इटरनट
मानक
Disclosure to Promote the Right To Information
Whereas the Parliament of India has set out to provide a practical regime of right to
information for citizens to secure access to information under the control of public authorities,
in order to promote transparency and accountability in the working of every public authority,
and whereas the attached publication of the Bureau of Indian Standards is of particular interest
to the public, particularly disadvantaged communities and those engaged in the pursuit of
education and knowledge, the attached public safety standard is made available to promote the
timely dissemination of this information in an accurate manner to the public.
“जान1 का अ+धकार, जी1 का अ+धकार”
“परा1 को छोड न' 5 तरफ”
Mazdoor Kisan Shakti Sangathan
Jawaharlal Nehru
“The Right to Information, The Right to Live”
“Step Out From the Old to the New”
SP 7 : Group 1 (2005): NATIONAL BUILDING CODE OF INDIA 2005
GROUP 1 [CED 46: National Building Code]
“!ान $ एक न' भारत का +नम-ण”
Satyanarayan Gangaram Pitroda
“Invent a New India Using Knowledge”
“!ान एक ऐसा खजाना > जो कभी चराया नहB जा सकता ह”
Bhartṛhari—Nītiśatakam
“Knowledge is such a treasure which cannot be stolen”
Hkkjr dh jk"Vh; Hkou fuekZ.k lfgrk
2005
lewg
1
NATIONAL BUILDING CODE
OF INDIA 2005
Group 1
NATIONAL
BUILDING
CODE OF INDIA
2005
GROUP 1
PART 0
INTEGRATED APPROACH — PREREQUISITE FOR APPLYING
PROVISIONS OF THE CODE
PART 2
ADMINISTRATION
PART 3
DEVELOPMENT CONTROL RULES AND GENERAL BUILDING
REQUIREMENTS
PART 4
FIRE AND LIFE SAFETY
PART 5
BUILDING MATERIALS
PART 10
LANDSCAPING, SIGNS AND OUTDOOR DISPLAY STRUCTURES
Section 1 Landscape Planning and Design
Section 2 Signs and Outdoor Display Structures
BUREAU OF INDIAN STANDARDS
SP 7 (Group 1) : 2005
FIRST PUBLISHED 1970
FIRST REVISION 1983
SECOND REVISION 2005
ICS 0.120; 91.040.01
ISBN 81-7061-026-5
PRICE Rs. 3030.00
PUBLISHED BY BUREAU OF INDIAN STANDARDS, MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR
MARG, NEW DELHI 110 002, PRINTED AT SUNSHINE PROCESS, C-105/5, NARAINA INDUSTRIAL
AREA, PHASE I, NEW DELHI 110 028 (INDIA).
BIS Website: www.bis.org.in
( iv )
FOREWORD
Construction programmes are interwoven in a large measure in all sectors of development, be it housing, transport,
industry, irrigation, power, agriculture, education or health. Construction, both public and private, accounts for
about fifty percent of the total outlay in any Five Year Plan. Half of the total money spent on construction
activities is spent on buildings for residential, industrial, commercial, administrative, education, medical, municipal
and entertainment uses. It is estimated that about half of the total outlay on buildings would be on housing. It is
imperative that for such a large national investment, optimum returns are assured and wastage in construction is
avoided.
Soon after the Third Plan, the Planning Commission decided that the whole gamut of operations involved in
construction, such as, administrative, organizational, financial and technical aspects, be studied in depth. For this
study, a Panel of Experts was appointed in 1965 by the Planning Commission and its recommendations are found
in the ‘Report on Economies in Construction Costs’ published in 1968.
One of the facets of building construction, namely, controlling and regulating buildings through municipal byelaws
and departmental handbooks received the attention of the Panel and a study of these regulatory practices revealed
that some of the prevailing methods of construction were outmoded; some designs were overburdened with
safety factors and there were other design criteria which, in the light of newer techniques and methodologies,
could be rationalized; and building byelaws and regulations of municipal bodies which largely regulate the
building activity in the country wherever they exist, were outdated. They did not cater to the use of new building
materials and the latest developments in building designs and construction techniques. It also became clear that
these codes and byelaws lacked uniformity and they were more often than not ‘specification oriented’ and not
‘performance oriented’.
These studies resulted in a recommendation that a National Building Code be prepared to unify the building
regulations throughout the country for use by government departments, municipal bodies and other construction
agencies. The then Indian Standards Institution (now Bureau of Indian Standards) was entrusted by the Planning
Commission with the preparation of the National Building Code. For fulfilling this task a Guiding Committee for
the preparation of the Code was set up by the Civil Engineering Division Council of the Indian Standards Institution
in 1967. This Committee, in turn, set up 18 specialist panels to prepare the various parts of the Code. The
Guiding Committee and its panels were constituted with architects, planners, materials experts, structural,
construction, electrical illumination, air conditioning, acoustics and public health engineers and town planners.
These experts were drawn from the Central and State Governments, local bodies, professional institutions and
private agencies. The first version of the Code was published in 1970.
After the National Building Code of India was published in 1970, a vigorous implementation drive was launched
by the Indian Standards Institution to propagate the contents and use of the Code among all concerned in the field
of planning, designing and construction activities. For this, State-wise Implementation Conferences were organized
with the participation of the leading engineers, architects, town planners, administrators, building material
manufacturers, building and plumbing services installation agencies, contractors, etc.
These Conferences were useful in getting across the contents of the Code to the interests concerned. These
Conferences had also helped in the establishment of Action Committees to look into the actual implementation
work carried out by the construction departments, local bodies and other agencies in different States. The main
actions taken by the Action Committees were to revise and modernize their existing regulatory media, such as,
specifications, handbooks, manuals, etc, as well as building byelaws of local bodies like municipalities at city
and town levels, zilla parishads, panchayats and development authorities, so as to bring them in line with the
provisions contained in the National Building Code of India. In this process, the Indian Standards Institution
rendered considerable support in redrafting process.
Since the publication in 1970 version of the National Building Code of India, a large number of comments and
useful suggestions for modifications and additions to different parts and sections of the Code were received as a
result of use of the Code by all concerned, and revision work of building byelaws of some States. Based on the
comments and suggestion received the National Building Code of India 1970 was revised in 1983.
(v)
Some of the important changes in 1983 version included : addition of development control rules, requirements
for greenbelts and landscaping including norms for plantation of shrubs and trees, special requirements for low
income housing; fire safety regulations for high rise buildings; revision of structural design section based on new
and revised codes, such as Concrete Codes (plain and reinforced concrete and prestressed concrete), Earthquake
Code, Masonry Code; addition of outside design conditions for important cities in the country, requirements
relating to noise and vibration, air filter, automatic control, energy conservation for air conditioning; and guidance
on the design of water supply system for multi-storeyed buildings.
The National Building Code of India is a single document in which, like a network, the information contained in
various Indian Standards is woven into a pattern of continuity and cogency with the interdependent requirements
of Sections carefully analyzed and fitted in to make the whole document a cogent continuous volume. A continuous
thread of ‘preplanning’ is woven which, in itself, contributes considerably to the economies in construction
particularly in building and plumbing services.
The Code contains regulations which can be immediately adopted or enacted for use by various departments,
municipal administrations and public bodies. It lays down a set of minimum provisions designed to protect the
safety of the public with regard to structural sufficiency, fire hazards and health aspects of buildings; so long as
these basic requirements are met, the choice of materials and methods of design and construction is left to the
ingenuity of the building professionals. The Code also covers aspects of administrative regulations, development
control rules and general building requirements; fire protection requirements; stipulations regarding materials
and structural design; rules for design of electrical installations, lighting, air conditioning and lifts; regulation for
ventilation, acoustics and plumbing services, such as, water supply, drainage, sanitation and gas supply; measures
to ensure safety of workers and public during construction; and rules for erection of signs and outdoor display
structures.
Some other important points covered by the Code include ‘industrialized systems of building’ and ‘architectural
control’. The increase in population in the years to come will have a serious impact on the housing problem. It
has been estimated that the urban population of India will continue to increase with such pace as to maintain the
pressure on demand of accommodation for them. Speed of construction is thus of an utmost importance and
special consideration has to be given to industrialized systems of building. With increased building activity, it is
also essential that there should be some architectural control in the development of our cities and towns if
creation of ugliness and slum-like conditions in our urban areas is to be avoided.
Since the publication of 1983 version of National Building Code of India, the construction industry has gone
through major technological advancement. In the last two decades, substantial expertise has been gained in the
areas of building planning, designing and construction. Also, lot of developments have taken places in the techno-
legal regime and techno-financial regime, apart from the enormous experience gained in dealing with natural
calamities like super cyclones and earthquakes faced by the country. Further, since the last revision in 1983
based on the changes effected in the Steel Code, Masonry Code and Loading Code as also in order to update the
fire protection requirements, three amendments were brought out to the 1983 version of the Code. Considering
these, it was decided to take up a comprehensive revision of the National Building Code of India.
The changes incorporated in the present Code, which is second revision of the Code, have been specified in the
Foreword to each Part/Section of the Code. Some of the important changes are:
a) A new Part 0 ‘Integrated Approach — Prerequisite for Applying the Provisions of the Code’ emphasizing
on multi-disciplinary team approach for successfully accomplishing building/development project, has
been incorporated.
b) New chapters on significant areas like structural design using bamboo, mixed/composite construction
and landscaping have been added.
c) Number of provisions relating to reform in administration of the Code as also assigning duties and
responsibilities to all concerned professionals, have been incorporated/modified. Also detailed provisions/
performance to ensure structural sufficiency of buildings, have been prescribed so as to facilitate
implementation of the related requirements to help safely face the challenges during natural disasters
like earthquake.
d) Planning norms and requirements for hilly areas and rural habitat planning, apart from detailed planning
norms for large number of amenities have been incorporated.
e) Fire safety aspects have been distinctly categorized into fire prevention, life safety and fire protection
( vi )
giving detailed treatment to each based on current international developments and latest practices followed
in the country.
f) Aspects like energy conservation and sustainable development have been consistently dealt with in
various parts and sections through appropriate design, usage and practices with regard to building
materials, construction technologies and building and plumbing services. Renewable resources like
bamboo and practices like rain water harvesting have been given their due place.
g) The latest revised earthquake code, IS 1893 (Part 1) : 2002 ‘Criteria for earthquake resistant design of
structures: Part 1 General provisions and buildings’, has been incorporated, due implementation of the
provisions of which in applicable seismic zone of the country, needs to be duly adhered to by the
Authorities.
The Code now published is the third version representing the present state of knowledge on various aspects of
building construction. The process of preparation of the 2005 version of the Code had thrown up a number of
problems; some of them were answered fully and some partially. Therefore, a continuous programme will go on
by which additional knowledge that is gained through technological evolution, users’ views over a period of time
pinpointing areas of clarification and coverage and results of research in the field, would be incorporated in to
the Code from time to time to make it a living document. It is, therefore, proposed to bring out changes to the
Code periodically.
The provisions of this Code are intended to serve as a model for adoption by Public Works Departments and
other government construction departments, local bodies and other construction agencies. Existing PWD codes,
municipal byelaws and other regulatory media could either be replaced by the National Building Code of India
or suitably modified to cater to local requirements in accordance with the provisions of the Code. Any difficulties
encountered in adoption of the Code could be brought to the notice of the Sectional Committee for corrective
action.
This publication forms part of the National Building Code of India 2005 and contains
the following Parts:
PART 0 INTEGRATED APPROACH - PREREQUISITE FOR APPLYING
PROVISIONS OF THE CODE
PART 2 ADMINISTRATION
PART 3 DEVELOPMENT CONTROL RULES AND GENERAL BUILDING
REQUIREMENTS
PART 4 FIRE AND LIFE SAFETY
PART 5 BUILDING MATERIALS
PART 10 LANDSCAPING, SIGNS AND OUTDOOR DISPLAY
STRUCTURES
Section 1 Landscape Planning and Design
Section 2 Signs and Outdoor Display Structures
The information contained in this publication will essentially serve the concerned
professionals in dealing with the development and building schemes from the early
stages of planning.
( vii )
National Building Code Sectional Committee, CED 46
Chairman
Dr H. C. VISVESVARAYA
‘Chandrika’, at 15th Cross, 63-64 East Park Road
Malleswaram, Bangalore 560 003
Vice-Chairman
SHRI V. SURESH
P-233/3, Officers Enclave,
Air Force Station, Rajokari, New Delhi 110 038
Organization
Representative(s)
Ahmedabad Municipal Corporation, Ahmedabad
SHRI VATSAL S. PATEL
SHRI JAGDISH A. PATEL (Alternate)
Bangalore Mahanagara Palike, Bangalore
SHRI M. R. SREENIVASA MURTHY
SHRI R. RAMEGOWDA (Alternate I)
SHRI N. KRISHNA (Alternate II)
Builders Association of India, Mumbai
SHRI B. G. AHUJA
Building Materials and Technology Promotion Council, New Delhi
SHRI T. N. GUPTA & SHRI D. B. N. RAO
Bureau of Energy Efficiency (Ministry of Power), New Delhi
REPRESENTATIVE
Central Building Research Institute (CSIR), Roorkee
SHRI V. K. MATHUR
SHRI B. S. GUPTA (Alternate)
Central Public Health and Environmental Engineering Organisation
SHRI B. B. UPPAL
(Ministry of Urban Development and Poverty Alleviation),
SHRI V. K. CHAURASIA (Alternate)
New Delhi
Central Public Works Department (Central Designs Organization),
CHIEF ENGINEER (DESIGNS)
New Delhi
SUPERINTENDING ENGINEER (S & S)
(Alternate)
Central Public Works Department (Electrical Department),
CHIEF ENGINEER (ELECTRICAL) I
New Delhi
Centre for Disaster Mitigation and Management, Anna University,
DIRECTOR
Chennai
Chennai Metropolitan Development Authority, Chennai
MEMBER SECRETARY
SHRI N. V. RAKHUNATH (Alternate)
Construction Industry Development Council, New Delhi
SHRI P. R. SWARUP
SHRI ANIL CHADHA (Alternate)
Council of Architecture, New Delhi
SHRI PREMENDRA RAJ MEHTA
SHRI SUDHIR VOHRA (Alternate)
Delhi Development Authority, New Delhi
ENGINEER MEMBER
CHIEF ENGINEER (HQ) (Alternate)
Delhi Fire Service, Government of National Capital Territory
SHRI R. C. SHARMA
of Delhi, Delhi
Department of Science and Technology (Ministry of Science
SHRI V. RAO ALYAGARI
and Technology), New Delhi
Directorate General of Employment and Training, New Delhi
SHRI ASHWANI KUMAR
Engineer-in-Chief’s Branch, Army Headquarters, New Delhi
BRIG S. K. SHARMA
SHRI D. K. DINKER (Alternate)
Forest Research Institute (Indian Council for Forestry Research
DIRECTOR GENERAL
and Education), Dehra Dun
DIRECTOR
(Alternate)
Housing and Urban Development Corporation Ltd, New Delhi
CHAIRMAN & MANAGING DIRECTOR
SHRI R. K. SAFAYA (Alternate)
Indian Geotechnical Society, New Delhi
SHRI D. B. MAHAJAN
DR M. D. DESAI (Alternate)
( viii )
Organization
Representative(s)
Indian Institute of Technology (Centre for Energy Studies),
PROF N. K. BANSAL
New Delhi
Indian Roads Congress, New Delhi
CHIEF ENGINEER (DESIGN), CPWD
SUPERINTENDING ENGINEER (DESIGN), CPWD (Alternate)
Institute of Town Planners, India, New Delhi
DR S. K. KULSHRESTHA
Institution of Fire Engineers (India), New Delhi
PRESIDENT
GENERAL SECRETARY (Alternate)
Ministry of Home Affairs, New Delhi
FIRE ADVISOR
Ministry of Home Affairs (Disaster Management Division),
SHRI M. P. SAJNANI
New Delhi
SHRI S. K. SWAMI (Alternate)
Ministry of Non-Conventional Energy Sources, New Delhi
DR T. C. TRIPATHI
Ministry of Road Transport and Highways, New Delhi
SHRI S. B. BASU
SHRI P. HALDER (Alternate)
Municipal Corporation of Greater Mumbai, Mumbai
DIRECTOR (ENGG SERVICES & PROJECTS)
CITY ENGINEER (Alternate)
National Buildings Construction Corporation, New Delhi
SHRI B. PRASAD
SHRI N. P. AGARWAL (Alternate)
National Council for Cement and Building Materials, Ballabgarh
SHRI SHIBAN RAINA
DR ANIL KUMAR (Alternate)
National Design and Research Forum, The Institution of Engineers
PROF R. NARAYANA IYENGAR
(India), Bangalore
SHRI B. SURESH (Alternate)
National Environmental Engineering Research Institute (CSIR),
DR ARINDAM GHOSH
Nagpur
DR V. P. DESHPANDE (Alternate)
North Eastern Council, Shillong
SHRI P. K. DEB
Public Works Department (Roads and Buildings), Gandhinagar
SHRI V. P. JAMDAR
SHRI M. S. JALLUNDHWALA (Alternate)
Research, Designs and Standards Organization (Ministry of Railways),
SHRI R. K. GUPTA
Lucknow
SHRI J. P. DAS (Alternate)
School of Planning and Architecture, New Delhi
DIRECTOR
Structural Engineering Research Centre (CSIR), Chennai
SHRI C. V. VAIDYANATHAN
SHRI K. MANI (Alternate)
Suri and Suri Consulting Acoustical Engineers, New Delhi
SHRI GAUTAM SURI
The Energy and Resources Institute, New Delhi
MS MILI MAJUMDAR
MS VIDISHA SALUNKE-PALSULE (Alternate)
The Indian Institute of Architects, New Delhi
SHRI BALBIR VERMA
SHRI ABHIJIT RAY (Alternate)
The Institution of Engineers (India), Kolkata
PROF G. P. LAL
SHRI O. P. GOEL (Alternate)
The Institution of Surveyors, New Delhi
SHRI K. S. KHARB
SHRI R. K. BHALLA (Alternate)
Town and Country Planning Organization, New Delhi
SHRI K. T. GURUMUKHI
SHRI J. B. KSHIRSAGAR (Alternate)
U.P. Housing and Development Board, Lucknow
SHRI HARI GOPAL
Unitech Ltd, Gurgaon
SHRI SUSHIL SHARMA
SHRI SHAHID MAHMOOD (Alternate)
In personal capacity (5, Sunder Nagar, New Delhi 110 003)
DR J. R. BHALLA
BIS Directorate General
SHRI S. K. JAIN, Director & Head (Civil Engineering)
[Representing Director General (Ex-officio Member)]
Member Secretary
SHRI SANJAY PANT
Joint Director (Civil Engineering), BIS
( ix )
Special Panel for Guiding and Co-ordinating the
Revision of National Building Code of India, CED 46:SP
Organization
Representative(s)
In personal capacity (P-233/3, Officers Enclave, Air Force Station,
SHRI V. SURESH (Convener)
Rajokari, New Delhi 110 038)
Building Materials and Technology Promotion Council, New Delhi
SHRI T. N. GUPTA
Central Building Research Institute (CSIR), Roorkee
SHRI V. K. MATHUR
Central Public Works Department, New Delhi
SHRI H. S. DOGRA
Council of Architecture, New Delhi
SHRI PREMENDRA RAJ MEHTA
Engineer-in-Chief’s Branch, Army Headquarters, New Delhi
LT-GEN HARI UNIYAL
The Institution of Engineers (India), Kolkata
PROF G. P. LAL
SHRI O. P. GOEL (Alternate)
Bureau of Indian Standards, New Delhi
SHRI SANJAY PANT
Ad-hoc Group for Part 0 of NBC, CED 46:AG
Organization
Representative(s)
In personal capacity (‘Chandrika’, at 15th Cross, 63-64, East Park Road, DR H. C. VISVESVARAYA (Convener)
Malleswaram, Bangalore 560 003)
Council of Architecture, New Delhi
SHRI PREMENDRA RAJ MEHTA
In personal capacity (P-233/3, Officers Enclave, Air Force Station,
SHRI V. SURESH
Rajokari, New Delhi 110 038)
In personal capacity (A-39/B, DDA Flats, Munirka, New Delhi 110 067)
SHRI P. B. VIJAY
In personal capacity (EA-345, Maya Enclave, New Delhi 110 064)
SHRI J. N. BHAVANI PRASAD
Panel for Administration, Development Control Rules and
General Building Requirements, CED 46:P1
Organization
Representative(s)
In personal capacity (P-233/3, Officers Enclave, Air Force Station,
SHRI V. SURESH (Convener)
Rajokari, New Delhi 110 038)
Ahmedabad Municipal Corporation, Ahmedabad
REPRESENTATIVE
Building Materials and Technology Promotion Council, New Delhi
SHRI T. N. GUPTA
SHRI RAJESH MALIK (Alternate)
Central Building Research Institute (CSIR), Roorkee
SHRI V. K. MATHUR
SHRI N. K. SHANGARI (Alternate)
Central Public Works Department, New Delhi
SHRI R. S. KAUSHAL
SHRI SANJIB SENGUPTA (Alternate)
Consulting Engineers Association of India, New Delhi
SHRI S. C. MEHROTRA
SHRI N. F. PATEL (Alternate)
Council of Architecture, New Delhi
SHRI PREMENDRA RAJ MEHTA
SHRI SUDHIR VOHRA (Alternate)
Delhi Development Authority, New Delhi
SHRI R. C. KINGER
SHRI A. K. GUPTA (Alternate)
Housing and Urban Development Corporation Ltd, New Delhi
SHRI K. C. BATRA
Indian Association of Structural Engineers, New Delhi
SHRI MAHENDRA RAJ
Institute of Town Planners (India), New Delhi
DR S. K. KULSHRESTHA
Municipal Corporation of Delhi, Delhi
ENGINEER-IN-CHIEF
SHRI M. M. DAS (Alternate)
Municipal Corporation of Greater Mumbai, Mumbai
CHIEF ENGINEER (DEVELOPMENT PLAN)
DEPUTY CHIEF ENGINEER (DEVELOPMENT PLAN)-I (Alternate)
National Council for Cement and Building Materials, Ballabgarh
DR ANIL KUMAR
(x)
Organization
Representative(s)
National Real Estate Development Council, New Delhi
BRIG R. R. SINGH (RETD)
School of Planning and Architecture, New Delhi
PROF SUBIR SAHA
The Indian Institute of Architects, Mumbai
SHRI BALBIR VERMA
SHRI ABHIJIT RAY (Alternate)
The Institution of Engineers (India), Kolkata
SHRI A. D. SHIRODE
SHRI P. B. VIJAY (Alternate)
Town and Country Planning Organization, New Delhi
SHRI J. B. KSHIRSAGAR
SHRI R. SRINIVAS (Alternate)
Panel for Fire Protection, CED 46:P2
Organization
Representative(s)
In personal capacity (29/25, Old Rajendra Nagar, New Delhi 110 060)
SHRI S. K. DHERI (Convener)
Central Building Research Institute (CSIR), Roorkee
DR T. P. SHARMA
DR GOPAL KRISHNA (Alternate)
Central Public Works Department, New Delhi
SHRI ARVIND KANSAL
SHRI R. S. KAUSHAL (Alternate)
Deolalikar Consultants Pvt Ltd, New Delhi
SHRI S. G. DEOLALIKAR
Directorate of Town and Country Planning, Government of Tamil Nadu,
SHRI S. DHANASEKARAN
Chennai
SHRI R. RAJAGOPALAN (Alternate)
Engineer-in-Chief’s Branch, Army Headquarters, New Delhi
SHRI R. A. DUBEY
SHRI AJAY SHANKAR (Alternate)
Institution of Fire Engineers (India), New Delhi
SHRI U. S. CHHILLAR
SHRI S. P. BATRA (Alternate)
Lloyd Insulations (India) Ltd, New Delhi
SHRI SANJEEV ANGRA
SHRI K. K. MITRA (Alternate)
Ministry of Home Affairs, New Delhi
SHRI OM PRAKASH
SHRI D. K. SHAMMI (Alternate)
Delhi Fire Service, Government of National Capital Territory of Delhi,
SHRI R. C. SHARMA
Delhi
SHRI G. C. MISRA (Alternate)
Municipal Corporation of Greater Mumbai (Mumbai Fire Brigade),
SHRI A. D. JHANDWAL
Mumbai
SHRI V. H. NAIK (Alternate)
National Council for Cement and Building Materials, Ballabgarh
DR ANIL KUMAR
National Fire Service College (Ministry of Home Affairs), Nagpur
DR K. C. WADHWA
SHRI SHAMIM (Alternate)
Oil Industry Safety Directorate, New Delhi
SHRI D. JAGANNATH
SHRI S. K. AGGARWAL (Alternate)
Regional Research Laboratory (CSIR), Jorhat
REPRESENTATIVE
Spectral Services Consultants Pvt Ltd, New Delhi
SHRI SANDEEP GOEL
Tariff Advisory Committee, Mumbai
SHRI Z. U. ISLAM
SHRI D. N. SAHA (Alternate)
The Institution of Engineers (India), Kolkata
PROF M. P. CHOWDIAH
SHRI K. B. RAJORIA (Alternate)
In personal capacity (P-233/3, Officers Enclave, Air Force Station,
SHRI V. SURESH
Rajokari, New Delhi 110 038)
Panel for Building Materials, CED 46:P3
Organization
Representative(s)
Building Materials and Technology Promotion Councils, New Delhi
SHRI T. N. GUPTA (Convener)
Central Building Research Institute (CSIR), Roorkee
DR C. L. VERMA
SHRI L. K. AGARWAL (Alternate)
Central Public Works Department, New Delhi
SHRI H. K. L. MEHTA
SHRI R. C. GUPTA (Alternate)
( xi )
Organization
Representative(s)
Council of Architecture, New Delhi
SHRI ANURAG ROY
SHRI ATUL GUPTA (Alternate)
Department of Science and Technology (Ministry of Science and
SHRI SOUMITRA BISWAS
Technology), New Delhi
SHRI G. SRIKANTH (Alternate)
Engineer-in-Chief’s Branch, Army Headquarters, New Delhi
SHRI A. K. SINGH
SHRI P. K. GUPTA (Alternate)
Housing and Urban Development Corporation Ltd, New Delhi
CHAIRMAN AND MANAGING DIRECTOR
SHRI S. K. TANEJA (Alternate)
Indian Plywood Industries Research and Training Institute,
SHRI K. SHYAMASUNDAR
Bangalore
SHRI M. PAWAN KUMAR (Alternate)
National Council for Cement and Building Materials, Ballabgarh
SHRI SHIBAN RAINA
DR K. MOHAN (Alternate)
The Institution of Engineers (India), Kolkata
SHRI G. L. RAO
SHRI R. S. GOEL (Alternate)
Panel for Landscaping, Signs and Outdoor Display Structures, CED 46:P18
Organization
Representative(s)
In personal capacity (5, Sunder Nagar, New Delhi 110003)
DR J. R. BHALLA (Convener)
Central Public Works Department, New Delhi
SHRI ARVIND KANSAL
SHRI A. N. DEVIKAR (Alternate)
Council of Architecture, New Delhi
KUMARI VINITA C. K. VIJAYAN
Delhi Urban Arts Commission, New Delhi
SHRI H. K. YADAV
SHRI DINA NATH (Alternate)
Housing and Urban Development Corporation, New Delhi
SHRI R. K. SAFAYA
Institute of Town Planners, India, New Delhi
DR S. K. KULSHRESTHA
Municipal Corporation of Delhi, Delhi
SHRI S. S. HADKE
SHRI S. RAMESH (Alternate)
Municipal Corporation of Greater Mumbai, Mumbai
SHRI M. S. GHAG
SHRI R. K. RAHATE (Alternate)
National Institute of Design, Ahmedabad
SHRI ANANDO DUTTA
SHRI J. G. SEVAK (Alternate)
Selvel Publicity and Consultants Pvt Ltd, Mumbai
SHRI K. S. NICHOLSON
Shaheer Associates, New Delhi
PROF M. SHAHEER
Town and Country Planning Organization, New Delhi
SHRI J. B. KSHIRSAGAR
SHRI Y. RAMESH (Alternate)
The Indian Institute of Architects, Mumbai
SHRI MAHESH PALIWAL
The Institution of Engineers (India), Kolkata
PROF JITENDRA SINGH
In personal capacity (D-198, Defence Colony, New Delhi 110024)
SHRI RAVINDRA BHAN
Member Secretary
SHRI SANJAY PANT
Joint Director (Civil Engineering), BIS
Joint Member Secretary
SHRI S. K. VERMA
Deputy Director (Civil Engineering), BIS
( xii )
Important Explanatory Note for Users of Code
In this Code, where reference is made to ‘accepted standards’ in relation to material
specification, testing or other related information or where reference is made to ‘good practice’
in relation to design, constructional procedures or other related information, the Indian
Standards listed at the end of the concerned Parts/Sections may be used to the interpretation
of these terms.
At the time of publication, the editions indicated in the above Indian Standards were valid.
All standards are subject to revision and parties to agreements based on the Parts/Sections
are encouraged to investigate the possibility of applying the most recent editions of the
standards.
In the list of standards given at the end of each Part/Section, the number appearing in the
first column indicates the number of the reference in that Part/Section. For example:
a) accepted standard [3(1)] refers to the standard given at serial number 1 of the list of
standards given at the end of Part 3, that is IS 8888 (Part 1) : 1993 ‘Guide for
requirements of low income housing: Part 1 Urban area (first revision)’.
b) good practice [4(3)] refers to the standard given at serial number 3 of the list of standards
given at the end of Part 4, that is IS 15394 : 2003 ‘Code of practice for fire safety in
petroleum refinery and fertilizer plants’.
c) accepted standard [4(11)] refers to the standard given at serial number 11 of the list of
standards given at the end of Part 4, that is IS 11360 : 1985 ‘Specification for smoke
detectors for use in automatic electrical fire alarm system’.
d) good practice [4(28)] refers to the standard given at serial number 28 of the list of
standards given at the end of Part 4, that is IS 12456 : 1988 ‘Code of practice for fire
protection of electronic data processing installations’.
e) good practice [10-2(3)] refers to the standard given at serial number 3 of the list of
standards given at the end of Section 2 of Part 10, that is IS 401 : 2001 ‘Code of
practice for preservation of timber (fourth revision)’.
( xiii )
INFORMATION FOR THE USERS
For the convenience of the users, the National Building Code of India 2005 is available as a comprehensive
volume as well as in the following five groups, each incorporating the related Parts/Sections dealing with particular
area of building activity:
Group 1
For Development, Building
Part 0:
Integrated Approach
— Prerequisite for Applying
Planning and Related
Provisions of the Code
Aspects
Part 2:
Administration
Part 3:
Development Control Rules and General Building
Requirements
Part 4:
Fire and Life Safety
Part 5:
Building Materials
Part 10:
Landscaping, Signs and Outdoor Display Structures
Section 1 Landscape Planning and Design
Section 2 Signs and Outdoor Display Structures
Group 2
For Structural Design and
Part 0:
Integrated Approach
— Prerequisite for Applying
Related Aspects
Provisions of the Code
Part 6:
Structural Design
Section 1 Loads, Forces and Effects
Section 2 Soils and Foundations
Section 3 Timber and Bamboo
3A Timber
3B Bamboo
Section 4 Masonry
Section 5 Concrete
5A Plain and Reinforced Concrete
5B Prestressed Concrete
Section 6 Steel
Section 7 Prefabrication, Systems Building and
Mixed/Composite Construction
7A Prefabricated Concrete
7B Systems Building and Mixed/
Composite Construction
Group 3
For Construction Related
Part 0:
Integrated Approach
— Prerequisite for Applying
Aspects including Safety
Provisions of the Code
Part 7:
Constructional Practices and Safety
Group 4
For Aspects Relating to
Part 0:
Integrated Approach
— Prerequisite for Applying
Building Services
Provisions of the Code
Part 8:
Building Services
Section 1 Lighting and Ventilation
Section 2 Electrical and Allied Installations
Section 3 Air conditioning, Heating and Mechanical
Ventilation
Section 4 Acoustics, Sound Insulation and Noise
Control
Section 5 Installation of Lifts and Escalators
Group 5
For Aspects Relating to
Part 0:
Integrated Approach
— Prerequisite for Applying
Plumbing Services
Provisions of the Code
including Solid Waste
Part 9:
Plumbing Services
Management
Section 1 Water Supply, Drainage and Sanitation
(including Solid Waste Management)
Section 2 Gas Supply
The information contained in different groups will essentially serve the concerned professionals dealing in the
respective areas.
( xiv )
The National Building Code of India consists of the following Parts and Sections:
Total Pages
PART 0
INTEGRATED APPROACH — PREREQUISITE FOR APPLYING PROVISIONS OF THE CODE
… 12
PART 1
DEFINITIONS
… 16
PART 2
ADMINISTRATION
… 24
PART 3
DEVELOPMENT CONTROL RULES AND GENERAL BUILDING REQUIREMENTS
… 64
PART 4
FIRE AND LIFE SAFETY
… 88
PART 5
BUILDING MATERIALS
… 40
PART 6
STRUCTURAL DESIGN
Section 1
Loads, Forces and Effects
…
104
Section 2
Soils and Foundations
…
48
Section 3
Timber and Bamboo
3A Timber
…
50
3B Bamboo
…
24
Section 4
Masonry
…
44
Section 5
Concrete
5A Plain and Reinforced Concrete
…
90
5B Prestressed Concrete
…
6
Section 6
Steel
…
8
Section 7
Prefabrication, Systems Building and Mixed/Composite
Construction
7A Prefabricated Concrete
…
22
7B Systems Building and Mixed/Composite Construction
…
12
PART 7
CONSTRUCTIONAL PRACTICES AND SAFETY
…
70
PART 8
BUILDING SERVICES
Section 1
Lighting and Ventilation
…
48
Section 2
Electrical and Allied Installations
…
68
Section 3
Air Conditioning, Heating and Mechanical Ventilation
…
48
Section 4
Acoustics, Sound Insulation and Noise Control
…
44
Section 5
Installation of Lifts and Escalators
…
42
PART 9
PLUMBING SERVICES
Section 1
Water Supply, Drainage and Sanitation (including Solid
…
90
Waste Management)
Section 2
Gas Supply
…
14
PART 10
LANDSCAPING, SIGNS AND OUTDOOR DISPLAY STRUCTURES
Section 1
Landscape Planning and Design
…
30
Section 2
Signs and Outdoor Display Structures
…
24
( xv )
NATIONAL BUILDING CODE OF INDIA
PART 0 INTEGRATED APPROACH — PREREQUISITE FOR
APPLYING PROVISIONS OF THE CODE
BUREAU OF INDIAN STANDARDS
C O N T E N T S
FOREWORD
…
3
1
SCOPE
…
5
2
TERMINOLOGY
…
5
3
GENERAL
…
5
4
TEAM APPROACH
…
5
5
PLANNING, DESIGNING AND DEVELOPMENT
…
6
6
CONSTRUCTION/EXECUTION (ACTUALIZATION)
…
7
7
OPERATION AND MAINTENANCE
…
8
ANNEX A BRIEF DETAILS OF THE COVERAGE OF VARIOUS PROVISIONS
… 9
UNDER DIFFERENT OTHER PARTS/SECTIONS OF THIS CODE
2
NATIONAL BUILDING CODE OF INDIA
National Building Code Sectional Committee, CED 46
FOREWORD
In order to provide safe and healthy habitat, careful consideration needs to be paid to the building construction
activity. Building planning, designing and construction activities have developed over the centuries. Large number
of ancient monuments and historical buildings all over the world bear testimony to the growth of civilization
from the prehistoric era with the extensive use of manual labour and simple systems as appropriate to those ages
to the present day mechanized and electronically controlled operations for designing and constructing buildings
and for operating and maintaining systems and services. In those days those buildings were conceptualized and
built by master builders with high levels of artisan skills. Technological and socio-economic developments in
recent times have led to remarkable increase in demand for more and more sophistication in buildings resulting
in ever increasing complexities. These perforce demand high levels of inputs from professionals of different
disciplines such as architecture, civil engineering, structural engineering, functional and life safety services
including special aspects relating to utilities, landscaping, etc in conceptualization, spatial planning, design and
construction of buildings of various material and technology streams, with due regard to various services including
operation, maintenance, repairs and rehabilitation aspects throughout the service life of the building.
This Code, besides prescribing the various provisions, also allows freedom of action to adopt appropriate practices
and provides for building planning, designing and construction for absorbing traditional practices as well as
latest developments in knowledge in the various disciplines as relevant to a building including computer aided
and/or other modern sensors aided activities in the various stages of conceptualization, planning, designing,
constructing, maintaining and repairing the buildings. India being a large country with substantial variations
from region to region, this Code has endeavoured to meet the requirements of different regions of the country,
both urban and rural, by taking into consideration factors, such as, climatic and environmental conditions,
geographical terrain, proneness to natural disasters, ecologically appropriate practices, use of eco-friendly materials,
reduction of pollution, protection and improvement of local environment and also socio-economic considerations,
towards the creation of sustainable human settlements.
This Part of the Code dealing with ‘integrated approach’ is being included for the first time. It gives an overall
direction for practical applications of the provisions of different specialized aspects of spatial planning, designing
and construction of buildings, creation of services, and proposes an integrated approach for utilizing appropriate
knowledge and experience of qualified professionals right from the conceptualization through construction and
completion stages of a building project and indeed during the entire life cycle. The ‘integrated approach’ should
not only take care of functional, aesthetic and safety aspects, but also the operational and maintenance requirements.
Also, cost optimization has to be achieved through proper selection of materials, techniques, equipment
installations, etc. Further, value engineering and appropriate management techniques should be applied to achieve
the aim set forth for the purpose of construction of a building fully meeting the specified and implied needs of
spatial functions, safety and durability aspects, life and health safety, comfort, services, etc in the building.
The aim of the ‘integrated approach’ is to get the maximum benefit from the building and its services in terms of
quality, timely completion and cost-effectiveness. In the team approach which is an essential pre-requisite for
integrated approach, the aim clearly is to maximize the efficiency of the total system through appropriate
optimization of each of its sub-systems. In other words, in the team, the inputs from each of the professional
disciplines have to be so optimized that the total system’s efficiency becomes the maximum. It may be re-
emphasized that maximizing the efficiencies of each sub-system may not necessarily assure the maximization of
the efficiency of the total system. It need hardly to be stated that specified or implied safety will always get
precedence over functional efficiency and economy. Further, progressive approach such as that relating to the
concept of intelligent buildings would be best taken care of by the ‘integrated approach’ as laid down in this Part.
Quality systems approach and certification thereunder covering the various dimensions brought out above may
go a long way in achieving the above goal of real integrated approach.
PART 0 INTEGRATED APPROACH
3
NATIONAL BUILDING CODE OF INDIA
PART 0 INTEGRATED APPROACH — PREREQUISITE FOR
APPLYING PROVISIONS OF THE CODE
1 SCOPE
development control rules and general building
requirements; building materials; fire and life safety;
This Part covers guidelines to be followed for judicious
structural design; constructional practices and safety;
implementation of the provisions of various Parts/
building and plumbing services; and landscaping, signs
Sections of the Code.
and outdoor display structures, other parts/sections of
2 TERMINOLOGY
the Code may be referred to.
2.0
For the purpose of this Part, the following
3.2
The scope of various Parts/Sections of the Code
definitions and those given in Part 1 ‘Definitions’ shall
which cover detailed provisions on different aspects
apply.
of development of land/building construction activity,
are given in Annex A, with a view to providing an
2.1 Authority Having Jurisdiction — The Authority
overview for the users of the Code.
which has been created by a statute and which, for the
purpose of administering the Code/Part, may authorize
4 TEAM APPROACH
a committee or an official or an agency to act on its
A land development/building project comprises the
behalf; hereinafter called the ‘Authority’.
following major stages:
2.2 Building — Any structure for whatsoever purpose
a) Location/siting,
and of whatsoever materials constructed and every part
b) Conceptualization and planning,
thereof whether used as human habitation or not and
includes foundation, plinth, walls, floors, roofs,
c) Designing and detailing,
chimneys, plumbing and building services, fixed
d) Construction/execution, and
platforms, VERANDAH, balcony, cornice or projection,
e) Maintenance and repair.
part of a building or anything affixed thereto or any
Each stage necessarily requires professionals of many
wall enclosing or intended to enclose any land or space
disciplines who should work together as a well
and signs and outdoor display structures. Tents/
coordinated team to achieve the desired product
SHAMIANAHS/PANDALS, tarpaulin shelters, etc,
delivery with quality, in an effective manner.
erected for temporary and ceremonial occasions shall
not be considered as building.
Appropriate multi-disciplinary teams need to be
constituted to successfully meet the requirements of
2.3 Owner — Person or body having a legal interest
different stages. Each team may comprise need based
in land and/or building thereon. This includes free
professionals out of the following depending upon the
holders, leaseholders or those holding a sub-lease
nature, magnitude and complexity of the project:
which both bestows a legal right to occupation and
gives rise to liabilities in respect of safety or building
a) Architect,
condition.
b) Civil engineer,
In case of lease or sub-lease holders, as far as ownership
c) Structural engineer,
with respect to the structure is concerned, the structure
d) Electrical engineer,
of a flat or structure on a plot belongs to the allottee/
e) Plumbing engineer,
lessee till the allotment/lease subsists.
f) Fire protection engineer,
NOTE — For the purpose of the Code, the word ‘owner’ will
g) HVAC engineer,
also cover the generally understood terms like ‘client’, ‘user’,
etc.
h) Environment specialist,
j)
Town planner,
3 GENERAL
k) Urban designer,
3.1
Buildings, shall be classified as Residential,
m) Landscape architect,
Educational, Institutional, Assembly, Business,
n) Security system specialist,
Mercantile, Industrial, Storage and Hazardous in
groups and sub-division as classified in Part 4 ‘Fire
p) Interior designer,
and Life Safety’.
q) Quantity surveyor,
r) Project/construction manager, and
For further sub-classification of buildings and various
related provisions thereof with respect to administration;
s) Other subject specialist(s).
PART 0 INTEGRATED APPROACH
5
4.1 Design Team
depending on the size and complexity of the project,
are carefully selected considering their qualification,
In building projects various aspects like form; space
experience and expertise in these fields.
planning; aesthetics; fire and life safety; structural
adequacy; plumbing services; lighting and natural
4.3
Operation and Maintenance Team
ventilation; electrical and allied installations; air
Operation, maintenance and repairs also require a
conditioning, heating and mechanical ventilation;
multi-disciplinary approach to ensure that all the
acoustics, sound insulation and noise control;
requirements of the users are satisfactorily met. During
installation of lifts and escalators; building automation;
maintenance and repairs, the jobs requiring inter-
data and voice communication; other utility services
disciplinary co-ordination have to be executed in such
installations; landscape planning and design; urban
a manner as not only to cause least inconvenience to
planning; etc need to be kept in view right at the
the user but also to ensure that there is no mismatch or
concept stage. The project requiring such multi-
damage to the structure, finishings, fittings and fixtures.
disciplinary inputs need a co-ordinated approach
For carrying out routine maintenance/repair jobs,
among the professionals for proper integration of
utilization of the services of trained technicians
various design inputs. For this, and to take care of the
preferably having multi-disciplinary skills should be
complexities of multi-disciplinary requirements, a
encouraged.
design team of professionals from required disciplines
shall be constituted at the appropriate stage. Here, it is
Special repairs, rehabilitation and retrofitting are
desirable that the multi-disciplinary integration is
specialized jobs which demand knowledge of the
initiated right from the concept stage. The team shall
existing structure/installations. Association of
finalize the plan. The composition of the team shall
concerned specialists may be helpful for these works.
depend on the nature and magnitude of the project.
The Operation and Maintenance Team may also be
Design is an evolutionary and participatory process,
known as Asset Management or Estate Management
where participation of owner constitutes a very
Team.
important input at all stages, and the same shall be
ensured by the design team.
5 PLANNING, DESIGNING AND DEVELOPMENT
To ensure proper implementation of the design, the
5.1
The main functions of design team (see 4.1)
design team, may be associated during the construction/
constituted for the planning, designing and development,
execution stage.
are as under:
4.2
Project Management and Construction
a)
Formalization of design brief in consultation
Management Teams
with the owner.
b)
Site investigation/survey.
The objective of project management or construction
management is primarily to achieve accomplishment
c)
Preparation of alternative concept designs.
of project in accordance with the designs and
d)
Selection of a concept in consultation with
specifications in a stipulated time and cost framework,
and with the consent of owner.
with a degree of assurance prior to commencement and
e)
Sizing the system.
satisfaction on accomplishment.
f)
Development of design, covering :
For large projects, separate teams of experienced
1) Integration of architecture, structure and
professionals from the required disciplines may
services,
beconstituted for project management and for
2) Synthesis of requirements of each
construction management depending upon the
discipline, and
complexities of the project. However, for smaller
3) Interaction with each other and with the
projects these teams may be combined. The teams shall
owner.
be responsible for day-to-day execution, supervision,
g)
Preparation of preliminary designs and
quality control, etc and shall ensure inter-disciplinary
drawings and obtaining owner’s approval.
co-ordination during the construction stage. The team
h)
Preparation of preliminary cost estimates for
shall be responsible to achieve satisfactory completion
approval of owner.
of the project with regard to cost, time and quality.
Some members of the design team may also be
j)
Preparation of work-breakdown structure and
included in the project management team and/or
programme for pre-construction activities.
associated actively during the project execution stage.
k)
Assisting client to obtain approvals of the
It is important that leaders and members of project
Authority.
management/construction management teams,
m)
Preparation of detailed specification and
6
NATIONAL BUILDING CODE OF INDIA
construction working drawings with integration
j)
Acoustical controls for buildings and the
of engineering inputs of all concerned
surroundings.
disciplines.
k)
Promotion of artwork in buildings, specially
n) Preparation of detailed design of each
buildings of importance.
discipline for various services.
m)
Due cognizance of recommendations of the
p) Peer review/proof checking of the drawings/
Archeological Survey of India with regard to
designs in case of important projects,
national monuments and construction in
depending upon their complexity and
archeologically important sites.
sensitivity.
n)
Due cognizance of relevant provisions of
q) Preparation of detailed cost estimate.
applicable coastal zone regulation act.
r) Obtaining final approval of client.
p)
Conservation of heritage structures and areas.
s) Preparation of bill of quantities, specifications
q)
Environmental and social impact analysis.
and tender documents.
r)
Design of services with emphasis on aspects
of energy efficiency, environment friendliness
5.2
The following considerations, as may be
and maintainability.
applicable to the project, may be considered during
planning, notwithstanding other relevant aspects
s)
Integrated waste management.
specifically prescribed in concerned parts/sections of
t)
Voice and data communication, automation
this Code; these considerations in general are with the
of building services, and intelligent building;
objective of addressing to the important issues like
use of security and surveillance system in
environmental protection, energy conservation,
important and sensitive buildings, such as,
cultural issues, creating barrier free built-environment,
access control for the people as well as for
safety aspects, etc, all of these leading towards
vehicle.
sustainable development, and have to be applied with
u)
Interlinking of fire alarm system, fire
due regard to the specific requirements of size and type
protection system, security system, ventilation,
of project:
electrical systems, etc.
a)
Geoclimatic, geological and topographical
v)
Analysis of emergency power, standby power
features.
requirement and captive power systems.
b)
Varied sociological pattern of living in the
w)
Cost optimization through techniques like
country.
value engineering.
c)
Effective land use to cater to the needs of the
y)
Adoption of innovative technologies giving
society in a most convenient manner.
due consideration to constructability and
quality aspects.
d)
Modular planning and standardization to
take care of future planning giving due
z)
Instrumentation of buildings and monitoring
consideration to the specified planning
and use of information so generated to effect
controls.
improvements in planning and design of
future building projects.
e)
Emphasis on daylight utilization, natural
ventilation, shielding, and window area
6
CONSTRUCTION/EXECUTION
and its disposition; daylighting to be
(ACTUALIZATION)
supplemented with an integrated design of
artificial lighting.
6.1
The main functions of the teams (see 4.2)
constituted for Project Management/Construction
f)
Optimum utilization of renewable energy
Management may be, to :
sources duly integrated in the overall energy
system design; with consideration of active
a) specify criteria for selection of constructors;
and passive aspects in building design
b) specify quality control, quality audit system
including thermal performance of building
and safety system;
envelope.
c) short-list constructors;
g)
Rain water harvesting, and use of appropriate
d) have pre-bid meetings with the intending
building materials considering aspects
constructors;
like energy consumption in production,
e) receive and evaluate tenders;
transportation and utilization, recyclability,
etc for promoting sustainable development.
f) select constructors;
h)
Requisite mandatory provisions for
g) execution and supervision;
handicapped persons.
h) monitor quality, time and cost control;
PART 0
INTEGRATED APPROACH
7
j)
prepare/certify the completion (as-built)
system of periodic maintenance and upkeep of
drawings; and
constructed buildings.
k) ensure availability of operation manuals for
7.2 The operation and maintenance team shall be
field use.
responsible for preparation/application of operation
6.2 Apart from the specific provisions laid down in
and maintenance manual, and draw maintenance
the concerned Parts/Sections of the Code, the following
schedule/frequencies and guidelines for maintenance
considerations, as may be applicable to the project
personnel. Apart from the specific provisions laid down
concerned, shall be given due attention:
in concerned Parts/Sections of the Code, the following,
as may be applicable to the project concerned shall
a) Adopting scientific principles of construction
additionally be taken into account:
management, quality management, cost and
time control.
a) Periodic validation of buildings by competent
b) Engagement of executing and supervising
professionals through inspection of the
agencies, which meet the specified norms of
buildings in respect of structural safety and
skills, specialization, experience, resource-
safety of electrical and other installations and
fulness, etc for the work.
ensuring that all fire safety equipments/
c) Ensuring inter-disciplinary co-ordination
systems are in proper working condition.
during construction.
b) Preparation of preventive maintenance
d) Contract management and techno-legal
schedules for all installations in the building
aspects.
and strictly following the same; the record of
the preventive maintenance to be properly
e) Completion, commissioning and trial run of
kept.
installations/equipments and their operation
and maintenance through the suppliers/other
c) Ensuring inter-disciplinary co-ordination
teams, where necessary.
during maintenance and repairs; deployment
f) Make available shop drawings as well as as-
of trained personnel with multi-disciplinary
built drawings for the building and services.
skills to be encouraged.
g) Arrange all maintenance and operation
d) Condition survey of structures and
manual from the concerned suppliers/
installations, identification of distress of
manufacturers.
various elements and initiating plans for
rehabilitation/retrofitting well in time.
6.3 The team of professionals (see 4.2) shall work
and monitor the project activities for successful
7.3 The proposals for rehabilitation/retrofitting should
construction/execution of the project with regard to
be prepared after detailed investigations through visual
cost, time, quality and safety.
inspection, maintenance records and testing as required
and got executed through specialized agencies
7 OPERATION AND MAINTENANCE
under the guidance and supervision of competent
7.1 The team of professionals (see 4.3) shall set up a
professionals.
8
NATIONAL BUILDING CODE OF INDIA
ANNEX A
(Clause 3.2)
BRIEF DETAILS OF THE COVERAGE OF VARIOUS PROVISIONS UNDER
DIFFERENT OTHER PARTS/SECTIONS OF THIS CODE
A-1 PART 1 DEFINITIONS
A-6.2 Section 2 Soils and Foundations
It lists the terms appearing in all the Parts/Sections of
It covers structural design (principles) of all building
the Code. However, some common definitions are
foundations, such as, raft, pile and other foundation
reproduced in this Part also.
systems to ensure safety and serviceability without
exceeding the permissible stresses of the materials of
A-2 PART 2 ADMINISTRATION
foundations and the bearing capacity of the supporting
soil.
It covers the administrative aspects of the Code, such
as applicability of the Code, organization of building
A-6.3 Section 3 Timber and Bamboo
department for enforcement of the Code, procedure
for obtaining development and building permits, and
A-6.3.1 Section 3A Timber
responsibility of the owner and all professionals
It covers the use of structural timber in structures or
involved in the planning, design and construction of
elements of structures connected together by fasteners/
the building.
fastening techniques.
A-3 PART 3 DEVELOPMENT CONTROL RULES
A-6.3.2 Section 3B Bamboo
AND GENERAL BUILDING REQUIREMENTS
It covers the use of bamboo for constructional purposes
It covers the development control rules and general
in structures or elements of the structure, ensuring
building requirements for proper planning and design
quality and effectiveness of design and construction
at the layout and building level to ensure health safety,
using bamboo. It covers minimum strength data,
public safety and desired quality of life.
dimensional and grading requirements, seasoning,
A-4 PART 4 FIRE AND LIFE SAFETY
preservative treatment, design and jointing techniques
with bamboo which would facilitate scientific
It covers the requirements for fire prevention, life
application and long-term performance of structures.
safety in relation to fire, and fire protection of
It also covers guidelines so as to ensure proper
buildings. TheCode specifies planning and
procurement, storage, precautions and design
construction features and fire protection features for
limitations on bamboo.
all occupancies that are necessary to minimize danger
to life and property.
A-6.4 Section 4 Masonry
A-5 PART 5 BUILDING MATERIALS
It covers the structural design aspects of unreinforced
load bearing and non-load bearing walls, constructed
It covers the requirements of building materials and
using various bricks, stones and blocks permitted in
components, and criteria for accepting new or
accordance with this Section. This, however, also
alternative building materials and components.
covers provisions for design of reinforced brick and
A-6 PART 6 STRUCTURAL DESIGN
reinforced brick concrete floors and roofs. It also
covers guidelines regarding earthquake resistance of
This Part through its seven sections provides for
low strength masonry buildings.
structural adequacy of buildings to deal with both
internal and external environment, and provide
A-6.5 Section 5 Concrete
guidance to engineers/structural engineers for varied
A-6.5.1 Section 5A Plain and Reinforced Concrete
usage of material/technology types for building
design.
It covers the general structural use of plain and
reinforced concrete.
A-6.1 Section 1 Loads, Forces and Effects
A-6.5.2 Section 5B Prestressed Concrete
It covers basic design loads to be assumed in the design
of buildings. The live loads, wind loads, seismic loads,
It covers the general structural use of prestressed
snow loads and other loads, which are specified therein,
concrete. It covers both work carried out on site and
are minimum working loads which should be taken
the manufacture of precast prestressed concrete
into consideration for purposes of design.
units.
PART 0 INTEGRATED APPROACH
9
A-6.6 Section 6 Steel
A-8.3 Section 3 Air Conditioning, Heating and
Mechanical Ventilation
It covers the use of structural steel in general building
construction including the use of hot rolled steel
This Section covers the design, construction and
sections and steel tubes.
installation of air conditioning and heating systems and
equipment installed in buildings for the purpose
A-6.7 Section 7 Prefabrication, Systems Building
of providing and maintaining conditions of air
and Mixed/Composite Construction
temperature, humidity, purity and distribution suitable
for the use and occupancy of the space.
A-6.7.1 Section 7A Prefabricated Concrete
A-8.4 Section 4 Acoustics, Sound Insulation and
It covers recommendations regarding modular
Noise Control
planning, component sizes, prefabrication systems,
design considerations, joints and manufacture, storage,
It covers requirements and guidelines regarding
transport and erection of prefabricated concrete
planning against noise, acceptable noise levels and the
elements for use in buildings and such related
requirements for sound insulation in buildings with
requirements for prefabricated concrete.
different occupancies.
A-6.7.2 Section 7B Systems Building and Mixed/
A-8.5 Section
5 Installation of Lifts and
Composite Construction
Escalators
It covers recommendations regarding modular
It covers the essential requirements for the installation,
planning, component sizes, joints, manufacture,
operation, maintenance and also inspection of lifts
storage, transport and erection of prefabricated
(passenger lifts, goods lifts, hospital lifts, service lifts
elements for use in buildings and such related
and dumb-waiter) and escalators so as to ensure safe
requirements for mixed/composite construction.
and satisfactory performance.
A-7 PART 7 CONSTRUCTIONAL PRACTICES
A-9 PART 9 PLUMBING SERVICES
AND SAFETY
This Part through its two sections gives detailed
It covers the constructional planning, management and
guidance to concerned professionals/plumbing
practices in buildings; storage, stacking and handling
engineers with regard to plumbing and other related
of materials and safety of personnel during construction
requirements in buildings.
operations for all elements of a building and demolition
A-9.1 Section 1 Water Supply, Drainage and
of buildings. It also covers guidelines relating to
Sanitation (Including Solid Waste Management)
maintenance management, repairs, retrofitting and
strengthening of buildings. The objective can be best
It covers the basic requirements of water supply for
achieved through proper coordination and working by
residential, business and other types of buildings,
the project management and construction management
including traffic terminal stations. This Section also
teams.
deals with general requirements of plumbing connected
to public water supply and design of water supply
A-8 PART 8 BUILDING SERVICES
systems.
This Part through its five elaborate sections on utilities
It also covers the design, layout, construction and
provides detailed guidance to concerned professionals/
maintenance of drains for foul water, surface water
utility engineers for meeting necessary functional
and sub-soil water and sewage; together with all
requirements in buildings.
ancillary works, such as connections, manholes and
inspection chambers used within the building and from
A-8.1 Section 1 Lighting and Ventilation
building to the connection to a public sewer, private
It covers requirements and methods for lighting and
sewer, individual sewage-disposal system, cess-pool,
ventilation of buildings.
soakaway or to other approved point of disposal/
treatment work. It also includes the provisions on solid
A-8.2 Section 2 Electrical and Allied Installations
waste management.
It covers the essential requirements for electrical and
A-9.2 Section 2 Gas Supply
allied installations in buildings to ensure efficient use
of electricity including safety from fire and shock. This
It covers the requirements regarding the safety of persons
Section also includes general requirements relating to
and property for all piping uses and for all types of gases
lightning protection of buildings.
used for fuel or lighting purposes in buildings.
10
NATIONAL BUILDING CODE OF INDIA
A-10 PART 10 LANDSCAPING, SIGNS AND
A-10.2 Section 2
Signs and Outdoor Display
OUTDOOR DISPLAY STRUCTURES
Structures
A-10.1 Section 1 Landscape Planning and Design
It covers the requirements with regard to public safety,
structural safety and fire safety of all signs and outdoor
It covers requirements of landscape planning and
display structures including the overall aesthetical
design with the view to promoting quality of outdoor
aspects of imposition of signs and outdoor display
built environment and protection of land and its
structures in the outdoor built environment.
resources.
PART 0 INTEGRATED APPROACH
11
NATIONAL BUILDING CODE OF INDIA
PART 2 ADMINISTRATION
BUREAU OF INDIAN STANDARDS
C O N T E N T S
FOREWORD
…
3
SECTION 1 GENERAL
1
SCOPE
…
5
2
TERMINOLOGY
…
5
3
APPLICABILITY OF THE CODE
…
6
4
INTERPRETATION
…
7
5
ALTERNATIVE MATERIALS, METHODS OF DESIGN AND
…
7
CONSTRUCTION, AND TESTS
SECTION 2 ORGANIZATION AND ENFORCEMENT
6
DEPARTMENT OF BUILDINGS
…
7
7
POWER AND DUTIES OF TEAM OF BUILDING OFFICIALS
…
8
8
BOARD OF APPEALS
…
9
9
VIOLATIONS AND PENALTIES
…
9
10
POWER TO MAKE RULES
…
9
SECTION 3 PERMIT AND INSPECTION
11
DEVELOPMENT/BUILDING PERMIT
…
9
12
APPLICATION FOR DEVELOPMENT/BUILDING PERMIT
…
10
13
RESPONSIBILITIES AND DUTIES OF THE OWNER
…
15
14
INSPECTION, OCCUPANCY PERMIT AND POST-OCCUPANCY
…
15
INSPECTION
15
UNSAFE BUILDING
…
16
16
DEMOLITION OF BUILDING
…
16
17
VALIDITY
…
17
18
ARCHITECTURAL CONTROL
…
17
ANNEX A GUIDE FOR THE QUALIFICATIONS AND COMPETENCE OF
…
18
PROFESSIONALS
ANNEX B FORM FOR FIRST APPLICATION TO DEVELOP, ERECT,
…
20
RE-ERECT OR TO MAKE ALTERATION IN ANY PLACE IN A
BUILDING
ANNEX C FORM FOR CERTIFICATE FOR STRUCTURAL DESIGN
…
21
SUFFICIENCY
ANNEX D FORM FOR SUPERVISION
…
21
ANNEX E FORM FOR SANCTION OR REFUSAL OF DEVELOPMENT/
…
22
BUILDING PERMIT
ANNEX F FORM FOR NOTICE FOR COMMENCEMENT
…
22
ANNEX G FORM FOR CERTIFICATE FOR EXECUTION OF WORK AS
…
23
PER STRUCTURAL SAFETY REQUIREMENTS
ANNEX H FORM FOR COMPLETION CERTIFICATE
…
23
ANNEX J FORM FOR OCCUPANCY PERMIT
…
24
2
NATIONAL BUILDING CODE OF INDIA
National Building Code Sectional Committee, CED 46
FOREWORD
A need for codifying and unifying administrative provisions in different development control rules and building
byelaws had been felt, particularly in regard to the applicability of the Code, desirable qualifications for the enforcing
Authority and the representative of the owner and responsibilities and duties of the Authority and the owner.
It is expected that the town and country planning department will co-ordinate the administrative provisions of
this Part and the same given in the State Town and Country Planning Acts.
This Part recommends the setting up of a ‘Board of Appeal’. The ‘Board of Appeal’ gives the owner/architect/
engineer an opportunity to defend the schemes which are based on conventional or new methods of design and
construction or using new materials, which have been otherwise rejected by the Authority.
This Part also emphasizes the need for setting up an Arts Commission for metropolitan areas to safeguard existing
aesthetics in the event of new schemes proposed for buildings of public importance or buildings coming up in an
important area near historic/monumental buildings. The Commission can assist the civic authorities in reviewing
plans for development from the stand point of assuring good taste and regard for often threatened natural beauties.
The Commission can serve as a means whereby by the government and public bodies and individuals could get
advice on artistic questions in connection with building schemes.
The first version of this Part was brought out in 1970, which was subsequently revised in 1983. As a result of
implementing 1970 version of this Part in rewriting building byelaws and development control rules of some
municipal corporations and municipalities, some useful suggestions were emerged. These were incorporated in
the first revision to the extent possible. The significant changes in 1983 version of this Part included the new
administrative provisions related to development control rules, additional information to be furnished/indicated
in the building plan for multi-storeyed and special buildings and modified provisions regarding submission of
building plans by Government Departments to the Authority.
In this second revision, number of modifications have been incorporated based on the experience gained over the
years specially in view of different techno-administrative and techno-legal regime encountered in various situations
faced. Specially the provisions of this Part have been thoroughly reviewed in the context of the natural calamities
faced by the country, such as the devastating earthquake in Gujarat in the year 2001, and provisions have been
accordingly modified to further ensure structural adequacy of the buildings. In this context, structural design of
buildings in accordance with the provisions of the Code and construction and supervision thereof by competent
professionals to ensure structural safety have been given due importance in this revision. Other significant
modifications incorporated include:
a) Modifications in the definitions of certain terms;
b) Inclusion of the concept of team of building officials;
c) Inclusion of provision of single window approach for permit for all services;
d) Inclusion of provisions regarding computerization of approval processes for building permits;
e) Inclusion of provision to certify safety of buildings against natural disaster by engineer/structural engineer
and owner;
f) Inclusion of provision of two stage permit for high rise residential buildings and special buildings;
g) Provisions regarding inspection of completed and occupied building by the Authority from safety point
of view have been made comprehensive;
h) Inclusion of provision empowering engineers/architects for sanctioning plans of residential buildings
up to 500 m2;
j)
Provisions for architectural control to effectively take care of the urban aesthetics, have been modified;
and
k) Inclusion of landscape architect and urban designer among the registered professionals for the concerned
applicable works.
PART 2 ADMINISTRATION
3
The Sectional Committee responsible for revision of the Code has examined the use of the words ‘surveyor/
building surveyor/supervisor’, etc under various building bye-laws with varying qualifications in different states.
It has been decided not to use the generic word ‘surveyor’ or such other words. The Sectional Committee has, on
the other hand recommended association of various professionals for various job responsibilities depending
upon their qualifications/competence.
Also, it is noted that the words ‘licencing/licensed, etc’ are in use by local bodies in different states. The Sectional
Committee, however, decided for use of words ‘registration/registered, etc’ for the same, which may now be
adopted uniformly. The registration requirements of professionals are given in Annex A.
4
NATIONAL BUILDING CODE OF INDIA
NATIONAL BUILDING CODE OF INDIA
PART 2 ADMINISTRATION
SECTION 1 GENERAL
of last livable floor of the building adjacent to the
external walls; and in the case of pitched roofs, up to
1 SCOPE
the point where the external surface of the outer wall
intersects the finished surface of the sloping roof, and
This Part covers the administrative aspects of the Code,
in the case of gables facing the road, the midpoint
such as applicability of the Code, organization of
between the eaves level and the ridge. Architectural
building department for enforcement of the Code,
features serving no other function except that of
procedure for obtaining development and building
decoration shall be excluded for the purpose of
permits, and responsibility of the owner.
measuring heights.
NOTE — This Code is called the National Building Code of
India, hereinafter referred to as ‘the Code’.
2.7
Building Line — The line up to which the plinth
of a building adjoining a street or an extension of a
2 TERMINOLOGY
street or on a future street may lawfully extend. It
2.0
For the purpose of this part, the following
includes the lines prescribed, if any, in any scheme.
definitions shall apply.
The building line may change from time-to-time as
decided by the Authority.
2.1
Accessory Use — Any use of the premises
subordinate to the principal use and customarily
2.8
Conversion — The change of occupancy or
incidental to the principal use.
premises to any occupancy or use requiring additional
occupancy permit.
2.2
Alteration — A change from one type of
occupancy to another, or a structural change, such as
2.9
Development — ‘Development’ with grammatical
an addition to the area or height, or the removal of part
variations means the carrying out of building,
of a building, or any change to the structure, such as
engineering, mining or other operations in, or over, or
the construction of, cutting into or removal of any wall,
under land or water, or in the use of any building or
partition, column, beam, joist, floor or other support,
land, and includes redevelopment and layout and
or a change to or closing of any required means of
subdivision of any land; and ‘to develop’ shall be
ingress or egress or a change to the fixtures or
construed accordingly.
equipment.
2.10 Drain — A conduit or channel for the carriage
2.3 Approved — Approved by the Authority having
of storm water, sewage, waste water or other water-
jurisdiction.
borne wastes in a building drainage system.
2.4 Authority Having Jurisdiction — The Authority
2.11 Drainage — The removal of any liquid by a
which has been created by a statute and which, for the
system constructed for the purpose.
purpose of administering the Code/Part, may authorize
2.12
Occupancy or Use Group — The principal
a committee or an official or an agency to act on its
occupancy for which a building or a part of a building
behalf; hereinafter called the ‘Authority’.
is used or intended to be used; for the purposes of
2.5 Building — Any structure for whatsoever purpose
classification of a building according to occupancy,
and of whatsoever materials constructed and every part
an occupancy shall be deemed to include the subsidiary
thereof whether used as human habitation or not and
occupancies which are contingent upon it.
includes foundation, plinth, walls, floors, roofs,
2.13 Occupier — Occupier includes any person for
chimneys, plumbing and building services, fixed
the time being, paying or liable to pay rent or any
platforms, verandah, balcony, cornice or projection, part
portion of rent of the building in respect of which the
of a building or anything affixed thereto or any wall
ward is used, or compensation or premium on account
enclosing or intended to enclose any land or space
of the occupation of such building and also a rent-free
and signs and outdoor display structures. Tents/
tenant, but does not include a lodger, and the words
SHAMIANAHS, tarpaulin shelters, etc, erected for
‘occupy’ and ‘occupation’ do not refer to the lodger.
temporary and ceremonial occasions with the permission
of the Authority shall not be considered as building.
An owner living in or otherwise using his own building
shall be deemed to be the occupier thereof.
2.6 Building, Height of — The vertical distance
measured, in the case of flat roofs from the average
2.14 Operational Construction/Installation — A
level of the ground around and contiguous to the
construction/installation put up by Government
building or as decided by the Authority to the terrace
Departments for operational purposes (see 12.1.1.1).
PART 2 ADMINISTRATION
5
2.15 Owner — Person or body having a legal interest
carriageway, footway, square, place or bridge, whether
in land and/or building thereon. This includes free
a thoroughfare or not, over which the public have a
holders, leaseholders or those holding a sub-lease
right of passage or access or have passed and had access
which both bestows a legal right to occupation and
uninterruptedly for a specified period, whether existing
gives rise to liabilities in respect of safety or building
or proposed in any scheme and includes all bunds,
condition.
channels, ditches, storm-water drains, culverts,
sidewalks, traffic islands, roadside trees and hedges,
In case of lease or sub-lease holders, as far as ownership
retaining walls, fences, barriers and railings within the
with respect to the structure is concerned, the structure
street lines.
of a flat or structure on a plot belongs to the allottee/
lessee till the allotment/lease subsists.
2.26
Street Level or Grade — The officially
established elevation or grade of the centre line of the
2.16 Permit — A permission or authorization in
street upon which a plot fronts and if there is no
writing by the Authority to carry out work regulated
officially established grade, the existing grade of the
by the Code.
street at its mid-point.
2.17 Registered Architect, Engineer, Structural
2.27 Street Line — The line defining the side limits
Engineer, Supervisor, Town Planner, Landscape
of a street.
Architect, Urban Designer — A qualified architect,
engineer, structural engineer, supervisor, town
2.28 To Erect — To erect a building means:
planner, landscape architect or urban designer who
a) to erect a new building on any site whether
has been registered by the Authority or by the body
previously built upon or not;
governing such profession and constituted under a
b) to re-erect any building of which portions
statute, as may be applicable. The registration
above the plinth level have been pulled down,
requirements of these professionals shall be as given
burnt or destroyed.
in Annex A.
NOTES
2.29
Unsafe Building — Buildings which are
1 Unless specified otherwise, the word ‘engineer’ shall mean
structurally and constructionally unsafe or insanitary
‘civil engineer’ or ‘architectural engineer’.
or not provided with adequate means of egress or
2 The word ‘licencing/licensed, etc’ if used by the Authority
which constitute a fire hazard or are otherwise
in the above context shall be deemed to mean ‘registration/
dangerous to human life or which in relation to
registered’, etc.
existing use constitute a hazard to safety or health or
2.18 Road — See 2.25.
public welfare, by reason of inadequate maintenance,
dilapidation or abandonment.
2.19 Road Line — See 2.27.
2.20 Room Height — The vertical distance measured
3 APPLICABILITY OF THE CODE
from the finished floor surface to the finished ceiling
3.1
All Parts of the Code and their sections shall apply
surface. Where a finished ceiling is not provided, the
to all buildings described in 3.2 to 3.8, as may be
underside of the joists or beams or tie beams shall
applicable.
determine the upper point of measurement for
3.2
Where a building is erected, the Code applies to
determining the head room.
the design and construction of the building.
2.21
Sanctioned Plan — The set of plans and
3.3
Where the whole or any part of the building is
specifications submitted in connection with a building
removed, the Code applies to all parts of the building
or development and duly approved and sanctioned by
whether removed or not.
the Authority.
3.4
Where the whole or any part of the building is
2.22 Service Road — A road/lane provided at the rear
demolished, the Code applies to any remaining part
or side of a plot for service purposes.
and to the work involved in demolition.
2.23 Set-back Line — A line usually parallel to the
3.5
Where a building is altered (see 12.4 and 12.4.1),
plot boundaries and laid down in each case by the
the Code applies to the whole building whether existing
Authority, beyond which nothing can be constructed
or new except that the Code applies only to part if that
towards the site boundaries.
part is completely self-contained with respect to
2.24 Site (Plot) — A parcel (piece) of land enclosed
facilities and safety measures required by the Code.
by definite boundaries.
3.6
Where the occupancy of a building is changed,
2.25 Street — Any means of access, namely, highway,
the Code applies to all parts of the building affected
street, lane, pathway, alley, stairway, passageway,
by the change.
6
NATIONAL BUILDING CODE OF INDIA
3.7 Where development of land is undertaken the Code
there are no appropriate test methods specified in the
applies to the entire development of land.
Code, the Authority shall determine the test procedure.
For methods of test for building materials, reference
3.8 Existing Buildings/Development
may be made to Part 5 Building Materials.
Nothing in the Code shall require the removal,
5.3.2
Copies of the results of all such tests shall be
alteration or abandonment, nor prevent continuance
retained by the Authority for a period of not less than
of the use or occupancy of an existing building/
two years after the acceptance of the alternative material.
development, unless in the opinion of the Authority,
such building/development constitutes a hazard to the
SECTION 2 ORGANIZATION AND
safety of the adjacent property or the occupants of the
ENFORCEMENT
building itself.
6 DEPARTMENT OF BUILDINGS
4 INTERPRETATION
6.1
The department of buildings shall be created by
4.1 The heading which appears at the beginning of a
the Authority and a team of building officials shall be
clause or sub-clause of the Code shall be deemed to be
appointed to carry out work of such department.
a part of such clause or sub-clause respectively.
6.2
Appointment of Team of Building Officials
4.2 The use of present tense includes the future tense,
The team of building officials shall be appointed by
the masculine gender includes the feminine and the
the Authority. The team shall comprise officials drawn
neuter, the singular number includes the plural and the
from concerned disciplines such as engineer, architect,
plural includes the singular. The word ‘person’ includes
town planner, landscape architect and urban designer
a corporation as well as an individual; writing includes
as may be decided by the Authority. For scrutiny of
printing and typing and ‘signature’ includes thumb
layout plans of plots of one hectare and above in metro
impression made by a person who cannot write if his
cities and two hectares and above in other places, town
name is written near to such thumb impression.
planner shall be part of the team of building officials.
For plots of five hectares and above, landscape architect
5 ALTERNATIVE MATERIALS, METHODS OF
shall also be part of the team. An urban designer shall
DESIGN AND CONSTRUCTION, AND TESTS
also be required to be the part of team of building
5.1 The provisions of the Code are not intended to
officials for examining proposals on integrated urban
prevent the use of any material or method of design or
design and development for residential/business/
construction not specifically prescribed by the Code,
institutional and assembly building.
provided any such alternative has been approved.
NOTE — Metro cities are cities with population more than
1 000 000.
5.2 The Authority may approve any such alternative
provided it is found that the proposed alternative is
6.3 Organization
satisfactory and conforms to the provisions of relevant
In the department of buildings, such number of officers,
parts regarding material, design and construction and
technical assistants, inspectors and other employees
that material, method, or work offered is, for the purpose
shall be appointed to assist the team of building officials
intended, at least equivalent to that prescribed in the
as shall be necessary for the administration of the Code
Code in quality, strength, compatibility, effectiveness,
and as authorized by the Authority.
fire and water resistance, durability and safety.
6.4
Delegation of Powers
5.3 Tests
The Authority may designate one of the building
Whenever there is insufficient evidence of compliance
officials who shall exercise all the powers of the team
with the provisions of the Code or evidence that any
of building officials. The work of the team of building
material or method of design or construction does not
officials may be outsourced to competent professional/
conform to the requirements of the Code or in order to
agency/group as may be deemed necessary.
substantiate claims for alternative materials, design or
6.5
Qualification of Building Officials
methods of construction not specifically prescribed in
the Code, the Authority may require tests sufficiently
The qualification of building officials scrutinizing the
in advance as proof of compliance. These tests shall
plans and carrying out inspection of buildings shall
be made by an approved agency at the expense of the
not in any case be less than those prescribed in
owner.
Annex A.
5.3.1
Test methods shall be specified by the Code for
6.5.1
In small local bodies having insufficient
the materials or design or construction in question. If
resources to appoint such officials with the above
PART 2 ADMINISTRATION
7
qualifications, two or three such bodies contiguously
7.3
Right of Entry
located could join together and share the services of
Upon presentation of proper credentials and with
one team of building officials.
advance notice, the team of building officials or its
6.6 Qualifications of Assistant
duly authorized representative may enter at any
reasonable time any building or premises to perform
No person shall be appointed as Assistant unless he
any duty imposed upon him by the Code.
has got the qualifications prescribed in Annex A for a
registered Supervisor.
7.4
Inspection
6.7 Restriction on Employees
The team of building officials shall make all the
required inspections or it may accept reports of
No official or employee connected with the department
inspections of authoritative and recognized services
of buildings except one whose only connection is that
or individuals; and all reports of inspections shall be
of a member of the Board of Appeals, established
in writing and certified by a responsible officer of such
under 8 shall be engaged directly or indirectly in a work
authoritative service or by the responsible individual
connected with the furnishing of labour, materials
or engage any such expert opinion as he may deem
or appliances for the construction, alteration or
necessary to report upon unusual technical issues that
maintenance of a building, or the preparation of plans
may arise, subject to the approval of the Authority.
or of specifications thereof unless he is the owner of
building; nor shall such official or employee engage
7.5
Construction Not According to Plan
in any work which conflicts with his official duties or
Should the team of building officials determine at any
with the interests of the Department.
stage that the construction is not proceeding according
6.8
Records
to the sanctioned plan or is in violation of any of the
provisions of the Code, or any other applicable Code
Proper records of all applications received, permits and
Regulation, Act or Byelaw, it shall notify the owner,
orders issued, inspections made shall be kept and copies
and all further construction shall be stayed until
of all papers and documents connected with the
correction has been effected and approved.
administration of its duties shall be retained and all
such records shall be open to public inspection at all
7.5.1
Should the owner fail to comply with the
appropriate times.
requirements at any stage of construction, the Authority
shall issue a notice to the owner asking explanation
7 POWER AND DUTIES OF TEAM OF BUILDING
for non-compliance. If the owner fails to comply within
OFFICIALS
14 days from the date of receiving the notice, the
Authority shall be empowered to cancel the building
7.0 The team of building officials shall enforce all the
permit issued and shall cause notice of such
provisions of the Code and shall act on any question
cancellation to be securely pasted upon the said
relative to the mode or manner of construction and the
construction, if the owner is not traceable at his address
materials to be used in the erection, addition, alteration,
given in the notice. Pasting of such a notice shall be
repair, removal, demolition, installation of service
considered sufficient notification of cancellation to the
equipment and the location, use, occupancy and
owner thereof. No further work shall be undertaken or
maintenance of all buildings except as may otherwise
permitted upon such construction until a valid building
be specifically provided.
permit thereafter has been issued. If the owner, in
7.1 Application and Permits
violation of the notice for cancellation, continues the
construction, the Authority may take all necessary
The team of building officials shall receive all
means to stop such work and further appropriate actions
applications and issue permits (see 12.10) for the
including demolitions. The owner shall, however, have
erection and alteration of buildings and examine the
right to appeal against cancellation of permit, to the
premises for which such permits have been issued and
board of appeal, within a stipulated period, as may be
enforce compliance with the Code.
decided by the Authority.
7.2 Building Notices and Orders
7.6
Modification
The team of building officials shall issue all necessary
Wherever practical difficulties are involved in carrying
notices or orders to remove illegal or unsafe conditions,
out any provision of the Code, the team of building
to require the necessary safeguards during construction,
officials may vary or modify such provisions upon
to require adequate exit facilities in existing buildings
application of the owner or his representative provided
and to ensure compliance with all the requirements of
the spirit and intent of the Code shall be observed and
safety, health and general welfare of the public as
public welfare and safety be assured. The application
included in the Code.
8
NATIONAL BUILDING CODE OF INDIA
for modification and the final decision of the team of
9.1.3
The registered architect, engineer, structural
building officials shall be in writing and shall be
engineer, supervisor, town planner, landscape architect,
officially recorded with the application for the permit
urban designer and utility service engineer (see
in the permanent records of the Department of Building
Annex A) responsible for the services rendered for
Inspection.
supervision of the construction/development and for the
completion certificate; in the event of violation of the
7.7 Occupancy Violations
provisions of the Code, shall be liable to penalties as
Wherever any building is being used contrary to
prescribed by the Authority including cancellation of
provisions of the Code, the team of building officials
registration done by it or make such recommendation
may order such use discontinued and the building or
to the statutory body governing such profession.
portion thereof, vacated by the notice served on any
9.2
Further Obligation of Offender
person, causing such use to be discontinued. Such
The conviction of any person for an offence under the
person shall discontinue the use within 10 days after
provision of 9.1 shall not relieve him from the duty of
receipt of such notice or make the building or portion
carrying out the requirements or obligations imposed
thereof, comply with the requirements of the Code.
on him by virtue of the provisions of the Code; and if
8 BOARD OF APPEALS
such requirements or obligations are not complied with
in accordance with an order made under provisions
In order to determine the suitability of alternative
of 9.1, the Authority under the provisions of the Code
materials or methods of design or construction and to
may, if necessary and advisable, enter upon the
provide for reasonable interpretation of the provisions
premises in respect of which a conviction has been
of the Code or in the matter of dispute relating to an
made and carry out at the expense of the convicted
ongoing construction vis-a-vis the sanctioned plan, a
person, the requirements or obligations referred to in
Board of Appeals consisting of members who are
the said order and the expense, if not paid on demand,
qualified by experience and training and to pass
may be recovered with cost in a court.
judgement upon matters pertaining to building
9.3
Conviction No Bar to Further Prosecution
construction, shall be appointed by the Authority. A
representative of the team of building officials shall
The conviction of any person under the provisions of
be an ex-officio member and shall act as secretary to
this part for failing to comply with any of the said
the Board. The Board shall adopt reasonable rules and
requirements or obligations shall not operate as a bar
regulations for conducting its investigations and shall
to further prosecution under this part for any
render all decisions and findings in writing to the team
subsequent failure on the part of such person to comply.
of building officials with a duplicate copy to the
appellant and may recommend such modifications as
10 POWER TO MAKE RULES
are necessary.
The Authority may make rules for carrying out the
provisions and intentions of the Code provided that
9 VIOLATIONS AND PENALTIES
any rule shall not be in direct/indirect conflict or
9.1 Offences and Penalties
nullify/dilute any of the provisions of the Code.
9.1.1
Any person who contravenes any of the
SECTION 3 PERMIT AND INSPECTION
provisions of the Code or any requirements of
obligations imposed on him by virtue of the Code, or
11 DEVELOPMENT/BUILDING PERMIT
who interferes with or obstructs any person in the
11.1 Permit Required
discharge of his duties, shall be guilty of an offence
and the Authority shall levy suitable penalty or take
No person shall carry out any development, erect, re-
other actions as per the Code (see also 7.5 and 15).
erect or make alterations or demolish any building or
cause the same to be done without first obtaining a
NOTE — The penalty may be in the form of collection of
arrears of tax.
separate permit for each such development/building
from the Authority. No permits shall, however, be
9.1.2
The buildings/developments violating any
required for works referred to in 12.1.1.1 and 12.4.1.
applicable statutory rules shall be demolished/brought
within the limits as prescribed in such rules at the
11.1.1
The development/building permit shall take
expense of the owner. The buildings coming up in the
into cognizance the provisions under the relevant Town
vicinity of an aerodrome in violation of the height
Planning Act/Development Act/Municipal Act/any
restriction laid down by the Directorate General of Civil
other applicable statutes for layout, building plans,
Aviation shall be accordingly demolished/brought
water supply, sewerage, drainage, electrification, etc,
within the limits prescribed by DGCA rules.
as provided in the said Act/statute. Also, if so directed
PART 2 ADMINISTRATION
9
by the Authority, the permit shall take care of the need
12 APPLICATION FOR DEVELOPMENT/
for landscape development plan incorporating rain-
BUILDING PERMIT
water harvesting proposals in the layout and building
12.1 Notice
plans.
Every owner who intends to develop, erect, re-erect or
11.1.2
Specific approvals shall be obtained from
make alterations in any place in a building shall give
Civil Aviation Authorities, Fire Services Department
notice in writing to the Authority of his said intention
(in case the building proposed is 15 m and above),
in the prescribed form (see Annex B) and such notice
Pollution Control Board, designated authorities under
shall be accompanied by plans and statements in
Factories Act/Cinema Regulation Act, Urban Arts
triplicate as required under 12.2 and 12.3 except for
Commission, designated Coastal Regulation Zone
special buildings (high rise, non-residential) where
Authority, Archeological Survey of India, Heritage
additional copies may be submitted as desired by the
Committee and any such other authority as may be
Authority. The Authority shall permit submission of
applicable.
plans/documents in electronic form in addition to hard
11.1.3 In order to facilitate clearance from above
copy. The Authority should also progressively
bodies with the concept of single window clearance
computerize the approval process.
approach and thereby final approval by the Authority
12.1.1
Regarding submission of plans by Government
within the stipulated time frame, the Authority may
Departments, the procedure shall be as given
constitute a Development/Building Permit Approval
in 12.1.1.1 and 12.1.1.2.
Committee consisting of representative of the team of
building officials, representatives of all bodies/
12.1.1.1 The operational construction/installation of
organizations from whom clearance for development/
the Government, whether temporary or permanent,
building permit clearance is required.
which is essential for the operation, maintenance,
development or execution of any of the following
Recommendations from such Committee shall be
services may be exempted from the point of view of
summarily utilized by the team of building officials
the byelaws:
in sanctioning process. The Committee may meet
a) Railways;
once in 15/30 days depending upon the work load.
The first response/invalid notice/non-compliance
b) National highways;
intimation shall be issued by the Authority to the
c) National waterways;
owner within 30 days of submission of the plans to
d) Major ports;
the Authority.
e) Airways and aerodromes;
11.1.4
The Authority shall permit a registered
f) Posts and telegraphs, telephones, wireless,
architect/engineer to approve the building proposals
broadcasting, and other like forms of
including plans, and certify completion of building for
communications;
issue of related regulatory building permits and
g) Regional grid for electricity;
occupancy certificate for residential buildings designed
h) Defence; and
by self or otherwise, on plot size up to 500 m2. The
j)
Any other service which the Central/State
responsibility of compliance with respect to provisions
Government may, if it is of opinion that the
of Code shall rest with the registered architect/engineer.
operation, maintenance, development of
However, the plans shall be required to be submitted
execution of such service is essential to the
to the Authority for information and record.
life of the community, by notification, declare
NOTE — Where the experience clearly shows that satisfactory
to be a service for the purpose of this clause.
building permit activities are being carried out through the
above empowerment of professionals, the Authority may
In case of construction/installation where no approvals
extend such provision for larger areas and other building
are required, the concerned agencies which are
occupancies.
exempted from seeking approval shall submit the
drawings/plans/details for information and records of
11.2 Pre-Code Development/Building Permit
the Authority before construction/installation.
If any development/building, permit for which had
12.1.1.2 However, the following construction of the
been issued before the commencement of the Code, is
Government departments do not come under the
not wholly completed within a period of three years
purview of operational construction for the purpose of
from the date of such permit, the said permission shall
exemption under 12.1.1.1:
be deemed to have lapsed and fresh permit shall be
necessary to proceed further with the work in
a) New residential building (other than gate
accordance with the provisions of the Code.
lodges, quarters for limited essential operational
10
NATIONAL BUILDING CODE OF INDIA
staff and the like), roads and drains in railway
12.2.1.2 The plans shall be coloured as specified in
colonies, hospitals, clubs, institutes and
Table 2.
schools, in the case of railways; and
12.2.2 Key Plan
b) A new building, new construction or new
installation or any extension thereof in the
A key plan drawn to a scale of not less than 1 in 10 000
case of any other services.
shall be submitted along with the application for a
development/building permit showing the boundary
12.2 Information Accompanying Notice
locations of the site with respect to neighbourhood
The notice shall be accompanied by the key plan, site
landmarks. The minimum dimension of the key plan
plan, building plan, services plans, specifications
shall be not less than 75 mm.
structural sufficiency certificate and certificate of
12.2.3 Site Plan
supervision as prescribed in 12.2.2 to 12.2.8.
The site plan sent with an application for permit shall
12.2.1
Sizes of Drawing Sheets and Recommended
be drawn to a scale of not less than 1 in 500 for a site
Notation for Colouring Plans
up to one hectare and not less than 1 in 1 000 for a site
12.2.1.1 The size of drawing sheets shall be any of
more than one hectare and shall show:
those specified in Table 1.
a) the boundaries of the site and of any contiguous
Table 1 Drawing Sheet Sizes
land belonging to the owner thereof;
(Clause 12.2.1.1)
b) the position of the site in relation to
neighbouring street;
Sl No.
Designation
Trimmed Size
mm
c) the name of the streets in which the building
(1)
(2)
(3)
is proposed to be situated, if any;
d) all existing buildings standing on, over or
i)
A0
841 × 1 189
under the site including service lines;
ii)
A1
594 × 841
iii)
A2
420 × 594
e) the position of the building and of all other
iv)
A3
297 × 420
buildings (if any) which the applicant intends
v)
A4
210 × 297
to erect upon his contiguous land referred to
vi)
A5
148 × 210
in (a) in relation to:
Table 2 Colouring of Plans
(Clause 12.2.1.2)
Sl
Item
Site Plan
Building Plan
No.
White Plan
Blue Print
Ammonia Print
White Plan
Blue Print
Ammonia Print
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
i)
Plot lines
Thick black
Thick black
Thick black
Thick black
Thick black
Thick black
ii)
Existing street
Green
Green
Green
—
—
—
iii)
Future street, if any
Green dotted
Green dotted
Green dotted
—
—
—
iv)
Permissible building
Thick dotted
Thick dotted
Thick dotted
—
—
—
lines
black
black
black
v)
Open spaces
No colour
No colour
No colour
No colour
No colour
No colour
vi)
Existing work
Black (outline)
White
Blue
Black
White
Blue
vii)
Work proposed to be
Yellow hatched
Yellow hatched Yellow hatched Yellow hatched Yellow hatched
Yellow hatched
demolished
viii)
Proposed work
Red filled in
Red
Red
Red
Red
Red
(see Note 1)
ix)
Drainage and sewerage
Red dotted
Red dotted
Red dotted
Red dotted
Red dotted
Red dotted
work
x)
Water supply work
Black dotted
Black dotted
Black dotted
Black dotted
Black dotted
Black dotted
thin
thin
thin
thin
thin
thin
NOTES
1 For entirely new construction this need not be done; for extension of an existing work this shall apply.
2 For land development, subdivision, layout, suitable colouring notations shall be used which shall be indexed.
PART 2 ADMINISTRATION
11
1) the boundaries of the site and in case
area of the site proposed to be subdivided;
where the site has been partitioned, the
and
boundaries of the portion owned by the
g) In case of plots which are subdivided in built-
applicant and also of the portions owned
up areas in addition to the above, the means
by others;
of access to the sub-division from existing
2) all adjacent street, buildings
(with
streets.
number of storeys and height) and
12.2.5
Building Plan and Details
premises within a distance of 12 m of the
site and of the contiguous land (if any)
The plan of the buildings and elevations and sections
referred to in (a); and
accompanying the notice shall be drawn to a scale of
3) if there is no street within a distance of
1
: 100. The plans and details shall:
12 m of the site, the nearest existing
a)
include floor plans of all floors together with
street;
the covered area clearly indicating the size
f)
the means of access from the street to the
and spacings of all framing members and sizes
building, and to all other buildings (if any)
of rooms and the position of staircases, ramps
which the applicant intends to erect upon his
and liftwells;
contiguous land referred to in (a);
b)
show the use or occupancy of all parts of the
g)
space to be left about the building to secure a
buildings;
free circulation of air, admission of light and
c)
show exact location of essential services, for
access for scavenging purposes;
example, WC, sink, bath and the like;
h)
the width of the street (if any) in front and of
d)
include at least one elevation from the front
the street (if any) at the side or near the
showing height of building and rooms and
buildings;
also the height of parapet;
j)
the direction of north point relative to the plan
e)
include at least one section through the
of the buildings;
staircase;
k)
any physical features, such as wells, drains,
f)
include the structural arrangements with
etc; and
appropriate sections showing type/
m)
such other particulars as may be prescribed
arrangement of footings, foundations,
by the Authority.
basement walls; structural load bearing walls,
columns and beams, and shear walls; and
12.2.4 Sub-Division/Layout Plan
arrangement/spacing of framing members,
In the case of development work, the notice shall be
floor slabs and roof slabs with the material
accompanied by the sub-division/layout plan which
used for the same;
shall be drawn on a scale of not less than 1 : 500
g)
show all street elevations;
containing the following:
h)
give dimensions of the projected portions
a) Scale used and north point;
beyond the permissible building line;
b) The location of all proposed and existing
j)
include terrace plan indicating the drainage
roads with their existing/proposed/prescribed
and the slope of the roof; and
widths within the land;
k)
give indications of the north point relative to
c) Dimensions of plot along with building lines
the plan.
showing the setbacks with dimensions within
NOTE — The requirement of
1 : 100 is permitted to
each plot;
be flexible for specific details needed for further
illustration; and also for drawings for these in electronic
d) The location of drains, sewers, public facilities
form.
and services, and electrical lines, etc;
12.2.5.1
Building plan for multi-storeyed/special
e) Table indicating size, area and use of all the
buildings
plots in the sub-division/layout plan;
f) A statement indicating the total area of the
For all multi-storeyed buildings which are 15 m or more
site, area utilized under roads, open spaces
in height and for special buildings like educational,
for parks, playgrounds, recreation spaces for
assembly, institutional, industrial, storage and
parks, playgrounds, recreation spaces and
hazardous and mixed occupancies with any of the
development plan reservations, schools,
aforesaid occupancies having covered area more than
shopping and other public places alongwith
500 m2, the building sanction shall be done in two
their percentage with reference to the total
stages.
12
NATIONAL BUILDING CODE OF INDIA
Stage 1: First stage for planning clearance
12.2.6
Services Plans
The following additional information shall be
The services plans shall include all details of building
furnished/indicated in the building plan in addition to
and plumbing services, and also plans, elevations and
the items given in 12.2.5 as applicable:
sections of private water supply, sewage disposal system
and rainwater harvesting system, if any (see Part 8
a)
Access to fire appliances/vehicles with details
‘Building Services’ and Part 9 ‘Plumbing Services’).
of vehicular turning circle and clear motorable
12.2.7
Specifications
accessway around the building;
b)
Size (width) of main and alternative staircases
Specifications, both general and detailed, giving type
along with balcony approach, corridor,
and grade of materials to be used, duly signed by the
ventilated lobby approach;
registered architect, engineer, structural engineer or
supervisor shall accompany the notice (see Annex B).
c)
Location and details of lift enclosures;
d)
Location and size of fire lift;
12.2.8
Structural Sufficiency Certificate
e)
Smoke stop lobby/door, where provided;
The plans shall be accompanied by structural
f)
Refuse chutes, refuse chamber, service duct,
sufficiency certificate in the prescribed form (see
etc;
Annex C) signed by the engineer/structural engineer
g)
Vehicular parking spaces;
(see Annex A) and the owner jointly to the effect that
h)
Refuse area, if any;
the building is safe against various loads, forces and
effects including due to natural disasters, such as,
j)
Details of building services — Air-conditioning
earthquake, landslides, cyclones, floods, etc as per
system with position of fire dampers,
Part 6 ‘Structural Design’ and other relevant Codes.
mechanical ventilation system, electrical
The engineer/structural engineer shall also have the
services, boilers, gas pipes, etc;
details to substantiate his design.
k)
Details of exits including provision of ramps,
etc, for hospitals and special risks;
12.2.9 Supervision
m)
Location of generator, transformer and
The notice shall be further accompanied by a certificate
switchgear room;
in the prescribed form (see Annex D) by the registered
n)
Smoke exhauster system, if any;
architect/engineer/structural engineer/supervisor/town
p)
Details of fire alarm system network;
planner (see Annex A) undertaking the supervision
(see 9.3).
q)
Location of centralized control, connecting
all fire alarm systems, built-in-fire protection
12.3 Preparation and Signing of Plans
arrangements and public address system,
The registered architect/engineer/supervisor/town
etc;
planner/landscape architect/urban designer/utility
r)
Location and dimensions of static water
service engineer shall prepare and duly sign the plans
storage tank and pump room along with fire
as per their competence (see Annex A) and shall
service inlets for mobile pump and water
indicate his/her name, address, qualification and
storage tank;
registration number as allotted by the Authority or the
s)
Location and details of fixed fire protection
body governing such profession. The structural plans
installations, such as, sprinklers, wet risers,
and details shall also be prepared and duly signed by
hose-reels, drenchers, etc; and
the competent professionals like registered engineer/
t)
Location and details of first-aid fire fighting
structural engineer (see Annex A). The plans shall also
equipments/installations.
be duly signed by the owner indicating his address.
The type and volume of buildings/development work
Stage 2:
Second stage for building permit clearance
to be undertaken by the registered professionals may
generally be as in Annex A.
After obtaining the sanction for planning
(Stage 1)
from the Authority, a complete set of structural plans,
12.4 Notice for Alteration only
sections, details and design calculations duly signed
When the notice is only for an alteration of the building
by engineer/structural engineer (see Annex A) along
(see 3.5), only such plans and statements, as may be
with the complete set of details duly approved in
necessary, shall accompany the notice.
Stage 1 shall be submitted. The building plans/details
shall be deemed sanctioned for the commencement of
12.4.1
No notice and building permit is necessary for
construction only after obtaining the permit for Stage 2
the following alterations, and the like which do not
from the Authority.
otherwise violate any provisions regarding general
PART 2 ADMINISTRATION
13
building requirements, structural stability and fire and
12.9
Qualifications of Architects/Engineers/
health safety requirements of the Code:
Structural Engineers/Landscape Architect/Urban
Designer/Supervisors/Town Planners/Services
a) Opening and closing of a window or door or
Personnel
ventilator;
b) Providing intercommunication doors;
Architects, engineers, structural engineers, landscape
architect, urban designer, supervisors and town
c) Providing partitions;
planners wherever referred in the Code, shall be
d) Providing false ceiling;
registered by the Authority or the body governing such
e) Gardening;
profession constituted under a statute, as competent to
f) White washing;
do the work for which they are employed. A guide for
g) Painting;
the equivalent technical qualifications and professional
h) Re-tiling and re-roofing;
experience required for such registration with the
Authority is given in Annex A. In case of building and
j)
Plastering and patch work;
plumbing services, qualifications for engineers for
k)
Re-flooring; and
utility services shall be as given in A-2.8.
m) Construction of sunshades on one’s own land.
12.9.1
In case the registered professional associated
12.5 Fees
with the preparation and signing of plans or for
supervision, is being changed during any stage of
No notice as referred to in 12.1 shall be deemed valid
building/land development process, the professional
unless and until the person giving notice has paid the
shall intimate the Authority in writing about the further
fees to the Authority and an attested copy of the receipt
non-association with the project.
of such payment is attached with the notice.
NOTE — The fees may be charged as a consolidated fee. In
12.10 Grant of Permit or Refusal
the event of a building/development permit is not issued, the
fees so paid shall not be returned to the owner, but he shall be
The Authority may either sanction or refuse the plans
allowed to re-submit it without any fees after complying with
and specifications or may sanction them with such
all the objections raised by the Authority within a period of
modifications or directions as it may deem necessary
one year from the date of rejection after which fresh fees shall
and thereupon shall communicate its decision to the
have to be paid.
person giving the notice (see Annex E).
12.6 Duration of Sanction
12.10.1 The building plans for buildings identified
in 12.2.5.1 shall also be subject to the scrutiny of the
The sanction once accorded shall remain valid up to
Fire Authority and the sanction through building permit
three years. The permit shall be got revalidated before
shall be given by the Authority after the clearance from
the expiration of this period. Revalidation shall be
the Fire Authority (see also 11.1.3).
subject to the rules then in force.
12.10.2 If within 30 days of the receipt of the notice
12.7 Deviations During Construction
under 12.1 of the Code, the Authority fails to intimate
If during the construction of a building any departure
in writing to the person, who has given the notice, of
(excepting for items as given in 12.4.1) from the
its refusal or sanction, the notice with its plans and
sanctioned plan is intended to be made (see 7.5),
statements shall be deemed to have been sanctioned;
sanction of the Authority shall be obtained before the
provided the fact is immediately brought to the notice
change is made. The revised plan showing the
of the Authority in writing by the person who has given
deviations shall be submitted and the procedure laid
notice and having not received any intimation from
down for the original plan heretofore shall apply to all
the Authority within fifteen days of giving such written
such amended plans except that the time limit specified
notice. Subject to the conditions mentioned in this
in 12.10.2 shall be three weeks in such cases.
clause, nothing shall be construed to authorize any
person to do anything in contravention of or against
12.8 Revocation of Permit
the terms of lease or titles of the land or against any
other regulations, byelaws or ordinance operating on
The Authority may revoke any permit issued under
the site of the work.
the provisions of the Code, wherever there has been
any false statement, misrepresentation of any material
12.10.3 In the case of refusal, the Authority shall quote
fact in the application on which the permit was
the reason and relevant sections of the Code which the
based or violation of building permit or in case of
plans contravene. The Authority shall as far as possible
noncompliance thereof, and shall state the reasons for
advise all the objections to the plans and specifications
revoking the permit.
in the first instance itself and ensure that no new
14
NATIONAL BUILDING CODE OF INDIA
objections are raised when they are resubmitted after
occupancy for a building or part thereof, before the
compliance of earlier objections.
entire work covered by permit shall have been
completed, provided such portion or portions may be
12.10.4 Once the plan has been scrutinized and
occupied safely prior to full completion of building
objections have been pointed out, the owner giving
without endangering life or public welfare.
notice shall modify the plan to comply with the
objections raised and re-submit it. The Authority shall
13.3 Documents at Site
scrutinize the re-submitted plan and if there be further
objections, the plan shall be rejected.
13.3.1 Where tests of any materials are made to ensure
conformity with the requirements of the Code, records
13 RESPONSIBILITIES AND DUTIES OF THE
of the test data shall be kept available for inspection
OWNER
during the construction of the building and for such a
period thereafter as required by the Authority.
13.1 Neither the granting of the permit nor the approval
of the drawings and specifications, nor inspections
13.3.2
The person to whom a permit is issued shall
made by the Authority during erection of the building
during construction keep pasted in a conspicuous place
shall in any way relieve the owner of such building
on the property in respect of which the permit was
from full responsibility for carrying out the work in
issued:
accordance with the requirements of the Code (see 9).
a) a copy of the building permit; and
13.2 Every owner shall:
b) a copy of the approved drawings and
specifications referred in 12.
a)
permit the Authority to enter the building or
premises for which the permit has been
14 INSPECTION, OCCUPANCY PERMIT AND
granted at any reasonable time for the purpose
POST-OCCUPANCY INSPECTION
of enforcing the Code;
b)
submit a document of ownership of the site;
14.1 Generally all construction or work for which a
permit is required shall be subject to inspection by the
c)
obtain, where applicable, from the Authority,
Authority and certain types of construction involving
permits relating to building, zoning, grades,
unusual hazards or requiring constant inspection shall
sewers, water mains, plumbing, signs,
have continuous inspection by special inspectors
blasting, street occupancy, electricity,
appointed by the Authority.
highways, and all other permits required in
connection with the proposed work;
14.2 Inspection, where required, shall be made within
d)
give notice to the Authority of the intention
7 days following the receipt of notification, after
to start work on the building site (see
which period the owner will be free to continue the
Annex F);
construction according to the sanctioned plan. At the
e)
give written notice to the Authority intimating
first inspection, the Authority shall determine to the
completion of work up to plinth level;
best of its ability that the building has been located
in accordance with the approved site plans. The final
f)
submit the certificate for execution of work
inspection of the completion of the work shall be
as per structural safety requirements (see
made within 21 days following the receipt of
Annex G); and give written notice to the
notification [see 13.2(f)] for the grant of occupancy
Authority regarding completion of work
certificate.
described in the permit (see Annex H);
g)
give written notice to the Authority in case of
14.2.1
The owner/concerned registered architect/
termination of services of a professional
engineer/structural engineer/town planner will serve
engaged by him; and
a notice/completion certificate to the Authority that
the building has been completed in all respects as per
h)
obtain an occupancy permit (see Annex J)
the approved plans. The deviations shall also be
from the Authority prior to any:
brought to the notice of the Authority (with relevant
1) occupancy of the building or part thereof
documents). The team of building officials or its duly
after construction or alteration of that
authorized representative shall then visit the site and
building or part, or
occupancy certificate shall be given in one instance.
2) change in the class of occupancy of any
building or part thereof.
14.2.2
The occupancy certificate should clearly state
the use/type of occupancy of the building. However,
13.2.1
Temporary Occupancy
the applicant can apply for change of use/occupancy
Upon the request of the holder of the permit, the
permitted within the purview of the Master Plan/Zonal
Authority may issue a temporary certificate of
Plan/Building Byelaws, where so required.
PART 2 ADMINISTRATION
15
14.3 When inspection of any construction operation
15.3.1
The Authority may direct in writing that the
reveals than any lack of safety precautions exist, the
building which in his opinion is dangerous, or has
Authority shall have right to direct the owner to stop
no provision for exit if caught fire, shall be vacated
the work immediately until the necessary remedial
immediately or within the period specified for the
measures to remove the violation of safety precautions
purpose; provided that the Authority concerned shall
are taken.
keep a record of the reasons for such action with
him.
14.4 Periodic Occupancy Renewal Certificate
If any person does not comply with the orders of
14.4.1
For buildings covered in 12.2.5.1 after
vacating a building, the Authority may direct the police
completion of the building and obtaining the occupancy
to remove the person from the building and the police
certificate, periodic inspections of buildings shall be
shall comply with the orders.
made by the Fire Authority to ensure the fire safety of
the building and compliance with the provisions of fire
15.4 Disregard of Notice
and life safety requirements (see Part 4 ‘Fire and Life
In case the owner or occupier fails, neglects, or refuses
Safey’). Periodic occupancy renewal certificate shall
to comply with the notice to repair or to demolish the
be made available by the Authority/Fire Authority which
said building or portion thereof, the Authority shall
shall also include safekeep of fire fighting installations
cause the danger to be removed whether by demolition
and equipments for such buildings.
or repair of the building or portion thereof or otherwise.
14.4.2 All occupied building and buildings covered
under 12.2.5.1 shall also be subjected to periodic
15.5 Cases of Emergency
physical inspection by a team of multi-disciplinary
In case of emergency, which, in the opinion of the
professionals of local Authority. The work by team of
Authority involves imminent danger to human life or
professionals may be outsourced by the Authority to
health, the decision of the Authority shall be final. The
competent professionals as may be deemed necessary.
Authority shall forthwith or with such notice as may
The team shall ensure the compliance of byelaws,
be possible promptly cause such building or portion
natural lighting, ventilation, etc, besides structural and
thereof to be rendered safe by retrofitting/strengthening
electrical safety. After checking, the team shall be
to the same degree of safety or removed. For this
required to give the certificate for above aspects. If
purpose, the Authority may at once enter such structure
any shortcoming/deficiencies or violations are noticed
or land on which it stands, or abutting land or structure,
during inspection, the Authority shall ensure the
with such assistance and at such cost as may be deemed
compliance of these within a specified time frame of
necessary. The Authority may also get the adjacent
six months. If not complied with, the building shall be
structures vacated and protect the public by an
declared unsafe. The period of inspection shall usually
appropriate fence or such other means as may be
be 3 to 5 years but in any case not more than 5 years.
necessary.
15 UNSAFE BUILDING
15.6 Costs
15.1 All unsafe buildings shall be considered to
Costs incurred under 15.4 and 15.5 shall be charged to
constitute danger to public safety and shall be restored
the owner of the premises involved. Such costs shall
by repairs or demolished or dealt with as otherwise
be charged on the premises in respect of which or for
directed by the Authority (see 15.2 to 15.5).
the benefit of which the same have been incurred and
15.2 Examination of Unsafe Building
shall be recoverable as provided under the laws (see
Note).
The Authority shall examine or cause to be examined
NOTE — The costs may be in the form of arrears of taxes.
every building reported to be unsafe or damaged, and
shall make a written record of such examination.
16 DEMOLITION OF BUILDING
15.3 Notice to Owner, Occupier
Before a building is demolished, the owner shall notify
Whenever the Authority finds any building or portion
all utilities having service connections within the
thereof to be unsafe, it shall, in accordance with
building, such as water, electric, gas, sewer and other
established procedure for legal notice, give to the owner
connections. A permit to demolish a building shall not
and occupier of such building written notices stating
be issued until a release is obtained from the utilities
the defects thereof. This notice shall require the owner
stating that their respective service connections and
or the occupier within a stated time either to complete
appurtenant equipment, such as, meters and regulators
specified repairs or improvements or to demolish and
have been removed or sealed and plugged in a safe
remove the building or portion thereof.
manner.
16
NATIONAL BUILDING CODE OF INDIA
17 VALIDITY
Code from the point of view of structural safety and
functional requirements.
17.1 Partial Invalidity
18.2 An Urban Arts Commission shall be established
In the event any part or provision of the Code is held
at the city/state level on issues related to urban
to be illegal or void, this shall not have the effect of
aesthetics, through a statute. This statutory authority/
making void or illegal any of the other parts or
commission established by an Act of State Legislative
provisions thereof, which may or shall be determined
Assembly, shall accord approval to all major buildings/
to be legal, and it shall be presumed that the Code
important development projects having bearing on the
would have been passed without such illegal or invalid
urban aesthetics, depending upon the importance of
parts or provisions.
the area with respect to natural or built heritage or
projects on plot areas above 1 hectare and located
17.2 Segregation of Invalid Provisions
in specifically identified areas. The Urban Arts
Any invalid part of the Code shall be segregated
Commission shall act as guardian of urban architecture;
from the remainder of the Code by the court holding
mainly with regard to building form and envelope, the
such part invalid, and the remainder shall remain
relationship between the building, and the ambient
effective.
environment vis-a-vis other dependants should be seen
in depth.
17.3 Decisions Involving Existing Buildings
18.3 The Commission may work in the following
The invalidity of any provision in any clause of the
manner:
Code as applied to existing buildings and structures
a) The Commission may select only the
shall not be held to effect the validity of such section
important buildings as in 18.1 and examine
in its application to buildings hereafter erected.
the same. The person responsible for the
18 ARCHITECTURAL CONTROL
schemes, say an architect or an engineer, may
examine either alone or with the owner. A
18.1 Compliance with the provisions of the Code is
study of the plans, elevations, models, etc,
adequate for normal buildings. But for major public
should be made. The architect/engineer
building complexes or buildings coming up in an
should explain in general terms the purposes
important area near historic/monumental buildings and
which the building is to serve and the main
areas of heritage, the aesthetics of the whole scheme
conditions which have influenced him in
may also have to be examined, vis-a-vis existing
preparing the design.
structures. In addition, any development which may
b) The Commission after full discussion, may
mar the general characteristics and environment of
communicate their decision in writing to the
historical, architectural or other monuments should also
parties concerned. The Commission may
be subject to the provisions of this clause. This clause
recommend a change in the whole scheme or
is intended to cover very few structures to come up in
suggest modifications in the existing scheme,
the vicinity of other declared/historically important
if so required.
structures, and the scrutiny shall be limited to the
external architectural features only so as to ensure an
18.4 The Urban Arts Commission should also be
aesthetic continuance of the existing structures with
charged with advising the city government, on schemes
the new. The scrutiny shall not deal with the routine
which will beautify the city and add to its cultural
building plan scrutiny from other requirements of
vitality.
PART 2 ADMINISTRATION
17
ANNEX A
(Foreword and Clauses 2.17, 6.5, 6.6, 9.1.3, 12.2.8, 12.3 and 12.9)
GUIDE FOR THE QUALIFICATIONS AND COMPETENCE OF PROFESSIONALS
A-1 ESSENTIAL REQUIREMENTS
Engineering Division of the Institution of Engineers
(India) or the statutory body governing such profession,
A-1.1 Every building/development work for which
as and when established.
permission is sought under the Code shall be planned,
designed and supervised by registered professionals.
A-2.2.1 Competence
The registered professionals for carrying out the
The registered engineer shall be competent to carryout
various activities shall be: (a) architect, (b) engineer,
the work related to the building/development permit
(c) structural engineer, (d) supervisor, (e) town planner,
as given below:
(f) landscape architect, (g) urban designer, and
(h) utility service engineer. Requirements of
a) All plans and information connected with
registration for various professionals by the Authority
building permit;
or by the body governing such profession and
b) Structural details and calculations of buildings
constituted under a statute, as applicable to practice
on plot up to 500 m2 and up to 5 storeys or
within the local body’s jurisdiction, are given in A-2.1
16 m in height;
to A-2.5. The competence of such registered personnel
c) Issuing certificate of supervision and
to carry out various activities is also indicated
completion for all buildings;
in A-2.1.1 to A-2.5.1.
d) Preparation of all service plans and related
A-2 REQUIREMENTS FOR REGISTRATION
information connected with development
AND COMPETENCE OF PROFESSIONALS
permit; and
e) Issuing certificate of supervision for
A-2.1 Architect
development of land for all area.
The minimum qualifications for an architect shall be
A-2.3 Structural Engineer
the qualifications as provided for in the Architects Act,
1972 for registration with the Council of Architecture.
The minimum qualifications for a structural engineer
shall be graduate in civil engineering of recognized
A-2.1.1 Competence
Indian or foreign university, or Corporate Member of
The registered architect shall be competent to carryout
Civil Engineering Division of Institution of Engineers
the work related to the building/development permit
(India), and with minimum 3 years experience in
as given below:
structural engineering practice with designing and field
work.
a) All plans and information connected with
building permit except engineering services
NOTE — The 3 years experience shall be relaxed to 2 years in
of multistoreyed/special buildings given
the case of post-graduate degree of recognized Indian or foreign
university in the branch of structural engineering. In case of
in 12.2.5.1.
doctorate in structural engineering, the experience required
b) Issuing certificate of supervision and
would be one year.
completion of all buildings pertaining to
A-2.3.1 Competence
architectural aspects.
c) Preparation of sub-division/layout plans and
The registered structural engineer shall be competent
related information connected with
to prepare the structural design, calculations and details
development permit of area up to 1 hectare
for all buildings and supervision.
for metro-cities and 2 hectare for other places.
A-2.3.1.1 In case of buildings having special structural
d) Issuing certificate of supervision for
features, as decided by the Authority, which are within
development of land of area up to 1 hectare
the horizontal areas and vertical limits specified
for metro-cities and 2 hectare for other places.
in A-2.2.1(b) and A-2.4.1(a) shall be designed only
by structural engineers.
A-2.2 Engineer
A-2.4 Supervisor
The minimum qualifications for an engineer shall be
graduate in civil engineering/architectural engineering
The minimum qualifications for a supervisor shall
of recognized Indian or foreign university, or the
be diploma in civil engineering or architectural
Member of Civil Engineering Division/Architectural
assistantship, or the qualification in architecture or
18
NATIONAL BUILDING CODE OF INDIA
engineering equivalent to the minimum qualification
building/development permit for land areas 5 hectares
prescribed for recruitment to non-gazetted service by
and above. In case of metro-cities, this limit of land
the Government of India plus 5 years experience in
area shall be 2 hectares and above.
building design, construction and supervision.
NOTE — For smaller areas below the limits indicated above,
association of landscape architect may also be considered from
A-2.4.1 Competence
the point of view of desired landscape development.
The registered supervisor shall be competent to carryout
A-2.7 Urban Designer
the work related to the building permit as given below:
The minimum qualification for an urban designer shall
a) All plans and related information connected
be the master’s degree in urban design or equivalent
with building permit for residential buildings
from recognized Indian or foreign university.
on plot up to 100 m2 and up to two storeys or
7.5 m in height; and
A-2.7.1 Competence
b) Issuing certificate of supervision for buildings
The registered urban designer shall be competent to
as per (a).
carryout the work related to the building permit for
A-2.5 Town Planner
urban design for land areas more than 5 hectares and
campus area more than 2 hectares. He/She shall also
The minimum qualification for a town planner shall
be competent to carryout the work of urban renewal
be the Associate Membership of the Institute of Town
for all areas.
Planners or graduate or post-graduate degree in town
and country planning.
NOTE — For smaller areas below the limits indicated above,
association of urban designer may be considered from the point
A-2.5.1 Competence
of view of desired urban design.
The registered town planner shall be competent to
A-2.8 Engineers for Utility Services
carryout the work related to the development permit
For buildings identified in 12.2.5.1, the work of
as given below:
building and plumbing services shall be executed under
a) Preparation of plans for land sub-division/
the planning, design and supervision of competent
layout and related information connected with
personnel. The qualification for registered mechanical
development permit for all areas.
engineer (including HVAC), electrical engineer and
b) Issuing of certificate of supervision for
plumbing engineers for carrying out the work of Air-
development of land of all areas.
conditioning, Heating and Mechanical Ventilation,
NOTE — However, for land layouts for development
Electrical Installations, Lifts and Escalators and Water
permit above 5 hectare in area, landscape architect
Supply, Drainage, Sanitation and Gas Supply
shall also be associated, and for land development
installations respectively shall be as given in Part 8
infrastructural services for roads, water supplies,
‘Building Services’ and Part 9 ‘Plumbing Services’ or
sewerage/drainage, electrification, etc, the registered
as decided by the Authority taking into account
engineers for utility services shall be associated.
practices of the National professional bodies dealing
A-2.6 Landscape Architect
with the specialist engineering services.
The minimum qualification for a landscape architect
A-3 BUILDER/CONSTRUCTOR ENTITY
shall be the bachelor or master’s degree in landscape
architecture or equivalent from recognized Indian or
The minimum qualification and competence for the
foreign university.
builder/constructor entity for various categories of
building and infrastructural development shall be as
A-2.6.1 Competence
decided by the Authority to ensure compliance of
The registered landscape architect shall be competent
quality, safety and construction practices as required
to carryout the work related to landscape design for
under the Code.
PART 2 ADMINISTRATION
19
ANNEX B
(Clause 12.1)
FORM FOR FIRST APPLICATION TO DEVELOP, ERECT, RE-ERECT OR TO MAKE
ALTERATION IN ANY PLACE IN A BUILDING
To
Sir,
I hereby give notice that I intend to develop, erect, re-erect or to make alteration in the building No
or to
on/in Plot No
in Colony/
Street
MOHALLA/BAZAR/Road
City
and
in accordance with the building code of
Part II, Clauses
and
I forward herewith the following plans and specifications in triplicate duly signed by me and
the Architect/Engineer/Structural Engineer/Supervisor/Town Planner/Landscape Architect/Urban Designer1),
Registration No
who will supervise its erection.
(Name in block letters)
1. Key plan
2. Site plans
3. Sub-division/layout plan
4. Building plans
5. Services plans
6. Specifications, general and detailed2)
7. Title of ownership of land/building
8. Certificates for structural sufficiency and supervision
I request that the development/construction may be approved and permission accorded to me to execute the
work.
Signature of Owner
Name of the Owner
(in block letters)
Address of Owner
Date:
1) Strike out whichever is not applicable.
2) A format may be prepared by the Authority for direct use.
20
NATIONAL BUILDING CODE OF INDIA
ANNEX C
(Clause 12.2.8)
FORM FOR CERTIFICATE FOR STRUCTURAL DESIGN SUFFICIENCY
With respect to the building work of erection, re-erection or for making alteration in the building
No
or to
on/in Plot No
Colony/
Street
MOHALLA/BAZAR/Road
City
,
we certify that the structural plans and details of the building submitted for approval satisfy the structural safety
requirements for all situations including natural disasters, as applicable, as stipulated under Part 6 Structural
Design of the National Building Code of India and other relevant Codes; and the information given therein is
factually correct to the best of our knowledge and understanding.
Signature of owner
Signature of the
with date
Registered Engineer/
Structural Engineer with
date and registration No.
Name:
Address:
ANNEX D
(Clause 12.2.9)
FORM FOR SUPERVISION
I hereby certify that the development, erection, re-erection or material alteration in/of building No
or the
on/in Plot No
in Colony/
Street
MOHALLA/BAZAR/Road
City
shall be carried out under my supervision and I certify that all the materials (type and grade) and the workmanship
of the work shall be generally in accordance with the general and detailed specifications submitted along with,
and that the work shall be carried out according to the sanctioned plans.
Signature of Architect/Engineer/Structural Engineer/Supervisor/Town Planner/Landscape Architect/Urban
Designer1)
Name of Architect/Engineer/Structural Engineer/Supervisor/Town Planner/Landscape Architect/Urban
Designer1)
(in block letters)
Registration No. of Architect/Engineer/Structural Engineer/Supervisor/Town Planner/Landscape Architect/Urban
Designer1)
Address of Architect/Engineer/Structural Engineer/Supervisor/Town Planner/Landscape Architect/Urban
Designer1)
Date:
1) Strike out whichever is not applicable.
PART 2 ADMINISTRATION
21
ANNEX E
(Clause 12.10)
FORM FOR SANCTION OR REFUSAL OF DEVELOPMENT/BUILDING PERMIT
To
Sir,
With reference to your application
dated
for grant of permit
for the development, erection, re-erection or material alteration in the building No
or to
on/in Plot No
in Colony/
Street
MOHALLA/BAZAR/Road
City
I have to inform you that the sanction has been granted/refused by the Authority on the following grounds:
1.
2.
3.
4.
5.
6.
Office Stamp
Signature of the Authority
Office (Communication) No
Name, Designation and Address
of the Authority
Date:
ANNEX F
[Clause 13.2 (d)]
FORM FOR NOTICE FOR COMMENCEMENT
I hereby certify that the development, erection, re-erection or material alteration in/of building No
or the
on/in Plot No
in Colony/Street
MOHALLA/
BAZAR/Road
City
will be commenced on as per your permission,
vide No
dated
under the supervision of
Registered
Architect/Engineer/Structural Engineer/Supervisor/Town Planner/Landscape Architect/Urban Designer1),
Registration No
and in accordance with the plans sanctioned, vide
No
dated
Signature of Owner
Name of Owner
(in block letters)
Address of Owner
Date:
1) Strike out whichever is not applicable.
22
NATIONAL BUILDING CODE OF INDIA
ANNEX G
[Clause 13.2(f)]
FORM FOR CERTIFICATE FOR EXECUTION OF WORK AS PER
STRUCTURAL SAFETY REQUIREMENTS
With respect to the building work of erection, re-erection or for making alteration in the building No
or to
on/in Plot No
Colony/Street
MOHALLA/
BAZAR/Road
City
, we certify:
a) that the building has been constructed according to the sanctioned plan and structural design (one set of
drawings as executed enclosed), which incorporates the provisions of structural safety as specified in
Part 6 ‘Structural Design’ of the National Building Code of India and other relevant Codes; and
b) that the construction has been done under our supervision and guidance and adheres to the drawings and
specifications submitted and records of supervision have been maintained.
Any subsequent changes from the completion drawings shall be the responsibility of the owner.
Signature of owner
Signature of the
with date
Registered Engineer/
Structural Engineer with
date and registration No.
Name:
Address:
ANNEX H
[Clause 13.2 (f)]
FORM FOR COMPLETION CERTIFICATE
I hereby certify that the development, erection, re-erection or material alteration in/of building No
or the
on/in Plot No
in Colony/Street
MOHALLA/BAZAR/
Road
City
has been supervised by me and has been completed on
........................... according to the plans sanctioned, vide No
dated
The work
has been completed to my best satisfaction, the workmanship and all the materials (type and grade) have been
used strictly in accordance with general and detailed specifications. No provisions of the Code, no requisitions
made, conditions prescribed or orders issued thereunder have been transgressed in the course of the work. The
land is fit for construction for which it has been developed or re-developed or the building is fit for use for which
it has been erected, re-erected or altered, constructed and enlarged.
I hereby also enclose the plan of the building completed in all aspects.
Signature of Architect/Engineer/Structural Engineer/Supervisor/Town Planner/Landscape Architect/Urban
Designer1)
Name of Architect/Engineer/Structural Engineer/Supervisor/Town Planner/Landscape Architect/Urban
Designer1)
(in block letters)
Registration No. of Architect/Engineer/Structural Engineer/Supervisor/Town Planner/Landscape Architect/Urban
Designer1)
Address of Architect/Engineer/Structural Engineer/Supervisor/Town Planner/Landscape Architect/Urban
Designer1)
Date:
Signature of the Owner
1) Strike out whichever is not applicable.
PART 2 ADMINISTRATION
23
ANNEX J
[Clause 13.2(h)]
FORM FOR OCCUPANCY PERMIT
The work of erection, re-erection or alteration in/of building No
or the
on/
in Plot No
in Colony/Street
MOHALLA/BAZAR/Road
City
completed under the supervision of
Architect/Engineer/Structural
Engineer/Supervisor, Registration No
has been inspected by me. The building can be permitted/
not permitted for occupation for
occupancy subjected to the following:
1.
2.
3.
One set of completion plans duly certified is returned herewith.
Signature of the Authority
Office Stamp
Date:
24
NATIONAL BUILDING CODE OF INDIA
////////////////////////////////////////// |
||
|
|
|