G ENERAL R
1.26.4 Submittals Submittals for O&M data shall comply with the following requirements: a. Informational: 1. Data outline: Submit two copies of a detailed outline of proposed organization and contents of final data before preparation of preliminary data 2. Preliminary data: i. Submit three copies for Engineer ’s review ii. If data meets conditions of the Contract: a) One copy will be returned to the Contractor b) One copy will be forwarded to the Owner c) One copy will be retained in Engineer ’s file iii. If data does not meet conditions of the Contract: a) All copies will be returned to the Contractor with Engineer ’s comments (on separate document) for revision b) Engineer ’s comments will be retained in Engineer’s file c) Resubmit three copies revised in accordance with Engineer ’s comments. 3. Final data: i. Submit two hardcopies of each manual in format specified herein ii. Submit five copies of each CD of the electronic media format with printed labels iii. Final electronic manual shall be organized in the same format as the hardcopy manual 1.26.5 Data for Equipment and Systems Data for equipment and systems shall meet the requirements of the following articles under this 1.26.5.1 Content for Each Unit (or Common Units) and System a. Product data: 1. Include only those sheets that are pertinent to specific product 2. Clearly annotate each sheet to: i. Identify specific product or part installed ii. Identify data applicable to installation iii. Delete references to inapplicable information iv. Function, normal operating characteristics, and limiting conditions v. Performance curves, Engineering data, nameplate data, and tests vi. Complete nomenclature and commercial number of replaceable parts vii. Original manufacturer’s parts list, illustrations, detailed assembly drawings showing viii. Spare parts ordering instructions |