G

ENERAL 

R

 

 

 

f.  All portable containers for gas and other inflammable liquids shall have self closing lids. No 

plastic containers are allowed 

g.  All accidents are to be reported directly to supervisors, and the Engineer 

1.  If serious  injury  is  apparent  or  suspected,  utilize  the  pre  established  emergency  hospital 

services 

2.  Telephone number shall be prominently displayed at all site telephone locations 

3.  For small cuts, scratches, etc. approved first aid kits are to be available from the Contractor, 

and each subcontractor 

h.  In  the  event  of  a  fire:  Emergency  evacuation  plans  and  procedures  shall  be  prepared  and 

posted on the safety notice board(s) and communicated 

1.  In  the  event  of  a  fire,  the  procedures  to  be  followed  if  the  fire  cannot  be  immediately 

contained, shall include notifying the nearest Abu Dhabi Civil Defence Fire Brigade, whose 
telephone number shall be prominently displayed at all site telephone locations, and site 
safety notice boards. 

2.  Attempt to put out a manageable fire with available fire extinguishers and water hoses until 

help arrives, shall be encouraged, however, the contactor shall ensure they do not endanger 
any personnel in fighting a fire if their personnel are not suitably trained or volunteer to do 
so. 

i.  Project specific hazards: 

1.  The Contractor shall ensure the workers site orientation includes reference to site-specific 

hazards  related  to  the  workers  field  of  operation,  and  that  both  known  hazards  and 
Engineering controls measures are communicated to them, including the contents from the 
Contractor

’s approved health and safety plan. 

2.  Workers site safety orientation shall be documented. 

j.  Heavy equipment suppliers must supply certification of testing and obtain clearance from the 

project Engineer before commencement of their work. 

k.  Security: 

1.  Watchman shall be deployed at controlled entrance and exit location(s), as required. 

2.  No  site  visiting  during  nights,  week-ends  or  holidays  shall  be  permitted  without  prior 

permission from the Engineer. 

3.  Visitors  to  site  shall  be  instructed  to  report  to  the  reception,  and  the  Contractor

’s  safety 

representative for site safety induction and authorization to enter site areas, as approved 
by the Engineer. 

1.12.9 

Final Conditions of Work 

Before application is made for the Owner to accept the work, all items of work shall be complete, 
ready to operate and in a clean condition. All trash, debris, unused building material and temporary 
structures shall have been removed from the site of the work. Tools and construction machinery not 
needed for repair and adjustment consequent to operational tests shall not be on the site. Walkways, 
parking areas and roadways, streets and lanes pertaining to the works shall be completely cleaned. 

1.13 

Contractor Quality Control 

This section includes requirements for establishing and maintaining a quality control (QC) program 
and  Contractor  quality  control  (CQC)  staff  to  control  quality  for  on-site  and  off-site  work  and 
construction  operations  to  ensure  compliance  with  Contract  requirements.  The  Contractor  shall 
comply  with  the  requirements  outlined  in  the 

Owner’s  Quality  Assurance  and  Quality  Control  - 

Requirements 

 

G

ENERAL 

R

 

 

 

1.13.1 

Contractor Quality Control References 

Several  publications,  listed  below,  form  a  part  of  this  specification  to  the  extent  referenced. 
Publications are referred to in the text by the basic designation only. 

1.  ASTM A880 (1989) Criteria for Use in Evaluation of Testing Laboratories and Organizations 

for Examination and Inspection of Steel, Stainless Steel, and Related Alloys 

2.  ASTM  C1077  (1992)  Laboratories  Testing  Concrete  and  Concrete  Aggregates  for  Use  in 

Construction and Criteria for Laboratory Evaluation  

3.  ASTM  D3666  (1992;  Rev.  A)  Minimum  Requirements  for  Agencies  Testing  and  Inspecting 

Bituminous Paving Materials 

4.  ASTM D3740 (1988) Evaluation of Agencies Engaged in the Testing and/or Inspection of Soil 

and Rock as Used in Engineering Design and Construction  

5.  ASTM E329 (1993) Evaluation of Testing and Inspection Agencies as Used in Construction  

6.  ASTM E543 (1992; Rev. C) Evaluating Agencies That Perform Non-destructive Testing  

The Contractor shall apply appropriate specifications. A definable feature of work is a task that is 
separate and distinct from other tasks and requires separate control requirements. As a minimum, if 
approved  by  the  Engineer,  the  Contractor  shall  consider  each  section  of  the  specifications  as  a 
definable feature of work. However, at times, there may be more than one definable feature of work 
in each section of the specifications. 

1.13.2 

Submittals during Construction 

Submit  in  accordance  with  Section  1.13.21.13,  a  project-specific  Contractor  quality  control  plan 
within 21 calendar days after the NTC.   

1.13.3 

Information for the Engineer 

Deliver the following to the Engineer: 

1.  Combined Contractor production report/Contractor quality control report (one sheet): Original 

and one copy, by 10:00 AM the next working day after each day that work is performed 

2.  Testing plan and log: one copy, at the end of each month 

3.  Monthly summary report of field tests: Original and one copy attached to the Contractor quality 

control report at the end of each month 

4.  CQC meeting minutes: one copy, within two calendar days of the meetings 

5.  Rework items list: one copy, by the last working day of the month 

6.  CQC certifications: As required by Section 1.13.14 

1.13.4 

Contractor Quality Control Program Requirements 

Establish and maintain the Contractor quality control (CQC) program as described in this section. 
CQC  program  shall  include  a  CQC  organization,  a  CQC  plan,  CQC  meetings,  three  phases  of 
control, submittal review and approval (those submittals designated for Engineer approval shall be 
reviewed  and  approved  submittal  to  the  Engineer),  testing,  and  CQC  certifications  and 
documentation necessary to provide materials, equipment, workmanship, fabrication, construction 
and  operations  which  comply  with  the  requirements  of  this  Contract.  CQC  program  shall  cover 
construction operations on-site and shall be keyed to the proposed construction sequence. 

1.13.5 

Contractor Quality Control Organization 

CQC manager shall comply with the requirements outlined in this section.  

 

G

ENERAL 

R

 

 

 

1.13.5.1 

Duties 

Provide a CQC manager at the work site to manage and implement the CQC program. Duties and 
responsibility the CQC manager shall have on this Contract is only the managing and implementing 
the  CQC  program.  CQC  manager  is  required  to  conduct  the  CQC  meetings,  perform  the  three 
phases of control, perform submittal review and approval except for those submittals designated for 
Engineer approval, ensure testing is performed and prepare CQC certifications and documentation 
required in this Contract. CQC manager is responsible for managing and coordinating the work in 
conjunction  with  the  services  of  any  independent  testing  laboratory  when  required  by  the 
specifications. No work or testing may be performed unless the CQC manager is on the site. CQC 
Manager shall report directly to an officer of the Contractor's company and shall not be the same 
individual  as,  nor  be  subordinate  to,  the  construction  manager,  superintendent  or  the  project 
manager. 

1.13.5.2 

Qualifications 

This position may have collateral duties; however, the CQC manager shall be present full-time at the 
site and spend a minimum of 70 % of his time performing CQC duties. CQC manager shall have a 
collateral, direct reporting relationship to the Engineer. CQC manager may also be a member of the 
Contractor's design team and an active participant in the design of any plant being constructed under 
this  Contract. CQC manager  shall be a graduate of  a four year  accredited college program in an 
Engineering  or  architecture  discipline  with  a  minimum  of  five  years  experience  as  a  construction 
superintendent, inspector, project manager, or construction manager. He/she shall have at least five 
years experience as a CQC manager on similar size and type construction Contracts that included 
the major trades that are part of this Contract. 

1.13.6 

Contractor Quality Control Requirements 

Provide  for  approval  by the  Engineer,  a  CQC  plan  that  covers  both  on-site  and  off-site  work  and 
includes the following: 

1.  A chart showing the CQC organizational structure and its relationship to the production side of 

the organization.  

2.  Names and qualifications, in resume format, for each person in the CQC organization. 

3.  Duties, responsibilities and authorities of each person in the CQC organization.  

4.  A  listing  of  sub-consultant  organizations  such  as,  architectural  and  consulting  Engineering 

firms that will be employed by the Contractor and a description of the services these firms will 
provide, with respect to construction.  

5.  A letter signed by an officer of the Contractor's firm appointing the CQC manager and stating 

that he/she is responsible for managing and implementing the CQC program as described in 
this  Contract.  Include  in  this  letter  the  CQC  manager's  authority  to  direct  the  removal  and 
replacement of non-

conforming work. This letter shall indicate the CQC manager’s collateral 

reporting responsibility to the Engineer.  

6.  Procedures  for  reviewing,  approving  and  managing  submittals:  Provide  the  name(s)  of  the 

person(s) in the CQC organization authorized to review and certify submittals before approval. 

7.  Testing laboratory information required by Section 1.13.131.13.12.   

8.  A testing plan and log that includes the tests required, referenced by the specification section 

number and paragraph number requiring the test, the frequency, and the person responsible 
for each test.  

9.  Procedures to identify, record, track and complete rework items.  

10.  Documentation procedures, including proposed report formats. 

11.  A list of the definable features of work.  

 

G

ENERAL 

R

 

 

 

12.  A  personnel  matrix  showing,  for  each  section  of  the  specification,  which  will  review  and 

approve submittals, which will perform and document the three phases of control, and which 
will perform and document the testing. 

13.  Preliminary work authorized before approval: Construction work that is authorized to proceed 

before  the  approval  of  the  CQC  plan  is  only  the  mobilization  of  storage  and  modular  office 
units, temporary utilities, and surveying 

14.  Approval:  Approval  of  the  CQC  plan  is  required  before  the  start  of  construction.  Engineer 

reserves the right to require changes in the CQC plan and operations as necessary to ensure 
the specified quality of work. Engineer reserves the right to interview any member of the CQC 
organization at any time in order to verify his/her submitted qualifications 

15.  Notification of changes: Notify the  Engineer, in writing, of any proposed change,  including 

changes  in  the  CQC  organization  personnel,  a  minimum  of  seven  calendar  days  before  a 
proposed change. Proposed changes must be approved by the Engineer 

1.13.7 

Contractor Quality Control Planning Meeting 

Before developing and submitting a CQC plan, the Contractor shall meet with the Engineer to discuss 
the  CQC  plan  requirements  of  this  Contract.  In  this  meeting,  the  Contractor  and  Engineer  shall 
develop a mutual understanding of the CQC plan requirements. This meeting shall be conducted in 
conjunction with the pre-construction meeting. 

1.13.8 

Coordination 

After approval of the CQC plan, but before the start of construction, meet with the Engineer to discuss 
the  CQC  program  required  by  this  Contract.  Purpose  of  this  meeting  is  to  develop  a  mutual 
understanding of the CQC details, including forms to be used for documentation, administration for 
on-site and off-site work, and the coordination of the Contractor's management, production and CQC 
personnel  with  the  Engineer.  As  a  minimum,  the  Contractor's  personnel  required  to  attend  shall 
include the project manager, construction manager, and CQC manager. Minutes of the meeting shall 
be prepared by the CQC manager and signed by both the Contractor and the Engineer.  

1.13.9 

Contractor Quality Control Meetings 

After the start of construction, the CQC manager shall conduct bi-weekly CQC meetings at the work 
site with the Contractor

’s project manager. CQC manager shall prepare the minutes of the meeting 

and provide a copy to the Engineer within two working days after the meeting. Engineer will attend 
these  meetings.  CQC  manager  shall  notify  the  Engineer  at  least  48  hours  in  advance  of  each 
meeting. As a minimum, the following shall be accomplished at each meeting:  

a.  Review the minutes of the previous meeting 

b.  Review the schedule and the status of work: 

1.  Work or testing accomplished since last meeting 

2.  Rework items identified since last meeting 

3.  Rework items completed since last meeting 

c.  Review the status of submittals: 

1.  Submittals reviewed and approved since last meeting 

2.  Submittals required in the near future 

3.  Status of pending submittals 

d.  Review the status of request for information (RFI): 

1. 

RFI’s reviewed since last meeting 

2. 

RFI’s required in the near future 

 

G

ENERAL 

R

 

 

 

3.  Status of pending RFIs 

e.  Review  the  work  to  be  accomplished  in  the  next  two  weeks  and  documentation  required. 

Schedule the three phases of control and testing: 

1.  Establish completion dates for rework items 

2.  Preparatory phases required 

3.  Initial phases required 

4.  Follow-up phases required 

5.  Testing required 

6.  Status of off-site work or testing 

7.  Documentation required 

f.  Resolve CQC and production problems 

g.  Address items that may require revising the CQC plan: 

1.  Changes in CQC organization personnel 

2.  Changes in procedure 

h.  Discussion of the Contractor

’s “As-Built” documentation status. 

1.13.10 

Three phases of Contractor Quality Control 

Perform the three phases of control to ensure that work complies with Contract requirements. Three 
phases of control shall adequately cover both on-site and off-site work and shall include the following 
for each definable features of work. 

1.13.10.1  Preparatory Phase   

Notify  the  Engineer  at  least  two  working  days  in  advance  of  each  preparatory  phase.  Conduct  a 
preparatory  phase  meeting  with  the  construction  manager  and  the  foreman  responsible  for  that 
definable  feature  of  work.  Document  the  results  of  the  preparatory  phase  actions  in  the  daily 
Contractor  quality  control  report.  Perform  the  following  before  beginning  work  on  each  definable 
feature of work:  

1.  Review each paragraph of the applicable specification sections. 

2.  Review the Contract plans. 

3.  Verify that appropriate shop drawings and submittals for materials and equipment have been 

submitted and approved. Verify receipt of approved factory test results, when required. 

4.  Review the testing plan and ensure that provisions have been made to provide the required 

CQC testing. 

5.  Examine the work area to ensure that the required preliminary work has been completed. 

6.  Examine the required materials, equipment and sample work to ensure that they are on hand 

and conform to the approved shop drawings and submitted data. 

7.  Review the accident prevention plan and appropriate activity hazard analysis to ensure that 

applicable safety requirements are met, and that required material safety data sheets (MSDS) 
are submitted. 

8.  Discuss construction methods. 

1.13.10.2  Initial Phase 

Notify the Engineer at least two working days in advance of each initial phase. When construction 
crews  are  ready  to  start  work  on  a  definable  feature  of  work,  conduct  the  initial  phase,  the 

 

G

ENERAL 

R

 

 

 

construction manager, and the foreman responsible for that definable feature of work. Observe the 
initial  segment  of  the  definable  feature  of  work  to  ensure  that  the  work  complies  with  Contract 
requirements. Document the results of the initial phase in the daily Contractor quality control report. 
Repeat the initial phase for each new crew to work on-site, or when acceptable levels of specified 
quality are not being met. Perform the following for each definable feature of work:  

1.  Establish the quality of workmanship required 

2.  Resolve conflicts 

3.  Review  the  accident  prevention  plan  and  the  appropriate  activity  hazard  analysis  to  ensure 

that applicable safety requirements are met 

4.  Ensure that testing is performed by the approved laboratory 

1.13.10.3  Follow-up Phase 

Perform the following for on-going work daily or more frequently as necessary until the completion 
of each definable feature of work and document in the daily Contractor quality control report:  

1.  Ensure the work is in compliance with Contract requirements 

2.  Maintain the quality of workmanship required 

3.  Ensure that testing is performed by the approved laboratory 

4.  Ensure that rework items are being corrected 

1.13.11 

Contractor Quality Submittal Review and Approval 

Procedures for submission, review and approval of submittals are specified in Section 1.11. 

1.13.12 

Contractor Quality Control Testing 

Except as stated otherwise in the specification sections, perform sampling and testing required under 
this  Contract.  Requirements  for  the  independent  testing  laboratory  shall  be  governed  by  the 
American  Association  of  State  Highway  and  Transportation  Officials  (AASHTO)  program  and  the 
American  Association  for  Laboratory  Accreditation  (AALA)  program.  Furnish  to  the  Engineer  for 
review and approval accreditation documentation including, a copy of the certificate of accreditation, 
scope of accreditation and latest directory of the accrediting organization for accredited laboratories. 
Scope of the laboratory's accreditation shall include the test methods required by the Contract. 

1.13.13 

Inspection of Testing Laboratories 

Proposed testing laboratory facilities and records are subject to inspection by the Engineer. Records 
subject  to  inspection  include  equipment  inventory,  equipment  calibration  dates  and  procedures, 
library of test procedures, audit and inspection reports by agencies conducting laboratory evaluations 
and  certifications,  testing  and  management  personnel  qualifications,  test  report  forms,  and  the 
internal CQC procedures. 

1.  Capability  check:  Engineer  retains  the  right  to  check  laboratory  equipment  in  the  proposed 

laboratory  and  the  laboratory  technician's  testing  procedures,  techniques,  and  other  items 
pertinent to testing, for compliance with the standards set forth in this Contract.  

2.  Test  results:  Cite  applicable  Contract  requirements,  tests  or  analytical  procedures  used. 

Provide actual results and include a statement that the item tested or analyzed conforms or 
fails  to  conform  to  specified  requirements.  Conspicuously  stamp  the  cover  sheet  for  each 
report  in  large  red  letters  "CONFORMS"  or  "DOES  NOT  CONFORM"  to  the  specification 
requirements,  whichever  is  applicable.  Test  results  shall  be  signed  by  a  testing  laboratory 
representative  authorized  to  sign  certified  test  reports.  Furnish  the  signed  reports, 
certifications,  and  other  documentation  to  the  Engineer  via  the  CQC  manager.  Furnish  a 
summary report of field tests at the end of each month. Attach a copy of the summary report 
to the last daily Contractor quality control report of each month. 

 

G

ENERAL 

R

 

 

 

1.13.14 

Contractor Quality Certifications 

1.  The Contractor quality control report certification: Each Contractor quality control report shall 

contain the following statement: "on behalf of the Contractor, I certify that this report is complete 
and correct and equipment and material used and work performed during this reporting period 
is in compliance with the Contract plans and specifications to the best of my knowledge, except 
as noted in this report."  

2.  Invoice certification: Furnish a certificate to the Engineer with each payment request, signed 

by the CQC manager, attesting that as-built drawings are current and attesting that the work 
for  which  payment  is  requested,  including  stored  material  is  in  compliance  with  Contract 
requirements. 

3.  Completion certification: Upon completion of work under this Contract, the CQC manager shall 

furnish a certificate to the Engineer attesting that "the work has been completed, inspected, 
tested and is in compliance with the Contract." 

1.13.15 

Contractor Quality Control Documentation 

Maintain current and complete records of on-site and off-site CQC program operations and activities. 

1.13.15.1  The Contractor Production Report 

Reports are required for each day that work is performed and shall be attached to the Contractor 
quality control report prepared for the same day. Account for each calendar day throughout the life 
of the Contract. Reporting of work shall be identified by terminology consistent with the construction 
schedule. The Contractor production reports shall be prepared, signed and dated by the construction 
manager and shall contain the following information: 

a.  Date of report, report number, name of the Contractor, Contract number, title and location of 

Contract and superintendent present 

b.  Weather  conditions  in  the  morning  and  in  the  afternoon  including  maximum  and  minimum 

temperatures 

c.  A list of the Contractor and subcontractor personnel on the work site, their trades, Owner, work 

location, description of work performed and hours worked 

d.  A  list  of  job  safety  actions  taken  and  safety  inspections  conducted.  Indicate  that  safety 

requirements have been met including the results on the following:  

1.  Was a job safety meeting held? (If YES, attach a copy of the meeting minutes) 

2.  Were there any lost time accidents? (If YES, attach a copy of the completed accident report)  

3.  Was trenching/scaffold/high voltage electrical/high work done? (If YES, attach a statement 

or checklist showing inspection performed) 

4.  Was hazardous material/waste released into the environment? (If YES, attach description 

of  incident,  corrective  action  taken,  and  proposed  actions  to  be  taken  to  avoid  similar 
incidents) 

5.  A list of equipment/material received each day that is incorporated into the job 

6.  A list of construction and plant equipment on the work site including the number of hours 

used, idle and down for repair 

7.  Include a "remarks" section in this report, which will contain pertinent information including 

directions received, problems encountered during construction, work progress and delays, 
conflicts  or  errors  in  the  Contract  plans  or  specifications,  field  changes,  safety  hazards 
encountered,  instructions  given  and  corrective  actions  taken,  delays  encountered  and  a 
record of visitors to the work site 

 

G

ENERAL 

R

 

 

 

1.13.15.2  The Contractor Quality Control Report 

Reports are required for each day that work is performed and for every seven consecutive calendar 
days of no-work and on the last day of a no work period. Account for each calendar day throughout 
the  life  of  the  Contract.  Reporting  of  work  shall  be  identified  by  terminology  consistent  with  the 
construction schedule. Reports shall be prepared, signed and dated by the CQC manager and shall 
contain the following information:  

a.  Identify the control phase and the definable feature of work 

b.  Results of the preparatory phase meetings held including the location of the definable feature 

of  work  and  a  list  of  personnel  present  at  the  meeting.  Indicate  in  the  report  that  for  this 
definable  feature  of  work,  the  Contract  plans  and  specifications  have  been  reviewed, 
submittals  have  been  approved,  materials  comply  with  approved  submittals,  materials  are 
stored properly, preliminary work was done correctly, the testing plan has been reviewed, and 
work methods and schedule have been discussed. 

c.  Results of the initial phase meetings held including the location of the definable feature of work 

and  a  list  of  personnel  present  at  the  meeting.  Indicate  in  the  report  that  for  this  definable 
feature  of  work the  preliminary  work  was  done  correctly,  samples  have  been  prepared  and 
approved, the workmanship is satisfactory, test results are acceptable, work is in compliance 
with  the  Contract,  and  the  required  testing  has  been  performed  and  include  a  list  of  who 
performed the tests.  

d.  Results of the follow-up phase inspections held including the location of the definable feature 

of work. Indicate in the report for this definable feature of work that the work complies with the 
Contract as approved in the initial phase, and that required testing has been performed and 
include a list of who performed the tests.  

e.  Results of the three phases of control for off-site work, if applicable, including actions taken.  

f.  List the rework items identified, but not corrected by close of business.  

g.  List the rework items corrected from the rework items list along with the corrective action taken.  

h.  Include  a  "remarks"  section  in  this  report  which  will  contain  pertinent  information  including 

directions received, quality control problem areas, deviations from the CQC plan, construction 
deficiencies encountered, CQC meetings held, acknowledgement that as-built drawings have 
been updated, corrective direction given by the CQC organization and corrective action taken 
by the Contractor. 

i.  The Contractor quality control report certification. 

1.13.15.3  Testing Plan and Log 

As tests are performed, the CQC Manager shall record on the "testing plan and log" the date the test 
was  conducted,  the  date  the  test  results  were  forwarded  to  the  Engineer,  remarks  and 
acknowledgement  that  the  accredited  or  Engineer  approved  independent  testing  laboratory  was 
used. Attach a copy of the updated "testing plan and log" to the last daily Contractor quality control 
report of each month. 

1.13.15.4  Rework Items List 

CQC manager shall maintain a list of work that does not comply with the Contract, identifying what 
items need to be reworked, the date the item was originally discovered, and the date the item was 
corrected.  There  is  no  requirement  to  report  a  rework  item  that  is  corrected  the  same  day  it  is 
discovered.  Attach  a  copy  of the  "Contractor rework  items  list" to  the  last  daily  Contractor  quality 
control  report  of  each  month.  The  Contractor  shall  be  responsible  for  including  on  this  list  items 
needing rework including those identified by the Engineer. 

 

G

ENERAL 

R

 

 

 

1.13.15.5  As-Built Drawings 

CQC manager is required to review the as-

built drawings required in the “Contract closeout” section, 

to ensure that as-built drawings are kept current on a daily basis and marked to show deviations, 
which have been made from the Contract plans. CQC manager assigned to an area of responsibility 
shall  initial  each  deviation  and  each  revision.  Upon  completion  of  work,  the  CQC  manager  shall 
furnish a certificate attesting to the accuracy of the as-built drawings before submission of a copy to 
the Engineer. 

1.14 

Utility Coordinator 

This  section  specifies  the  duty  and  services  of  a  Utility  Coordinator  for  all  the  utility  works  to  be 
carried out under this Contract. 

The  Contractor  shall  employ  and  pay  for  services  of  a  person,  technically  qualified  and 
administratively experienced in field co-ordination for the type of utility work required for this project, 
for the duration of the work. 

1.14.1 

Utility Coordinator Submittal for Review 

Submit curriculum vitae of Utility Coordinator for review and approval by the Engineer. Submit duties 
and  powers  delegated  to  the  coordinator  Engineer.  Submit  co-ordination  drawings  and  progress 
schedules before submitting shop drawings, product data, and samples. 

1.14.2 

Utility 

&RRUGLQDWRU¶V5HTXLUHG'XWLHV 

Utility coordinator shall comply with the following requirements: 

a.  Coordinate all utility activities with that of other sections in the specification.  

b.  Coordinate progress schedules, including dates for submittals and for delivery of products.  

c.  Conduct meetings among those parties concerned with the work, to establish and maintain co-

ordination, progress schedules and to resolve any co-ordination matters. Transmit minutes of 
meetings and reports to all concerned parties.  

d.  Participate in progress meetings.  

e.  Report  on  progress  of  the  work  (to  be  adjusted  under  coordination  requirements)  and  any 

required changes in the schedules.  

f.  Follow-up submittals and the procurement process. 

1.14.3 

Utility Coordination Documentation 

Utility coordination documentation shall meet the following requirements. 

a.  Prepare coordination drawings in a manner to provide for the most efficient use of available 

space, the best sequence of installation and for identification of potential conflicts.  

b.  Prepare a master schedule to identify requirements (submittals, testing, commissioning, O&M 

manuals, etc.) designated under each section of the specifications for activities, which directly 
relate to the work, including temporary utilities.  

c.  Identify pipe and equipment connections, standards and pressure ratings.  

d.  Identify electrical power characteristics and control wiring required for each item of equipment.  

e.  Maintain documents for the duration of the work, recording changes due to site instructions, 

modifications or adjustments.  

f.   After the Engineer reviews and approves the original and/or revised documents, reproduce 

and distribute copies to all concerned parties. 

 

G

ENERAL 

R

 

 

 

1.14.4 

Coordination of Submittals 

The Contractor shall coordinate submittals in accordance with the following requirements: 

a.  Review shop drawings, product data, and samples for compliance with Contract documents 

and transmit these to the Engineer for approval.  

b.  Check field dimensions and clearances and relationship to available space and anchors.  

c.  Check compatibility with equipment and work of other sections, electrical characteristics and 

operational control requirements.  

d.  Check motor voltages related with starting mode and control characteristics.  

e.  Coordinate controls, interlocks, wiring of push button switches and relays.  

f.  Coordinate wiring and control diagrams.  

g.  Review the effect of any changes on work of other sections.  

h.  Verify information and coordinate the maintenance of record documents. 

1.14.5 

Coordination of Substitutions and Modifications 

The  Contractor  shall  review  proposals  and  requests  from  subcontractors.  Verify  compliance  with 
Contract  documents  and  for  compatibility  with  work  and  products  of  other  sections.  Substitutions 
shall conform to the requirements outlined in Section 1.18.4. Submit with recommendation for action.  

1.14.6 

Observation of Work 

Observe work for compliance with Contract documents. Maintain a list of observed deficiencies and 
defects; promptly submit. 

1.14.7 

Documentation  

Documentation shall include: 

a.  Observe and maintain a record of tests. Record:  

1.  Specification section number, product, and name of subcontractor/supplier 

2.  Name of testing agency and name of inspector 

3.  Phone/ fax no. or e-mail address of testing agency 

4.  Name of manufacturer's representative present 

5.  Date, time and duration of tests 

6.  Type of test and results 

7.  Retesting required 

b.  Assemble  background  documentation  for  dispute  and  Claim  settlement  by  Engineer  and 

Owner. 

c.  Submit copies of documentation to Engineer upon request. 

1.14.8 

Mains Electricity and Liaison with ADEWA 

Requirements of liaising with ADEWA include the following: 

a.  Be  acquainted  with  Abu  Dhabi  Electricity  and  Water  Authority  (ADEWA)  regulations  and 

requirements.  

b.  Liaise with ADEWA to determine the power supply required and all other pertinent information 

as required and make all necessary arrangements for its connection.  

 

G

ENERAL 

R

 

 

 

c.  Arrange through written request for ADEWA to undertake the testing and inspection necessary 

in order that the electricity supplies may be connected when required.  

Any delay caused by omission to make the request in good time, will not be accepted. 

1.14.9 

Utility Service and Process Interruption 

Utility service and process interruptions initiated by the Contractor during the course of the work shall 
be  scheduled  in  advance  and  approved  by  the  relevant  authority  and  Engineer  before  being 
implemented.  

Unforeseen circumstances may make it necessary to postpone scheduled utility service and process 
interruptions.  Such  actions  by  the  relevant  authority  shall  not  be  cause  for  extension  of  time  for 
completion or Claims for additional compensation. 

1.14.10 

Equipment Start-up 

Equipment start-up shall be done as follows: 

a.  Verify utilities, connections, and controls are complete and equipment is in operable condition 

as required by the specifications.  

b.  Observe start-up and adjustments, test run, record time and date of start-up, and results.  

c.  Observe  equipment  demonstrations  for  the  Owner;  record  times  and  additional  information 

required for operation and maintenance manuals. 

1.14.11 

Inspection and Acceptance of Equipment 

Before inspection, verify that equipment is tested, operational, clean and ready for operation. Assist 
Engineer with review. Prepare list of items to be completed and corrected. 

1.14.12 

Scheduling  

Schedule shall include the following: 

1.  Sequence of work 

2.  Materials and shop drawings submittal 

3.  Material procurement 

4.  Inspection and testing 

5.  Manufacturer services and training 

1.15 

Construction Facilities and Temporary Controls  

This  section  outlines  standards,  specifications,  and  requirements  for  construction  facilities  and 
temporary controls. 

1.15.1 

Submittals   

The Contractor shall submit for the Engineer

’s approval, the following items:   

a.  Copies  of  permits  and  approvals  for  construction  as  required  by  laws,  regulations  and 

governing agencies 

b.  Temporary utility submittals  

c.  Electric power supply and distribution plans 

d.  Water supply and distribution plans 

e.  Drainage plans 

f.  Dewatering well locations 

 

G

ENERAL 

R

 

 

 

g.  Sanitary service plan 

h.  Temporary construction and site use plan containing:  

1.  Access roads: Routes, cross-sections, and drainage facilities 

2.  Parking area plans 

3.  The  Contractor

’s  field  office,  storage  yard,  and  storage  building  plans,  including  gravel 

and/or paved surfaced area 

4.  Fencing and protective barrier locations and details 

5.  Engineer

’s field office 

6.  Staging area location plan 

7.  Construction stages and corresponding traffic control and routing plans 

8.  Plan for maintenance of existing plant operations (if applicable) 

9.  Temporary lighting including offices and roads  

i.  Temporary control submittals:  

1.  Plan  for  disposal  of  waste  materials  and  intended  haul  routes  as  part  of  the  CEMP 

prescribed in Sections 1.15.4 and 1.15.9.  

2.  Environmental, sediment and pollution control plan.  

1.15.2 

Site Mobilization  

Site mobilization shall include, but shall not be limited to, the following principal items:  

1.  Moving the Contractor

’s and the Engineer’s field offices and equipment required for the first 

month of operations onto the project site 

2.  Installing temporary construction power, wiring, and lighting facilities 

3.  Providing onsite communication facilities, including telephones 

4.  Providing and erecting the Contractor

’s work and storage yard 

5.  Posting required safety notices and establishing safety programs and procedures 

6.  Ensuring that the Contractor

’s construction manager is at the site full time 

7.  Having the Contractor

’s representative responsible for the site mobilization at site full time 

Use  area  for  the  Contractor

’s  temporary  facilities  within  worksite  or  as  agreed  by  the  Engineer. 

Submit site use plan for approval in accordance with the requirements in Section 1.15.1. All services 
and access shall be at the Contractor

’s expense.  

1.15.3 

Protection of Work and Property  

The Contractor shall follow the requirements in this section to protect work and property. 

1.15.3.1 

General 

a.  Comply with project safety rules while on Owner

’s property. 

b.  Keep Engineer informed of any onsite accidents and related Claims.  

c.  Use of explosives: No blasting or use of explosives will be allowed unless specifically approved 

by the Engineer, Owner and relevant authorities.  

d.  Perform  work  within  right-of-way  and  easements  in  a  systematic  manner  that  minimizes 

inconvenience to property owners and the public. Any excavations outside of the affection plan 
require an approved permit to dig from the Engineer.  

 

G

ENERAL 

R

 

 

 

e.  Maintain in continuous service all existing oil and gas pipelines, underground power, telephone 

or communication cable, water mains, irrigation lines, sewers, poles and overhead power, and 
all other utilities encountered along line of the work, unless other arrangements satisfactory to 
the owner of said utilities have been made.  

f.  Where completion of the work requires temporary or permanent removal and/or relocation of 

existing utility, coordinate all activities with owner of said utility and perform all work to their 
satisfaction.  

g.  Protect, shore, brace, support, and maintain underground pipes, conduits, drains, and other 

underground utility construction uncovered or otherwise affected by construction operations.  

h.  Keep water control valves free from obstruction and available for use at all times.  

i.  In  areas  where  the  Contractor

’s  operations  are  adjacent  to  or  near  a  utility,  such  as  gas, 

telephone, television, electric power, water, sewer, or irrigation system, and such operations 
may cause damage or inconvenience, suspend operations until arrangements necessary for 
protection have been made by the Contractor.  

j.  Notify property owners and utility offices that may be affected by construction operation at least 

2 days in advance.  

k. 

Before  exposing  a  utility,  obtain  utility  owner’s  permission.  Should  service  of  utility  be 
interrupted due to the Contractor

’s operation, notify proper authority immediately. Cooperate 

with said authority in restoring service as promptly as possible and bear costs incurred.  

l.  Do not impair operation of  existing sewer system. Prevent construction material, pavement, 

concrete, earth, volatile and corrosive wastes, and other debris from entering sewers, pump 
stations, or other sewer structures.  

m. Maintain original site drainage wherever possible.  

1.15.3.2 

Site Security  

a.  Provide and maintain additional temporary security fences as necessary to protect the work 

and the Contractor furnished products not yet installed.  

b.  Barricades and lights:  

1.  Provide as necessary to prevent unauthorized entry to construction areas inside and outside 

of fenced area, and as required to ensure public safety and the safety of the Contractor

’s 

employees, other Owner personnel, and others who may be affected by the work.  

2.  Locate to enable access by facility operators and property owners.  

c.  Signs and equipment:  

1.  Traffic  control:  Provide  temporary  traffic  control  devices  as  necessary  to  delineate  traffic 

lanes to guide and separate traffic movements.  

2.  High-level warning flag units: Provide two in advance of traffic approaching the work, each 

displaying three flags mounted at a height of 1 meter.  

3.  Warning signs: Provide at obstructions, such as material piles and equipment.  

4.  Illuminate barricades and obstructions with warning lights from sunset to sunrise.  

1.15.3.3 

Trees and Plantings  

a.  Protect from damage and preserve trees, shrubs, and other plants outside limits of the Work 

and within limits of the work, which are designated to remain undisturbed.  

b.  In event of damage to bark, trunks, limbs, or roots of plants that are not designated for removal, 

treat damage by corrective pruning, bark tracing, application of a heavy coating of tree paint, 
and other accepted horticultural and tree surgery practices.  

 

G

ENERAL 

R

 

 

 

c.  Replace each plant that dies as a result of construction activities.  

1.15.3.4 

Dewatering 

Construct,  maintain,  and  operate  cofferdams,  channels,  flume  drains,  sumps,  pumps,  or  other 
temporary diversion and protection works. Furnish materials required, install, maintain, and operate 
necessary pumping and other equipment for the environmentally safe removal and disposal of water 
from the various parts of the work. Maintain foundations and parts of the work free from water. Before 
dewatering works proceed, the Contractor will submit drawings and calculations to the Engineer for 
approval and issue of permit to dewater from the Owner.  

1.15.3.5 

Archaeological Finds  

a.  General: Should finds of an archaeological or paleontological nature be made within the limits 

of the site, immediately notify Engineer and proceed in accordance with the general conditions. 
Continue the work in other areas without interruption.  

b.  Archaeological  finds:  Evidence  of  human  occupation  or  use  of  an  area  within  the  Contract 

limits  before the  Year  1840.  Evidence may  consist  of  skeletons,  stone, or  other  utensils,  or 
evidence of habitations or structures.  

c.  Paleontological Finds: Evidence of prehistoric plant or animal life, such as skeletons, bones, 

fossils, or casts and other indications such as pictographs.  

d.  Engineer may order the work stopped in other areas if, in Engineer

’s opinion, the find is more 

extensive than may appear from uncovered material.  

e.  Protection of finds:  

1.  Cover, fence, or otherwise protect finds until notice to resume the work is given.  

2.  Cover finds with plastic film held in place by earth, rocks, or other weights placed outside 

the find. Should additional backfilling be necessary for safety or to prevent  caving, place 
backfill material loosely over the plastic film.  

3.  Sheet or shore as necessary to protect excavations underway. Place temporary fence to 

prevent unauthorized access.  

4.  Dewater finds made below water table as necessary to protect construction work underway. 

Divert groundwater or surface runoff away from find by ditching or other acceptable means.  

f.  Removal of finds:  

1.  All  finds  are  property  of  Owner.  Do  not  remove  or  disturb  finds  without  Owner

’s  written 

authorization.  

2.  Should  Owner  elect  to  have  a  find  removed,  provide  equipment,  labour,  and  material  to 

permit  safe  removal  of  find  without  damage.  Provide  transportation  for  delivery  to 
individuals, institutions, or other places as Owner may find desirable, expedient, or required 
by law.  

1.15.3.6 

Endangered Species  

a.  Take precautions necessary and prudent to protect native endangered flora and fauna.  

b.  Notify  Engineer  of  construction  activities  that  might  threaten  endangered  species  or  their 

habitats.  

c.  Engineer will mark areas known as habitats of endangered species before commencement of 

onsite activities.  

d.  Additional areas will be marked by Engineer as other habitats of endangered species become 

known during construction.  

e.  The Contractor shall provide temporary high visibility fencing around habitats to be protected 

 

G

ENERAL 

R

 

 

 

1.15.4 

Engineer

¶VField Offices  

As stipulated in project Particular Specifications as per project requirements. 

 

1.15.5 

Agency Representatives Field Offices  

As stipulated in project Particular Specifications as per project requirements. 

 

 

1.15.6 

Information Technology  

As stipulated in project Particular Specifications as per project requirements. 

 

1.15.7 

Site Laboratory 

Site laboratories shall comply with the requirements in this section. 

1.15.7.1 

Description  

1.  The  Contractor  shall  provide  a  site  laboratory  for  his  and  the  Engineers  quality  control  and 

testing.  

2.  Laboratory facilities shall be similar  in construction and shall be maintained as specified for 

Engineer's site office facilities, in Section 1.15.4.  

3.  The Contractor shall provide a sufficient number of qualified personnel to perform sampling 

and testing duties as specified. 

4.  The Contractor shall provide suitable transportation as approved by the Engineer during the 

Contract period, for the exclusive use of the site laboratory, sufficient for both the Contractor

’s 

and the Engineer

’s laboratory personnel.  

5.  The Contractor shall provide the laboratory with equipment list A for projects having primarily 

road  works  with  minor  structures  only.  The  Contractor  shall  provide  the  laboratory  with 
equipment list B for projects having major structures, unless otherwise required in the particular 
specifications or directed by the Engineer.  

1.15.7.2 

Use of the Laboratory  

Laboratory shall be for the use of the Contractor for his quality control program. However, Engineer 
shall have exclusive use of the laboratory at all times during the project for Engineer

’s acceptance 

and  quality  testing  as  otherwise  required.  The  Contractor  shall,  provide  a  sufficient  number  of 
qualified personnel to perform sampling, testing and related duties under the direct supervision of 
the Engineer.  

1.15.7.3 

Location of the Laboratory  

Location of the laboratory shall be adjacent to the Engineer's site office facilities unless otherwise 
approved by the Engineer. Laboratory shall be available and maintained until final acceptance of the 
project is provided.  

1.15.7.4 

Maintenance of the Laboratory  

The Contractor shall at all times be responsible for maintaining the building, utilities and all testing 
equipment in an acceptable condition for use. All consumables shall be restocked by the Contractor 
in a timely manner. 

 

G

ENERAL 

R

 

 

 

1.15.7.5 

Approval of the Laboratory  

Before constructing the laboratory, the Contractor shall submit and obtain written approval from the 
Engineer of the shop drawings for the laboratory.  

Before  the  start  of  work,  the  Engineer  will  inspect  the  laboratory  to  ensure  the  Contractor's 
compliance  with  these  specifications.  In  the  event  the  Contractor  fails  to  comply  with  these 
specifications  at  any  time  during  the  Contract  period,  the  Engineer  may  order  any  or  all  of  the 
sampling and testing to be performed at any other laboratory designated by the Engineer with such 
fees and charges to be deducted from any amounts due to the Contractor.  

1.15.7.6 

Building Requirements 

A site laboratory shall comply with the following building requirements. 

a.  Laboratory shall contain all necessary equipment in acceptable working order and adequate 

storage and working space for the following:  

1.  Preparation of soil, aggregate, concrete and asphalt mix samples, etc.  

2.  Storage of field sampling equipment, i.e. Sand cone density apparatus, stockpile sampling 

tools, concrete cube moulds, cement, bitumen and soil sampling equipment, etc. 

3.  Soil  and  aggregate  testing:  Gradation,  L.L.,  P.I.,  sand  equivalent,  proctor,  aggregate 

flakiness  and  elongation,  calibration  of  sand  for  density  testing,  speedy  moisture,  oven 
moisture, C.B.R., etc. 

4.  Concrete testing: Making and curing concrete cubes, etc. 

5.  Asphalt mix testing: Density of compacted samples,  extraction gradation, bitumenometer 

for ash correction, marshall moulds, etc. 

b.  Site laboratory shall provide a minimum of  120 m

2

 of office space with three separate individual 

offices of  twelve square meters each enclosed with glass windows facing the remainder of the 
laboratory and furnished as otherwise specified in this specs, plus equipped with the following 
for use by the Engineer as required: 

1.  Minimum 20 mbps broadband or wifi internet connection and router 

2.  Latest spec Standard PC with monitor: Three (3) 

3.  Laptop: One (1) 

4.  A3 colour printer: One (1) 

5.  Power supply surge protector: 1 per computer and peripheral device as required to protect 

all devices 

6.  Local area network including all cables, switches, routers and accessories. 

7.  Work centre: One (1) 

8.  Digital camera: Two (2); Kodak or HP digital cameras with minimum 7 mp with minimum 3x 

optical  zoom  with  minimum  1  GB  memory  card  and  all  accessories  (cables,  software, 
batteries, chargers, etc.), or equal 

c.  Laboratory  shall  be  provided  with  electricity;  lighting;  air  conditioning  and  heating  system; 

water; an inside storage tank for trichloroethylene; sinks; rigid flooring; desks; work benches; 
cupboards; curing tank; windows with blinds; doors and fans. A separate concrete curing room 
shall be provided which shall have a 15 m

2

 floor space with necessary lighting, humidity and 

temperature controls, as directed by the Engineer. 

The office furniture, desks, chairs, work benches with metal work surfaces (aluminium or GI 
sheet), and cupboards for the site laboratories shall be as required by the Engineer and be 
new, and of the quality and quantity as approved by the Engineer. 

 

 

 

 

 

 

 