Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 24

 

  Главная      Manuals     Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     22      23      24      25     ..

 

 

 

Abu Dhabi, United Arab Emirates. STANDARD CONSTRUCTION SPECIFICATIONS (PART 1 - ROADS, Second Edition 2020) - page 24

 

 

c.  Plant Mixed

a.  Mixing

Thoroughly  mix  materials  in  the  proportions  designated  on  the  mix  design,  in  a  plant  that 
meets the requirements “Mixing Plant.” Mix at optimum moisture content, unless otherwise 
directed, until a homogeneous mixture is obtained. 

b.  Placing

Place  lime-treated  base  on  a  subgrade  or  subbase  prepared  in  accordance  with  details 
shown on the plans. Bring the prepared roadway to the moisture content directed. Haul lime-
treated base to the roadway in clean trucks and begin placement immediately. Spread and 
shape  in  a  uniform  layer  with  an  approved  spreader.  Construct  individual  layers  to  the 
thickness shown on the plans, the same day as delivered, unless otherwise approved. Do 
not place lifts exceeding a compacted depth of 20 cm.  Correct or replace segregated areas 
as directed. 

d.  Compaction

Compact the mixture using density control, unless otherwise shown on the plans. Multiple lifts are 
permitted when shown on the plans or approved. Bring each layer to the moisture content directed. 
Determine the moisture content of the mixture at the beginning and during compaction. 

Begin rolling longitudinally at the sides and proceed toward the center, overlapping on successive 
trips by at least one-half the width of the roller unit.  Operate rollers at a speed between 3 and 10 
KMPH, as directed. 

Rework, recompact, and refinish material that fails to meet or that loses required moisture, density, 
stability, or finish before the next course is placed or the project is accepted. 

e.  Reworking a Section

When a section is reworked within 72 hours after completion of compaction, rework the section to 
provide  the  required  density.  When  a  section  is  reworked  more  than  72  hr.  after  completion  of 
compaction,  add  additional  lime  at  25%  of  the  percentage  determined  “Mix  Design.”  Reworking 
includes  loosening,  adding  material  or  removing  unacceptable  material  if  necessary,  mixing  as 
directed, compacting, and finishing. When density control is specified, determine a new maximum 
density of the reworked material and compact. 

f.  Construction joints

Construct vertical joints between segmented areas of lime-treated base. The vertical face may be 
created by using a header or by cutting back the face to approximately vertical. Place successive 
base courses using the same methods as the first course. Offset construction joints by at least 15 
cm. 

g.  Curing

Cure for 5 days with wet hessian cloth and watered so as to keep moist at all time or by applying an 
asphalt emulsion at a rate of 0.2 to 0.50 kg/m2 as directed. Maintain moisture during curing.  

No equipment or traffic will be permitted on the completed cement stabilized subbase/base during 
the first 7 days unless otherwise permitted by the Engineer 

At final compaction the finished surface of the lime stabilized base/subbase shall be uniform and 
shall  not  deviate  at  any  point  more  than  6  mm  from  the  bottom  of  3  m  straightedge  laid  in  any 
direction. 

Top  of  the  layer  shall  not  vary  from  the  required  elevation  by  more  than  6  mm.    All  bumps  and 
depressions exceeding the specified tolerance shall be corrected by removing the defective work 
and replacing it with new material as directed by the Engineer, all at the expense of the Contractor. 

i.  Thickness Requirement

Thickness  of  the  completed  lime treated  subbase/base  shall  not  vary more than  10 mm from  the 
thickness shown on the Contract plans.  Sufficient measurements of thickness shall be taken before 
and  after  compacting  to  establish  the  relationship  between  the  thickness  of  the  un-compacted 
material and the completed work.  Thickness shall be controlled first by measurements taken of the 
un-compacted  material.    When  the  measurements  indicate  that  an  area  will  not  be  within  the 
allowable  tolerance  for  the  completed  work,  the  un-compacted  area  shall  be  corrected  while  the 
material is still in workable condition. 

Immediately after final compaction the thickness shall be measured at one or more points in each 
300 m of the laid lane width of stabilized subbase/base layer.  Measurement shall be made by means 
of test holes or other approved methods.  Points for measurement shall be selected by the Engineer 
at random locations within each 300 m sections of the laid lane width in such a manner as to avoid 
any regular pattern.  Various points on the cross section shall be covered. 

Whenever a measurement indicates a variation from the thickness shown on the Contract plans of 
more  than  the  allowable  tolerance,  additional  measurements  shall  be  taken  at  intervals  of 
approximately 50 m until the measurements indicate the thickness is within the allowable tolerance. 
Any area not within the allowable tolerance shall be corrected by removing the defective work and 
replacing it with new material as directed by the Engineer all at the expense of the Contractor. Cutting 
of  test  holes  and  refilling  with  materials  properly  compacted  shall  be  done  by  the  Contractor  as 
observed and approved by the Engineer. 

j.  Compaction Control and Testing

Compaction of the cement stabilized subbase/base shall be controlled as the work progresses by 
means of field density tests. 

Field density tests shall be carried out immediately after compaction and before hardening of the 
material in accordance with AASHTO T 191(1) or AASHTO T 205(2) or as directed by the Engineer. 
Frequency of testing shall be 1 test every 100 lin. m of laid lane width. Field density of the compacted 
cement stabilized subbase/base shall not be less than 98% of the reference design maximum dry 
density. 

k.  Weather Limitation

Lime  stabilized  subbase/base  shall  not  be  mixed  or  placed  when  the  atmospheric temperature  is 
over 30° C or when the weather is rainy. 

Temperature  requirements  may  be  waived  but  only  when  so  directed  by  the  Engineer.  When 
temperature  is  higher  than  30°  C,  particular  care  shall  be  exercised  in  order  to  minimize  water 
evaporation from the mixture. 

In this case a test section shall be executed at the high temperature foreseen during the working 
period in order to evaluate the water content necessary to compensate evaporation and to establish 
actual setting time. 

According to such test section the Engineer may order pre-moistening of aggregates before cement 
mixing and watering of the granular subbase finished surface level. 

Engineer will give approval of the test section not before 7 days from the completion of curing. 

 

 

 

3.2.7 Recycled Crushed Aggregate Base Course  

3.2.7.1  Description  

This specification has been prepared to meet the requirements of the order issued by the Executive 
Council of the Emirate of Abu Dhabi, dated 26th of July 2010, under number BT9G25/2010 requiring 
the mandatory use (subject to availability) of a minimum of 40% aggregate (by volume) of recycled 
construction  and  demolition  waste  in  roads  projects,  as  well  as  any  other  infrastructure  projects 
throughout the Emirate of Abu Dhabi.  

The works described below shall consist of furnishing and placing one (1) or more layers of recycled 
crushed aggregate (RCA), including additives if required on a prepared surface in accordance with 
the specifications and in conformity with the lines, grades, thicknesses and typical cross-sections 
shown on the plans or established by the Engineer.  

3.2.7.2  Materials  

Materials  shall  conform  to  the  requirements  for  the  class  of  “Recycled  Crushed  Aggregate  Base 
Course” specified on the plans or directed by the Engineer. All RCA for base course shall consist of 
crushed rock, crushed concrete stone fragments including sand.  

a.  Components  

Crushed  concrete  aggregates  shall  consist  of  clean,  hard,  durable,  angular  fragments  of  rock, 
concrete and sand fragments of uniform quality complying with the general requirements specified 
in  Section 3.2.2  and  its use  limited  as  stated  in Section  4.3.10  of  Chapter  4,  Concrete Works,  of 
these Standard Specifications. 

The use of crusher fines passing the 4.75 sieve which are not produced from crushing concrete shall 
be subject to approval in writing by the Superintendent to the proposed source and nature of these 
materials and the proposed amounts to be added.  

b.  Physical requirements  

All  base  course  RCA  shall  conform  to  the  physical  requirements  described,  for  each  Class  of 
Aggregate.  

Foreign material in the fraction retained on the 4.75 sieve shall not exceed the percentages by mass 
specified: 

Table 3-14:  RCA Base Physical requirements

 

Foreign Material Type  

%  

High density materials such as glass, brick and asphalt  

10 

Metallic items such as steel, aluminum and iron 

Low density materials such as plastic, rubber, plaster, clay lumps and other 
liable material  

1  

Wood and other vegetable or decomposable matter  

0.2  

c.  Grading requirements  

Course materials for aggregate base course shall conform to the following requirements: 

Table 3-15:  RCA Base testing requirements

 

Properties 

Value 

50mm 

100  

37.5mm 

95-100  

Value 

19mm 

70-92

9.5mm 

50-70

4.75mm 

35-55

0.60mm 

12-25

0.075mm 

0-8

Loss by Abrasion Test (AASHTO T 96) 

40% maximum 

Liquid Limit (AASHTO T89) 

25 maximum 

Plasticity Index (AASHTO T 90) 

4 maximum 

Sand Equivalent (AASHTO T 176) 

35 minimum 

CBR on remolded sample (BS 1377 Test 16) after 4 days soaking 

120% minimum 

Soundness (Magnesium) 

– AASHTO T104 

15% maximum 

Flakiness 

– BS 812 

35% maximum 

Elongation 

– BS 812 

35% maximum 

Sulfate Content 

– BS 812 

2% maximum 

Chloride Content 

– BS 812 

2% maximum 

3.2.7.3  Acceptance 

When  the  stationary  plant  method  is  used,  the  aggregate  will  be  accepted  immediately  following 
mixing, based on periodic samples taken from the pug mill output. When a road mix method is used, 
the aggregate will be accepted after necessary blending and before laying, based on samples taken 
from  the  combined  windrow  for  each  layer.  When  the  aggregate  is  a  total  aggregate,  it  may  be 
accepted at the crusher. Acceptance of the material by the Engineer does not constitute acceptance 
of the base course, only that the material is approved for use in the base course.  

3.2.7.4  Equipment 

Equipment  shall  be  according  to  the  type  and  number  outlined  in  the  Contractor’s  detailed 
Programme of work as approved by the Engineer. 

 

3.2.7.5  Construction requirement 

a.  Groundwater levels and protection

The contractor must establish the high water table levels (HWT) along the length of the road, relative 
to  the  accepted  National  benchmark  (New  Abu  Dhabi  Datum 

–  NADD)  should  the  base  of  the 

proposed road be within 1 meter of the HWT, an impermeable barrier will be required to be installed 
to prevent groundwater coming in contact with the RCA.  

b.  Sub-grade preparation

Unless other sub-grade preparation is called for on the plans or appears as a pay item in the bill of 
quantities, the contractor shall, as part of the work and prior to the delivery of materials for the base 
course,  prepare  the  roadbed  surface  by  sprinkling  blading,  rolling  and  lightly  scarifying  where 
necessary, until the proper crown is obtained. However, in the process of shaping the roadbed, the 
originally compacting crust or top portion of the roadbed shall be disturbed as little as possible. When 
completed and ready for base course construction the roadbed shall be well compacted, smooth, 
hard and uniform, all irregularities having been bladed out and rolled down. 

 

1.  Handling of RCA

Handling of RCA, including the loading of trucks and stockpiling, shall be effected in such a 
manner as to minimize segregation. 

2.  Combining aggregates and water

Aggregates for base course shall be combined into a uniform mixture and water added only 
in  a  central  mixing  plant  before  final  placement  of  the  material.  Mixing  and  watering  by 
windows  will  not  be  permitted.  When  binder  is  to  be  added,  it  shall  be  combined  with  the 
aggregate base by thoroughly mixing binder and aggregate base in the central mixing plant. 

The moisture added to the aggregates shall be that required, as designated by the Engineer 
to  obtain  the  specified  density  thereby  preparing  an  aggregate  completely  ready  for 
compaction  after  spreading  on  the  roadbed.  In  no  case  will  be  wetting  of  aggregates  in 
stockpiles or trucks be permitted.  

3.  Spreading and combining aggregates

Unless otherwise specified, aggregate for base course shall be delivered to the roadbed as 
an  uniform  mixture  and  shall  be  placed  on  the  existing  roadway,  prepared  sub-base  or 
prepared sub-grade, as the case maybe in an uniform later or layers not exceeding fifteen 
(15) centimeters in compacted depth, including any binder that is to be blended on the road.
Spreading  shall  be  done  by  means  of  approved  self-propelled  stone  box  spreaders, 
distributing the material to the required width and loose thickness. When the required base 
thickness is greater than fifteen (15) centimeters, the materials shall be spread in layers of 
equal thickness.  

The material shall be so handled as to avoid segregation, if an aggregate spreader causes 
segregation  in  the  material,  or  leaves  ridges  or  other  objectionable  marks  on  the  surface 
which cannot be eliminated easily or prevented by adjustment of the spreader operation, the 
use  of  such  spreader  shall  be  removed  and  replaced  with  well-graded 

material.  No  “skin” 

patching shall be permitted.  

No hauling or placement of material will be permitted when, in the judgment of the Engineer, 
the weather or road conditions are such as hauling operations will cause cutting or rutting of 
the road surface or cause contamination of the base course material.  

4.  Compaction

If directed by the Engineer, prior to starting the aggregate base operation, the contractor shall 
construct the trial lengths in accordance with Section 3.2.1 and Sub-article e of Article 3.2.8.8. 

RCA  shall  be  laid  and  compacted  in  a  manner  which  will  not  result  in  segregation  of  the 
material and at a moisture content which allows the compaction stated. 

Immediately after placing, the base course material shall be compacted. The material shall 
be compacted to an average density of 100% of M.D.D. as determined according to AASHTO 
T  180  Method  D  with  no  single  value  below  ninety-eight  (98%)  percent.  The  field 
determination of density shall be made in accordance with AASHTO T 191. The percent of 
density shall be adjusted to compensate for the weight and volume of aggregate larger than 
the aggregate used in the compaction control test where acceptable.  

Rolling shall be continued until the entire thickness of each layer is thoroughly and uniformly 
compacted to the density specified. The final rolling of the compacted base course shall be 
done  with  a  self-propelled  roller.  Rolling  shall  be  accompanied  by  sufficient  blading  in  a 
manner  approved  by  the  Engineer,  to  insure  smooth  surface  free  from  ruts  or  ridges  and 
having the proper section and crown. When additional water is required, it shall be added in 
the  amount  and  manner  approved  by  the  Engineer.  Each  layer  of  base  course  must  be 

The surface of the finished base course will be tested with a three (3) metre straight-edge by 
the Engineer at selected locations. The variation of the surface from the testing edge of the 
straight-edge between any two (2) contacts with the surface shall at no point exceed six (6) 
millimetres  when  measured  in  any  direction.  The  base  course  shall  be  compacted  to  the 
thickness and cross-section as shown on the plans and shall not vary by more than five (5) 
millimetres  from  the  required  elevation.  All  humps  and  depressions  and  thickness 
deficiencies exceeding the specified tolerances shall be corrected by removing the defective 
work or by adding new material as directed by the Engineer.  

If  the  material  for  the  base  course  is  laid  and  compacted  in  more  than  one  (1)  layer,  the 
contractor shall plan and coordinate the work in such a manner that the previously placed 
and  compacted  layers  be  allowed  ample  time  for  drying  and  development  of  sufficient 
stability,  before  vehicles  hauling  materials  for  the  succeeding  layers  or  other  heavy 
equipment are permitted on the base. Prior to placing the succeeding layers of material, the 
top of the under layer shall be made sufficiently moist to insure bond between the layers. The 
edges and edge slopes of the base course shall be bladed or otherwise dressed to conform 
to the lines and dimensions shown on the plans and present straight, neat and workmanlike 
lines and slopes as free of loose material as practicable.  

The contractor shall also plan the work and handle the various operations so that the least 
amount  of  water  will  be  lost  by  evaporation  from  uncompleted  surfaces.  If  the  contractor 
delays placing of succeeding layers of base course material to the extent that additional water 
must be applied to prevent raveling or excessive dripping, the application of such water shall 
be at the contractor’s expense not to be considered as the basis for a claim for additional 
compensation. Water shall be applied at such times and in such quantities as directed by the 
Engineer  and  the  Engineer  shall  have  full  authority  to  require  the  suspension  of  all  other 
works on the project to ensure the proper maintenance of previously compacted material. If 
after the base is compacted, any areas are above or below proper grade and true elevations 
such  areas  shall  be  loosened  and  after  having  had  additional  materials  added  or  excess 
material  removed  as  the  case  may  require,  shall  be  reconstructed  as  described  herein.  If 
after  the  base  is  compacted  any  areas  fail  to  meet  the  specified  density  and  gradation 
requirements,  they  shall  be  loosened  ore  removed  as  directed  by  the  Engineer  and 
reconstructed as described herein.  

5.  Maintenance of base course

Following  the  construction  of  the  aggregate  base,  the  compacted  base  course  shall  be 
maintained by the contractor at his expense. The contractor shall blade, broom and otherwise 
maintain the base, keeping it free raveling and other defects until such time as the bituminous 
prime or other surface is applied. Water shall be applied at such time and in such quantities 
as directed by the Engineer.  

The Engineer shall determine when the surface of the base course is in the proper condition 
to permit the bituminous prime and/or surfacing to be applied. If the contractor chooses not 
to apply the bituminous prime and/or surfacing at the time, he must continue to maintain the 
surface of the base curse, including the application of the necessary water at his expense 
until such time as the bituminous prime and/or surfacing is applied. Any additional expense 
incurred  by  the  contractor  because  of  his  failure  to  apply  the  bituminous  prime  and/or 
surfacing when so permitted by the Engineer will not be considered as the basis for a claim 
for additional compensation.  

3.2.7.6  Minimum test requirements 

The Contractor shall test the crushed concrete and any approved components at a frequency which 
is  sufficient  to  ensure  that  the  material  supplied  under  the  contract  complies  with  the  specified 

a.  Minimum frequency of testing

Table 3-16:  RCA Base Minimum Testing requirements 

Test 

Minimum Frequency of Testing 

Grading 

On each day 

– one per 300 tonnes if part thereof 

Foreign Material Content 

On each day 

– one per 300 tonnes if part thereof 

Moisture Content 

On each day 

– 3 No.  

One per 200 tonnes or part thereof on each day 

Plasticity Index 

In each month 

– one per 5000 tonnes or part thereof 

California Bearing Ratio 

Prior to the commencement of work and when in the opinion of the 
Engineer the nature of the material has changed significantly  

Los Angeles Abrasion 

Once per month or when in the opinion of the Engineer the nature 
of the material has changed significantly.  

3.2.8 Recycled crushed aggregate sub-base 

3.2.8.1  Description  

This Specification has been prepared to meet the requirements of the Order issued by the Executive 
Council of the Emirate of Abu Dhabi, dated 28th July, 2010, under number BT9G25/2010 requiring 
the mandatory use (subject to availability) of a minimum of 40% aggregate (by volume) of recycled 
construction  and  demolition  waste  in  roads  projects,  as  well  as  any  other  infrastructure  projects 
throughout the Emirate of Abu Dhabi.  

The works described below shall consist of furnishing and placing one (1) or more layers of Recycled 
Crushed Aggregate (RCA), including additives if required, on a prepared surface in accordance with 
the Specifications and in conformity with the lines, grades, thicknesses and typical cross sections 
shown on the plans or established by the Engineer. 

 

3.2.8.2  Materials 

Materials  shall  conform  to  the  requirements  for  the  class  of  "Recycled  Crushed  Aggregate  Base 
Course" specified on the plans or directed by the Engineer. All RCA sub-base material shall be free 
from dirt, organic matter, shale or other deleterious matter and shall be of such quality that it will bind 
readily to form a firm stable sub-base.  

3.2.8.3  Components 

Crushed  concrete  aggregates  shall  consist  of  clean,  hard,  durable,  angular  fragments  of  rock, 
concrete  and  sand  fragments  of  uniform  quality  complying  with  the  general  requirements  of  the 
Section 3.2.1 and its use limited as stated in Section 4.3.10 of Chapter 4, Concrete Works, of these 
Standard Specifications.  

The  use  of  crusher  fines  passing the  4.75  sieve which  are  not  produced from  crushing concrete. 
Shall be subject to approval in writing by the Superintendent to the proposed source and nature of 
these materials and the proposed amounts to be added, 

 

 

 

 

3.2.8.4  Physical requirements  

All base course RCA shall conform to the physical requirements described below, for each Class of 
Aggregate.  

Foreign material in the fraction retained on the 4.75 sieve shall not exceed the percentages by mass 
specified: 

Table 3-17:  RCA Sub-base Physical requirements

 

Foreign Material Type  

%  

High density materials such as glass, brick, and asphalt  

10 

Metallic items such as steel, aluminum and iron 

Low density materials such as plastic, rubber, plaster, clay lumps and other 
friable materials  

1  

Wood and other vegetable or decomposable meter 

0.2 

3.2.8.5  Grading requirement  

a.  Sub-base  

Sub-base  shall  consist  of  well-graded  RCA  with  sand  and  silt,  conforming  to  the  following 
requirements: 

 

Table 3-18:  RCA subbase requirements 

Properties 

Value 

50mm  

100  

37.5 mm 

95-100 

19 

65-95 

9.5mm  

30-65 

4.75mm  

25-55 

2.00mm  

15-40 

0.425mm  

8-20 

0.075mm  

2-8  

Loss by Abrasion Test (AASHTO T 96)  

40% maximum  

Liquid Limit (AASHTO T89)  

25 maximum  

Plasticity Index (AASHTO T 90)  

4 maximum  

Sand Equivalent (AASHTO T 176)  

25 minimum  

CBR on remolded sample (BS 1377 Test 16) after 4 days soaking  

120% minimum  

Soundness (Magnesium) 

– AASHTO T104 

15% maximum 

Flakiness 

– BS 812 

35% maximum 

Elongation 

– BS 812 

35% maximum 

Sulphate Content 

– BS 812 

2% maximum 

Chloride Content 

– BS 812 

2% maximum 

When  the  stationary  plant  method  is  used,  the  aggregate  will  be  accepted  immediately  following 
mixing based on periodic samples taken from the pug mill output. When a road mix method is used, 
the aggregate will be accepted after necessary blending and before laying, based on samples taken 
from the combined  windrow  for  each  layer.  Acceptance  of  the  material  by  the  Engineer  does  not 
constitute acceptance of the sub-base, only that the material is approved for use in the sub-base.  

3.2.8.7  Equipment 

Equipment  shall  be  according  to  the  type  and  number  outlined  in  the  Contractor's  detailed 
Programme of Work, as approved by the Engineer.  

3.2.8.8  Construction requirements 

a.  Groundwater levels and protection

The Contractor must establish the high water table levels (HWT) along the length of the road, relative 
to  the  accepted  National  benchmark  (New  Abu  Dhabi  Datum  (NADD)).  Should  the  base  of  the 
proposed road be within 1 meter of the HWT, an impermeable barrier will be required to be installed 
to prevent groundwater coming in contact with the RCA subbase.  

b.  Preparation of sub-grade

Unless other sub-grade preparation is called for on the plans or sub-grade preparation appears as 
a separate item for compensation in the Bill of Quantities, the Contractor shall, as part of the Work 
of sub-base, prepare the sub-grade. The formation of the sub-grade will vary by either placing the 
"Granular  RCA  Sub-base"  on  the  roadway  surface  as  previously  constructed  or  by  excavating 
sufficient  material  from  the  roadway  and  placing  the "Granular  RCA  Sub-base"  on  the  sub-grade 
obtained thereby. In  either  case,  the  sub-grade, shall  as  hereinafter  described,  be  brought to the 
lines, grades and typical section shown on the plans for the bottom of the "Granular RCA Sub-base". 
All soft and yielding material or other portions of the sub-grade, which will not compact readily, when 
rolled or tamped, shall be removed, and all loose rock or boulders found In the excavation shall be 
removed or broken off to a depth of not less than fifteen (15) centimeters below the surface of the 
sub-grade. All holes or depressions made by the removal of material, as described above, shall be 
filled with approved material and the whole sub-grade brought to line and grade and compacted to 
density designated on the plans or directed by the Engineer.  

c.  Spreading

Sub-base aggregates shall be spread on sub-grade which has been approved by the Engineer. Sub-
base which has been placed on a sub-grade not approved by the Engineer shall be removed at the 
Contractor's expense.  

Sub-base aggregate shall be spread on the approved sub-grade in layers not exceeding fifteen (15) 
centimeters in compacted depth. Spreading shall be done by means of approved mechanical box 
spreaders, distributing the material to the required width and loose thickness. Where the required 
sub-base thickness is greater than fifteen (15) centimeters, the material shall be placed in layers of 
equal thickness, In no case shall a layer be less than seven and  one half (1.5) centimeters thick. 
Under no circumstances shall Class A Sub-base be dumped in a pile on the Sub-grade.  

The material shall be handled so as to avoid segregation. Segregated materials shall be remixed 
until  uniform.  Suitable  precautions  shall  be  taken  to  prevent  rutting  of  the  sub-grade  during  the 
spreading of the sub-base materials. No hauling or placement of material will be permitted when, in 
the judgment of the Engineer, the weather or road conditions are such that the hauling operations 
will cause cutting or rutting of the sub-grade or cause contamination of the sub-base material.  

 

 

 

d.  Compaction  

The moisture content of the sub-base material shall be adjusted prior to compaction, by watering 
with approved sprinkler trucks or by drying out, as directed by the Engineer, to that required to obtain 
the specified density for sub-base. Sub-base shall be compacted to an average value of 100% of 
the M.D.D. as determined according to AASHTO T 180 Method D with no single value below ninety 
eight (98%).  

The  sub-base  aggregate  shall  be  compacted  by  means  of  approved  compaction  equipment 
progressing gradually from the outside towards the centre with each succeeding pass uniformly over-
lapping  the  previous  pass.  Rolling  shall  continuous  until  the  entire  thickness  of  each  layer  is 
thoroughly  and  uniformly  compacted  to  the  specified  density.  Rolling  shall  be  accompanied  by 
sufficient blading in a manner approved by the Engineer, to insure a smooth surface free from ruts 
or ridges and having the proper section and crown.  

The surface of the material shall on completion of compaction be well closed, free from movement 
under the compaction plant and free from compaction planes, ridges, cracks, or loose materials. 

Any area inaccessible to normal compaction equipment shall be compacted by means of mechanical 
tampers until satisfactory compaction is obtained.  

Each layer of sub-base course must be completely compacted and approved by the Engineer, prior 
to the delivery of materials for a succeeding layer of sub-base.  

e.  Compaction trials  

If  directed  by  the  Engineer,  prior  to  the  commencement  of  his  sub-base  or  aggregate  base 
operations, the Contractor shall construct trial lengths, not to exceed one (1) kilometre. The materials 
used in the trials shall be those approved for use as sub-base or aggregate base, and the equipment 
used shall be that according to the Contractor's approved detailed Programme of Works.  

The object of these trials is to determine the adequacy of the Contractor's equipment, the loose depth 
measurements  necessary  to  result  in  the  specified  compacted  layer  depths,  the  field  moisture 
content, and the relationship between the number of compaction passes and the resulting density of 
the material.  

f.  Finishing  

The  Contractor  shall  programme  his  operations  to  avoid  the  drying  out  of  the  sub-base  during 
construction. If any layer of sub-base material or part thereof, is permitted to dry out after compaction, 
or  does  not  conform  to  the  required  density  or  finish,  the  Contractor.  shall  at  his  own  expense, 
rework, water or recompact the material, as directed by the Engineer, to density specified before the 
next layer of sub-base or base course is superimposed thereon.  

Immediately prior to the placing of the first layer on the sub-base, the final layer of sub-base shall be 
at  the  specified  density  and  to  the  required  grade  and  section.  In  order  to  maintain  these 
requirements while placing the next course, it may be necessary to water and reshape the surface 
of the sub-base, which Work shall be at the Contractor's expense.  

The  surface  of  the  finished  sub-base  will  be  tested  with  a  three  (3)  meter  straight-edge  by  the 
Engineer  at  selected  locations.  The  variation  of the  surface  from  the testing  edge  of  the  straight-
edge between any two (2) contacts with the surface shall at no point exceed six (6) millimeters when 
measured in any direction. The sub-base shall be compacted to the thickness and cross-section as 
shown on the plans and shall not vary by more than six (6) millimeters from the required elevation. 
All humps and depressions and thickness deficiencies exceeding the specified tolerances shall be 
corrected by removing the defective Work or by adding new material as directed by the Engineer.

 

3.2.8.9  Minimum test requirements  

One sample every 1,000 m

shall be tested for Grading Plasticity index, Sand Equivalent Maximum 

Dry Density. C.B.R., Loss by Abrasion. One Situ Density Test every 300 m

2

 of Granular RCA Sub-

base laid. 

 

 

 

3.3  Asphalt Concrete Paving Courses 

3.3.1 Description    

Work constructs an asphaltic concrete paving course on a prepared surface in accordance with these 
specifications  and  in  compliance  with  the  lines,  grades,  thicknesses  and  typical  cross-sections 
shown on the Contract plans, as approved by the Engineer.  

3.3.2 Materials 

The materials used in asphaltic concrete mixes shall meet the requirements specified in the following 
sections: 

  Superpave mix design materials:  Paragraph 1 of Sub-article (a) of Article 3.3.2.5. 

  Marshall mix design materials: Paragraph 4 of Sub-article b of Article 3.3.2.5.  

3.3.2.1  Storage and Handling of Materials 

Materials shall be stored and handled so as to assure the preservation of their quality and fitness for 
the works.  Materials, even though approved before storage or handling, may again be inspected 
and tested prior to use in the work.  Stored materials shall be located so as to facilitate their prompt 
inspection.  All storage sites shall be restored to their original condition at 

the Contractor’s expense 

prior to acceptance of the works. 

Handling  and  stockpiling  of  aggregates  shall  at  all  times  be  such  as  to  eliminate  segregation  or 
contamination  of  the  various  sizes.    Stockpiles  shall  be  kept  flat  and  the  formation  of  high  cone-
shaped piles shall not be permitted.  When conveyor belts are used for stockpiling aggregates, the 
Engineer may  require the  use  of  baffle-chutes  or  perforated  chimneys.  When trucks  are  used  to 
construct stockpiles, the stockpiles shall be constructed one layer at a time with trucks depositing 
their loads as close to the previous load as possible.  Use of tractors or loaders to push  material 
deposited  at  one  location  to  another  location  in  the  stockpile  shall  not  be  allowed  during  the 
construction of the stockpile and their use shall be limited to leveling the deposited material only.  
Stockpiles of aggregate located at permanent asphalt plant sites shall be separated by bin walls and 
shall be constructed on asphaltic or concrete floors.  Stockpile locations and procedures at temporary 
asphalt plant sites shall be as approved by the Engineer. 

Intermediate storage of hydrated lime and commercial mineral filler for equipment feeding the asphalt 
plant shall be silos of adequate size to ensure a minimum of one day's continuous operation. 

3.3.2.2  Inspection, Testing and Control of Materials 

For verification of weights and measures, character of materials and determination of temperatures 
used  in  the  preparation  of  the  asphalt  mixes,  the  Engineer  shall  at  all  times  have  access  to  all 
portions of the mixing plant, aggregate plant, storage yards, crushers and other facilities used for 
producing and processing the materials of construction.  Engineer will have authority to take samples 
and  perform  tests  on  any  material  supplied  to  the  site  from  any  source  whatsoever  in  order  to 
establish their compliance with these specifications and to accept or reject as he deems necessary. 
Samples will also be taken by the Engineer from completed work to determine compliance with these 
specifications.  Frequency of all sampling and testing shall be in accordance with these specifications 
or as directed by the Engineer. 

3.3.2.3  Unacceptable Materials 

Materials that do not comply with the requirements of these specifications will be rejected and shall 
be removed immediately from the site of the works.  No rejected material, the defects of which have 
been corrected, shall be used until approval has been given by the Engineer. 

 

 

 

3.3.2.4  Sources of Materials 

Materials  used  in  the  work  shall  be  tested  and  approved  before  use.  Contractor  shall  notify  the 
Engineer  of  the  sources  of  materials  and  the  material  shall  not  be  delivered  to  site  before  the 
approval  by  the  Engineer.    Where  the  source  of  material  does  not  meet  the  specification 
requirements,  the  Contractor  shall  furnish  material  from  other  sources.  Delivery  of  materials 
produced from commercial manufacturing processes shall be accompanied by the manufacturer's 
certification and test report showing the materials comply with these specification requirements. 

3.3.2.5  Hot Mix Asphalt Design Requirements  

Either the Marshall Method of mix design (Asphalt Institute Manual Series MS-2) or the Superpave 
Volumetric Design Method (AASHTO MP 2) shall be used in designing the asphaltic concrete mixes, 
as may be required on the Contract plans, in the particular specifications and as approved by the 
Engineer.  

Bituminous  paving  course  mix  designs  shall  be  performed  by  the  Contractor  and  verified  by  the 
Engineer. A certified technician shall perform the mix design. 

a.  Superpave Volumetric Method 

Furnish  mixes  of  aggregate,  asphalt  binder,  and  additives  that  meet  the  applicable  material 
requirements and the appropriate design parameters in Table 3-24 and are capable of being placed 
and compacted as specified. 

Compact  specimens  with  the  gyratory  compactive  effort  specified  in  Table  3-24  for  the  specified 
ESAL or N

Design

1.  Superpave Materials 

Superpave hot asphalt concrete pavement nominal maximum size aggregate is designated 
as shown in Table 3-21 and Table 3-24. Equivalent single axle loads (ESAL) or number of 
gyrations at design (N

Design

) is designated as shown in Table 3-19, Table 3-20, and Table 3-

24.   

Asphalt binder is designated as shown in AASHTO M 320. Asphalt binder in asphalt mixes 
for road works shall be minimum PG grade 76-22. Asphalt binder in asphalt mixes for high 
stress  zones  such  as  intersections,  roundabouts,  steep  inclines,  areas  of  low  speed  with 
heavy loads, etc. shall be minimum PG grade 82-22. Modifiers shall be organic, inorganic or 
hybrid  types  of  polymers  specifically  designed  and  manufactured  for  use  in  a  dissolved, 
dispersed or reacted state within asphalt binders or asphalt mixes. Modifiers should be able 
to be dissolved, dispersed in or reacted with bitumen in a laboratory sample preparation to 
assess  the  properties  and  performances  of  the  modified  binder.  The  polymer  content  in 
asphalt binder or asphalt mixes shall be determined according to AASHTO T 302.  

Antistrip additive type is designated as shown in Sub-article a of Article 3.3.2.5. Where no 
type is designated, use type 3 (lime). 

Mineral filler shall conform to AASHTO M 17. 

Superpave Asphalt Concrete Pavement Aggregate   

Furnish  hard,  durable  particles  or  fragments  of  crushed  stone,  crushed  slag,  or  crushed 
gravel conforming to the following: 

i.  Los Angeles abrasion, AASHTO T 96: 35% max 

ii.  Magnesium sulfate soundness loss of coarse and fine aggregate (5 cycles), AASHTO T 

104:  12% max  

iii.  Fractured faces, ASTM D5821:  Table 3-19 

iv.  Fine aggregate angularity, AASHTO T 304, method A: Table 3-20 

 

 

 

v.  Flat and elongated particles, 3 to 1 ratio, ASTM D4791: Table 3-20 

vi.  Sand equivalent value, AASHTO T 176, alternate method no. 2, reference method: Table 

3-20 

vii.  Gradation.    See  Table  3-21.    Size,  grade,  and  combine  the  aggregate  fractions  in  mix 

proportions that result in a composite blend between the control points. Nominal maximum 
size is one sieve size greater than the first sieve to retain more than 10 % of the combined 
aggregate.  Test according to AASHTO T 27 and T 11. 

For  the  surface  course,  do  not  use  aggregates  known  to  polish  or  carbonate  aggregates 
containing  less  than  25  %  by  mass  of  insoluble  residue  when  tested  according  to  ASTM 
D3042. 

Table 3-19  Fractured faces coarse aggregate requirements 

Traffic 

ESALs (million) 

Fractured faces  

(1 face % min. / 2 face % min.) 

< 0.3 

55/- 

0.3 to < 3 

75/- 

3 to < 10 

100/85 

10 to < 30 

100/90 

≥ 30 

100/100 

Note:  "100/85" denotes that 100 percent of the aggregate has one fractured surface and 85 percent 
has two or more fractured faces. 

Table 3-20:  Superpave aggregate requirements 

Traffic ESALs 

(million) 

Uncompacted void content 

of fine aggregate (% 

minimum) 

Sand 

equivalent 

(minimum) 

Flat and 
elongated 
(% max.) 3:1 
ratio 

Depth from surface 

100 mm 

> 100 mm 

< 3 

40 

40 

50 

10 

3 to < 10 

45 

40 

70 

10 to < 30 

45 

40 

70 

 30 

45 

45 

70 

Table 3-21:  Superpave aggregate gradation 

Sieve size 

Nominal maximum aggregate size 

– percent passing 

grading designation 

25.0 mm 

19.0 mm 

12.5 mm 

9.5 mm 

Min. 

Max. 

Min. 

Max. 

Min. 

Max. 

Min. 

Max. 

37.5 mm 

100 

 

 

 

 

 

 

 

25.0 mm 

90 

100 

100 

 

 

 

 

 

19.0 mm 

90 

100 

100 

 

 

 

12.5 mm 

90 

100 

100 

 

9.5 mm 

90 

100 

 

 

 

Sieve size 

Nominal maximum aggregate size 

– percent passing 

grading designation 

25.0 mm 

19.0 mm 

12.5 mm 

9.5 mm 

Min. 

Max. 

Min. 

Max. 

Min. 

Max. 

Min. 

Max. 

4.75 mm 

2.36 mm 

600 µm 

300 µm 

75 µm 

*Contractor specified target values.  See Table 3-22 for allowable deviations. 

Table 3-22:  Allowable deviations for target value gradations 

Gradation Range 

Allowable deviation 

Minimum 

Maximum 

70.1 

89.9 

60.1 

70.0 

55.1 

60.0 

45.1 

55.0 

40.1 

45.0 

30.1 

40.0 

21.1 

30.0 

8.1 

21.0 

8.0 

Table 3-23:  Coarse and fine gradation classification 

Nominal maximum aggregate size

 

Primary control sieve (PCS) for mixture nominal 

maximum sieve size 

25.0 mm 

19.0 mm 

12.5 mm 

9.5 mm 

PCS 

4.75 mm 

4.75 mm 

2.36 mm 

2.36 mm 

PCS control point (% passing) 

40 

47 

39 

47 

Table 3-24:  Superpave hot asphalt concrete pavement design requirements (AASHTO MP2) 

Design 

Gyratory compaction level 

Minimum voids-in-the-

mineral aggregate (VMA), 

%

(d)

 

Voids 

Filled 

with 

Dust-

to-

Minimum 

Tensile 

Strength 

 

 

 

ESAL 

(million) 

 

(% theoretical maximum 

specific gravity, Gmm) 

AASHTO PP 28 

Nominal maximum size 

aggregate 

(c)

 

Asphalt 

(VFA), 

%

(e) (f)

 

Binder 

Ratio

(a)

 

Ratio, 

AASHTO 

T 283

(b)

 

N

Initial

 

N

Design

 

N

Max

 

25.0 

mm 

19.0 

mm 

12.5 

mm 

9.5 

mm 

< 0.3 

 91.5% 

50 

96% 

75 

 98% 

12.0 

13.0 

14.0 

15.0 

70-80 

0.8-1.6 

0.80 

0.3 to 

 < 3 

90.5% 

75 

96% 

115 

 98% 

65-78 

3 to 

 < 30 

89% 

100 

96 % 

160 

98% 

65-75 

 30 

89% 

125 

96% 

205 

98% 

(a)

Include non-liquid antistrip, baghouse fines, and other mineral matter added to the mixture.  

Calculate the ratio using effective asphalt content (calculated by mass of mix). 

(b)

Prepare specimens in accordance with AASHTO PP 28. 

(c)

The nominal maximum size is one size greater than the first sieve to retain more than 10 % of the 

combined aggregate. 

(d)

When mineral filler or hydrated lime is used, include in the calculation for compliance with the VMA. 

(e)

For 9.5 mm nominal maximum size aggregate mixtures with 

3 million ESALs, provide a VFA of 

73 to 76 %. 

(f)

For 25.0 mm nominal maximum size aggregate mixtures with < 0.3 million ESALs, provide a VFA 

 67 %. 

Combined  aggregate  gradation  is  classified  as  coarse  graded  when  it  passes  below  the 
primary control sieve control point in Table 3-23. All other gradations are classified as fine 
graded. 

Antistrip Additive 

Contractor shall conform to the following: 

i. 

Type 1.  Furnish commercially produced, heat stable liquid products that when added to 
asphalt have the chemical and physical properties to prevent separation of the asphalt 
from aggregates. 

ii. 

Type 2.  Furnish cement conforming to Section 4.3.1 or fly ash conforming to Section 
4.3.2 

iii. 

Type 3.  Furnish lime conforming to AASHTO M 303. 

Recycled Asphalt Pavement Use   

Do not use recycled asphalt pavement in the top lift. 

Furnish  recycled  asphalt  pavement  that  is  processed  in  some  form  (by  crushing  and 
screening)  to  produce  a  well  graded  gradation  and  asphalt  content.    Process  recycled 
asphalt pavement so that no particle in the mixture made with recycled asphalt pavement 
will exceed the mixture maximum aggregate size at the time of production.  Millings will be 
considered processed provided they have a uniform gradation and asphalt content.  Provide 
recycled asphalt pavement material with a maximum of 2 % deleterious materials. 

 

 

 

Recycling agents shall conform to AASHTO R 14 or use an approved petroleum product 
additive that restores aged asphalt to the required specifications 

Up to and including 15 % recycled asphalt pavement material by mass may be used in the 
mix without adjusting the asphalt binder grade.  For mixes with over 15 % and up to and 
including 25 %, recycled asphalt pavement material by mass, decrease the asphalt binder 
grade one performance level for both the upper and lower grade level of the asphalt binder 
specified or use an approved blending procedure with a recycling agent.  Do not use more 
than 25 % recycled asphalt pavement by mass. 

For mixture design, use the specific gravity of the new (virgin) asphalt binder as the specific 
gravity of the asphalt binder in the recycled asphalt pavement.  For calculation purposes, 
use the effective specific gravity of the aggregate in the recycled asphalt pavement as the 
bulk  specific  gravity.    When  the  recycled  asphalt  pavement  contains  highly  absorptive 
materials,  estimate  the  amount  of  absorbed  asphalt  from  historical  records,  and  use  the 
estimate to back-calculate the bulk specific gravity of the aggregate. 

2.  Submission 

Contractor  shall  submit  written  job  mix  formulas  for  approval  at  least  30  days  before 
production.  Include the location of all commercial mixing plants to be used and a separate 
job-mix formula for each plant.  Include a signed statement prepared by the testing laboratory 
that certifies that the proposed job-mix formula meets the requirements of the Contract and 
can be compacted in the field during production to meet  Contract requirements.  For each 
job-mix formula, submit the following: 

i.  Aggregate and mineral filler. 

a)  Target values:   

1)  Target value for percent passing each sieve size for the aggregate blend 

2)  Designate  target  values  within  the  gradation  band  specified  for  the  nominal 

maximum size aggregate grading shown in Table 3-21. 

b)  Source and percentage of each aggregate stockpile to be used. 

c)  Average gradation of each aggregate stockpile 

d)  Representative samples from each aggregate stockpile.  Use split samples of material 

taken at the same time samples are taken for testing by the Contractor

’s laboratory 

1) 

375  kg  of  aggregates  proportioned  by  stockpile  according  to  the  stockpile’s 
proportion in the mix 

2)  10 kg of bag house fines if proposed for the mix 

3)  10 kg of mineral filler if proposed for mix 

4)  Results of aggregate quality tests for Contractor selected sources.  Include the sand 

equivalent,  fractured  faces,  Los  Angeles  abrasion,  sodium  sulfate  soundness, 
coarse  durability,  and  fine  durability  results  from  tests  performed  within  1  year  of 
aggregate use 

ii.  Asphalt binder:   

a)  Target asphalt binder content 

b)  Five 4-liter samples of the asphalt binder to be used in the mix.  Do not include antistrip 

additives in these samples 

c)  Recent  test  results  from  the  manufacturer  for  the  asphalt  binder  including  a 

temperature-viscosity curve 

d)  Material safety data sheets 

 

 

 

 

 

 

 

Content      ..     22      23      24      25     ..