Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 6

 

 

R

 

5.  The  Contractor  shall  provide  the  names  and  details  of  the  experience,  qualifications  and

previous appointments for the supervisory staff including those of the Subcontractors who will 
be allocated to the project all as stipulated under the Department of Transport Conditions of 
Contract and Schedule of Further Requirements.  

6.  The  Contractor

’s  project  manager  shall  be  a  degreed  Engineer  and  have  documented  and

recognized  experience  which  shall  include  previous  experience  as  a  project  manager  and 
he/she shall be full-time assigned to the site. The Contractor

’s project manager shall have a 

minimum of 20-years proven experience as a project manager for construction projects similar 
in  nature  to  the  current  contract  plus  be  in  continuous  employment  with  The  Contractor

’s 

organization for at least the last two years.   

7.  The Contractor

’s supervisory staff submittal shall include project nominated sponsors who are

the senior officers or operational managers from the Contractor’s headquarters or main office 
who are also shown as senior persons within the Contractors overall corporate organizational 
structure.   

8.  A full-time safety Engineer shall be assigned to the site to manage the Contractor

’s health and

safety plan. 

9.  Submittal  shall  include  the  personal  contact  information,  including  telephone  numbers  and

email  addresses  where  the  Contractor  organization’s  sponsors,  project  manager,  safety 
engineer and other senior site supervisory staff can be reached as applicable for both normal 
working coordination or 

in case of emergency by the Owner or the Owner’s representatives. 

1.9.2 

Use of Site 

The Contractor shall not use the site for any purpose other than carrying out the works. 

1.9.3 

Advertising 

Do not display or permit advertisements to be displayed on the site without written approval of the 
Owner. 

1.9.4 

Working Hours 

Normal working hours shall be 48 hours per week, Saturday through Thursday. The Contractor shall 
comply with Labour Laws and requirements of the Department of Transport Conditions of Contract 
and Schedule of Further Requirements. 

1.9.5 

Work Schedule Notifications 

a.  Any work done in the absence of the Engineer or his authorized inspector may be subject to

rejection. 

b.  The Contractor shall notify the Engineer three working days in advance of any work to be done

in order that inspection services may be provided. 

c.  Inspection by the Engineer during defects liability period is to be performed as follows:

1.  Engineer  will  give  the  Contractor  due  notice  of  his  intention  to  carry  out  any  inspections

during the defects liability period. 

2.  The Contractor shall arrange for a responsible representative to be present at the times and

dates named by the Engineer. 

3.  The Contractor

’s representative shall render all necessary assistance and take note of all

matters and issues to which the Engineer directs his attention. 

1.9.6 

Adjoining Plant and Property 

The Contractor shall meet the following requirements pertaining to adjoining construction plant and 
property. 

R

 

1.  Take  all  reasonable  precautions  to  avoid  interference  with  the  operation  of  and  to  prevent

damage to adjoining plant and property. 

2.  Obtain permission as necessary from the concerned authority and pay all necessary charges

if required to use adjoining property. 

3.  Clear away and make good on completion or when directed.

1.9.7 

Temporary Work 

Provide and maintain during the execution of the works all shoring, strutting and other supports as 
may  be  necessary  to  preserve  the  stability  of  all  plant  and  property  that  may  be  endangered  or 
affected  by  the  works.  Temporary  diversion  of  traffic  shall  be  as  per  the  requirements  of  Section 
1.15.13. 

1.9.8 

Coordination 

The Contractor shall provide coordination assurances for the following items: 

1.9.8.1 

General

a.  Coordinate  construction  activities  included  under  various  sections  of  these  specifications  to

assure efficient and orderly installation of each part of the works. 

b.  Coordinate construction operations included under different sections of the specifications that

are dependent upon each other for proper installation, connection and operation. 

c.  Where installation of one part of the work is dependent on installation of other components,

either before or after its own installation, schedules detailed design and construction activities 
in the sequence required to obtain the best results.  

d.  Where availability of space is limited, coordinate installation of different components to assure

maximum accessibility for required maintenance, service and repair. 

e.  Make adequate provisions to accommodate items scheduled for later installation.

f.  Where necessary, prepare memoranda for distribution to each party involved outlining special

procedures  required  for  coordination.  Include  such  items  as  required  notices,  reports  and 
attendance at meetings.  

g.  Prepare similar memoranda for the Engineer and separate Contractors, where coordination of

their work is required. 

1.9.8.2 

Administrative Procedures

a.  Contractors constructing other utilities and buildings may be working in the vicinity of the works

during the course of this Contract. 

b.  Co-ordinate  scheduling  and  timing  of  required  administrative  procedures  with  other

construction  activities  to  avoid  conflicts  and  ensure  orderly  progress  of  the  work.  Such 
administrative activities include, but are not limited to, the following:  

1.  Preparation of schedules

2.  Preparation of project correspondence

3.  Preparation of submittals

4.  Progress and coordination meetings

5.  Estimating and pricing Variation Orders

6.  Project closeout activities

R

 

1.9.8.3 

Drawings

a.  The Contractor shall be responsible for and shall pay the extra cost, if any, occasioned by any

discrepancies,  errors,  or  omissions  in  the  drawings  and  other  submittals  furnished  by  him, 
whether or not approved by the Engineer.  

b.  Prepare and submit coordination drawings where close and careful coordination is  required:

1.  Installation of products

2.  Materials fabricated off-site by separate entities

3.  Where  limited  space  availability  necessitates  maximum  utilization  of  space  for  efficient

installation of different components. 

c.  Drawings shall indicate:

1.  Interrelationship of components detailed on separate shop drawings

2.  Required installation sequences

3.  Comply with requirements contained in Section 1.11.

4.  Take  special  care  and  precautions  for  specific  coordination  requirements  for  plant,

equipment  and  other  electromechanical  installations,  specified  elsewhere  or  otherwise 
required. 

1.9.8.4 

Specifications 

a.  Arrangement of the specifications into divisions, sections and paragraphs shall not control or

determine the division of work among  subcontractors nor establish the extent of work to be 
performed by any particular trade.  

b.  The  Contractor  shall  be  responsible  for  the  proper  coordination  of  all  Works  including  that

required  between  different  trades,  Subcontractors,  suppliers,  utility  authorities,  government 
authorities, etc. 

1.9.9 

Work Plan 

The  Contractor  shall  submit  his  Construction  work  plan    including  his  entire  working  procedure, 
forms,  administration,  submission  of  technical  documents,  correspondence,  reporting,  meeting, 
documentation, communication, etc, as otherwise may be specified or as required by the Engineer. 
The Contractor

’s work plans shall meet the following requirements: 

1.  The Contractor shall provide a work plan for each key activity, as requested by Engineer, to

show construction methods. Relate the work plan to activities shown on the project schedule 

2.  The Contractor shall conduct a pre-work coordination meeting before the start of the work in

each work zone or where a change in the construction operations is contemplated 

3.  The Contractor shall include in its baseline schedule and all progress schedules, allowances

for normal inclement weather 

1.9.10 

Daily Report 

Refer to Sections 1.13 and 1.13.10 , for daily reporting requirements. 

1.9.11 

Plant Record 

Submit a daily record to the project Engineer in a format that the Engineer has approved, showing 
the type, model, number of hours worked, and capacity of all mechanical and power operated plant 
employed  on  the  works.  The  Contractor  shall  incorporate  this  record  in  the  daily  report;  refer  to 
Section 1.131.9.10.  

R

 

1.9.12 

Defective Work 

When  any  part  of  the  works  is  known  or  suspected  to  be  defective,  the  Contractor  shall  submit 
proposals  as  soon  as  possible  to  the  Engineer  for  his  approval  for  further  testing,  opening  up, 
inspection, making good or removal and re-execution.  

Whenever  inspection  or  testing  shows  that  any  part  of  the  works  is  not  in  accordance  with  the 
Contract,  the  Contractor  shall  take  necessary  measures,  such  as  further  testing,  opening  up,  or 
experimental  work,  to  establish  the  acceptability  of  the  work.    Such  measures  shall  be  at  the 
Contractor

’s expense and shall not be grounds for extension of time. 

1.9.13 

Representatives for Emergencies 

The  Contractor  shall  file  with  the  Engineer,  the  names,  addresses,  and  telephone  numbers  of 
representatives who can be contacted at any time, in case of emergency. Representatives must be 
fully  authorized  and  equipped  to  correct  unsafe  or  excessively  inconvenient  conditions  at  short 
notice. 

1.9.14 

Maintaining Existing Facilities in Operation 

The Contractor shall carry out the works in such manner to avoid disruption to existing utilities. In no 
case  shall  the  Contractor  interfere  with  the  operation  of  existing  facilities,  pipelines,  cables  etc., 
without first obtaining the permission of the Engineer, the Owner and the relevant authority to which 
such facility pertains. 

1.9.15 

Working Hours and Engineers Supervision 

No work shall be carried out during the night, on Fridays or on public holidays without the permission 
in  writing  of  the  Engineer,  except  when  the  work  is  unavoidable  or  absolutely  necessary  for  the 
saving of life or property or for the safety of the works in which case the Contractor shall immediately 
advise the Engineer. 

1.10 

Construction Progress Documentation 

Construction progress documentation shall meet the requirements outlined in this section. 

1.10.1 

Submittals 

a.  The Contractor shall submit the following: Preliminary progress schedule to the Engineer no

later than 14 calendar days after notice of commencement for approval. 

b.  Detailed progress schedule, as follows:

1.  Submit  initial  detailed  progress  schedule  within  28  calendar  days  after  notice  of

commencement for approval by Engineer. The Contractor shall resubmit until such time as 
it has been approved by the Engineer. 

2.  Submit an updated progress schedule utilizing the critical path method (CPM).

c.  Submit the following with each progress schedule submission:

1.  The  Contractor

’s  certification  that  progress  schedule  submission  is  the  actual  schedule

being utilized for execution of the work. 

2.  CD with .XER file of the progress updated schedule prepared with the latest version of (P6)

Enterprise  Project  Portfolio  Manager  or  Professional  Project  Manager  from  Primavera 
Systems Incorporated or similar.  

3.  Progress schedule: 5 legible copies

4.  Narrative progress report: 5 legible copies

5.  Progress quantity chart(s)

W

ORKS

 

 

Second Edition -SEP 2020 

 

All  mortar  shall  be  conveyed fresh to  the site  of  the  works  as required  for  use. Mortar  which  has 
begun to set or which has been site-mixed for a period of more than one hour in the cases of Classes 
M1, M2, M5 and M6, and two hours in the case of classes M3, M4, M7 and M8 shall not be used. 

4.3.10.5 

Shotcrete  

Shotcrete, also called pneumatically placed concrete, shall be proportioned to produce a nominal 30 
MPa compressive strength at 28-days.  Shotcrete mix design and evidence that the proposed design 
will  produce  the  required  compressive  strength  shall  be  submitted  to  the  Engineer  for  approval. 
Constituent materials shall meet the following requirements of these Standard Specifications:  

1.  Cement 

– Section 4.3.1: Low-alkali cement in cases where the aggregates are reactive with 

the alkalies in cement. Type V cement in cases where the shotcrete will be exposed to sulfates, 
such  as  used  in  the  coastal  areas.    Type  III  cement  in  cases  where  high  early  strength  is 
required. 

2.  Admixtures 

– Section 4.3.6:  Per approval of the Engineer. 

3.  Fine aggregate 

– Type 2 per Table 4-10  

4.  Coarse aggregate 

– Size 8 per Table 4-11   

Admixtures  shall  be  used  only  with  written  approval  of  the  Engineer.    If  admixtures  are  used  to 
increase  workability,  to  reduce  water-to-cement  ratio,  to  retard  or  accelerate  setting  time,  or  to 
accelerate the development of strength, the admixtures shall be used at the rate specified by the 
manufacturer and approved by the Engineer.   

Shotcrete for reinforced concrete slope protection,  shall be  1-part cement to 4.5 parts sand.  Fine 
aggregate moisture content at time of use shall be 3 % to 6 % by weight.    

Two test cubes 

shall be made for each full day’s operation.  Test cubes shall be tested as required 

in Article 4.3.12.3. Cubes shall develop a minimum compressive strength of 28 MPa at 28 days. 

Shotcrete  facing  shall  conform  to  the  requirements  of  Section  7.3.3  of  Chapter  7,  Incidental 
Construction. 

4.3.10.6 

Permeable Concrete  

High porosity is attained by a highly interconnected void content. Typically, permeable concrete has 
little  or  no  fine  aggregate  and  has  just  enough  cementitious  paste  to  coat  the  coarse  aggregate 
particles, while preserving the interconnectivity of the voids. 

Permeable concrete mix design shall be submitted to the Engineer for approval with evidence that 
the proposed design will produce the required compressive strength per ASTM C39M, void space, 
and initial permeability. Contractor shall prepare trial pavement sections for inspection of the in-situ 
concrete properties, as well as 

a demonstration of the Contractor’s proposed installation methods, 

for approval by the Engineer.  Constituent materials shall meet the following requirements:  

1.  Cement 

– Section 4.3.1:  Utilize Type V in coastal areas and Type I or II for inland areas 

2.  Admixtures 

– Section 4.3.6 

3.  Aggregate 

– Section 4.3.7   

Table 4-22: Typical permeable concrete mix design

 

Material 

Typical value 

Cement (any type) 

224 kg to 388 kg 

Coarse aggregate 

1,431 kg to 1,670 kg 

Water-to-cement ratio 

0.27 to 0.38 

Admixtures 

Retarders 

W

ORKS

 

 

Second Edition -SEP 2020 

 

Flexural strength of the cured pavement can range from 3.5 MPa to 5.0 MPa.  

Mixes  shall  be  designed  in  accordance  with  the  ACI  Design  Guide  211,  Appendix  6.  Due  to  the 
relatively low water content of the concrete mix, an admixture is required to retard the concrete set 
time. 

Permeable  pavement  shall  have  an  in-place  void  space  of  at  least  15  %,  which  allows  rapid 
percolation  of  stormwater  through  pavements.  Initial  permeability  of  cured  pavements,  in  clean 
conditions, shall be at least 5 m/hr. 

4.3.10.7 

Contents of Chlorides and Sulphates 

Total water soluble chloride ion (Cl

-

) content of the mixed concrete shall not exceed 0.06 % by weight 

of cementitious material for prestressed concrete nor 0.10 % by weight of cementitious material for 
reinforced concrete. An initial evaluation may be obtained by testing individual concrete ingredients 
for  total  chloride  ion  content  per  AASHTO  T  260  and  totalling  these  to  determine  the  total  water 
soluble chloride ion or the total water soluble chloride ion in accordance with ASTM C1218M.  

Sulphate in the concrete shall not exceed 800 ppm when calculated on the total concrete mass, or 
5,000 ppm when calculated on the amount of the cement in the actual mix.  

Total sulphate content of the concrete mix, expressed as SO

3

, shall not exceed 4 % (m/m) of the 

cementitious binder content of the mix per ASTM C265. Sulphate content shall be calculated as the 
total from the various constituents of the mix.  

4.3.11 

Concrete Batching Requirements 

All  concrete  shall  be  batched  in  a  prequalified  manual,  semi-automatic,  or  automatic  plant  as 
described in this section of these Standard Specifications. Delays to the Contractor due to problems 
in getting the plant certified shall not be the responsibility of the Engineer.  

4.3.11.1 

Batching Plant 

Concrete batch plant shall be suitable in type, capacity and design for its purpose and acceptable to 
the  Engineer.  Batch  plants  shall  meet  the  requirements  specified  herein  and  per  the  applicable 
requirements of Article 4.3.11.3.   

Continuous mixers shall not be permitted. Mixers for designed mixes shall be of the pan type. Mixers 
and their accessories shall be to an internationally recognised standard such as BS 1305, and shall 
be in good condition. Performance of the batch plant and its disposition shall be adequate for the 
Contractor’s work programme and acceptable to the Engineer. Mixers shall operate at the speeds 
and  mix  for  at  least  the  length  of  time  recommended  by  the  manufacturer.  Mixing  time  shall  be 
increased if necessary to achieve a uniform distribution of materials in the mix and a uniform colour.  

Mixers which have been out of use for more than 30 minutes shall be thoroughly cleaned before any 
fresh concrete is mixed. Unless otherwise agreed by the Engineer, a small first batch shall be used 
to coat the mixer, and this coating batch shall not be incorporated in the works. 

Standby  mixing  capacity  shall  be  provided  by  the  Contractor  (sufficient  to  ensure  continuity  of 
concreting in the event of breakdowns of mixing plant) and shall be maintained ready for immediate 
use during the course of all concrete pours.  

Precautions shall be taken to avoid the loss of cementitious material during windy conditions. The 
batching  plant  shall  have  separate  balances  for  cementitious  materials  and  aggregates  unless 
otherwise agreed by the Engineer. Weighing and water dispensing mechanisms shall be maintained 
in good order, and their accuracy shall be maintained to ensure batch weights within the tolerances 
required  by  the  AASHTO  LRFD  specification.  Facilities  shall  be  provided  for  calibration  of  all 
weighing equipment, gauges and meters for use in the manufacture of concrete. Calibration checks 
shall be carried out jointly with the Engineer at monthly intervals.  

 

G

ENERAL 

R

 

 

 

d.  Before final payment, submit a final updated progress schedule. 

1.10.2 

Project Schedule 

The Contractor shall use the critical path method (CPM) for preparing all project schedules, hereafter 
defined as the progress schedule. 

1.10.3 

Software 

The Contractor shall use the following software applications to prepare the project schedule: 

1.  Professional Project Manager or Enterprise Project Portfolio Manager (P6) latest version, from 

Primavera Systems Incorporated or similar. 

2.  The Contractor shall provide to the Engineer one license of the latest version of the scheduling 

software. This license shall be added to the license serial number of the Owner. 

1.10.4 

Basis for Payment 

The Contractor shall comply with the following requirements for basis of payment. 

1.10.4.1 

General 

Schedule  shall  be  the  basis  for  measuring  the  Contractor  progress.  Failure  of  the  Contractor  to 
provide  all  information,  as  specified  below,  shall  result  in  the  disapproval  of  the  entire  progress 
schedule  submission  and  may  result  in  the  inability  of  the  Engineer  to  evaluate  the  Contractor 
progress for payment purposes. 

1.  Failure  to  submit  acceptable  progress  schedule  or  progress  schedule  revisions  If  the 

Contractor fails within the time limits set forth in this article to submit an acceptable progress 
schedule, or fails to submit acceptable progress schedule revisions for modifications issued 
under  the  terms  of  this  Contract,  or  fails  to  submit  acceptable  progress  schedule  revisions 
otherwise required, or to adequately status the progress schedule, or perform an acceptable 
mathematical analysis, to provide acceptable progress reports as required by this article, the 
Engineer may, in addition to other remedies provided under this article, withhold approval of 
all or any portion of the progress payments until an acceptable revision, status, mathematical 
analysis, or progress report is submitted and approved.  

1.10.4.2 

Non-Compliance 

Failure of the Contractor to comply with the requirements of the Engineer under this article shall be 
grounds for  a  determination  by  the  Engineer that  the  Contractor  is  not  prosecuting the  work  with 
sufficient diligence to ensure completion within the time specified in the Contract. Upon making this 
determination,  the  Owner  may  terminate  the  Contractor's  right  to  proceed  with  the  work,  or  any 
separable part of it, in accordance with the default terms of this Contract. 

1.10.4.3 

Errors and unrealistic and/or unreasonable logic 

In the event that any error, or unrealistic or unreasonable component, parameter, logical relationship 
or  activity  duration  results  is  discovered  in  an  approved  network,  or  updating  information, 
mathematical analysis, progress report, or pay estimate, the Engineer may require the Contractor to 
correct, revise and resubmit the network, or status information, or mathematical analysis, or progress 
report, or payment estimate for approval. Any payment amount made on the basis of such error, or 
unrealistic  or  unreasonable  component,  parameter  or  result  may  be  adjusted  by  the  Engineer  in 
subsequent payment estimates. 

1.10.5 

Preliminary Critical Path Method 

In addition to basic requirements outlined in the Department of Transport Conditions of Contract and 
Schedule of Further Requirements, the Contractor shall show, using the critical path method (CPM), 

R

 

a  detailed  schedule,  beginning  with  notice  to  commence,  for  at  least  90  days,  and  a  balance 
summary for a project through final completion. Show at least the following activities: 

1.  Notice to commence

2.  Permits

3.  Design period, by phases of design

4.  Submittals, with review time. The Contractor may use schedule of shop drawings and samples

specified in Section 1.11. 

5.  Submittals of the Contractor quality control plan and health and safety plan

6.  Early procurement activities for long lead equipment and materials

7.  Mobilization

8.  Engineer

’s review periods

9.  Earthwork

10.  Specified work sequences and construction constraints

11.  Tender schedule

12.  Contract milestone and completion dates

13.  Major  structural,  mechanical,  equipment,  electrical,  architectural,  and  instrumentation  and

control work 

14.  System start-up summary

15.  Project close-out summary

16.  Demobilization summary

Update preliminary progress schedule monthly; as part of progress payment process. Failure to do 
so may cause Engineer to withhold all or part of the monthly progress payment until the preliminary 
progress  schedule  is  updated  in  a  manner  acceptable  to  Engineer.  Format  a  detailed  progress 
schedule in accordance with Section 1.10.7 and Section 1.10.5. 

1.10.6 

Detailed Progress Schedule 

Detailed progress schedules shall comply with the following requirements: 

1.  In  addition  to  requirements  of  the  Department  of  Transport  Conditions  of  Contract  and

Schedule of Further Requirements, submit detailed progress schedule beginning with notice 
to commence and continuing through final completion. 

2.  Show the duration and sequences of activities required for complete performance of the work

reflecting means and methods chosen by the Contractor. 

3.  When  accepted  by  Engineer,  detailed  progress  schedule  will  replace  preliminary  progress

schedule and become baseline schedule. Subsequent updated submittals will be considered 
as updated progress schedules.  

4.  Format a detailed progress schedule in accordance with Section 1.10.7 and Section 1.10.5.

5.  Update monthly to reflect actual progress and occurrences to date, including weather delays

using a date agreed with the Engineer. 

1.10.7 

Progress Schedule Bar Chart 

The Contractor shall provide a progress schedule bar chart that meets the following requirements: 

1.10.7.1 

General

comprehensive  bar  chart  schedule,  generally  as  outlined  in  Associated  General  Contractors  of 
America Publication No. 1107.1, “Construction Planning and Scheduling, latest edition. If a conflict 
occurs between the AGC publication and this specification, this specification shall govern.  

 

G

ENERAL 

R

 

 

 

1.10.7.2 

Format 

a.  Unless otherwise approved, white paper, A3 sheet size 

b.  Title block: Show name of project and Owner, date submitted, revision or update number, and 

name of the Contractor  

c.  Identify horizontally, across the top of the schedule, the time frame by year, month, and day 

d.  Identify each activity with a unique number and a brief description of the work associated with 

that activity.  

e.  Legend: Describe standard and special symbols used.  

1.10.7.3 

Contents 

Identify, in chronological order, those activities reasonably required to complete the Work, including 
as applicable, but not limited to:  

a.  Obtaining permits, submittals for early product procurement, and long lead time items 

b.  Mobilization and other preliminary activities 

c.  Initial site work 

d.  Specified  work  sequences,  constraints,  and  milestones,  including  substantial  completion 

date(s) 

e.  Subcontract work 

f.  Major equipment design, fabrication, factory testing, and delivery dates 

g.  Site work 

h.  Concrete work 

i.  Structural steel work 

j.  Architectural features work 

k.  Equipment work 

l.  Mechanical work 

m. Electrical work 

n.  Instrumentation and controls work 

o.  Other important Work for each major facility 

p.  Equipment and system start-up and test activities 

q.  Project closeout and cleanup 

r.  Demobilization 

1.10.8 

Progress Schedule Using Critical Path Method 

The  Contractor  shall  apply  the  critical  path  method  (CPM),  in  accordance  with  the  following 
requirements, to prepare progress schedules: 

1.10.8.1 

General 

Comprehensive  computer-generated  schedule  using  CPM,  generally  as  outlined  in  Associated 
General  Contractor

s of America Publication No. 1107.1, “Construction Planning and Scheduling”, 

latest  edition.  If  a  conflict  occurs  between  the  AGC  publication  and  this  specification,  this 
specification shall govern. 

1.10.8.2 

Contents 

a.  Begin  schedule  with  notice-to-commencement  date  and  conclude  with  the  date  of  final 

completion of defects liability period and end of maintenance period. 

b.  Identify work calendar basis using days as a unit of measure and UAE calendar. 

R

 

c.  Show complete interdependence and sequence of construction and project related activities

reasonably required to  complete  the  work. Identify  the  work  of  separate sections  (or  areas) 
and stages and other logically grouped activities, and clearly identify critical path of activities. 
Reflect sequences of the work, restraints, delivery windows, review times, Contract times and 
project milestones set forth in the agreement. Include as applicable, at a minimum:  

1.  Obtaining permits, submittals for early product procurement, and long lead time items

2.  Mobilization and other preliminary activities

3.  Initial site work

4.  Specified  work  sequences,  constraints,  and  milestones,  including  substantial  completion

date(s) 

5.  Subcontract work

6.  Major equipment design, fabrication, factory testing, and delivery dates

7.  Site work

8.  Concrete work

9.  Architectural features work

10. 

Equipment work

11. 

Mechanical work

12. 

Electrical work

13. 

Instrumentation and control work

14. 

Other important work for each major facility

15. 

Equipment and system start-up and test activities

16. 

Project closeout and cleanup

17. 

Demobilization

d.  No activity duration, exclusive of those for submittals review and product fabrication/delivery,

shall be less than 1 day or more than 21 days, unless otherwise approved. 

e.  Activity duration for submittal review shall not be less than review time specified unless clearly

identified and prior written acceptance has been obtained from the Engineer. 

1.10.8.3 

Network Graphical Display 

a.  Plot or print on paper not greater than A0 or smaller than A1, unless otherwise approved.

b.  Title block: Show name of the Project, Owner, Engineer, Contractor, date submitted, revision

or update number, and the name of the scheduler. Updated schedules shall indicate data date. 

c.  Identify horizontally across top of schedule the time frame by year, month, and day.

d.  Identify each activity with a unique number and a brief description of the work associated with

that activity. 

e.  Indicate the critical path.

f.  Show, at a minimum, the controlling relationships between activities.

g.  Plot activities on a time-scaled basis, with the length of each activity proportional to the current

estimate of the duration. 

h.  Plot activities on an early start basis unless otherwise requested by Engineer.

i.  Provide a legend to describe standard and special symbols used.

1.10.8.4 

Schedule Report

On A4 white paper, unless otherwise approved. List information for each activity in tabular format, 
including, at a minimum:  

 

 

 

 

 

 

 