Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 7

 

  Главная      Manuals     Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     5      6      7      8     ..

 

 

 

Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 7

 

 

C

ONSTRUCTION

 

 

High visibility red and white markings shall be included as shown on the Contract plans and where 
necessary, temporary fences shall have steady state or flashing lighting units attached to them. 

7.7.3.6 

 Sand Fence Construction 

a.  Camel Fence Construction 

Camel  fence  construction  shall  meet  the  applicable  requirements  of  Article  7.7.3.4,  as  per  the 
manufacturers recommendations and as approved by the Engineer. 

b.  Sand Trapping Fence Construction 

Installation of sand control fences shall be done in accordance with the applicable requirements of 
Article  7.7.3.4

,  in accordance with the manufacturer’s  recommendations  and  as approved by the 

Engineer. 

Installation shall leave a bottom gap below the slats of 10 % of the height  

Posts shall be bedded in either pre-cast or cast-in-place foundations, and plumbed vertically. 

7.7.3.7 

Animal Grid Construction 

The width of the animal grid shall be fixed by the Engineer in accordance to the width of the gate or 
road. The plain round bars shall be continuous over a minimum of two spans. 

7.7.4  

Median Fences, Steel 

a. Description 

The Contractor shall fabricate and erect steel median fences, Type 1 and Type 2, furnishing 
all  materials,  labour,  tools,  equipment  and  appurtenances  and  performing  all  work  as 
indicated on the Drawings and in accordance with these Standard Specifications.  

b. Materials  

1. Steel for c-channels shall be to ASTM A36.  

2. Steel for circular hollow sections shall be to ASTM A500, Grade A. 

3. Steel for square hollow sections shall be to ASTM A500, Grade A.  

4. Welded galvanized wires shall comply with ASTM A1064.  

5.  All  sections  of  median  fences  shall  be  galvanized  after  fabrication  in  accordance  with 
ASTM A123, A153 and A385, as applicable. The paint system for median fences shall consist 
of  a  zinc  phosphate  pre-treatment  (primer)  followed  by  super  durable  polyester  powder 
coating (PE SDF), or equivalent, to a minimum thickness of 100 microns.  

6. All welding shall comply with the requirements of the applicable sections of Chapter 27.  

7. All base plate and post fastening hardware shall be hot-dip galvanized steel (galvanized 

to ASTM A153).  

Alternatively,  hardware  may  be  stainless  steel  with  non-metallic  washers  and  sleeves. 
Stainless steel bolts shall comply with ASTM A193, Grade B8,  Class 2; nuts shall comply 
with ASTM A194, Grade 8; and flat washers with ASTM A240, Type 316.  

8. Elastomeric bearing pads shall comply with the requirements of Chapter 25.  

9.  Precast  concrete  foundations  shall  be  class  C25/20  concrete  as  per  requirements  of 
Chapter  4  and  waterproofed  with  a  rubberized  bituminous  coating,  as  indicated  on  the 
drawings,  and  shall  meet  the  requirements  for  quality  and  construction  as  specified  in 
Chapter 4, Concrete Works of these Standard Specifications. 

c. Fabrication and Erection 

All metal median fencing shall be fabricated and erected in sections to the line and grades 
indicated  on  the  Drawings  and  shall  not  reflect  any  unevenness  in  the  structure.  Unless 
otherwise specified or indicated on the Drawings, all railing posts shall be vertical.  

The fabrication and erection of all metal median fencing shall comply with the requirements 
of Chapter 23 and as specified herein.  

The ends of all tubular sections shall be capped or covered with a welded steel plate. 

d. Information Required

The Contractor shall supply the Engineer with detailed shop drawings in accordance with the 
requirements of Chapter 1 of these Standard Specifications. The shop drawings shall indicate 
all  materials,  details,  and  other  technical  information  to  clearly  show  the  fabrication  and 
erection of all median fencing sections. 

7.8  Decorative Finishes for Concrete and Masonry 

Decorative concrete finishes types shall be of the type as shown on the Contract plans, as may be 
required in the Particular Specifications and as approved by the Engineer. In general, colour coatings 
of  concrete  surfaces  shall  comply  with  the  applicable  material  and  installation  requirements  of 
Sections 24.1 and 24.7 of Chapter 24, Painting, of these Standard Specifications. Protective surface 
waterproofing shall meet the requirements of Chapter 28, Waterproofing. 

The Contractor shall prepare and submit to the Engineer for approval trial samples of the type and 
colours as shown on the Contract plans or as included in the Particular Specifications.  Trial sample 
sizes,  numbers  and  methods  shall  be  agreed  with  the  Engineer  prior  to  preparation  which  may 
require a full size trial section for final approval by the Owner.   

7.8.1 Concrete Colour Pigment 

Pigments for cement and cement products shall conform to the requirements of BS 1014. Dry-shake 
colour  hardener  or  integral  concrete  colourant  shall  be  as  shown  on  the  Contract  plans  and  as 
approved by the  Engineer. Pigment shall be in the form of dry, soft powder and shall not contain 
chemical compounds capable of affecting adversely the setting and development of strength of the 
cement and other properties of the finished products and shall be compatible with other admixtures 
used in the same mix. 

Minimum  pigment  content  shall  be  5  %  by  weight  of  cement,  unless  otherwise  approved  by  the 
Engineer. 

Coloured wax meeting the requirements of ASTM C309 shall be used as a curing membrane, unless 
otherwise as shown on the Contract plans.  

7.8.2 Plaster for Decorative Finishing 

7.8.2.1 

Description 

This section defines a cement plaster system directly applied on concrete and concrete blocks. 

7.8.2.2 

General 

Plaster shall comply with provisions of ACI 301, ACI 318, and CRSI 

Manual of standard practice

 

— 

except where more stringent requirements are indicated.  

Shop  drawings  showing locations  and  installation  of control  and  expansion joints,  including  plans 
and elevation sections and details of component and attachments to other works shall be submitted 
by the Contractor. 

Surfaces shall be constructed such that the maximum gap between a 3 m straightedge and any point 
on the surface shall be 3 mm. 

Prior to installing plaster work, the Contractor shall construct panels measuring at least 3 m by 3 m 
and demonstrating finish and application required, aesthetic effects, and qualities of materials and 
execution. Test panels shall not be part of permanent works. 

7.8.2.3 

Materials 

Plaster shall be composed of materials meeting the requirements specified in this section of these 
Standard Specifications, Table 7-40, the referenced standards, and any additional qualifications as 
stated on the Contract plans or as directed by the Engineer.  

Table 7-40 Plaster material requirements 

Material 

Specifications Requirements 

Cement 

Section 4.3.1 of Chapter 4, Concrete Works; Type I 

Lime 

BS EN 459-1 

Special  hydrated  lime  for  finishing  purposes  meeting  the 
requirements of ASTM C206, Type S 

Sand 

ASTM C 897, graded per Table 7-41 

Bonding agent 

ASTM C 932 and as approved by the Engineer 

Concrete pigment 

Section 7.8.1 

Plaster shall be tested in accordance with BS 4551, Method of testing mortars, screeds, and plasters. 

Table 7-41: Sand for plaster 

Sieve Size (mm) 

Percent Retained by Weight 

4.75 

2.36 

1.18 

40 

600 μm 

65 

300 μm 

90 

150 μm 

100 

75 μm 

100 

Plaster mixes shall meet the requirements of ASTM C926. All mix proportions included herein are 
suggestive, variations to meet local  conditions and achieve the desired finish are permitted within 
the limits specified in ASTM C926. 

Interior plastering shall be 20 mm thick. Proportions of mixes given are for damp, loose sand. 

Table 7-42: Suggested mix proportions for interior plastering 

Coat 

Suggested Mix Proportions by Volume 

Scratch coat on masonry 
or concrete 

Portland cement, sand, and coarse aggregate (2.38-mm maximum), 
1:1:1/4 

Brown coat 

Portland cement, hydrated lime, sand, 1:1/4: 3 

Finish coat (skim coat) 

Type N hydrated lime in putty as ASTM C206 

 

G

ENERAL 

R

 

 

 

a.  Activity identification number 

b.  Activity description 

c.  Original duration 

d.  Remaining duration 

e.  Early start date (actual start on updated progress schedules) 

f.  Early finish date (actual finish on updated progress schedules) 

g.  Late start date. (early start on updated progress schedules) 

h.  Late finish date. (early start on updated progress schedules) 

i.  Total float 

j.  Cost-loading: 

1.  Note the estimated cost to perform each work activity as per the approved rates, including 

submittals and submittal reviews, in the network in a tabular listing.  

2.  Sum of all activity costs shall equal the Contract price. An unbalanced or front-end-loaded 

schedule will not be acceptable.  

3.  Accepted cost-loaded progress schedule shall constitute the schedule of values. 

1.10.9 

Progress Quantity Charts  

Reflect activity and Contract dates of progress schedule and show the planned number of units of 
production for each of above listed activities and cumulative progress to date and show average rate 
and cumulative curves for  initial projected progress,  actual progress, and revised planned project 
progress. 

Submit  revised  progress  quantity  charts  for  each  production  activity  named  with  each  progress 
schedule submission. 

1.10.10 

Progress of the Work 

A progress schedule shall document work progress in accordance with the following requirements: 

a.  Updated progress schedule shall reflect:  

1.  Progress of work to within 5 working days before submission 

2.  Approved  changes  in  work  scope  and  activities  modified  since  submission3.  Delays  in 

submittals or resubmittals, deliveries, or work 

3.  Adjusted or modified sequences of work 

4.  Other identifiable changes 

5.  Revised projections of progress and completion 

6.  Report of changed logic 

b.  Produce detailed and specific schedule reports during the project, upon request of Engineer, 

to further define critical portions of the work 

c.  If the Contractor fails to complete an activity by its latest scheduled completion date and this 

failure is anticipated to extend  Contract dates (or milestones), the Contractor shall, within 7 
days of such failure, submit a written statement as to how  the Contractor intends to correct 
non-performance  and  return  to  acceptable  current  progress  schedule.  Actions  by  the 
Contractor to complete the work within Contract times (or milestones) will not be justification 
for adjustment to Contract price or Contract times.  

d.  The Engineer may order the Contractor to increase plant, equipment, labour force or working 

hours if the Contractor fails to:  

R

 

1.  Complete a milestone activity by its completion date

2.  Satisfactorily execute work as necessary to prevent delay to overall completion of project,

at no additional cost to Owner. 

1.10.11 

Narrative Progress Report 

The Contractor shall provide a narrative progress report that meets the following requirements: 

1.10.11.1  Format

a.  Organize same as progress schedule

b.  Identify, on a cover letter, reporting period, date submitted, and name of the Contractor

1.10.11.2  Contents

a.  Number of days worked over the period, work force on hand, construction equipment on hand

(including utility vehicles such as pickup trucks, maintenance vehicles, stake trucks) 

b.  General progress of work, including a listing of activities started and percentage of completion

over the reporting period, mobilization/demobilization of subcontractors, and major milestones 
achieved 

c.  The Contractor

’s plan for management of site (e.g., lay down and staging areas, construction

traffic),  utilization  of  construction  equipment,  build-up  of  trade  labour,  and  identification  of 
potential Contract changes  

d.  Identification of new activities and sequences as a result of executed Contract changes

e.  Documentation of weather conditions over the reporting period, and any resulting impacts to

the work. 

f.  Description  of  actual  or  potential  delays,  including  related  causes,  and  the  steps  taken  or

anticipated to mitigate their impact 

g.  Changes to activity logic

h.  Changes to the critical path

i.  Identification of, and accompanying reason for, any activities added or deleted since the last

report 

j.  Steps taken to recover the schedule from the Contractor-caused delays

1.10.12 

Progress Schedule Acceptance 

Progress schedule acceptance will comply with the following requirements: 

1.10.12.1 

Engineer’s Acceptance 

Engineer

’s acceptance will demonstrate agreement that: 

a.  Proposed progress schedule is accepted with respect to:

1.  Contract  dates,  including  final  completion  and  all  intermediate  milestones  are  within  the

specified times 

2.  Specified work sequences and constraints are shown as specified

3.  Access restrictions are accurately reflected

4.  Start-up and testing times are as specified

5.  Submittal review times are as specified

6.  Start-up testing duration is as specified and timing is acceptable

R

 

b.  In  all  other  respects,  Engineer

’s  acceptance  of  the  Contractor’s  schedule  indicates  that,  in

Engineer

’s  judgment,  schedule  represents  reasonable  plan  for  constructing  project  in 

accordance  with  the  Contract  documents.  Engineer

’s  review  will  not  make  any  change  in 

Contract requirements. Lack of comment on any aspect of schedule that is not in accordance 
with the Contract documents will not thereby indicate acceptance of that change, unless the 
Contractor  has  explicitly  called  the  non-conformance  to  Engineer

’s  attention  in  submittal. 

Progress  schedule  remains  the  Contractor

’s  responsibility  and  the  Contractor  retains 

responsibility  for  performing  all  activities,  for  activity  durations,  and  for  activity  sequences 
required to construct project in accordance with the Contract documents. 

1.10.12.2  Unacceptable Preliminary Progress Schedule 

a.  Make requested corrections; resubmit within 10 calendar days

b.  Until acceptable to Engineer, the Contractor shall continue review and revision process, during

which time the Contractor shall update schedule on a monthly basis to reflect actual progress 
and occurrences to date 

1.10.12.3  Unacceptable Detailed Progress Schedule 

a.  Make requested corrections; resubmit within 10 days

b.  Until acceptable to Engineer, the Contractor shall continue review and revision process

1.10.12.4  Narrative Report

All  changes  to  activity  logic,  duration,  sequences,  including  addition  or  deletion  of  activities 
subsequent  to  Engineer

’s  acceptance  of  baseline  progress  schedule,  shall  be  delineated  in  the 

narrative report current with proposed updated progress schedule. 

1.10.13 

Adjustment of Contract Dates 

Evaluation  and  reconciliation  of  adjustments  of  Contract  times  shall  be  based  on  the  updated 
progress schedule at the time of proposed adjustment or claimed delay and as follows: 

1.10.13.1  Schedule contingency 

a.  Use  of  schedule  contingency  suppression  techniques  such  as  preferential  sequencing  and

extended activity times is prohibited. 

b.  Pursuant  to  contingency  sharing  provisions  of  this  specification,  no  time  extensions  will  be

granted, nor will delay damages be paid until a delay occurs which (1) consumes all available 
contingency time, and (2) extends work beyond the Contract completion date 

1.10.13.2  Float

a.  Use of float suppression techniques such as preferential sequencing or logic, special lead/lag

logic  restraints,  and  extended  activity  times  are  prohibited.  Use  of  float  time  disclosed  or 
implied  by  use  of  alternate  float-suppression  techniques  shall  be  shared  to  proportionate 
benefit of the Owner and the Contractor. 

b.  Pursuant  to  above  float-sharing  requirement,  no  time  extensions  will  be  granted  nor  delay

damages paid until a delay occurs which an 

impacts project’s critical path. consumes available 

float or contingency time and extends work beyond Contract completion date 

1.10.13.3  Claims based on Contract dates

a.  Where Engineer has not yet rendered formal decision on the Contractor

’s Claim for adjustment

of Contract times, and parties are unable to agree as to amount of adjustment to be reflected 
in  progress  schedule,  the  Contractor  shall  reflect  an  interim  adjustment  in  the  progress 
schedule as acceptable to Engineer.  

R

 

b.  It  is  understood  and  agreed  that  such  interim  acceptance  will  not  be  binding  on  either  the

Contractor or the Owner, and will be made only for the purpose of continuing to schedule work 
until  such  time  as  formal  decision  has  been  rendered  as  to  an  adjustment,  if  any,  of  the 
Contract times. 

c.  The  Contractor  shall  revise  progress  schedule  prepared  thereafter  in  accordance  with

Engineer

’s formal decision. 

1.10.14 

Qualifications for Personnel Responsible for Schedules 

The Contractor shall designate a team with an authorized representative who shall be responsible 
for the preparation of all required progress schedule reports. This person shall be dedicated full-time 
to preparing all required schedule reports. This person shall be a qualified project controls Engineer 
or  a  planning  Engineer  who  has  previously  created  and  reviewed  computerized  schedules. 
Qualifications  of  this  individual  shall  be  submitted  to  the  Engineer  for  review  with  the  preliminary 
progress schedule submission. 

1.11 

Submittal Procedures 

This section describes submittal procedures, standards, and requirements for the following items: 

1.  Product data

2.  Shop drawings

3.  Samples

4.  Operation and maintenance manuals

5.  Certificates and affidavits

6.  Miscellaneous submissions

7.  Contract plans

8.  Mistakes in Information

1.11.1 

Definitions 

This section defines submittal procedure terms. 

a.  Product data and shop drawings:

1.  Includes  drawings,  diagrams,  illustrations,  brochures,  schedules,  bills  of  materials,  and

other data prepared specifically for the works 

2.  Information may be prepared by the Contractor, his subcontractors, suppliers or distributors,

equipment manufacturer, or fabricators 

3.  Information  must  illustrate  or  describe  manufacture,  fabrication,  construction,  and

installation of the works or a portion thereof 

b. 

Manufacturer’s representative:

1. 

Person actively working at manufacturer’s factory with minimum 5 years experience

2.  Familiar with actual problems of manufacturing, installing, and operating the product

3.  Sales representatives or agents are not acceptable

c.  Working (shop) drawings:

1.  The Contractor prepared plans for temporary structures and facilities

2.  Elements of work which may affect the safety of persons or property shall be checked and

certified by a qualified Engineer 

3.  Calculations demonstrating adequacy of the Contractor

’s design shall be submitted with the

working drawings 

 

 

 

 

 

 

 