  be  made  in  accordance  with  ASTM  C295  and    ASTM  C1260  as  required  to  insure 
reactivity is not present. 

b.  Fine Aggregate.  Fine aggregate shall conform to the requirements of ASTM C33 and with 

additional  requirements  as  modified  acceptance  criteria  specified  in  project  specification.  
Gradation shall meet the requirements of Table 3-50 when tested in accordance with ASTM 
C136. Dust and other coating shall be removed from the aggregates by washing or suitable 
means. 

Table 3-50:  Gradation for fine aggregate 

Sieve designation (square openings) 

Percentage by weight passing sieves 

9.5 mm 

4.75 mm 

2.36 mm 

1.18 mm 

600 µm 

300 µm 

150 µm) 

100 

95-100 

80-100 

50-85 

25-60 

10-30 

2-10 

c.  Coarse  aggregate:.    Coarse  aggregate  shall  conform  to  the  requirements  of  ASTM  C33.  

Gradation, within the separated size groups, shall meet the requirements of Table 3-51. when 
tested in accordance with ASTM C136.  When the nominal maximum size of the aggregate 
is greater than 25 mm, the aggregates shall be furnished in two size groups.   

i. 

Aggregates delivered to the mixer shall consist of crushed stone, crushed or uncrushed 
gravel,  air-cooled  blast  furnace  slag.    Aggregate  shall  be  composed  of  clean,  hard, 

 

 

 

uncoated particles and shall meet the requirements for deleterious substances contained 
in ASTM C33, Class 4S and the additional requirements as modified acceptance criteria 
specified  in  project  specification.    Dust  and  other  coating  shall  be  removed  from  the 
aggregates by washing.  Aggregate in any size group shall not contain more than 15 % by 
weight of flat or elongated pieces when tested in accordance with ASTM D4791.  A flat or 
elongated  particle  is  one  having  a  ratio  between  the  maximum  and  the  minimum 
dimensions of a circumscribing rectangular prism exceeding 3 to 1. 

ii. 

Percentage  of  wear  shall  be  no  more  than  40  percent  when  tested  in  accordance  with 
ASTM C131 or ASTM C535. 

Table 3-51:  Gradation for coarse aggregate per ASTM C33 

Sieve Designations 

(square openings) 

From 50.8 mm to 4.75 mm  

% by weight passing sieves 

Mm 

50.8 mm-25.4 mm 

25.4 mm-4.75 mm 

63 

50.8 

38.1 

25.0 

19.0 

12.5 

9.5 

4.75 

2.36 

--- 

90-100 

35-70 

0-15 

--- 

0-5 

--- 

--- 

--- 

--- 

--- 

100 

95-100 

--- 

25-60 

--- 

0-10 

0-5 

d.  Alternative gradation: Contractor may use the combined aggregate gradation specified in BS 

EN  12620.    Contractor  shall  submit  to  the  Engineer  for  approval  the  combined  aggregate 
gradation, however , in no case shall materials passing 0.075 mm sieve exceed 3 % by weight 
of the combined aggregate.  Changes from gradation to another shall not be made during 
progress of the work unless approved by the Engineer. 

3.8.2.2  Cement and Cement Replacements 

Cement  and  cement  replacements  shall  comply  the  requirements  of  Section  4.3,  of  Chapter  4, 
Concrete Works, and with the following: 

a.  Ordinary portland cement (OPC) 

1.  Conform  to  ASTM  C150  Type I.  Do  not  use  cement  meeting  the  requirements  of  rapid 

hardening portland cement. Use OPC with the heat of hydration not exceeding 325 kJ per 
kg  when  tested  in  accordance  with  ASTM  C186.  Do  not  use  OPC  with  the  tricalcium-
aluminate  (C3A)  content  less  than  4  %  by  weight  as  tested  in  accordance  with  ASTM 
C114. 

2. 

If necessary because of potential silica reactivity concerns, use “low alkali” OPC as defined 
in ASTM C150 

3.  Supply the manufacturer's test certification with each delivery of cement that confirms the 

material  complies  with  the  above  requirements  and  submit  not  later  than  the  day  of 
delivery. Engineer may call for tests on each delivery of cement if necessary to establish 
or confirm that the cement meets the above requirements. 

b.  Fly ash or pulverized-fuel ash (PFA): 

1.  Conform  to  ASTM  C618,  Class  F  requirements  including  the  optional  requirements  for 

effectiveness  of  controlling  alkali-silica  reaction  and  sulfate  expansion  in  high  sulfate 
environments. 

 

 

 

2.  Supply  the  manufacturer's  test  certification  with  each  delivery  of  PFA  that  confirms  the 

material  complies  with  the  above  requirements  and  submit  not  later  than  the  day  of 
delivery. Engineer may call for tests on each delivery of PFA if necessary to establish or 
confirm that the cement meets the above requirements. 

c.  Silica Fume (SF): 

1.  Conform  to  ASTM  C1240  including  the  optional  requirements  for  very  high  sulfate 

resistance and, if necessary, the optional requirements for reactivity with cement alkalis 
because of reactive aggregate concerns identified in the petrographic report.  

2.  Engineer  shall  have  the  right  to  call  for  tests  on  each  delivery  of  SF  if  necessary  to 

establish or confirm that the SF meets the above requirements. Engineer may call for tests 
on  each  delivery  of  SF  if  necessary  to  establish  or  confirm  that  the  cement  meets  the 
above requirements. 

3.8.2.3  Premolded Joint Filler 

Premolded joint filler for expansion joints shall conform to the requirements of ASTM D1751 shall be 
punched to admit the dowels where called for on the plans.  Filler for each joint shall be furnished in 
a single piece for the full depth and width required for the joint, unless otherwise specified  by the 
Engineer.  When the use of more than one piece is required for a joint, the abutting ends shall be 
fastened  securely  and  held  accurately  to  shape  by  stapling  or  other  positive  fastening  means 
satisfactory to the Engineer. 

3.8.2.4  Joint Sealer 

Joint  sealer  for  the  joints  in  the  concrete  slab  shall  meet  the  requirements  of  Section  4.3.15  of 
Chapter 4, Concrete Works,  of these Standrad Specifcations and shall be of the type(s) specified in 
the plans. 

3.8.2.5  Steel Reinforcement 

Reinforcing shall consist of plain or deformed steel bars meeting the requirements of Chapter 5 and 
conforming  to  the  requirements  of  ASTM  A615  Grade  60.    Use  epoxy  coating  conforming  to  the 
requirements of AASHTO M 254 

3.8.2.6  Dowel and Tie Bars 

Tie bars shall be deformed steel bars conforming to ASTM A615 Grade 60, unless noted otherwise. 

Dowel bars shall be plain steel bars conforming to ASTM A615 or A616

 

and shall be free from burring 

or other deformation restricting slippage in the concrete.  Use epoxy-coated steel dowels conforming 
to the requirements of AASHTO M 254. 

Sleeves for dowel bars used in expansion joints shall be metal or other type of an approved design 
to cover 50 mm to 75 mm of the dowel, with a closed end and with a suitable stop to hold the end of 
the bar at least 25 mm from the closed end of the sleeve.  Sleeves shall be of such design that they 
will not collapse during construction. 

Dowel and tie bars shall conform to AASHTO M 284M and M 31M or M 42M. Dowels shall be free 
of loose, flaky rust and loose scale and shall be clean and straight. 

3.8.2.7  Admixtures 

Admixtures shall meet the requirements of Section 4.3.6 of Chapter 4, Concrete Works.  Engineer 
shall approve the use of any material added to the concrete mix.  Contractor shall submit certificates 
indicating that the material to be furnished meets all of the requirements indicated below.  In addition, 
the Engineer may require the Contractor to submit complete test data from an approved laboratory 
showing that the material to be furnished meets all of the requirements of the cited specifications.  
Subsequent tests may be made of samples taken by the Engineer from the supply of material being 

 

 

 

furnished or proposed for use on the work to determine whether the admixture is uniform in quality 
with that approved.  Contractor shall also comply with the following: 

1.  Do not use air-entraining admixtures. 

2.  Chemical admixtures.  Water reducing, set retarding, and set accelerating admixtures shall 

meet the requirements of ASTM C494, including the flexural strength test. 

3.8.2.8  Epoxy Resin 

Epoxy-resin used to anchor dowels and tie bars in slabs shall conform to the requirements of ASTM 
C881, Type I, Grade 3, and Class C.  Class A or B shall be used when the surface temperature of 
the hardened concrete is below 16º C. 

3.8.2.9  Material Acceptance 

All materials shall meet the applicable sampling and testing requirements per Section 4.3, of Chapter 
4, Concrete Works, of these Standard Specifications. 

3.8.2.10 

Mix Design 

All concrete mix design, testing and acceptance shall meet the applicable requirements of Section 
4.3.10 of Chapter 4, Concrete Works, of these Standrad Specifications. 

3.8.3 Construction Requirements 

In addition to the requirements listed below, Contractor shall conform to the latest edition of FHWA 
Standard specifications for construction of roads and bridges. 

3.8.3.1  Forms 

Furnish straight, steel forms.  For edge radii less than 60 m, furnish flexible or curved forms.  Conform 
to all the following: 

1.  Depth equal to edge of pavement thickness 

2.  3-meter minimum length 

3.  Stabilizing devices to withstand paving operations 

4.  Joint locks to join form lengths tightly together 

5.  Clean and oil before each use 

3.8.3.2  Paving Equipment 

Contractor shall furnish the paving and finishing equipment applicable to the type of construction as 
follows: 

a.  Slip  form  construction.    Furnish  slip  form  machines  capable  of  spreading,  consolidating, 

screeding,  and  float-finishing  the  freshly-placed  concrete  in  one  complete  pass  of  the 
machine to provide a dense and homogeneous pavement with minimal hand finishing.  Equip 
the paving machine with the following: 

1.  Electronic controls to control line and grade from either or both sides of the machine 

2.  Vibrators to vibrate the concrete for the full width and depth of the strip of pavement being 
placed 

3.  A positive interlock system to stop all vibration and tamping elements when the forward 
motion of the machine is interrupted. 

Operate the  paving machine  with  a continuous  forward movement  and  coordinate mixing, 
delivering, and spreading concrete to provide uniform progress without stopping and starting 

 

 

 

the paving machine.  Apply no tractive force to the machine except that which is controlled 
from the machine. 

b.  Side form construction.  Furnish mechanical, self-propelled spreading and finishing machines 

capable  of  compacting  and  finishing  the  concrete  with  minimal  hand  finishing.    Equip  the 
machine with one 450 mm minimum width screed with compensating springs to minimize the 
effect of the screed's momentum on the side forms, or 2 independently-operated screeds. 

Coordinate the number of  driving wheels, power of  the motor, and the machine's mass to 
prevent slippage.  Any machine that displaces the side forms will not be permitted. 

c.  Vibrators.  Furnish internal immersed tube or multiple spud type vibrators for all paving more 

than  200  mm  thick.    Surface  pan  type  vibrators  are  acceptable  for  full-width  concrete 
consolidation  of  slabs  200  mm  or  less  in  thickness.    Attach  vibrators  to  the  spreader  or 
finishing machine or mount on a separate carriage.  For construction of irregular areas, use 
hand-held vibrators.  

d.  Joint  sealing:    Furnish  sealing  equipment  according  to  the  sealant  manufacturer's 

recommendations. 

e.  Joints  and  concrete  removal:    Furnish  an  adequate  supply  of  concrete  saws  with  sufficient 

power to saw full depth and complete the work with water-cooled, diamond-edged blades or 
abrasive wheels.  Equip saws with blade guards and guides or devices to control alignment 
and depth.  Furnish and maintain standby equipment and an adequate supply of replacement 
blades or wheels. 

f.  Concrete removal:  Furnish concrete saws, drop hammers, hydro hammers, and jack hammers 

to  break  concrete.    Concrete  saws  shall  conform  to  5  above.    Ball  drop  breakers  are  not 
permitted.  Furnish equipment that will not damage the subgrade, subbase, base, or existing 
concrete slabs designated to remain. If new or existing slabs not scheduled for replacement 
are chipped, spalled, or damaged during the removal operations, replace the damaged slabs. 

3.8.3.3  Preparing Surface for Concrete Pavement 

Place base course on top of prepare subgrade meeting the requirements of Section 2.6, of Chapter 2, 
Earthworks, for subgrade preparation.  Type and thickness of base course should match the typical 
cross-sections on the plans. Uniformly dampen the base course before placing the concrete.  If traffic 
is allowed to use the prepared roadbed, check and correct the surface immediately before the concrete 
is placed. 

3.8.3.4  Placing Concrete 

For  storing,  handling,  batching,  and  mixing  material  and  delivering  concrete,  conform  to  the 
requirements of Section 4.3.11 of Chapter 4, Concrete Works, of these Standard Specifications.  

Where a paving machine is impractical, place concrete according to Article 3.8.3.5 

When concrete is placed adjoining a previously-constructed lane of pavement, do not allow mechanical 
equipment to be operated on the existing lane until the lane has attained a minimum flexural strength 
of 3.8 mPa according to AASHTO T 97 or compressive strength of 24 mPa according to AASHTO T 
22.  Protect the previously constructed lane from damage by the paving equipment. 

Install reinforcing steel according to the requirements of Section 5.5, of Chapter 5, Reinforcing Steel. 
Firmly  position  the  reinforcement  on  acceptable  supports  before  placing  the  concrete,  or  after 
spreading, mechanically place or vibrate the reinforcement to the required depth in the plastic concrete. 

3.8.3.5  Construction of Irregular Areas 

In irregular areas or areas inaccessible to paving equipment, construct the pavement using side forms.  
Strike-off, consolidate, float, and surface finish the concrete as follows: 

 

 

 

1.  Thoroughly  and  uniformly  vibrate  and  compact  the  concrete  during  placement  without 

segregating the material 

2.  Using templates or screeds, strike-off the concrete to shape it to the required cross-section 

between the forms.  Carry a slight excess of concrete in front of the leading edge of the template 
or screed 

3.  Float the surface to the required grade and cross-section 

4.  Finish the surface according to Article 3.8.3.7 

3.8.3.6  Joints 

Do not vary longitudinal joints more than 13 mm and transverse joints more than 6 mm from the true 
alignment.  When kerbs or medians are constructed integral with the pavement, construct transverse 
joints continuous through the kerb or median.  Protect all joints from the intrusion of deleterious matter 
until sealed. 

Form isolated joints at structures by placing 25 mm expansion joint filler around each structure that 
extends into or through the pavement before concrete is placed. 

Remove and replace all newly-placed concrete pavements where uncontrolled cracking occurs. 

a.  Longitudinal Joints 

Construct longitudinal joints by forming or sawing.  Construct sawed longitudinal joints (with tie bars) 
when  the  concrete  pavement  placement  width  exceeds  4.5  m.  Construct  the  longitudinal  joint 
continuous with no gaps in either the transverse or longitudinal joints at intersections. 

Place tie bars, as shown in the typical sections, perpendicular to the longitudinal joints with mechanical 
equipment or rigidly secured chairs without damaging or disrupting the concrete.  Do not paint or coat 
tie bars with any material or enclose them in tubes or sleeves. 

Where adjacent lanes of pavement are constructed separately, use slip form paving machines or steel 
side forms to form a keyway along the construction joint.  Tie bars may be bent at right angles against 
the form of the first lane constructed and straightened into final position before placing concrete in the 
adjacent lane.  Repair or replace broken or badly-damaged tie bars. 

Threaded hook bolts may be used instead of tie bars.  Fasten hook bolts to the form of the longitudinal 
construction joint.  With slip form paving, tie bars may be hydraulically inserted through metal keyways. 

1.  Formed  joints.    Form  joints  with  an  approved  nonmetallic  or  removable  device  while  the 

concrete  is  plastic.    When  adjacent  lanes  are  constructed  separately,  form  the  sealant 
reservoir in the lane placed last 

2.  Sawed joints.  After placing concrete, saw joints as soon as equipment can be supported and 

before uncontrolled cracking occurs and it shall be performed within the sawing window.  Do 
not ravel the joints while sawing.  Saw longitudinal joints immediately after sawing transverse 
joints.  Protect the sawed concrete faces from drying during the curing period.  If necessary, 
continue  sawing  day  and  night, regardless  of  weather conditions.   Clean  the  saw  cut  and 
adjacent concrete surface of slurry residue after sawing each joint. 

i.  Do  not  saw  a  joint  if  a  crack  occurs  at  or  near  the  joint  location  before  sawing.  

Discontinue sawing when a crack develops ahead of the saw 

ii.  If a crack develops in reinforced concrete pavement, remove and replace at least a 3 m 

long, full-width slab properly attached to adjacent slabs 

iii.  If a full depth crack develops in plain concrete pavement, remove and replace a full slab 

properly attached to adjacent slabs. 

 

 

 

b.  Transverse Expansion Joints 

Form transverse expansion joints where shown on the Contract plans or as directed by the Engineer.  
Place dowel bars through transverse joints.  Hold dowels parallel to the surface and center line of the 
slab by a metal device that remains in the pavement. 

Dowel placement implanters may be used while the concrete is plastic provided they conform to the 
dowel tolerance specified.  Remove all concrete that leaks into the joint expansion space. 

Install the preformed joint filler full-depth, perpendicular to the subgrade, and continuous across the 
full-pavement width.  Do not use damaged or repaired joint filler.  If joint filler is assembled in sections, 
construct without an offset between adjacent sections. 

c.  Transverse Contraction Joints 

Place dowel bars per the details shown on the Contract plans.  Dowel bar sleeves and finishing caps 
are not required.  Saw joints according to Article 7.6.4.2 of Chapter 7, Incidental Construction, of these 
Standard Specifications.  For adjacent lanes placed separately, construct joints continuously across 
full width of pavement. 

Concrete edges adjacent to the joint may be rounded or beveled to a radius or length as approved.  
Re-saw or grind any joint having an insufficient opening.  Where a joint is larger than required, furnish 
a larger size joint seal as approved. 

d.  Transverse Construction Joints 

Unless an expansion joint occurs at the same location, construct a transverse construction joint at the 
end of each day's work or where concrete placement is interrupted for more than 30 minutes.  Do not 
construct a transverse joint within 3 m of any parallel joint. 

If sufficient concrete has not been mixed to form a slab at least 3 m long when an interruption occurs, 
remove and dispose of the excess concrete back to the last preceding joint. 

Use  a  metal  or  wooden  bulkhead  to  form  the  joint,  shaped  to  the  pavement  cross-section,  and 
designed to permit the installation of dowel bars. 

Install dowel bars in all transverse construction joints whose location does not coincide with the location 
of a transverse expansion or contraction joint. 

3.8.3.7  Finishing 

Protect the surface from rain damage. 

After floating, check the surface of the fresh concrete with a 3 m straightedge.  Remove high areas 
indicated  by  the  straightedge.    Lap  each  successive  check  with  the  straightedge  1.5  m  over  the 
previous check path. 

Correct pavement edge slump in excess of 6 mm in 3 m before the concrete has hardened.  If edge 
slump exceeds 25 mm on any 0.3 m or greater length of hardened concrete, remove and replace the 
entire panel between the transverse and longitudinal joints. 

Before the concrete has initially set, work the pavement edges on each side of transverse expansion 
joints, formed joints, transverse construction joints, and emergency construction joints to produce a 6 
mm continuous radius and a smooth, dense mortar finish.  Do not use mortar buildup to round edges. 

In case fine cracks or hair checks appear in newly placed concrete before it is thoroughly set, apply 
water  to  the  concrete  surfacing,  in  the  form  of  a  fine  fog  mist  until  the  finishing  operations  are 
completed and the curing is applied. 

Apply  the  fog  mist  to  the  area  between  the  finishing  machine  and  the  tining  machine.  If  the 
combination of fogging and curing compound application are not, or will not be effective in preventing 
plastic  shrinkage  cracking,  stop  paving  operations  until  environmental  conditions  improve 
substantially or until other preventative measures are approved in writing.  Contractor shall use one 

 

 

 

of  the  following  finishing  methods,  as  shown  on  the  Contract  plans,  included  in  the  particular 
specifications or as directed by the Engineer: 

1.  Tining method:  In advance of curing operations first texture the concrete pavement with a 

drag  strip  of  burlap  and  then  with  a  mechanical  spring  steel  tine  device  which  will  form 
grooves parallel to the centerline. Do not perform tining too early, whereby the grooves may 
close up. Make tines of rectangular cross section and of sufficient thickness and resilience to 
result in grooves spaced 19 mm on center, 2 mm to 3 mm wide and 3 mm to 5 mm deep in 
the finished concrete pavement.  

Operate the tine machine at a speed which keeps up with paving operations.  Leave a 25 
mm gap between each tine strip to prevent overlapping the tined surface and producing a 
weak surface area. 

Tine the pavement within 75 mm but no closer than 50 mm of pavement edges. 

Do  not tine  the surface adjacent  to  longitudinal  weakened  plane  joints. Untined  area  is to 
extend to no less than 19 mm nor more than 50 mm from the centerline of the longitudinal 
weakened plane joint.  

Omit tining at this location for a total width no less than 38 mm and no more than 100 mm 
uniformly throughout the Contract. 

Maintain the tining device clean and free of encrusted mortar and debris to ensure uniform 
groove dimensions. 

Do not tine pavement which has set, whereas the operation is lifting aggregate out of, tearing, 
or  causing  excessive  roughness  to  the  pavement  surface.  In  such  a  case,  groove  the 
hardened pavement, as directed, at own expense. 

2.  Oscillating  screed  method:    Provide  free  floating  oscillating  screed  device  attached  to  the 

slipform paver, behind the conforming pan, which is capable of performing final finishing on 
the concrete surface. 

Machine shall have a lightweight aluminum float 300 mm wide and a minimum of 3.6 m long, 
which oscillates fore and aft in the direction of traffic. Provide float able to traverse the entire 
concrete slab from edge to edge. 

Connect the float in such a way that it is driven (oscillated), yet it is free floating on the surface 
of the concrete. 

Adjust  and  set  the  movements  of  the  float  according  to  concrete  surface  conditions  and 
forward speed of the paver. 

3.  Hand  Float  Method.  Finish  the  surface  of  the  concrete  smooth  and  true  to  grade  with  2 

wooden floats 4.8 m long, 25 mm thick and 100 mm wide, rigidly ribbed and with adjusting 
screws between the rib and float bars at not more than 600 mm centers, to insure a true and 
flat surface on the underside at all times. Operate each float from the side of the pavement 
and with the float parallel with the centerline of the pavement. Use the edge of the float to cut 
down  all  high  areas,  and  float  the  material  so  removed  into  the  depressions  until  a  true 
surface is obtained. Lap each successive passage of the float just over the previous path. 
Upon  completion  of  the  passage,  bring  the  float  back  and  the  overlap  between  the  2 
passages smoothed. 

Operate the floats as far back of the tamping machine as the concrete remains workable and 
use a number of passes sufficient to remove all irregularities. 

Make available at least one spare float in good condition at all times. 

Final  Finish:  After  the  preliminary  finishing  has  been  completed,  round  the  edges  of  an  initial 
pavement  lane  to  a  13  mm  radius.  Round  transverse  contact  joints,  expansion  joints,  and  joints 
adjacent to an existing pavement to a 6 mm radius. 

 

 

 

In advance of the curing operations, or as directed, texture the pavement with a drag strip of burlap 
or other device which will produce scoring parallel to the centerline. Burlap drag shall consist of one 
or more pieces of burlap fastened to a cross member riding on the subgrade or side forms by means 
of wheels or skids to form a continuous strip of burlap the full width of the pavement. Keep drags 
clean and free from encrusted mortar. 

Discard drags that cannot be cleaned and substitute new drags. Grind or score completed concrete 
pavement, which does not have a satisfactory skid resistant surface texture, by abrasive means to 
provide a satisfactory surface texture. 

3.8.3.8  Curing 

Immediately after finishing and when marring will not occur, cure the concrete for a minimum of 72 
hours.  Do not leave the concrete exposed for more than one half hour during the curing period.  Cure 
using one of the following methods: 

a.  Water Method 

Entirely cover the surface of the pavement and the edges of the slab with water saturated mats.  Extend 
mats at least twice the thickness of the pavement beyond the edges of the slab.  Place the mats in 
complete contact with the surface.  Use masses or other approved methods to maintain contact. 

b.  Liquid Membrane Curing Compound Method 

Protect sawed joints from intrusion of foreign material into the joint before sealing.  Repair damaged 
areas immediately with additional compound. 

c.  Waterproof Cover Method 

 Thoroughly wet the surface using a fog mist applicator.  Cover the entire surface with a waterproof 
cover.  Lap the cover at least 0.5 m.  Extend the cover beyond the edges of the slab at least twice the 
thickness of the pavement.  Place the cover in complete contact with the surface. 

Contractor should use curing procedure that will not cause shrinkage. If excessive shrinkage cracking 
occurs, the Engineer will stop the work until the Contractor submits a revised plan for approval by the 
Engineer that can address shrinkage cracking 

Remove forms when the concrete has hardened sufficiently to resist damage but no earlier than 12 
hours after placing concrete.  Protect the sides of the exposed slabs immediately with a curing method 
equal  to  that  provided  for  the  surface.    Prevent  erosion  of  the  base  course  beneath  the  exposed 
pavement edges until shoulders are constructed. 

3.8.3.9  Sealing Joints 

 Saw cut and seal joints before the pavement is opened to construction or public traffic.  Do not saw 
sealant reservoirs within 72 hours after placing concrete. 

Clean  each  joint  of  all  foreign  material,  including  membrane  curing  compound  and  concrete  slurry, 
immediately after sawing the joint.  Blow dry joints with compressed air.  Do not apply sealing material 
unless the joint faces are clean and surface dry. 

Use preformed joint seals, silicone sealant, or hot-poured sealant for expansion joints.  Use silicone or 
hot-poured sealants for longitudinal and transverse Contraction joints. 

a.  Silicone or Hot-Poured Sealants 

Install backer rod with a steel wheel to the depth required.  Do not stretch or twist the backer rod during 
installation.    Limit  the  length  of  backer  rod  installed  to  that  which  can  be  sealed  during  the  same 
workday. 

Place poured joint sealing material.  Immediately remove any excess or spilled material, and clean the 
pavement surface.  Do not use sand or similar material to cover the seal. 

 

 

 

b.  Preformed Joint Seals 

Furnish the seal in one piece in the size specified for the joint opening.  Install seals with a lubricant 
adhesive covering both sides of the concrete joint.  Compress the seal to between 20 and 50 % of its 
nominal width.  Install the top of the seal about 6 mm below the pavement surface. 

Remove and replace seals that are damaged, twisted, improperly positioned, or stretched more than 
3 %. 

3.8.3.10 

Pavement Smoothness/Roughness 

Measure the smoothness/roughness of the final pavement surface after the concrete has sufficiently 
hardened and according to the designated type shown in the plans or approved by the Engineer.  

a.  Driveways and Alleys smoothness  

Depend solely on surface tolerance levels. 

b.  Concrete Pavement roughness (International Roughness Index (IRI)) 

Engineer will direct and observe operation.  Measure in the middle portion of each lane. 

Areas of localized roughness will be identified using a 7.62 m moving average filter.  The difference 
between the 7.62 m moving average and the reported relative elevation for every profile point will be 
determined.  Deviations greater than 3.81 mm are areas of localized roughness. 

An IRI value will be determined for each 0.1-lane kilometer of traveled way.   

Defective areas are 0.1-lane kilometer segments with IRI values greater than 1.5 m/km or areas of 
localized roughness. 

c.  Straightedge Pavement Smoothness/Roughness 

Use a 4 m metal straightedge to measure at right angles and parallel to the centerline.  Defective areas 
are surface deviations in excess of 6 mm in 3 m between any two contacts of the straightedge with the 
surface. 

d.  Defective area correction   

Correct  defective  areas  from  above.    Obtain  approval  for  the  proposed  method  of  correction.  Re-
measure  corrected  areas  according  to  the  specified  type  of  pavement  smoothness/roughness.  
Smoothness/roughness value obtained will replace the original. 

3.8.3.11 

Full-Depth, Full-Width Patching 

Construct the pavement patch to provide a similar appearance to the existing pavement.  Prepare test 
panels using the same materials proposed for the work. 

Begin pavement work after the test panels have been inspected and approved for appearance and the 
concrete mix design 28-day compressive strength is verified. 

a.  Concrete removal:   

1.  For  mesh-reinforced,  plain  dowel,  or  plain  jointed  concrete  pavement,  saw  cut  slabs  full 

depth leaving vertical edges at the limits of the patch. 

2.  For continuously reinforced concrete pavement, saw cut the exterior transverse patch limits 

to a depth of 45 ±5 mm.  Do not allow the saw cut to penetrate the steel reinforcement.  Saw 
cut longitudinal limits full depth.  Break up the concrete with a chipping hammer down to the 
steel. 

If replacement steel is welded, cut the existing reinforcing steel and leave 200 mm of steel 
exposed.  If replacement steel is tied, cut the existing steel to leave the lap length plus 50 
mm.  Lap lengths are shown in the following table. 

 

 

 

Table 3-52:  Reinforcing steel splices 

Bar size 

Length of overlap (mm) 

10 M 

375 

15 M 

450 

20 M 

550 

Remove the concrete by either or both of the following methods: 

i.  Break-up and clean-out method:  Break up the concrete from the center of the patch 

area toward the end saw cuts.  Remove the concrete pieces with equipment that will 
not damage the underlying surface or adjacent slab. . 

ii.  Lift-out method.  Lift the slab in one or more pieces without disturbing the underlying 

surface.  Clean out the area with hand tools. 

Dispose of the concrete in a designated area outside the right-of-way.   When directed, 

excavate  the  underlying  material  to  a  maximum  depth  of  300  mm,  and  replace  with 
aggregate base as shown in the typical sections.  Prevent adjacent concrete slabs from 
being undermined. 

Repair  all  saw  overcuts  at  the  corner  of  repair  areas  and  nicks  to  adjacent  pavement 

outside the perimeter of the repair area with non-corrosive, non-shrink grout. 

b.  Replacing  reinforcing  steel.    For  concrete  pavement  patches,  provide  a  75  mm  clearance 

between the ends of new reinforcing steel and the existing slab face.  Match the number, type, 
and spacing of the new reinforcement to the existing pavement.  Support reinforcing steel with 
bar chairs or other approved methods while placing concrete. 

c.  Joints.  Construct joints according to Article 3.8.3.6.  Field adjust locations and lengths of joints 

as directed at intersections, median openings, and other areas of odd-shaped slabs such that 
no  joint  is  less  than  460  millimeters  long  and  no  slab  has  an  angle  less  than  60  degrees.  
Construct joints perpendicular to the edge of pavement. 

Place dowels or tie bars into the existing slab.  Drill the dowel or tie bar holes into the face at 
the  required  diameter  with  the  drill  rigidly  supported.    Completely  fill  the  holes  around  the 
dowels and tie bars with an epoxy or nonshrink grout for a permanent fastening to the existing 
concrete.  Furnish a plug or donut to prevent epoxy or grout loss. 

Edge  all  transverse  and  longitudinal  joints  against  forms  or  existing  pavement.    Transverse 
joints  in  a  continuous  lane  pour  or  longitudinal  joints  in  a  continuous  dual  lane  pour  do  not 
require edging. 

Clean  the  exposed  faces  of  joints  and  seal  joints  according  to  Article  7.6.4.2  of  Chapter  7, 
Incidental Construction, of these Standard Specifications. 

d.  Concrete placement.  Construct side forms to overlap the ends of the existing slab.  Securely 

fasten side forms so they do not move when concrete is placed.  To accommodate forms for 
the patch, excavate the adjacent shoulders a maximum width of 300 mm. 

Cast each patch in one continuous full-depth operation.  After removal of the forms, backfill, 

compact, and return the excavated shoulder area to its previous condition. 

e.  Finishing.  Finish patches according to  Article 3.8.3.8 to match the plane and texture of the 

contiguous pavement. 

3.8.3.12 

Opening to Traffic 

Do not allow traffic on new concrete pavement earlier than 14 days after concrete placement unless 