Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 31

 

  Главная      Manuals     Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     29      30      31      32     ..

 

 

 

Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 31

 

 

 

 

 

saws or grinders shall not be used.  If power equipment is used before removing mortar from the 
structure,  the  operator  shall  demonstrate  proficiency  to  the  Engineer.    After  removing  mortar  the 
Contractor shall complete the following sequence to repoint:  

1.  Remove mortar to a depth of 2.5 times the width of the joint.  

2.  Remove any dirt or vegetation with a wire brush or other tools approved by the Engineer.  

3.  Clean joint of all loose fragments and dust with pressurized air or water. 

4.  Before filling the joint, dampen adjacent stone.  

5.  Do not place mortar to a depth greater than 2.5 times the joint width.  

6.  Place mortar in layers of approximately 6mm for joints deeper than 2.5 mm.  

7.  Add successive layers, once mortar has reached thumb-print hardness.  

8.  Tool the final layer to match the approved joint appearance.  

A  1  m  test  section  of  joint  shall  be  constructed  along  the  structure  for  the  Engineer

’s  approval 

before continuing with work. Approved test section maybe incorporated into the work. 

After the mortar has dried,  but before the initial set, the Contractor shall clean excess mortar and 
stain  from  rock  masonry  using  a  bristle  brush.  Chemicals  shall  not  be  used  for  cleaning  unless 
approved  by  the  Engineer.  Joints  shall  be  protected  by  keeping  damp  for  3  days  after  work  has 
been completed. 

6.3.3.1 

Rock Walls 

Rock walls shall be constructed per  Article 7.3.4.2 of Chapter 7, Incidental Construction, of these 
standard specifications. 

6.3.3.2 

Facing for Concrete 

Rock  masonry  may  be  used  as  a  facing  for  concrete  in  two  scenarios:  where  the  rock  is  placed 
before the concrete, and where the concrete is placed before the rock 

a.  Rock Placed before Concrete 

To  improve  the  bond  to  the  concrete  backing,  the  back  of  the  masonry  shall  be  made  uneven. 
Contractor  shall  use  32  mm  reinforcing  steel  bent  into  an  elongated  letter  S  to  anchor  the  rock. 
Each anchor shall be embedded in a mortar bed to within 50 mm of the face of the stones while the 
opposite end shall project ±250 mm into the concrete backing. Anchor spacing shall be 0.5m both 
horizontally and vertically.  

After the mortar has attained sufficient strength,  Contractor shall clean the back masonry surface 
of  all  dirt,  loose  material,  and  mortar  drippings,  and  then  wash  surfaces  using  a  high-pressure 
water jet just before placing the concrete. 

When  placing  the  concrete,  a  neat  cement  grout  of  the  consistency  of  cream shall  be  carried  on 
top of the concrete and against the masonry at all times. All interstices in the back of the masonry 
shall be coated with grout. 

b.  Concrete Placed before Rock 

Facing  thickness  shall  be  allowed  as  shown  on  the  Contract  plans.  Galvanized  metal  slots  with 
anchors shall be set in the concrete face. Anchors spacing shall be at most 600 mm in the vertical 
and  horizontal  directions.  Contractor  shall  place  a  temporary  filling  of  felt  or  other  material  in  the 
slots to prevent filling with concrete. 

Where  setting  the  rock  facing,  the  metal  anchors  shall  be  fit  tightly  in  the  slots  at  an  average 
vertical  spacing  of  600  mm.  At  least  25  %  of  the  anchors  shall  be  bent  at  a  short  right  angle  to 
engage a recess cut in the stone. Anchors shall extend to within 75 mm of the exposed face of the 
stone work. 

 

 

 

Where the shape of the concrete face is unsuitable for the use of metal slots, the Contractor shall 
use 3.8 mm coated steel wire ties conforming to ASTM A884/A884M - 06, Class A.   at a rate of 7 
ties for each m

2

 of exposed surface. Contractor shall use a gut to install ties after the concrete has 

cured. 

Concrete  face  shall  be  kept  continuously  wet  for  2  hours  preceding  the  placing  of  the  rock  and 
spaces between the stones and concrete shall be filled with mortar. 

6.3.3.3 

Masonry Guardwall 

When  shown  on  the  Contract  plans  or  required  in  the  Particular  Specifications,  decorative  rock 
masonry  may  be  used  for  guardwalls  (refer  to  Figure  6-1,  below  for  typical  sections  of  typical 
guardwall  used  for  traffic  barriers,  refer  to  AASHTO, 

Roadside  Design  Guide,  Section  5.4.1.10

). 

Concrete  corewalls  for  guardwall  may  be  cast-in-situ  or  precast  units  as  shown  on  the  Contract 
plans, otherwise defined in the Particular Specifications, or as approved by the Engineer. Concrete 
shall have a minimum 28-day compressive strength of 25 mPa.  Contractor shall construct an 8 m 
sample  section  of  guardwall  and  shall  not  construct  additional  guardwall  before  the  sample  is 
approved. 

Guardwall shall be constructed true and uniform along its length with no stone projecting more than 
38  mm.  Mortar  beds  and  joints  shall  be  made  according  to  Table  6-6.  Joints  and  beds  shall  be 
raked to a depth of 50 mm on the front and top, and to 38 mm on the back. 

A  1-piece  capstone  shall  be  used  for the full  width  of  the  guardwall  for  at  least  25  %  of  the total 
length. A 2-piece capstone with the joint within 100 mm of the guardwall centre shall be  used for 
the remaining length. 

All  stones,  including  the  capstones,  shall  be  placed  randomly to  avoid  a  pattern.  Stones  shall  be 
laid  to  reflect  the  width  of  the  expansion  joints  without  leaving  a  gap  or  a  mortar  edge  at  the 
expansion joint. Stones of various sizes shall be used to coin or key the corners of the guardwall.  
Typical examples of masonry guardwalls are shown below. 

 

 

 

Figure 6-1: Typical examples of masonry guardwalls. 

 

 

Material or accessory 

Requirement 

Steel drill screws 

For metal-to-metal fastening, ASTM C1002 or 
ASTM C954, as required by thickness of metal 
being fastened; with pan head that is suitable for 
application; in lengths required to achieve 
penetration through joined materials of not fewer 
than 3 exposed threads 

Fasteners  for  attaching  metal  lath  to 
substrates 

ASTM C1063 

Sound attenuation blankets 

ASTM C665, Type I (blankets without membrane 
facing), produced by combining thermosetting 
resins with mineral fibres manufactured from 
glass, slag wool, or rock wool 

Fire-resistance-rated assemblies 

Comply with mineral-fibre requirements of 
assembly 

Isolation strip at exterior walls 

asphalt-saturated organic felt 

Foam gasket 

ASTM D226M, Type I (No. 15 asphalt felt), 
unperforated 

Adhesive-backed, closed-cell vinyl foam strips that 
allow fastener penetration without foam 
displacement, 3.1 mm thick, in width to suit steel 
stud size 

Water for mixing shall meet the requirements of Section 4.3.8 of Chapter 4, Concrete Works. 

Plaster materials shall meet the requirements of Table 7-46.  

Table 7-46: Requirements for plaster materials for integral colour plaster 

Material 

Requirement 

Portland cement 

Colour for finish coats 

ASTM C150M, Type I 

Gray 

Masonry cement 

Colour for finish coats 

ASTM C91, Type N 

Gray 

Plastic cement 

ASTM C1328 

Colourants for job-mixed finish-coats 

Colourfast  mineral  pigments  that  produce  finish 
plaster colour to match Engineer's sample 

Lime 

ASTM C206, Type S; or ASTM C207, Type S 

Sand aggregate 

Colour for job-mixed finish coats 

ASTM C897 

In colour matching Engineer's sample 

Plaster mixes shall comply with ASTM C926 for applications indicated, and shall comply with the 
requirements of Table 7-47. Fibre shall be added to base-coat mixes after ingredients have mixed 
at  least  2  minutes.  Fibre  quantities  in  mixes  shall  comply  with  the  fibre  manufacturer's  written 
instructions and shall not exceed 16 kg fibre per m

3

 of cementitious materials. Aggregate quantities 

shall be reduced accordingly to maintain workability.  

Table 7-47: Integral colour plaster mixes 

Mix description 

Requirements 

Masonry cement mixes: 

Scratch coat 

One part masonry cement and 2.5 parts to 4 parts aggregate 

Brown coat 

One part masonry cement and 3 to 5 parts aggregate 

Portland and masonry cement mixes:

 

Scratch coat 

For cementitious material, mix 1 part Portland cement and 1-
part masonry cement. Use 2.5 parts to 4 parts aggregate per 
part of cementitious material (sum of separate volumes of each 
component material) 

Brown coat 

For cementitious material, mix 1 part Portland cement and 1part 
masonry cement. Use 3 to 5 parts aggregate per part of 
cementitious material (sum of separate volumes of each 
component material) 

Portland and plastic cement mixes: 

Scratch coat 

For cementitious material, mix 1-part plastic cement and 1 part 
Portland cement. Use 2.5 parts to 4 parts aggregate per part of 
cementitious material (sum of separate volumes of each 
component material) 

Brown coat 

For cementitious material, mix 1-part plastic cement and 1 part 
Portland cement. Use 3 to 5 parts aggregate per part of 
cementitious material (sum of separate volumes of each 
component material) 

Base-coat mixes for use over 
monolithic concrete 

Portland cement mix 

Portland 

and 

masonry 

cement mix 

Plastic cement mix 

Single base coats for 2-coat plasterwork 

For cementitious material, mix 1 part Portland cement and 0-
part to three-quarters part lime. Use 2.5 parts to 4 parts 
aggregate per part of cementitious material (sum of separate 
volumes of each component material) 

For cementitious material, mix 1 part Portland cement and 1 
part masonry cement. Use 2.5 parts to 4 parts aggregate per 
part of cementitious material (sum of separate volumes of each 
component material) 

Use 1 part plastic cement and 2.5 parts to 4 parts aggregate 

Base-coat mixes for use over 
concrete masonry units 

Portland cement mix 

Masonry cement mix 

Plastic cement mix 

Single base coats for 2-coat plasterwork 

For cementitious material, mix 1 part Portland cement and 
three-quarters part to 1.5 parts lime. Use 2.5 parts to 4 parts 
aggregate per part of cementitious material (sum of separate 
volumes of each component material) 

Use 1-part masonry cement and 2.5 parts to 4 parts aggregate 

Use 1 part plastic cement and 2.5 parts to 4 parts aggregate 

Job-mixed finish-coat mixes 

Portland cement mix 

For cementitious materials, mix 1 part Portland cement and 1.5 
parts to 2 parts lime. Use 1.5 parts to 3 parts aggregate per part 

Mix description 

Requirements 

Masonry cement mix 

Portland 

and 

masonry 

cement mix 

Plastic cement mix 

Factory-prepared finish-coat 
mixes 

of cementitious material (sum of separate volumes of each 
component material) 

one-part masonry cement and 1.5 parts to 3 parts aggregate 

For cementitious materials, mix 1 part Portland cement and 1 
part masonry cement. Use 1.5 parts to 3 parts aggregate per 
part of cementitious material (sum of separate volumes of each 
component material) 

one-part plastic cement and 1.5 parts to 3 parts aggregate 

For ready-mixed finish-coat plasters comply with manufacturer's 
written instructions 

7.8.3.3 

Construction Requirements 

Project  conditions  shall  meet  the  requirements  of  ASTM  C926.  For  interior  plasterwork,  the 
Contractor shall do the following: 

a.  Maintain  room  temperatures  at  greater  than  10

o

  C  for  at  least  48  hours  before  plaster

application, and continuously during and after application 

b.  Avoid conditions that result in plaster drying out during curing period

c.  Distribute heat evenly; prevent concentrated or uneven heat on plaster

d.  Ventilate building spaces as required to remove water in excess of that required for hydrating

plaster  in  a  manner  that  prevents  drafts  of  air  from  contacting  surfaces  during  plaster 
application and until plaster is dry 

For exterior plasterwork, the Contractor shall do the following: 

1.  Apply and cure plaster to prevent plaster drying out during curing period

2.  Use procedures required by climatic conditions, including moist curing, providing coverings,

and providing barriers to deflect sunlight and wind 

3.  Apply plaster when ambient temperature is greater than 10

o

 C.

4.  Protect  plaster  coats  from  freezing  for  not  less  than  48  hours  after  set  of  plaster  coat  has

occurred 

Contractor  shall  ensure  that  the  manufacturer's  written  recommendations  for  environmental 
conditions are met before applying finishes. Adjacent work shall be protected from soiling, spattering, 
moisture deterioration, and other harmful effects caused by plastering. Solid-plaster bases that are 
smooth or that do not have the suction capability required to bond with plaster shall be prepared 
according to ASTM C926. 

Before sprayed fire-resistive materials are applied, the Contractor shall attach offset anchor plates 
or  ceiling  runners (tracks)  to  surfaces  indicated to receive  sprayed  fire-resistive materials.  Where 
offset anchor plates are required, continuous plates fastened to building structure not more than 610 
mm  on  centre  shall  be  provided.  After  sprayed  fire-resistive  materials  are  applied,  they  shall  be 
removed only to the extent necessary for installation of plaster assemblies and without reducing the 
fire resistive material thickness to less than that required to obtain fire-resistance rating indicated. 
Remaining fire-resistive materials shall be protected by the Contractor from damage. 

Fire-resistance-rated  assemblies  shall  be  installed  according  to  the  requirements  for  design 
designations from listing organisation and publication indicated on Contract plans. 

Accessories  shall  be  installed  according  to  ASTM  C1063  and  at  locations  indicated  on  Contract 
plans. Reinforcement for external corners shall include the following: 

  Lath-type external-corner reinforcement at exterior locations

  Corner bead at interior and exterior locations.

Control joints shall be installed at locations indicated by the manufacturer subject to approval by the 
Engineer for visual effect as follows: 

a.  As required to delineate plasterwork into areas (panels) of the following maximum sizes:

1.  Vertical surfaces: 13.4 m

2

2.  Horizontal and other nonvertical surfaces: 9.3 m

2

b.  At distances between control joints of not greater than 6.0 m on centre

c.  As  required  to  delineate  plasterwork  into  areas  (panels)  with  length-to-width  ratios  of  not

greater than 2.5:1 

d.  Where control joints occur in surface of construction directly behind plaster

e.  Where plasterwork areas change dimensions, to delineate rectangular shaped areas (panels)

and to relieve the stress that occurs at the corner formed by the dimension change 

Plaster applications shall comply with ASTM C926. Finished surfaces shall not deviate more than 
±6.4 mm in 3 m from a true plane, as measured by a 3 m straightedge placed on the surface. Hollow-
metal frames, bases, and similar work occurring in plastered areas shall be grouted with base-coat 
plaster material, before lathing where necessary. Except where full grouting is indicated or required 
for fire-resistance rating, grout shall measure at least 152 mm at each jamb anchor. Plaster shall be 
finished flush with metal frames and other built-in metal items or accessories that act as a plaster 
ground, unless otherwise indicated. Where casing bead does not terminate plaster at metal frame, 
base coat shall be cut free from metal frame before plaster sets and groove finish coat at junctures 
with metal. 

Plaster surfaces that are ready to receive field-applied finishes indicated shall be provided by the 
Contractor, who shall use independent scaffolding to avoid putlog holes and other breaks in surfaces. 

Bonding compounds shall be applied on unit masonry and concrete plaster bases. Contractor shall 
apply wood or plastic float finish to achieve an even and rough Arabic texture finish. 

Concealed interior plasterwork shall be constructed of the following: 

a.  Where plaster application will be concealed behind built-in cabinets, similar furnishings, and

equipment, apply finish coat 

b.  Where plaster application will be concealed above suspended ceilings and in similar locations,

finish coat may be omitted 

c.  Where plaster application will be used as a base for adhesive application of tile and similar

finishes, finish coat may be omitted 

Contractor shall cut, patch, replace, and repair plaster, as necessary, to accommodate other work 
and to restore cracks, dents, and imperfections. Work shall also be repaired or replaced to eliminate 
blisters, buckles, crazing and check cracking, dry outs, efflorescence, sweat outs, and similar defects 
and where bond to substrate has failed. Temporary protection and enclosures of other work shall be 
removed by the Contractor. Promptly remove plaster from doorframes, windows, and other surfaces 
not indicated to be plastered. Repair floors, walls, and other surfaces stained, marred, or otherwise 
damaged during plastering. 

7.9  Interlocking Concrete Paving Blocks 

7.9.1 Description 

Interlocking  concrete  pavers  shall  comply  with  the  requirements  specified  herein.  All  interlocking 
concrete pavers shall be from manufacturers with valid product certification as per Abu Dhabi Quality 
Conformity Council product conformity scheme. 

C

ONSTRUCTION

 

 

A.  Paver  thickness  shall  be  60mm  for  pedestrian  areas  and  80-140  mm  for  vehicular  areas. 
Dimensions are based on ASTM C936. 

B. The paving block manufacturers shall achieve the desired aesthetic appearance and finish of the 
paving blocks by careful combination of fine and coarse aggregates within the general grading limits 
specified herein to ensure an acceptable smooth surface is achieved. 

 

7.9.2 Products 

7.9.2.1 

Constituent Materials Specifications 

The constituent materials of the interlocking concrete pavers shall comply with the requirements of 
the following articles. 

A. Cement: The cement to be used in the manufacture of paving blocks shall be sulphate-resisting 
Portland  cement  Type-V,  or  ordinary  Portland  cement  with  partial  cement  replacement  by 
supplementary  cementitious  materials  such  as  fly  ash  and  ground  granulated  blast-furnace  slag 
(GGBS), and microsilica, etc., in accordance with ASTM C150.  

B. Aggregates: The aggregates to be used in the manufacture of the paving blocks shall be from 
crushed  rocks  and  from  approved  sources,  conforming  to  the  requirements  of  BS  EN 
12620:2002+A1:2008.  The  sand  shall  be  washed  and  free  from  deleterious  substances.  The 
aggregate shall not contain harmful material such as coal, mica, shale or similar laminated materials 
which cause strength deterioration.  

1. 

Coarse  Aggregate

:  Coarse  aggregate  for  paving  blocks  shall  meet  the  following 

requirements: 

Table 7-48. Coarse Aggregate for Interlocking Concrete Pavers 

Properties 

Test Method

(1)

 

Permissible Limit 

Particle Size Distribution 

BS EN 933-1:2012 

As 

per 

BS 

EN 

12620:2002+A1:2008 

Clay Silt & Dust 

BS EN 933-1:2012 

Max 1% 

Organic Matter Content 

BS 1377-3:1990 

Nil 

Water Absorption 

BS EN 1097-6:2013 

Max 1.5% 

Relative Density 

BS EN 1097-6:2013 

Min 2.6 

Shell Content 

BS EN 933-7:1998 

Nil 

Flakiness Index 

BS EN 933-3:2012 

Max 25% 

Elongation Index 

BS 812-105.2:1990 

Max 25% 

Soundness  (Mg  SO

4

)  5 

cycles 

ASTM C88-13 

Max 5% 

Sulphate Content (SO

3

BS 

EN 

1744-

1:2009+A1:2012 

Max 0.3% 

Chloride Content (Cl) 

BS 

EN 

1744-

1:2009+A1:2012 

Max 0.20% 

C

ONSTRUCTION

 

 

Table 7-48. Coarse Aggregate for Interlocking Concrete Pavers 

Aggregate Crushing Value 

BS EN 1097-2:2010 

Max 25% 

Los Angeles Abrasion 

AASHTO T 96-02 

Max 25% 

Note:  1) All standards refer to the latest version unless otherwise specified. 

 

2. 

Fine Aggregate

: Fine aggregate for paving blocks shall meet the following requirements:  

Table  7-49: Fine Aggregate for Interlocking Concrete Pavers 

Properties 

Test Method 

Permissible Limit 

Particle Size Distribution 

BS EN 933-1:2012 

As 

per 

BS 

EN 

12620:2002+A1:2008 

Clay Silt & Dust 

BS EN 933-1:2012 

Max 3% passing 75 µm 
sieve 

Organic Matter Content 

BS 1377-3:1990 

Nil 

Water absorption 

BS EN 1097-6:2013 

Max 2% 

Relative Density (Apparent) 

BS EN 1097-6:2013 

Min 2.6 

Shell Content 

BS EN 933-7:1998 

Max 1% 

Soundness  (Mg  SO

4

)  5 

cycles 

ASTM C88:13 

Max 5% 

Acid Soluble Materials 

BS 

EN 

1744-

1:2009+A1:2012 

Max  0.25% 

Sulphate Content (SO

3

BS 

EN 

1744-

1:2009+A1:2012 

Max 0.3% 

Chloride Content (Cl) 

BS 

EN 

1744-

1:2009+A1:2012 

Max 0.1% 

 

C. Water: The water to be used in mixing and curing the precast concrete blocks shall be of drinking 
quality,  clean  and  free  from  injurious  substances  of  sewage,  oil,  acids,  strong  alkalis,  vegetable 
matter, clay and other such substances harmful to the finished product.  

D. Pigment: Pigment shall comply to ASTM C979 to be used in manufacturing of precast concrete 
interlocking blocks shall be in the form of dry, soft powder of mineral oxides and shall not contain 
chemical compounds capable of affecting adversely the setting and development of strength of the 
cement and other properties of the finished products and shall be compatible with other admixtures 
used in the same mix. Pigments can be used throughout the concrete or for the top layer only in 
double mix production. Surface protection against color fading or chemical attaches are possible, 
but must be specifically recommended by purchaser.  

7.9.3 Design Mix 

The design mix shall comply with the requirements of the following articles. 

A. Combined Aggregate Grading: The combined grading shall satisfy the following limits.

Table 7-50: Combined Aggregate Grading for Interlocking Concrete Pavers 

Diameter 

Limit (Percent Passing 

(1,2)

8.0 mm 

100% 

4.75 mm 

72-82%

2.36 mm 

41-61%

1.18 mm 

25-46%

600 μm 

16-31%

300 μm 

8-17%

150 μm 

3-8%

75 μm 

0-3%

Notes:  1. Smooth, non-gap graded curve is expected. 

2. Central tendency should be attempted.

B. Cement Content: The cement content shall be a minimum of 430 Kg/m

3

.

C. Water Cement (W/C) Ratio: The water cement ratio shall be a maximum of 0.42.

D.  Pigment  Content:  Only  mineral  oxide  type  from  reputable  source  with  test  certificates.  The
pigment content shall not exceed 10% by mass of cement. 

7.9.4 Physical & Mechanical Properties 

The  physical  and  mechanical  properties  of  the  interlocking  concrete  blocks  shall  conform  to  the 
following requirements.   

A. Bulk Density (min. 48 hrs. immersion):

1.  Average > 2.375 T/m

3

2.  Minimum = 2.330 T/m

3

B. Bulk/Apparent Density Ratio (min. 48 hrs. immersion)

1.  Average > 0.88

2.  Minimum = 0.87

C. Water Absorption (min. 48 hrs. immersion, tested according to ASTM C140)

1.  Maximum = 3% for aggressive exposure zones

1

, and 4.5% for less aggressive exposure

zones

2

 

D. Compressive Strength (min. 48 hrs. Immersion, tested according to BS 6717:1993)

1. 

Average ≥ 55 Mpa for aggressive exposure zones, and 49 for less aggressive exposure
zones 

2.  Minimum = 47 Mpa for aggressive exposure zones, and 44 for less aggressive exposure

zones 

E. Abrasion Resistance (for vehicular areas only, tested as per ASTM C418)

1.  Average thickness loss < 3 mm

2.

Maximum volume loss = 150 mm

3

 per 500 mm

3.  Or comply with BS EN 1338 (maximum volume loss 20,000 mm

3

 per 5,000 mm

2

F. Flexural Strength (tested according to ASTM C293 / C293M: 10)

1.  Average Flexural Strength > 5 Mpa (Dry)

2.  Minimum Flexural Strength = 4.5 Mpa (Dry)

G. At least 4 out of 5 of all tested specimens shall meet the specified average criteria for all physical
and mechanical properties specified. 

H.  The paving block manufacturers may achieve the physical properties specified herein for their
products  through  various  means  such  as  addition  of  mineral  and/or  chemical  admixtures  to  the 
concrete mix for the paving blocks.  

I. Concrete paving blocks shall be adequately cured, as specified, so that they comply with all the
physical and mechanical properties upon delivery to site. 

J. Any consignments delivered to site that do not comply with the specified physical and mechanical
properties shall be rejected by the Purchaser and the Manufacturer shall remove the consignment 
from site.  

K. Durability Criteria:

1.  AS/NZS 4456.10:2003, method B

2.  Resistance to sodium sulphate and sodium chloride

3.  Conduct the test for 40 cycles and record the total loss

4.  Total loss after 40 cycles < 1% of mass of specimen

7.9.5 Dimensional Tolerance 

A.  The  length  or  width  of  each  unit  shall  not  differ  by  more  than  ±1.6mm  from  the  designated
dimensions. 

B. The height of each unit shall not differ by more than ±3% from the specified standard thickness.

1

 Aggressive exposure zones are those areas where a shallow water table is known to be present. This underground water is generally 

brackish, where salt and other mineral content is capable of attacking Interlocking Concrete Pavers. This type of zone is generally found 
in Abu Dhabi City and other coastal areas throughout the Emirate.  

2

 Less aggressive exposure zones have deeper water tables, comprising more fresh water. This type of zone is generally found in regions of 

Al Ain and Al Gharbia.  

C

ONSTRUCTION

 

 

7.9.6 References 

1)  ASTM C88 

2)  ASTM C150 

3)  ASTM C293 

4)  ASTM C418 

5)  ASTM C936 

6)  BS 812 

7)  BS 1377 

8)  BS 6717 

9)  BS 7533 

10) BS EN 933 

11) BS EN 1097 

12) BS EN 12620 

13) BS EN 1744 

14) AASHTO T 96-02 

7.10 Installation Guidelines 

7.10.1 

General 

Interlocking  concrete  pavers  shall  comply  with  the  requirements  specified  herein.  Installation  of 
interlocking concrete pavers shall be carried out only by companies with a valid certification as per 
Abu Dhabi Conformity Council installation guidelines conformity scheme.   

A.  Pavers for vehicular areas shall be manufactured in a single or double mix as required by the 
purchaser. Single mix shall be preferred for vehicular load applications and double mix for pedestrian 
areas or where decorative appearances are requested. 

 

B.  The thickness of the paving blocks shall be selected in light  of the sub base material, the sub 
grade soil, the expected load, load frequency, and shape of the blocks as indicated on the contract 
document/ as applicable. 

C. An edge chamfer around the wearing surface is standard. Blocks without chamfers are possible, 
but must be requested by the purchaser.  

D. The project contractor shall provide a 10-year performance guarantee for the single and double 
mix  paving  blocks  against  de-lamination  and  colour  fading  beyond  normal  wear  and  tear  in  the 
emirate of Abu Dhabi environment. The 10- year (see Appendix 1) guarantee shall be back-to-back 
from the concrete paving block manufacturer.

 

7.10.2 

Products & Execution 

7.10.2.1 

Curing & Handling 

A. Following the manufacturer curing process, all consignments delivered to project site shall comply 
with performance criteria required on ADS 15.  

7.10.2.2 

Installation  

The installation of interlocking concrete pavers shall comply with the requirements specified herein, 
and elsewhere in these specifications.  

A. The subgrade and/or aggregate base course for pedestrian and vehicular concrete paving blocks
shall  be  prepared  as  per  the  particular  specifications  and  Contract  documents,  as  applicable. 
Moreover, in absence of these document, the subgrade shall follow ASTM, ASHTO, or EN standard. 

B. Installation teams are to be properly trained and to have previous experience in the installation of
interlocking pavers and shall follow the requirement/ specification recommended by manufacturers, 
as approved by the Owner. 

C. After preparation of the subgrade or aggregate base course for the concrete paving blocks, as
applicable,  the  Contractor  shall  place  50mm  of  bedding  sand  complying  with  the  grading  limits 
specified in the table below. The bedding sand shall be crushed material.  

Table 7-51: Grading for Bedding Sand for Less Aggressive Zone

(1) 

Sieve Size 

Percent Passing for Each Sieve

(2)

 

5 mm 

89 to 100% 

2.36 mm 

65 to 100% 

1.18 mm 

45 to 100% 

600 µm 

25 to 80% 

300 µm 

5 to 48% 

150 µm 

0 to 15% 

75 µm 

0 to 5% 

Notes:  1) Less aggressive exposure zones have deeper water tables, comprising 
more fresh water.    This type of zone is generally found in regions of Al Ain and Al 
Gharbia. 

2) As per BS 7533 Part 3 Category IV for pedestrian surface.

Table 7-52: Grading for Bedding Sand for Aggressive Zone

(1)

 

Sieve Size 

Percent Passing for Each Sieve

(2)

 

14mm 

100% 

10mm 

98 to 100% 

6mm 

85 to 99% 

2mm 

0 to 15% 

1mm 

0 to 2% 

63 µm 

0 to 1% 

Notes:  1) Aggressive exposure zones are those areas where a shallow water table is 
known to be present. This underground water is generally brackish, where salt and 
other mineral content is capable of attacking Interlocking Concrete Pavers. This type 

Table 7-52: Grading for Bedding Sand for Aggressive Zone

(1)

 

of zone is generally found in Abu Dhabi City and other coastal areas throughout the 
Emirate. 

2) According to BS EN 13043, category 2.8/6.3 G

c

80/15.

D.  The bedding sand shall be uniformly spread over the compacted subgrade or aggregate base
course, as applicable for pedestrian or vehicular areas, and screed uniformly to grade approximately 
5 to 10 mm higher than required. Actual height to be determined from site trial. 

E. The sub base/ subgrade below the bedding aggregates to a depth of 30 cm shall have maximum
acid-soluble total salt content < 1% (according to BS 1377 Part 3) 

F. Where utilities are present, preparation of subgrade and sub base should be in accordance with
utility providers’ requirements, including minimum depth of cover. 

G. Concrete paving blocks in the approved pattern should be placed as close together as possible
such that the spaces of the joints are between approximately 3 mm and 5 mm. It is important that 
the spaces be consistent so that the pattern will remain constant.  

H. Utility chamber access openings should be integrated with the paving pattern.

I. Paving blocks should be laid from a mix of pallets to avoid any significant colour banding due to
variation in batches. 

J. Any necessary cutting of concrete paving blocks shall be done with a mechanical block splitter or
a purpose built proprietary diamond saw. In all such situations, only cut paving units with true, even 
and undamaged edges shall be laid. Cut paving with ragged edges and producing voids shall not be 
installed. Cut pieces to be laid shall not be less than 30% of a full paving unit and where necessary 
the cut shall be shared uniformly with the next complete unit. 

K. Dimensional accuracy, uniformity of joint gaps, alignment and squareness shall be checked after
laying  the  first  three rows  of  blocks  and  thereafter  at  regular  intervals.  If  joints  begin to  open the 
blocks shall be knocked together using a rubber mallet. 

L. After each 100m², or such area that has been agreed with the Owner, has been laid the blocks
shall be compacted to the required levels using a plate vibrator. 

M. Interlocking concrete paving blocks should be tamped with a mechanical plate vibrator equipped
with a rubber pad on the tamping face (to minimize damage to the finished surface and appearance 
of the paving blocks), until pavers are uniformly levelled, true to grade and free of any movement. 
The mechanical plate vibrator shall have a plate area of 0.20 to 0.35m² and have a compaction force 
of  12-24  KN  and  a  frequency  of  approximately  75  to  100  Hz.  Compaction  above  and  around 
underground chambers requires particular attention. 

N. The joints in the paving blocks shall be filled with sand complying BS 7533-3:2005+A1:2009 by
sweeping in the jointing sand, unless otherwise approved by project Owner. The grading limits for 
the jointing sand specified in BS 7533-3:2005+A1:2009 are indicated in the table below. 

Table 7-53: Grading for Jointing Sand 

Sieve Size 

Percentage Passing Each Sieve 

2.36 mm 

100% 

1.18 mm 

95-100%

600 μm 

50-100%

C

ONSTRUCTION

 

 

Table 7-53: Grading for Jointing Sand  

300 μm 

15-60% 

150 μm 

0-15% 

75 μm 

0-3% 

 

P.  No  paving  shall  be  left  uncompacted  overnight  except  for  the  1m  strip  at  the  temporary 
unrestrained edge. 

Q.  Upon  completion,  the  finished  surface  level,  shall  be  within  5mm  of  the  design  level  and  the 
maximum deviation within the compacted surface, measured by a 3m straight edge shall not exceed 
2mm. The level of any two adjacent blocks shall not differ by more than 1mm. Any areas of paving 
which do not comply with these tolerances shall be removed, the aggregate bedding laying course 
adjusted and the paving blocks re-laid to the correct levels. 

R. The Contractor shall submit shop drawings indicating various patterns to the Owner for review 
and  approval.  No  interlocking  concrete  paving  blocks  shall  be  fabricated  and  delivered  before  a 
specific pattern has been approved. 

7.10.3 

References 

1)  ASTM C88 
2)  ASTM C150 
3)  ASTM C293 
4)  ASTM C418 
5)  ASTM C936 
6)  BS 812 
7)  BS 1377 
8)  BS 6717 
9)  BS 7533 
10) BS EN 933 
11) BS EN 1097 
12) BS EN 12620 
13) BS EN 1744  
14) AASHTO T 96-02 

7.10.4 

Suggested Delivery, Storage & Handling 

A.  Requirements of On-Site Delivery:   

1.  The  receipts  for  pavers  delivered  for  use  on  the  Project  must  state  the  name  of  the 

Contractor,  the  Contract  Number  and  the  identification  number  of  each  batch/bundle 
delivered to the site.  

2.  Each  delivery  shall  also  be  accompanied  by  copies  of  the  In-house  Certification  and 

reports on the testing relevant to the batches delivered. The certificate shall confirm that 
raw material used in the mixes and finished products comply with ADS 15. On delivery of 
pavers to the site, originals or certified copies of these documents must be transmitted to 
the Owner.  

3.  No  pavers  shall  be  laid  on  site  until  the  Owner  receives  and  approves  the  aforesaid 

documentation.  

4.  The Owner shall be notified 24 hours in advance of pending paver deliveries. No truck 

shall be offloaded until inspected by the Owner.  

5.  At the Owner's option, test samples may be taken from the loaded truck and immediately

checked for compressive and flexural strength at the site lab, prior to permission to off-
load.  

6. 

As  per  the  Owner’s  determination,  truck  loads  may  be  rejected  based  on  visual  and
immediate test observations. 

7.  Approval by the Owner to off load the pavers is a conditional approval, subject to the final

result  of  the  manufacture,  independent  and  site  laboratory  testing,  proper  handling, 
installation, and performance.  

B.  Removal and Replacement of Removable Pavement: For reasons beyond the control of the

Contractor, it may become necessary to remove and then replace interlocking pavers (either 
vehicular or pedestrian) or precast tile blocks that are in a present condition acceptable to 
the Owner. In such cases, the Contractor shall carry out the removal and replacement of the 
removable  pavement  in  such  a  way  that  the  replaced  pavement  meets  the  exact  same 
specification requirements that governed the original placement of that pavement, including 
the requirements for the subgrade and base courses.  

C.  Removal  and  Transportation  of Interlocking  Concrete  Pavers to the  Owner  Stores: Where

existing  interlocking  concrete  pavers  in  vehicular  or  pedestrian  areas  require  removal  to 
facilitate  the  proposed  works,  and  are  not  to  be  reinstated,  the  Contractor  shall  carefully 
remove the pavers and transport them to a designated Owner storage area off the island of 
Abu Dhabi.  

1.  The work shall consist of, but not be limited to, preparing shop drawings indicating the

removal  limits,  removal,  on-site  storage,  loading,  transporting,  and  unloading  of  the 
pavers selected for storage.  

2.  During all operations, the Contractor shall proceed with due care and attention so as not

to damage the pavers. Any pavers made unsuitable for future use due to the Contractor’s 
actions or operations shall be deducted from the measurement for this item. 

3.  Pavers identified as unsuitable for future use prior to commencement of the works shall

be  removed  and  disposed  of  in  accordance  with  the  relevant  division  of  these 
specifications. 

I

NDEX

 

barrer, cast-in-situ fixed formwork, 7-54 
barrier, concrete placement, 7-54 
barrier, hydraulically pressed precast, 7-58 
barrier, precast placement, 7-60 
barrier, temporary precast, 7-62 
barriers, 7-51 
boundary wall materials, 7-24 
boundary walls, 7-24 
decorative finish, integral colour plaster, 7-

100 

decorative finish, plaster, 7-96 
decorative finishes for concrete and masonry, 

7-96

decorative finishes, concrete colour pigment, 

7-96

fence construction, 7-88 
fence grounding, 7-91 
fence, barbed wire, 7-94 
fence, camel fence construction, 7-95 
fence, chain-link, 7-75, 7-77 
fence, chain-link coatings, 7-80 
fence, chain-link fence and gate construction, 

7-88

fence, chain-link gates, 7-78 
fence, glare screen, 7-75 
fence, glare screen construction, 7-91 
fence, glare screen type 1, 7-83 
fence, glare screen type 2, 7-83 
fence, glare screens, 7-83 
fence, glare screen-vertical vane, 7-91 
fence, motorised gates, 7-81 
fence, sand, 7-75, 7-86, 7-87 
fence, sand control, 7-87 
fence, sand trapping fence construction, 7-95 
fence, sand-wire camel, 7-86 
fence, temporary, 7-75, 7-86 
fence, temporary construction, 7-94 
fence, type 2 style B, 7-83 
fence, type 2, style A, 7-83 
fence, wire, 7-75, 7-84 
fence, wire construction, 7-92 
fence, wire gates, 7-86 
fence, wire mesh, 7-94 
fencing, 7-75 
foundation, kerb-gutter-barrier, 7-53 
galvanisation repair, 7-11 
guardrail anchors, 7-12 
guardrail and guardrail anchor removal, 7-18 
guardrail kerb, 7-17 
guardrail post erection, 7-15 
guardrail rail erection, 7-16 
guardrail raising, 7-18 
guardrail reflectors, 7-13 

guardrail salvage, 7-18 
guardrail terminal and anchor installation, 7-

17 

guardrail wire rope installation, 7-16 
gutters, 7-51 
impact attenuators, 7-19 
kerb painting, 7-53 
kerb ramps, 7-66 
kerb, cast-in-situ fixed formework, 7-54 
kerb, concrete placement, 7-54 
kerb, hydraulically pressed precast, 7-58 
kerb, placement, 7-59 
kerbs, 7-51 
precast kerb and barrier, 7-57 
qualifications of Contractor’s personnel, 7-31 
red rust, 7-11 
repairing precast kerb, gutter, and barrier, 7-

61 

Sampling, 7-1 
shotcrete application, 7-31 
shotcrete equipment, 7-29 
shotcrete facing, 7-28 
shotcrete finishing, 7-33 
shotcrete materials, 7-28 
shotcrete testing, 7-30 
sidewalk construction, 7-65 
sidewalk curing, 7-68 
sidewalk finishing, 7-68 
sidewalk joints, 7-67 
sidewalks, 7-62 
sidewalks, architectural concrete, 7-75 
sidewalks, cement concrete, 7-67 
sidewalks, paver, 7-72 
sidewalks, pervious concrete, 7-69 
sidewalks, precast tile blocks, 7-64 
sidewalks, quarry tiles, 7-63 
sidewalks, tile, 7-73 
slip-formed kerb and barrier, 7-56 
slope protection, 7-42 
slope protection, cast-in-situ reinforced 

concrete, 7-45 

slope protection, coarse aggregate covering, 

7-51

slope protection, grouted riprap, 7-50 
slope protection, hand-placed riprap, 7-48 
slope protection, keyed riprap, 7-50 
slope protection, paving, 7-42 
slope protection, quarry spalls, 7-49 
slope protection, riprap, 7-47 