Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 47

 

  Главная      Manuals     Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     45      46      47      48     ..

 

 

 

Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 47

 

 

C

ONSTRUCTION

 

 

Kerb openings at driveways and sidewalk ramps shall be constructed by the Contractor as shown 
on Contract plans and as directed by the Engineer. 

Formwork,  expansion  joints,  curing,  and  finishing  shall  be  completed  in  accordance  with  the 
requirements of Article 7.5.3.3, with the following exceptions:  

1.  Surfaces shall be finished immediately after slip-forming 

2.  Foundation pavement shall be dry and cleaned of loose and deleterious material prior to slip-

form kerb placement  

3.  Placing concrete on an unstable, saturated base will not be permitted. If required, the base 

shall be damped with water prior to placing concrete 

In constructing the slip-form work, the Contractor shall do the following:  

a.  Consolidate concrete so as to be free of honeycomb  

b.  Provide concrete of a consistency that will maintain the shape of the barrier, parapet, kerb, or 

gutter without support  

c.  Minimise starting and stopping of the slip-form operation by ensuring a continuous supply of 

concrete. 

d.  Provide a wire line or laser guided controls to maintain vertical and horizontal alignment of the 

slip-form machine  

e.  Operate the slip-form machine within th

e manufacturer’s recommended speed 

f.  Provide rails or supports at the required grade instead of sensor controls, at the Contractor

’s 

option 

Curing shall conform to Article 4.4.2.5 of Chapter 4, Concrete Works.  

7.5.3.5 

Precast Kerb, Parapet and Barrier 

Units shall be precast in sections per the Contract plans and as directed by the Engineer. Unless the 
Engineer agrees otherwise, the manufacturer shall be a company with at least 3 years experience 
in fabricating precast concrete units. Precast sections shall be 6 m or less in length with end faces 
perpendicular to their bases. Casting method shall be either one of the following, as approved by the 
Engineer:  

  By hydraulically pressing concrete 

  Per Section 4.4.8 of Chapter 4, Concrete Works  

Requirements  for  each  casting  method  are  described  in  the  following  subsections.  Additional 
requirements shall be as follows:  

  No concrete barrier shall be shipped until test cylinders made of the same concrete and cured 

under the same conditions show the concrete has reached 30 MPa 

  No  concrete  kerb  shall  be  shipped  from  the  manufacturing  plant  prior  to  21  days  after 

manufacture, however, shorter period may be accepted, if approved by engineer, but shall not 
be less than 14 days in all cases.  If Type III cement has been used, the units may be shipped 
14 days after manufacture. 

All barriers in the same project, except end sections and variable-length units needed for closure, 
shall  be  the  same  length.  All  barriers  shall  be  new,  unused,  and  true  to  the  required  dimensions 
within the tolerances established in Table 7-30. Any damage or distortion from fabrication shall be 
the responsibility of the Contractor. 

Table 7-30: Tolerances for precast barrier 

Dimension 

Tolerance 

C

ONSTRUCTION

 

 

Length 

±25 mm 

Insert placement 

±13 mm 

Horizontal alignment 

±3 mm per metre of length 

Horizontal skew at end 

±6 mm 

Vertical batter 

±3 mm per 300 mm of depth 

Tolerances for precast kerb sections shall be ±3 mm in any dimension.  

Precast concrete units damaged in the process of fabricating, curing, handling, or placing shall be 
repaired or replaced by the Contractor, as directed by the Engineer. 

a.  Hydraulically Pressed Precast Method 

Precast  kerb,  gutter,  kerb  and  gutter,  parapet,  and  barrier  shall  consist  of  hydraulically  pressed 
precast products manufactured in a fully automatic batching plant and comply with the requirements 
of BS EN 1340, except as modified herein, as approved by the Engineer. Units shall be fabricated 
by  the  manufacturer  using  steel  or  other  approved  moulds,  in  compliance  with  the  approved 
manufacturing and testing procedures. 

Unless otherwise approved by the  Engineer, precast kerbs shall be 900 mm long for straight line 
applications or as short as 200 mm long for curves, depending on the radii of the curves. Quality 
control recommendations and dimensional tolerance shall be in accordance with BS EN 1340. 

If required by the Engineer, testing for compressive strength shall conform to the following procedure:  

1.  Sample size shall consist of 3 products from a consignment of up to 1,000 products.  

2.  2-100-mm-diameter cores shall be cut from each of the 3 samples.  

3.  Cores shall be tested in accordance with BS 1881: Part 120.  

4.  Mean compressive strength of 2 cores shall be reported as the compressive strength of that 

product.  

5.  Average compressive strength of 3 products shall not be less than 35.05 N/mm

2

6.  Mean water absorption of cubes, per BS EN 1340, shall not exceed 3.0 %. 

b.  Standard Precast Method 

When kerb, kerb and gutter, gutter, parapet, or barrier are cast in accordance with Section 4.4.8 of 
Chapter 4, Concrete Works, then curing, shipping, and handling shall be per the same section, as 
approved by the Engineer. Forms shall be steel.  

Test  results  from  the  manufacturer’s  testing  shall  demonstrate  compliance  to  the  consistency, 
temperature, and time of placement; air content; and compressive strength requirements of Chapter 
4, Concrete Works.  

c.  Curing and Finishing Precast Units 

Immediately after each unit has been cast, it shall be cured by one of the following:  

  Low-pressure steam 

  Steam vapour 

  Radiant heat and moisture 

  Other similar process, as approved by the Engineer 

Radiant heat and moisture shall be provided by water sprays and a relative humidity at least 90 % 
with a temperature between 16

C and 38

C.  

Each unit shall remain in the curing room for at least 10 days, or at least 5 days if Type III cement is 
used.  

Exposed surfaces of kerb, parapet, and barrier shall be smooth with uniform colour and appearance. 
Finish on the bottom of precast kerbs shall prevent mechanical interlocking of the mortar bed and 
the kerb bottom or anchor groove. 

After  release,  barriers  shall  be  finished  to  an  even,  smooth,  dense  surface,  free  from  any  rock 
pockets or holes larger than 6 mm across. Towelling shall remove all projecting concrete from the 
bearing surface of the barrier. Barriers shall be cured in the forms until test cylinders that have been 
cured under the same conditions as the barrier indicate the concrete has reached a compressive 
strength of a least 15  MPa. No additional curing is required once the barrier is removed from the 
forms. 

d.  Surface Treatment and Marking of Kerbs

After  installation  of  units  on  site,  the  exposed  surfaces  of  all  precast  and  cast  in-situ  concrete 
kerbs, which will not to be painted for parking classifications (turquoise, black, white) or restrictions 
(yellow, grey)  as  per  clause  8.2.3.3  (b),  shall  receive  2  brush  or  roller-applied  coats  of  a  water-
repellent  compound,  meeting  the  requirements  of  Table  24-13  of  Chapter  24,  Painting.  When 
the first coat has dried, the second coat of water-repellent compound shall be applied. 

At the manufacturing plant, each piece of kerb shall be marked in black paint on the back or end of 
the unit with the date of manufacture, length, and identification number corresponding to the detail 
layout.  Alternatively,  each  bundle  of  precast  kerbs  shall  have  a  robust  tag  attached  to  it  with 
the aforementioned information printed on the tag.  

Rejected kerb shall be marked on the back or end to identify each cause of rejection. 

e.  Placing Concrete Kerb

Kerb shall be constructed as shown on the Contract plans, to be placed on top of the pavement base 
courses or on a separately cast concrete footing. At time of placement, kerb shall be firmly bedded 
for its entire length and breadth on either a wet concrete base or a mortar bed composed of Class 
M6 mortar per Article 4.3.10.4 of Chapter 4, Concrete Works, 25 mm thick, placed on approved sub-
grade. Dimensions of the base and haunching shall be as shown on the Contract plans. Concrete 
base shall be constructed with Class C20 concrete. Kerb placement will be inspected and approved 
by  the  Engineer  prior  to  placement  of  the  concrete  kerb  haunching  or  other  work  adjacent  to  or 
against the freshly placed kerb line.  

Anchor grooves in the bottom of the kerb shall be entirely filled with the mortar. Before the cement 
mortar bed is laid, all dirt shall be cleaned from the pavement surface by washing. 

Expansion joints, consisting of approved joint filler  10 mm thick, shall be placed every 9 m, or as 
shown on the Contract plans or otherwise approved by the Engineer. Filler shall extend through the 
kerbs, bed, backing, and gutter and shall be trimmed to the finished slope of the kerb and gutter.  

All joints between adjacent pieces of kerb, except expansion or drainage joints, shall adhere to the 
following:  

  Measure 4 mm or less in width

  Be  filled  with  joint  mortar  meeting  the requirements  for  M1  in  Article  4.3.10.4  of  Chapter  4,

Concrete  Works,  with  one-fifth  part  hydrated  lime  and  sufficient  water  to  make  the  mixture 
plastic  and  easily  smoothed.  A  grooving  tool  shall  be  used  to  produce  a  smooth,  circular 
section groove not more than 3 mm deep in all joints. 

Alignment and the top surface of adjoining sections of kerb shall be true and even with a maximum 
tolerance of 1.5 mm.  

Unless  otherwise  indicated,  after  kerb  units  have  been  laid,  a  continuous  backing  of  Class  C20 
concrete shall be poured. No pavement layers shall be laid against kerbing until such time as the 
backing is complete, back filled and approved by the Engineer.  

Immediately after any concrete is in place and for seven days thereafter, the kerbs, base backing 
and mortared joints shall be fully cured and protected from drying out and against the harmful effects 
of weather, including rain and rapid temperature changes. Concrete not properly cured and protected 
will be rejected and shall be removed from the works. 

Nosing pieces, connecting dividers, and radial sections for kerbs shall be as detailed in the Contract 
plans and will be required at the ends of the kerb lines, at transitions between different kerb types, 
and kerbs with radii less than 3 m. Bull noses and curved faces shall be of constant radius with a 
smooth change from radius to plain face. 

For sloped mountable kerb installed in curves, the units shall be either curved blocks precast to the 
radii shown in the Contract plans or tangent blocks sawn to the dimensions shown in the Contract 
plans to conform to the specified radii. 

At the end of any kerb run, the end element shall be sloped down to ground level and angled away 
from the road at 30 degrees. 

f.  Placing Precast Barrier

Precast barrier lengths shall be as shown on the Contract plans, except that the Contractor may use 
one short section to adjust a line for length. Creating a short section by cutting or breaking a section 
will  not  be  allowed.  Short  sections  shall  be  manufactured  to  meet  the  material  requirements  as 
otherwise specified. Hardware identical to that used with other sections shall interlock such a section 
with adjacent precast sections. 

Precast concrete barrier shall rest on a paved foundation shaped to a uniform grade and section. 
Foundation surfaces shall meet the following test for uniformity:  

When a 3 m straightedge is placed on the surface parallel to the centreline for the barrier, the surface 
shall not vary more than 6 mm from the lower edge of the straightedge.  

Precast segment joins shall be aligned so that they offset no more than 6 mm transversely and no 
more than 18 mm vertically. Grouting to correct alignment is not permitted. If foundation grade and 
section are acceptable, the Engineer may permit the Contractor to obtain vertical alignment of the 
barrier by shimming. Shimming shall be done with a polystyrene, foam pad measuring 300 mm by 
600 mm under the end 300 mm of bearing surface. 

Barrier connection voids for permanent installations of precast barrier shall be filled with grout. 

g.  Rejecting Precast Kerb, Gutter, Parapet, and Barrier

Precast units shall be uniform in colour; free from cracks, flaws, or other defects; and shall have well-
defined edges. 

Excessive cracking, surface checking, broken or rounded corners, air holes, or lines of discolouration 
due to a damaged mould are cause for rejection or repair of precast concrete kerb, gutter, parapet, 
or barrier. An air hole shall be defined as any hole measuring 3 mm or larger in diameter or depth 
that is visible on the surface or appears when the surface is struck with a rubber hammer. A crack is 
defined as any separation of the concrete of a continuous length greater than 75 mm. 

A piece of kerb, gutter, parapet, or barrier shall be rejected for any of the following conditions: 

1.  Variation in dimensions, alignment, or surface contour exceeding ±6 mm in length and ±3 mm

in alignment 

2.  Failure to comply with the Contract plans, Specifications, or instructions of the Engineer

3.  Evident cracking immediately after removal from the moulds.

4.  Surface checking within the first 5 days after manufacture

C

ONSTRUCTION

 

 

5.  Excess honeycombing in the back, unless the Engineer states it is not detrimental  

6.  More than 2 % of the top area is deemed defective.  

7.  More than 5 % of the total length of the top corners of reflecting faces is broken or rounded  

8.  More than 40 holes in any linear 250 mm  

9.  Sum of the length of lines of discolouration exceeds 50 % of the length of the unit. 

10.  Any single line of discolouration exceeds 450 mm long  

For the total amount of precast units of a single type installed in the works, 75 % of each total shall 
be entirely free from lines of discolouration, and 90 % of the total laid shall demonstrate the following:  

  Less than 0.2 % of the top area is deemed defective 

  Less than 0.5 % of the total length of the top corners of reflecting faces is broken or rounded 

  Less than 4 holes in any 250 mm length 

Totals shall be taken by type of precast unit, including total kerb, total gutter, total parapet, or total 
barrier. Failure to reject a unit at the time of manufacture will not ensure its final acceptance.  

h.  Repairing Precast Kerb, Gutter, Parapet, and Barrier 

Precast  units  having  defects  that  are  not  sufficient  cause  for  rejection  shall  be  neatly  repaired 
immediately after removal from the moulds in a manner subject to the approval of the Engineer. No 
patching or repairs shall be made without the permission of the Engineer.  

Chipped or broken moulds shall be repaired such that broken or chipped areas will not be apparent 
on the precast units made in those moulds. Heat shall not be used to obliterate lines of discolouration. 
Processes used to obliterate lines of discolouration shall be subject to the approval of the Engineer. 

Patches shall be undercut if, in the opinion of the Engineer, this operation is necessary to achieve a 
satisfactory patch. 

All holes larger than a 1.5 mm diameter in the exposed surface of acceptable kerb or buttons shall 
be filled with cement mortar.  

i.  Sampling and Inspection of Precast Kerb, Gutter, Parapet, and Barrier 

An  advanced  sample  of precast  kerb,  gutter,  parapet,  and  barrier  that  demonstrates the  required 
colour, texture, and bottom finish shall be submitted to the Engineer for approval. No repairing of any 
kind shall be done on the advance sample.  

Upon approval, the advance sample shall be stored at the plant or site of manufacture in a location 
readily  accessible  to  the  Engineer  where  there  is  adequate  daylight  for  examination.  Advance 
samples  shall  be  protected  from  damage  and  discolouration  and  shall  be  used  as  a  standard  of 
comparison for colour, surface texture, and bottom finish. All precast units furnished to the worksite 
shall be equivalent to the advance sample in the foregoing respects. 

Inspections at the plant will be made just prior to shipment, at which time examination will be made 
of  the  alignment,  contour,  colour,  cracks,  surface  damage  or  discolouration,  broken  corners  or 
edges, and any other defects that may have developed; and to check the laboratory test reports for 
strength. Intermediate inspections may be made to determine surface checking and hidden air holes, 
if examination for these defects is impractical at the final inspection. 

j.  Removing and Resetting Permanent Concrete Barrier, Parapet, and Kerbs 

Contractor shall reset concrete barrier, parapet, or kerb if the Contract plans or the Engineer require. 
If resetting is impossible immediately after removal, the Contractor shall store the units at Engineer-
approved locations and protect them from damage. 

k.  Temporary Concrete Barrier

Temporary concrete barrier shall be new or used precast barrier complying with the requirements of 
the Contract plans for precast barrier, except the following:  

  Lengths may differ from those shown in the Contract plans

  Permanent lifting holes less than 100 mm in diameter may remain

  Lifting loops are permitted

 

A stamp or stencil reading “temporary” shall be visible on each barrier segment

Permanent  barriers  that  will  be  removed  and  reset  per  the  Contract  plans  or  the  direction  of  the 
Engineer  may  be  used  as  temporary  concrete  barrier  without  being  stamped  or  stencilled 
“temporary.” Any permanent barrier damaged during its use as a temporary barrier will become the 
property of the Contractor and be replaced with an undamaged permanent barrier at no expense to 
the Owner when the permanent barrier is reset to its location. 

All barrier shall be in good condition, without cracks, chips, spalls, dirt, or traffic marks. If any barrier 
segment becomes damaged during or after placement, the Contractor, at no expense to the Owner, 
shall immediately repair it to the Engineer

’s satisfaction or replace it with an undamaged section. 

As soon as the temporary barrier is no longer needed, the Contractor shall remove it from the site of 
the works. Owner-furnished barrier shall remain Owner property, and the Contractor shall deliver it 
to  a  stockpile  site  noted  in  the  Contract  or  to  locations  approved  by  the  Engineer.  Contractor-
furnished barrier shall remain the property of the Contractor. 

As  an  alternative  to  precast  temporary  barrier,  and  only  with  the  approval  of  the  Engineer,  the 
Contractor may use a quick-change moveable barrier (QMB) system with a QMB machine, both of 
which  shall  be  installed  and  operated  by  the  Contractor 

in  accordance  with  the  manufacturer’s 

instructions. 

7.6  Sidewalks 

7.6.1 Description 

This work constructs sidewalks in accordance with lines, grades, and details shown in the Contract 
plans and these standard specifications or as established by the Engineer. Types of sidewalk consist 
of the following:  

  Cement concrete sidewalks

  Pervious concrete sidewalks

  Pavers sidewalks

  Tile sidewalks

  Architectural concrete sidewalks

7.6.2 Materials 

Materials shall meet the requirements of Table 7-31. Concrete for cement concrete sidewalks shall 
be Class C20/20 concrete that meets the requirements of Chapter 4, Concrete Works. 

Table 7-31: Material requirements for sidewalks 

Material 

Specifications Requirements 

Concrete 

and 

its 

constituent 

materials; 

premolded joint filler; curing materials 

Section 4.3 of Chapter 4, Concrete Works 

Concrete pigment; decorative finishes; concrete 
stain 

Section 7.8 

Geotextile fabric 

Article 2.5.2.9 of Chapter 2, Earthworks 

Pervious concrete 

Article  4.3.10.6  of  Chapter  4,  Concrete 
Works, and Section 7.6.5 

Adhesives for tiles 

Epoxy-resin-base adhesive 

BS EN 12004:2007 

ASTM C881M 

For the purpose of examining and sampling the materials, the Engineer shall have access at all times 
to the place where paving blocks and other items and their constituent materials are manufactured 
and stored.  

Before the Contractor may begin the work, the Engineer must approve all materials. 

7.6.2.1 

Quarry Tiles 

Quarry tiles shall be standard grade per the minimum grade specifications established by the Tile 
Council of North America (TCNA) and in compliance with the following standards:  

  BS EN 14411

  ANSI A 137.1

Materials  shall  match  the  Engineer

’s  samples.  Quarry  tiles  shall  be  manufactured  from  fine 

stoneware clay mixed with 15 % chamotte, which is burnt klinker fragments and fired in a kiln with a 
minimum temperature of  1,200 

0

C. Quarry tiles shall also meet the materials specifications of Table 

7-32.

Table 7-32: Required physical properties for quarry tiles 

Property 

Standard 

Requirement 

Material 

Burnt (kiln fired), extruded clay tile, unglazed, 
with 

ribbed 

underside 

and 

coloured 

throughout. 

Dimensions 

240 mm by 115 mm by 13 mm, ±5 % 

Density 

2200 kg/m

3

 to 2500 kg/m³ 

Water absorption 

6 % maximum 

Flexural strength 

27 N/mm² minimum 

Scratch hardness 

– 7 hardness according to Moh's scale 

Coefficient 

of 

thermal 

expansion 

4.0 by 10

-6

 

Chemical resistance 

ASTM C650 

No visible change 

Static coefficient of friction 

Walkways and steps 

Ramps 

ASTM C1028

 

Minimum 0.6 

Minimum 0.8 

Materials for quarry spalls shall additionally conform to Section 4.3 of Chapter 4, Concrete Works, 
including, but not by way of limitation, cement, sand, joint filler, and sealer for expansion joints. Sealer 
colours shall match that of the grouted tile joints. Other materials shall be used only with the approval 

of  the  Engineer.  Manufacturer  specifications  and  installation  instructions  for  materials  to  be  used 
shall be submitted to the Engineer for approval prior to start of the work. 

Contractor  shall  obtain  each  material  required  for  any  type  and  colour  of  tile  work  from  a  single 
source, so as to minimise variations in appearance and quality. Tile shall be factory-blended and 
packaged accordingly, so that tile units taken from one package show the same range in colours as 
those taken from other packages and match approved samples. If the tiles have not been factory 
blended, the Contractor shall either return them to the manufacturer or blend tiles at the site of the 
works before installing, to the satisfaction of the Engineer. 

Packaged  materials  shall  be  delivered  and  stored  in  original  containers  with  seals  unbroken  and 
labels intact until time of use. Labels shall comply with ANSI A 137.1. Damage or contamination to 
materials by water, foreign matter, or other causes shall be prevented.  Handle tile with temporary 
protective coating on exposed surfaces to prevent coated surfaces from contacting backs or edges 
of  other  units.  If  despite  these  precautions  coating  does  contact  bonding  surfaces  of  tile,  the 
Contractor shall remove coating from bonding surfaces before setting tile. 

Adhesives  formulated  for  tile  and  recommended  by  their  manufacturer  shall  by  used  for  the 
application indicated. Materials for setting the tiles shall conform to the following requirements:  

1.  For thick bed applications: Latex-Portland cement mortar per ANSI A 118.4 with liquid-latex

additive such as Laticrete 3701 or approved equal 

2.  For thin-set  applications and slurry bond coats at mortar and bed applications:  a mixture of

dry-mortar mix and latex additive such as Laticrete 4237 or an approved equal 

Grout  shall  be  as  recommended  by  the  manufacturer  for  the  type  of  tiles.  Latex-portland  cement 
grout shall meet the requirements of Article 4.3.10.4 of Chapter 4, Concrete Works.  

7.6.2.2 

Precast Tile Blocks 

Precast tile blocks consist of a precast  concrete base and quarry tiles specified in  Article 7.6.2.1. 
Precast  tile  blocks  shall  be  furnished  as  shown  on  the  Contract  plans  to  the  lines  and  grades 
approved by the Engineer. Installation of precast tile blocks shall likewise comply with the Contract 
plans, these Specifications, as approved by the Engineer.   

Quarry  tile  shall  be  per  Article  7.6.2.1.  Latex-portland  cement  mortar  shall  meet  the  latex 
manufacturer's recommendations. Concrete shall be Class C25/20 and its reinforcing shall conform 
to ASTM A185M.  

Precast tile blocks shall be constructed as follows: 

1.  Precast tile blocks shall be installed, where quarry tiles cross service reservations and ducts

are not provided, to the lines and grades determined by adjacent quarry tiles 

2.  Construction of the precast concrete base shall be as shown on the Contract plans using Class

C25/20 concrete 

3.  Placement of quarry tiles shall be on a 5-mm-thick latex portland cement mortar in accordance

with ANSI A 108.5 and ANSI A 118.5 and shall match the pattern and colour of quarry tiles 
elsewhere in the project  

4.  Pointing and grouting material shall be latex portland cement mortar

7.6.3 Construction Requirements 

7.6.3.1 

General  

Sidewalks shall be installed to the lines, grades, and details shown on the Contract plans, as may 
be required by the Particular Specifications, as approved by the Engineer. Geotextile fabric shall be 
used  where  shown  on  the  Contract  plans,  as  approved  by  the  Engineer.  Except  as  otherwise 
approved  in  writing  by  the  Engineer,  the  following  standards  shall  be  met  for  all  new  sidewalk 
installations:  

C

ONSTRUCTION

 

 

  Detectable warning strip extending the width of the ramp and 600 mm from the kerb flow line 

shall be installed per the details provided on the Contract plans  

  Abrupt changes in sidewalk elevation shall not exceed 6 mm  

  Cross slope of the sidewalk shall not exceed 2 % 

  Kerb ramp grades shall not exceed 8.3 %  

  Sloped flares adjacent to the kerb ramps shall not exceed 10 % slope  

Where a sidewalk crosses a concrete driveway, the sidewalk depth and reinforcement shall not be 
less than the driveway cross-sectional details shown on the Contract plans. 

Completed  sidewalks  shall  demonstrate  a  well-compacted  mass,  a  surface  free  from  voids  and 
honeycombs, and dimensions true-to-line shape and grade.  

Unless otherwise shown on the Contract plans or required by the Particular Specifications, sidewalks 
shall  typically  be  100  mm  thick,  or  150  mm  thick  where  they  parallel  depressed  kerbs  or  cross 
driveway entrances. 

Sidewalks  on  bridge  decks  shall  not  be  constructed  until  prestressing  is  complete,  formwork  has 
been removed, and the bridge deck has been surveyed to establish final lines and levels. 

7.6.3.2 

Preparation of the Foundation 

Excavations shall be made to the required depth and to a width that will permit the installation and 
bracing of the forms. Foundations shall be shaped and compacted to a firm-even surface conforming 
to the section shown in the Contract plans. Foundation materials shall be compacted to a density of 
not less than 95 % of the maximum density. 

All soft and yielding material shall be removed and replaced with acceptable material at least 150 
mm  deep,  per  Article  2.4.2.5  of  Chapter  2,  Earthworks.  If  borrow  is  required,  it  shall  conform  to 
2.5.2.2 of Chapter 2, Earthworks. If bedding aggregate is required, it shall be placed in layers of not 
more than a 100-mm compacted thickness. Each layer shall be compacted with at least 3 passes of 
a lightweight mechanical tamper, roller, or vibratory system. If a base course of concrete is required, 
it shall be Class C15 concrete.  

After  the  forms  have  been  set  to  line  and  grade,  the  foundation  shall  be  brought  to  the  required 
grade. Prior to concrete placement, the Contractor shall thoroughly wet the foundation. At the time 
of concrete placement, the forms shall contain no extraneous material or standing water.  

Existing concrete surfaces shall be free of loose or foreign material, scrubbed with wire brooms, and 
kept wet before new concrete is placed. Immediately before placement, the old surface shall be thinly 
coated with a Class M5 mortar meeting the requirements of Article 4.3.10.4 of Chapter 4, Concrete 
Works. 

7.6.3.3 

Formwork 

Formwork shall comply with Section 1.20.8 of Chapter 1, General Requirements, and extend for the 
full depth of the concrete.  

Forms  shall  be  of  wood  or  metal  in  accordance  with  Article  1.20.8.2  of  Chapter  1,  General 
Requirements, and shall extend for the full depth of the concrete. All forms shall be straight, free 
from warp, and of sufficient strength to resist the pressure of the concrete without springing. Bracing 
and staking of forms shall be such that the forms remain true to the required alignment, horizontal 
and vertical, until their removal.  

Clamps, spreaders, and braces shall be used, where required, to insure rigid forms.  

7.6.3.4 

Screed Rail Supports 

Screed rail supports, if used, shall be placed 600 mm on centres.  

C

ONSTRUCTION

 

 

Before concrete operations are started, the screed shall be operated over the full length of sidewalk 
to be constructed and the depth of construction shall be checked. Screed rails shall be adjusted, as 
needed, to install sidewalks as shown on the Contract plans, as approved by the Engineer.  

7.6.3.5 

Acceptance 

Completed  sidewalks  shall  have  clean  planar  faces,  be  free  of  segregation,  honeycombing,  pits, 
broken corners or other defects, and show no evidence of external rendering.  

After curing, the Contractor shall wash the surface with brush and water to remove all laitance and 
cement from the exposed, coarse aggregate.  

Before acceptance of the work, all sidewalks shall be cleaned of all discolouration resulting from the 
Contractor's operations, including, but not limited to, dirt, stains, bitumens, and equipment tire marks. 
Cleaning may be by abrasive blast methods or by other methods approved by the Engineer. 

Concrete sidewalk surfaces shall be tested with a  3-m straightedge. Any deviation in excess of  6 
mm shall be corrected by the Contractor to the satisfaction of the Engineer at no additional expense 
to the Owner. 

7.6.3.6 

Kerb Ramps 

Kerb ramps shall be of the type specified in the Contract plans. Along kerb ramps, the kerb, including 
the bed backing, shall be dropped to show a face of 25 mm or less, or as otherwise designated.  

Kerb ramps shall be cast-in-situ. Forms shall meet the requirements of Article 7.6.3.3 and Section 
1.20.8 of Chapter 1, General Requirements.  

Expansion joints shall be placed in all concrete sections larger than 3 m in any direction as well as 
between  existing  concrete  works  and  the  new  concrete.  New  concrete  shall  be  tied  to  adjacent 
existing concrete by drilling and epoxying dowels into the existing concrete face where any of the 
following conditions are met:  

  Excessive load transfers are possible  

  Foundation for the ramp provides only marginal support capability  

Ramp finishes shall be as shown on the Contract plans and in conformance with the requirements 
of the applicable section of these specifications. For instance, a sidewalk finish, a tile finish, or other 
finish may be specified. Exposed ramp surfaces shall be protected by a clear, penetrating sealant 
meeting the requirements of Section 29.6.1 of Chapter 29, Miscellaneous Items for Structures. 

A detectable warning pattern shall be required for all new sidewalk ramp installations. Detectable 
warning patterns shall have a truncated-dome shape and may be installed using a manufactured 
material before or after the concrete has cured, or by installing masonry or ceramic tiles. Embossing 
or stamping the wet concrete to achieve the truncated-dome pattern or using a mould into which a 
catalyst hardened material is applied shall not be allowed. When masonry or ceramic tiles are used 
to  create  the  detectable  warning  pattern,  the  Contractor  shall  block  out  the  detectable  warning 
pattern area to the depth required for installation of the tiles and finish the construction of the concrete 
ramp. After the concrete has set and the forms have been removed, the Contractor shall install the 
tiles using standard masonry practices.  

Dimensions and details of the detectable warning pattern area on the ramp shall be as shown on the 
Contract plans. Unless otherwise shown on the Contract plans, colour shall be  yellow and match 
Federal Standard 595C, colour number 33538.  

7.6.3.7 

Ramp Detectable Warning Retrofit 

Where shown in the Contract plans, the Contractor shall retrofit existing cement concrete sidewalk 
ramps by installing a detectable warning pattern having a truncated-dome shape and in conformance 
to  the  details  shown  on the  Contract  plans.  Warning  patterns  shall  be  the  width  of  the  ramp  and 

cover the bottom 600 mm of the ramp. Truncated-dome patterns shall be perpendicular to the long 
axis of the ramp. 

Warning patterns shall be capable of being bonded to an existing cement concrete surface. Surface 
of the warning pattern, excluding the domes, shall not be more than 10 mm above the surface of the 
concrete after installation. 

7.6.4 Cement Concrete Sidewalks 

7.6.4.1 

Concrete Placement, Finishing and Texturing 

Concrete shall be mixed and placed in accordance with Sections 4.3 and 4.4 of Chapter 4, Concrete 
Works. Sidewalks may be constructed either by the use of conventional fixed forms or by slip-form 
machines.  

Slip-form equipment shall comply with the requirements established in Article 7.5.3.4, for slip-form 
equipment. All applicable requirements of sidewalk construction by use of fixed forms shall apply to 
the use of slip-form equipment.  

After  placement  in  the  forms,  concrete  shall  be  struck  off  or  screeded  with  approved  equipment. 
During  the  placing  and  finishing  of  concrete,  premolded  joint  filler  for  expansion  joints  shall  be 
restrained in its proper position.  

Concrete  shall  be  thoroughly  worked  so  that  the  coarse  aggregate  is  below  the  surface  and  the 
mortar comes to the top. 

7.6.4.2 

Joints 

Expansion, Contraction, and construction joints shall be constructed in the locations, at the intervals, 
and to the thicknesses shown on the Contract plans. All free mortar and concrete shall be removed 
from the joints.  

Expansion joints shall be placed vertically across the full cross section of the sidewalk at the following 
locations, unless otherwise shown in the Contract plans or directed by the Engineer:  

1.  At locations that match the spacing of expansion joints in adjacent kerb, kerb and gutter, or

pavement. 

2.  At tangent points or kerb returns

3.  Between the sidewalk and all structures and foundations.

4.  At a maximum of 12-m intervals.

5.  Between sidewalks and driveways.

6.  Around poles, posts, boxes, and other fixtures that protrude through the sidewalk.

Workday production shall be terminated at an expansion joint. 

Contraction joints shall be formed with a jointing tool or sawed, and shall consist of the following: 

a.  Constructed vertically

b.  Installed at locations shown on the Contract plans or indicated by the Engineer

c.  Sawed to a depth of 50 mm or one-third the thickness of the concrete, whichever is greater

d.  Formed by parting the large aggregates in the fresh concrete with a straightedge to a depth of

50 mm 

e.  Constructed at a maximum of 4.5 m intervals

f.  Placed at locations that match the spacing of expansion joints in adjacent kerb, kerb and gutter,

or pavement 

Longitudinal Contraction joints shall be constructed in the centre of sidewalk having a width greater 
than 2 m and parallel to or concentric with the lines of the work.  

Where scoring lines are indicated, they shall measure at least 6 mm deep with a 3-mm radius. 

Final joint finishing shall be accomplished with a jointer tool having a radius of 6 mm and leaving a 
finished joint depth of at least 19 mm. If indicated on the Contract plans or by the Engineer, joints 
shall be sealed with a sealer that meets the requirements of Section 4.3.15 of Chapter 4, Concrete 
Works. 

Contraction  joints  shall  be  formed  around  all  appurtenances,  such  as  manholes,  utility  poles, 
buildings, bridges, and where abutting an existing or separately placed kerb.  

7.6.4.3 

Curing 

Concrete sidewalks shall be cured for at least 72 hours using Method A or Method C, as described 
in Articles 4.4.2.1 and 4.4.2.3 of Chapter 4, Concrete Works.  

During the curing period, all traffic, both pedestrian and vehicular, shall be excluded. Sidewalks shall 
be protected from pedestrian traffic for at least 72 hours and from vehicular traffic for at least 7 days. 

7.6.4.4 

Finishing 

Type of finish shall be as shown on the Contract plans, as approved by the Engineer. 

Broom finishes shall be constructed in the following manner:  

1.  Strike-off the surface using a strike board and then float the surface

2.  Using a steel trowel, smooth the surface as soon as it can be worked

3.  Brush  the  walking  surfaces  of  the  sidewalk  and  ramps  in  a  direction  perpendicular  to  the

centreline with a stiff bristled broom. Broom from edge to edge with adjacent strokes slightly 
overlapped  to  produce  regular  corrugations  not  more  than  3  mm  deep  without  tearing  the 
concrete  

4.  While the concrete is plastic, correct porous spots, irregularities, depressions, small pockets,

and rough spots 

5.  Install the Contraction joints or perimeter edging, using an approved grooving tool

6.  Tool all exposed edges, including those at expansion joints, using an edging tool with a 6 mm

radius, or as indicated on the Contract plans 

Exposed aggregate finish shall be accomplished as follows: 

a.  Strike-off the surface using a strike board and then float the surface

b.  As  soon  as  the  concrete  hardens  sufficiently  to  prevent  particles  of  gravel  from  being

dislodged,  broom  the  surface  with  stiff  brooms  approved  by  the  Engineer  in  the  following 
manner:  

1.  Broom transversely across the pavement

2.  Pull the loosened semi-stiff mortar entirely off the pavement

3.  Remove the mortar from all adjacent pavements

4.  Broom parallel to the pavement centreline

5.  Repeat this operation to expose the required amount of coarse aggregate

c.  Exercise care to prevent marring of the surface and cracking or chipping of slab edges or joints

d.  If  approved  by  the  Engineer,  apply  a  light  spray  of  retardant  to  the  unfinished  surface  to

facilitate this work 

e.  Other methods of aggregate exposure, such as using a water spray attachment on a special

exposed aggregate broom, will be permitted if satisfactory results are demonstrated and the 
Engineer provides written approval 

f.  Install the Contraction joints or perimeter edging, using an approved grooving tool

g.  Tool all exposed edges, including those at expansion joints, using an edging tool with a 6 mm

radius or as indicated on the Contract plans. 

7.6.5 Pervious Concrete Sidewalks 

Concrete for pervious concrete sidewalks shall meet the requirements of permeable concrete,  as 
specified in Article 4.3.10.6 of Chapter 4, Concrete Works. 

Pervious concrete sidewalks shall be constructed in careful compliance to the  Contract plans, the 
Particular  Specifications,  and  these  Specifications.  Pervious  concrete  shall  be  properly  mixed, 
placed, and compacted, as approved by the Engineer, to be effective. Documentation that proves 
the following shall be provided by the Contractor to the Engineer:  

a.  Pervious concrete supplier, the Contractor, and each individual responsible for the installation

of  pervious  concrete  have  successfully  completed  at  least  3  pervious  concrete  installations 
within the past 3 years   

b.  Contractor has at least 3 years of competent work with pervious concrete

c.  Any applicable test results from previous jobs, if so requested by the Engineer

Alternately,  the  Engineer  may  approve  the  Contractor  for  pervious  concrete  sidewalk  installation 
based on his successful performance of mixing and placing of trial sections of sidewalk as required 
below. 

Preparation  for  the  Engineer

’s  inspection  and  approval  of  a  test  panel  shall  be  done  at  the 

Contractor

’s expense.  

Construction  of  pervious  concrete  sidewalks  shall  not  commence  until  the  Contractor  has 
successfully produced a test panel meeting the following requirements:  

1.  Test panels shall measure at least 9 m

and be of the same depth as the proposed sidewalk

2.  Test panels shall be prepared with the same materials and means, and on the same sub-base,

that the Contractor proposes for use in the final product 

3.  Test panel shall be marked for identification of batch number and date

4.  There shall be no skin of cement or mortar at the bottom or top of the pavement. Such skin

could prevent passage of water through the slab at its designed percolation rate 

5.  Concrete void spaces shall be 15 % to 20 %

6.  Unit weight shall be within ±5 % of the mix design unit weight

7.  Using a permeameter, or a procedure that the Engineer and the Contractor agree upon, the

Contractor shall demonstrate that the pavement has a percolation rate of at least 5 m per hour 

Preparation  of  the  foundation  shall  be  per  Article  7.6.3.17.6.3.2,  except  that  no  organic  material, 
clay, or organic sludge shall be allowed to remain in the soil below subbase.   

Subbases shall be installed in accordance with the dimensions, materials, and compaction shown 
on  the  Contract  plans,  with  the  additional  requirement  that  the  subbase  beneath  the  pervious 
concrete  must  be  of  enough  depth  and  properly  installed  to  temporarily  store  the  water  while  it 
infiltrates into the soil. If not otherwise shown on the Contract plans, the subbase depth, aggregate 
void ratio, aggregate sizing, and subgrade preparation shall meet the requirements of 

ADQCC (WA-

726) Stormwater and subsoil drainage system (Vol. 1,2,3, and 4);

 for permeable pavement design.

Sub-bases typically consist of at least 150 mm to 250 mm of open-graded aggregate or crushed or 
recycled  concrete  with  a  geotextile  fabric  layer  between  the  subgrade  soil  and  the  subbase 
aggregate.   

Prior to the placement of pervious concrete, the sub-base shall be tested for the rate of permeability 
by the double-ring infiltrometer, or another suitable test, as approved by the Engineer. Test borings 
are recommended to determine soil conditions and water table level. Borings may not be required, 
if undisturbed soil under the base demonstrates good permeability and stability and has not been 
disturbed  for  3  years  or  more.  Permeability  testing  and  certification,  if  required,  shall  be  the 
responsibility of the Contractor. 

Forms shall be steel unless the Contractor can successfully demonstrate that reinforced plastic or 
plastic-coated  plywood  forms  will  not  warp  or  move  under  screed  vibration  and  compaction. 
Appropriate release agents shall be applied to the forms before placing concrete and rollers used in 
compaction. When debris or aggregate begins to stick to compaction rollers, they shall be cleaned 
and recoated with a release agent to prevent ravelling. 

Pervious  concrete  shall  be  delivered,  installed,  finished,  and  cured  in  a  similar  manner  to 
conventional concrete except that the requirements  of  Table 7-33 shall supersede any conflicting 
requirements for conventional concrete.  

Table 7-33: Requirements for the installation of pervious concrete 

Preparation of the subgrade: 

  Subgrade shall be moist with no standing water immediately prior to concrete placement.

Acceptance of concrete: 

  Shall be based on visual inspection of each load for consistency and aggregate coating.

  Shall be based on unit weight of each load in lieu of slump tests. Pervious concrete is so

stiff that slump testing does not provide meaningful quality control. 

Placement: 

  Pervious concrete shall not be pumped.

  Discharge shall be a continuous operation completed as quickly as possible.

  Concrete shall be deposited as close to its final position as practicable.

  Fresh  concrete  shall  be  entered  and  adhere  to  the  mass  of  previously  placed  green

concrete. 

  Workers shall spread pervious concrete in advance of the screed without stepping in the

pervious  concrete  because  footsteps  could  prevent  formation  of  a  successful  void 
structure. 

  A screed shall be used to level off the surface of the pervious concrete.

  Vibrating  screeds,  manual  screeds,  laser  screeds,  or  other  screeds  are  acceptable  as

approved by the Engineer with the following qualifications: 

i.  For  vibrating  screeds,  frequency  of  vibration  shall  be  low  enough  to  avoid  over-

compaction or closing off of the surface. 

ii.  Manual screeds shall be discontinued if they cause tears in the surface.

  Screed shall strike-off material above the forms, typically  15 mm to 20 mm, to allow for

compaction. 

i.  This may be accomplished using temporary strips attached to the top of the form.

ii.  Alternatively, height-adjusting screeds may also be used.

  Edges near forms shall be compacted using 300 mm by 300 mm steel tamp, or a similar

device, to prevent ravelling. 

  Any vibration shall be shut off immediately when forward progress is halted for any reason.

  An evaporation retarder may be applied before compaction to minimise surface water loss,

if approved by the Engineer. 

Compaction shall be complete within 15 minutes after placement: 

C

ONSTRUCTION

 

 

  Pervious concrete shall be compacted by a heavy steel roller after screeding.  

  Unless otherwise approved by the Engineer in writing, the Contractor shall provide either 

slip-form  or  form-riding  equipment  with  a  following  compactive  unit  that  will  provide  a 
minimum of 70 kPa vertical force.  

  After  strike-off  and  compaction,  no  other  finishing  operation  will  be  allowed.  Pervious 

concrete shall not be floated, trowelled, or worked in any other way that might cause the 
pavement surface to be sealed or the voids to be filled.  

  Proper compaction shall result in at least 15 % voids.  

Curing shall begin within 20 minutes after compaction: 

  After placement, pervious concrete shall be misted with water and then covered with plastic 

sheeting and kept damp for at least 7 days.  

  Curing materials shall be secured as quickly as possible.  

  Sheeting shall overlap all exposed concrete and film edges by at least 300 mm.  

  Sheeting  shall  be secured  to  the  pervious  surface  to minimise  air  invasion  between  the 

sheeting and the pervious concrete.  

i.  If the Contractor elects to use a layer of soil to secure the cover, the Contractor shall 

take precautions to prevent spillage or contamination of the fresh pavement in placing 
and removing the soil layer. Soil shall be swept off of the sheeting prior to removing 
the sheeting.  

ii.  If rebar or wood are used to secure the sheeting, the Contractor shall make every effort 

to minimise bubbles and openings for air.  

  Placement and securing of  plastic sheeting shall  be approved by the  Engineer, and  the 

Contractor  shall  comply  with  the  Engineer

’s  direction  for  adjustments  to  curing 

arrangements. 

Completed installation shall be the dimensions shown on the Contract plans, ±12 mm in 3 m.  

During placement all tools, including screed machines, compaction rollers, rakes, trowels, and forms 
shall be kept clean and coated with a release agent to reduce the possibility of ravelling. Compaction 
rollers displaying aggregate adhesion will accelerate ravelling and disintegration.  

Contraction  joints  shall  not  be  installed  due  to  the  potential  for  excessive  ravelling  at  the  joints. 
Expansion joints sufficiently accommodate Contraction, and minor cracking is not detrimental to the 
surface aesthetic or the structural integrity of pervious concrete. Expansion joints shall be installed 
in the following manner:  

a.  At the locations and to the dimensions shown in the Contract plans or directed by the Engineer  

b.  At the same locations as in adjacent pavements to avoid reflective cracking  

c.  At intervals of 12 m to 18 m  

d.  Directly after consolidation using a rolling joint tool approved by the Engineer, or by driving a 

steel straightedge to the required depth with a hammer 

e.  To a depth of one-quarter the thickness of the pavement  

If joints are not installed directly after compaction, they may be saw cut into the pervious pavement, 
preferably occurring within 4 days of completing concrete placement, and no later than 7 days after 
concrete placement. To perform saw cuts during the curing period, the Contractor shall sweep the 
plastic covering, slit it, and fold it back to accommodate the saw cut. Upon completion of the saw 
cut, the Contractor shall fold the plastic back over the edges, cover the slit with a new piece of plastic 
that overlaps each side by 300 mm or more, and secure the plastic for the remainder of the curing 
period.  

When a pour is interrupted, it should be terminated against a form and properly compacted. A 45° 
groove measuring 25 mm deep shall be created adjacent to the form. When the pour is continued 

thereafter,  a  similar  groove  shall  be  formed  into  the  joint  formed  by  the  new  pour,  matching  the 
previous groove. Resulting V-shapes can then be filled with an approved joint filler. 

No sand or soil shall be stored or placed directly on pervious surfaces.  Contractor shall schedule 
pervious installation as near the conclusion of a construction project as possible. At the Engineer

’s 

request, the Contractor shall vacuum pervious concrete before opening the area to pedestrians and 
traffic. 

7.6.6 Paver Sidewalks 

Materials,  tolerance,  curing,  and  installation  requirements  for  interlocking  concrete  paving  blocks 
shall be in accordance with Section 7.9. Other type of pavers for sidewalks shall be in accordance 
with the requirements specified herein. 

Kerbs or edging abutting the areas to be paved shall be laid in advance of paver installation. 

Preparation of the foundations shall be per  Article 7.6.3.17.6.3.2. Where specified, or required by 
the Engineer, the prepared surface shall be treated with an approved environmentally compatible 
herbicide and ant poison before the layer of sand for bedding is placed. 

Layers of uncompacted sand shall be screeded to a depth of 50 mm over the compacted base. This 
layer of bedding sand shall not be used for levelling. Sand shall be spread and then left loose and 
protected  against  precompaction,  including  compaction  by  rain  or  dew.  Any  sand  that  has 
precompacted shall be loosened in advance of the laying face to the extent to which paving will be 
completed that day. Sand shall continue to be lightly screeded by the Contractor in a loose condition 
to the predetermined depth, slightly ahead of laying the paving units. 

Pavers with chips, cracks, voids, discolouration, and other visible defects shall not be used. Pavers 
from several pallets or cubes shall be mixed as they are placed to produce a uniform blend of colours 
and textures. Pavers shall be  cut with a motor-driven masonry saw or block splitter equipment to 
provide clean, sharp, unchipped edges.  

When laying the pavers, the Contractor shall ensure that the blocks avoid disturbance of the sand 
cushion  until  the  unit  is  in  its  correct  position.  Disturbances  to  adjacent  pavers  shall  likewise  be 
avoided.  

Pattern for laying the paving blocks and their thickness shall be as shown on the Contract plans, as 
approved  by  the  Engineer.  Unbroken  blocks  shall  first  be  laid  and  filler  pieces  afterwards.  Filler 
pieces shall be neatly sawn or hewn to fit exactly into the space to be filled. Spaces of less than 25 
% of a full-sized block may be filled with Class C30 concrete. Top faces of blocks shall be flush.  

After each 15-m

to 20-m

2

 area of paving blocks has been laid, the pavement shall be compacted by 

2 passes of a suitable vibrating-plate compactor operating at a frequency of 65 hz to 100 hz and a 
low amplitude with the following requirements:  

1.  For 60-mm-thick blocks, the compactor shall have a centrifugal force of 7 kN to 16 kN and a

plate area of 0.2 m

2

 to 0.4 m

2

 

2.  For 80-mm-thick blocks, the compactor shall have a centrifugal force of 16 kN to 20 kN and a

plate area of 0.35 m

to 0.5 m

2

 

Two  passes  shall  be  made  at  90  degrees  of  each  other,  and  the  plate  compactor  shall  not  pass 
closer  than  1  m  to  a  temporarily  unrestrained  edge  during  laying.  No  paving  shall  be  left  in  an 
uncompacted condition overnight, except for the 1 m strip at the temporarily unrestrained edge.  

After compaction of the pavement as described above, joint and Class M3 mortar, per Article 4.3.10.4 
of Chapter 4, Concrete Works, shall be spread and brushed into the joints until the joints have been 
properly  filled.  After  the  joint  material  has  dried,  any  surplus  sand  shall  be  broomed  off  and  the 
pavement shall then be subjected to 2 further passes by the plate vibrator.  If necessary, the joint 
sand shall be filled again and further passes of the plate vibrator shall be made in each direction, 
until  the  sand  is  no  longer  absorbed  into the  joints.  Joint  widths  between  blocks  shall  be  per the 
Contract plans, typically between 2 mm and 6 mm. 

 

 

 

 

 

 

 

Content      ..     45      46      47      48     ..