labor shall be used so that there is continual production and distribution of the asphalt course being
constructed. Intermittent or “STOP & GO” type of operations will not be permitted by the Engineer.
Equipment approved for use shall not be removed from the site without the approval of the Engineer.
Contractor shall furnish the Engineer with the manufacturer's catalogues, specifications and other
published data for the equipment and machinery he proposes to use.
a. Mixing Plant
All plants used by the Contractor for the preparation of asphalt hot mixes shall comply with all the
requirements of Paragraph 1 of Sub-article (a) of Article 3.3.3.1. In addition, batch mixing plants
shall comply with the requirements of Paragraph 2 of Sub-article (a) of Article 3.3.3.1.
1. Requirements for all Plants
Automatic Operation
Plant shall be designed, coordinated and operated so as to continually produce asphalt mix
within the job mix tolerances specified. Plant shall be equipped and operated so that the
proportioning of the hot aggregate, commercial filler and bitumen, together with the dry and
wet mixing cycles, are all controlled automatically. Positive interlock shall be provided so that
proportioning, mixing and discharge are accomplished by one operation without manual
control of the separate phases.
Cold Feed System
Plant shall include a sufficient number of cold storage bins so that there is at least one bin for
each different stockpile of material being used. Intermixing of material from different
stockpiles in one bin or on the ground prior to putting into the bin is prohibited. Cold bins and
loading equipment used shall be compatible to prevent overflow between bins. Baffle plates
shall also be used between bins to prevent overflow of one bin into another. Each cold bin
shall include an accurate means for continuously feeding the required amount of mineral
aggregate so that uniform production shall be approved by the Engineer and shall be checked
and calibrated as often as he may deem necessary to ensure its continued accuracy. Change
of settings shall be made only with the approval of the Engineer.
Drier
A drier of satisfactory design shall be provided. Drier shall be capable of uniformly drying
and heating the aggregate to the moisture and temperature required without leaving any
visible unburned oil or carbon residue on the aggregate when discharged from the drier.
Dust Collector
Plant shall be provided with a dust collector designed to waste, or to return in a constant and
uniform flow to the hot elevator, all or part of the material collected. Prior to permitting the
return of such collected dust, the Engineer will examine its characteristics in relation to the
mix requirements and will designate the quantity to be returned.
Plant shall have a screen cover and such additional housings and emission control equipment
as may be necessary to ensure the proper control of dust in accordance with all local
regulations relating to control of dust.
Screens
Plant screens shall be capable of screening all aggregates to the specified sizes and
proportions. They shall have capacities equal to or greater than the maximum rated capacity
of the plant. Screens shall be placed directly above the storage bins for the heated aggregate
and shall receive the material coming from the drier. They shall have an operating efficiency
such that the aggregate deposited in any bin shall not contain more than 10 % of oversize or
undersize material. This screen tolerance shall not invalidate the job mix tolerances
specified.