Military reference books and manuals (2009-2023, Volume 6) - page 6

 

  Index      Manuals     Military reference books and manuals (2009-2023, Volume 6)

 

Search            copyright infringement  

 

   

 

   

 

Content      ..     4      5      6      7     ..

 

 

 

Military reference books and manuals (2009-2023, Volume 6) - page 6

 

 

Title: Procedure for:
Doc No: UNIF-HSE-PR0-104-C2
Authorisation
Rev No: C2
Page 4 of 14
Dated: October, 2004
Originating Dept: HSE
 Ensuring that the Permit to Work system is subject to active assurance.
 Acting upon all recommendations of the assurance process and proposing
system improvements.
2.2 AREA AUTHORITY
Personnel fulfilling the function of Area Authority are responsible, within the limits of
their designated area, for the:
 Safety of personnel and the safe execution of all activities
 Operation of the Permit to Work system and supporting procedures.
In addition, as an Affected Area Authorities
(an Area Authority whose area of
responsibility will be affected by work being undertaken principally in another area
and under the control of another Area Authority) they are required to be aware of,
and be in agreement with, all work activities taking place that have a potential impact
on their particular area of responsibility and control.
The Responsible Electrical Person will act as affected Area Authority for any
electrical work carried out on the site.
2.3 PERFORMING AUTHORITY
The Performing Authority is the person who requires the work to be done or who will
perform the work. Performing Authorities shall act as the senior person in charge of
work controlled by a Permit to Work and are responsible for safety at the work site.
2.4 AUTHORISED GAS TESTER LEVEL 2
An Authorised Gas Tester Level 2 is authorised to test for the presence of flammable
gas or vapour.
2.5 AUTHORISED GAS TESTER LEVEL 1
An Authorised Gas Tester Level 1 is authorised to test for the presence of flammable
gas or vapour, toxic gas and oxygen. In particular the Authorised Gas Tester will
document and record gas test results as defined in UNIF-HSE-PRO-108 - Confined
Space Entry.
2.6 AUTHORISED LEAK TESTER
An Authorised Leak Tester is authorised to test for the presence of leaks. In
particular the Authorised Leak Tester will perform document and record leak test
results as defined in UNIF-HSE-PRO-241 - Leak Testing
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/10/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Procedure for:
Doc No: UNIF-HSE-PR0-104-C2
Authorisation
Rev No: C2
Page 5 of 14
Dated: October, 2004
Originating Dept: HSE
2.7 ISOLATING AUTHORITY
2.7.1 Process Isolators
Process isolators are responsible for the identification, specification, application,
removal and recording of Process Isolations (Process / Mechanical Isolations).
2.7.2 Electrical Isolators
Electrical Isolators are responsible for the specification, application, removal and
recording of Electrical Isolations (Control/ Electrical/ Telecom Isolations).
2.7.2.1 Senior Authorized Electrical Personnel (SAEP)
Electrical personnel who have been formally assessed by the site Electrical
Technical Authority (or delegate), and authorized by the OIM / Site Manager / Site
Controller, to switch, isolate and test electrical equipment with voltage levels up to
and greater than one thousand volts (1000v), can act as an isolating authority under
the Safe Systems of Work for electrical systems with voltage levels up to and greater
than 1000V. As described in UNIF-HSE-PRO-106 Procedure for: Energy Isolation -
Electrical
Note: Where switching or isolation interfaces with an external organization the authorization
may also include an assessment by the external organization or the State Energy Control
2.7.2.2 Authorized Electrical Personnel (AEP)
Electrical personnel who have been formally assessed by the site REP, and
authorized by the OIM / Site Manager / Site Controller, to switch, isolate and test
electrical equipment with voltage levels less than one thousand volts (1000V) an act
as an isolating authority under the Safe Systems of Work for electrical systems with
voltage levels less than 1000V. As described in UNIF-HSE-PRO-106 Procedure for:
Energy Isolation - Electrical
2.7.2.3 Authorized Instrument Personnel (AIP)
Instrument personnel who have been formally assessed by the site REP, and
authorized by the OIM / Site Manager / Site Controller to switch, isolate and test
control, instrument and telecom equipment with voltage levels less than fifty volts
(50V), can act as an isolating authority under the Safe Systems of Work for control,
instrument and telecom systems with voltage levels less than 50V phase to earth.
As described in UNIF-HSE-PRO-106 Procedure for: Energy Isolation - Electrical
2.7.2.4 Competent Isolator (CI)
In special circumstances individuals can be assessed as competent isolators by the
site REP and authorized by the OIM / Site Manager / Site Controller for specific items
of equipment providing that they have completed the formal training and have been
assessed as competent, as described in UNIF-HSE-PRO-106 Procedure for: Energy
Isolation - Electrical
2.8 FIREWATCHER
Personnel competent in the use of fire fighting equipment that they are expected to
handle as described in UNIF-HSE-PRO-103 Procedure for: Permit To Work
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/10/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Procedure for:
Doc No: UNIF-HSE-PR0-104-C2
Authorisation
Rev No: C2
Page 6 of 14
Dated: October, 2004
Originating Dept: HSE
2.9 PERMIT TO WORK COORDINATOR
Personnel authorized to act as a permit to work coordinator (some times this function
is covered by the site control room operator and the area authority) as described in
UNIF-HSE-PRO-103 Procedure for: Permit To Work
2.10 RADIOLOGICAL PROTECTION SUPERVISOR
Personnel authorised to act as a Radiological Protection Supervisor are authorised to
supervise the handling of radioactive sources and test for radiation levels as
described in UNIF-HSE-PRO-205 Radioactive Sources Management.
2.11 RESPONSIBLE ELECTRICAL PERSON (REP)
This is a role under the ‘Safe System of Work’ or ‘Permit To Work system’ to clearly
identify which authorized person, has the responsibility for the electrical system. The
REP is nominated by the OIM / Site Manager / Site Controller from those persons
having the highest level of authorization required for that site.
The REP will:
 Approve any switching programs
 Countersign permits with electrical content where the Area Authority isn’t
electrically competent, ensuring that the isolation has been correctly designed
and the Isolating Authority has the appropriate authorization level for the work
 Assess and recommend site personnel for authorization to AEP, AIP, and CI
As described in UNIF-HSE-PRO-103 Procedure for: Permit To Work and
UNIF-HSE-PRO-106 Procedure for: Energy Isolation - Electrical
3 TRAINING AND COMPETENCY REQUIREMENTS
The requirements for training, competency evaluation and authorisation are given in
Table 1: Training and Competency Requirements for Authorisation.
Function
Training
Competency Evaluation
Valid
Authorised
(yrs)
by
Site Manager/ Site
Permit to Work Area
Course evaluation test plus
2
Operations
Controller/ OIM
Authority.
a minimum of 2 years
Manager
experience as an Area
Authority
Area Authority
Permit to Work Area
Course evaluation tests and
2
Site Manger/
Authority.
interview by Site Manager
Site Controller/
Confined Space Entry.
Offshore
Energy Isolation.
Installation
Task Risk. Assessment.
Manager
Performing
Permit to Work.
Course evaluation test and
2
Area Authority
Authority
Performing Authority
interview by an Area
Authority
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/10/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Procedure for:
Doc No: UNIF-HSE-PR0-104-C2
Authorisation
Rev No: C2
Page 7 of 14
Dated: October, 2004
Originating Dept: HSE
Function
Training
Competency Evaluation
Valid
Authorised
(yrs)
by
Gas Tester Level 2
Gas Tester level 2
Course evaluation test and
2
Area Authority
practical test by a Gas
Tester Level 2
Gas Tester Level 1
Gas Tester Level 1
Course evaluation test and
2
Site Manger/
practical test by a Senior
Site Controller/
Safety Adviser
Offshore
Installation
Manager
Authorised Leak
Permit To Work
Course evaluation test and
3
Site Manger/
Tester
Performing Authority
interview by an Area
Site Controller/
Gas Tester Level 1
Authority
Offshore
Course evaluation test and
Installation
practical test by Senior
Manager
Safety Adviser
Competent Isolator
Permit to Work.
Assessment by Site
3
Site Manger/
Responsible Electrical
Site Controller/
Performing Authority
person
Offshore
Energy Isolation
Installation
Written statement of
Specific training
Manager
competence by REP
Endorsed by the Electrical
technical authority.
See Appendix D for
Electrical Assessment Areas
Authorised
Permit to Work.
Assessment by Site
3
Site Manger/
Instrument Person
Performing Authority
Responsible Electrical
Site Controller/
Person (REP)
Offshore
Energy Isolation.
Installation
Comp’Ex (on
Written statement of
Manager
hydrocarbon sites)
competence by REP
See Appendix D for
Electrical Assessment Areas
Authorised
Permit to Work.
Assessment by Site
3
Site Manger/
Electrical Person
Performing Authority
Responsible Electrical
Site Controller/
person
Offshore
Energy Isolation.
Installation
First aid
Written statement of
Manager
competence by the (REP)
Comp’Ex (on
hydrocarbon sites)
See Appendix D for
Electrical Assessment Areas
Senior Authorised
Permit to Work.
Assessment by BP
3
Site Manger/
Electrical Person
Performing Authority
Electrical Technical authority
Site Controller/
/ or nominated delegate
Offshore
Energy Isolation.
Installation
First aid
Written statement of
Manager
competence by BP Electrical
Comp’Ex (on
Technical authority / or
hydrocarbon sites)
nominated delegate
HV switching
See Appendix D for
Electrical Assessment Areas
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/10/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Procedure for:
Doc No: UNIF-HSE-PR0-104-C2
Authorisation
Rev No: C2
Page 8 of 14
Dated: October, 2004
Originating Dept: HSE
Function
Training
Competency Evaluation
Valid
Authorised
(yrs)
by
Responsible
Permit to Work. Area
Assessment by BP
3
Site Manger/
Electrical Person
Authority
Electrical Technical authority
Site Controller/
/ or nominated delegate
Offshore
Energy Isolation.
Installation
First aid
Written statement of
Manager
competence by BP Electrical
Comp’Ex (on
Technical authority / or
hydrocarbon sites)
nominated delegate
HV switching (if
applicable for the site)
See Appendix D for
Electrical Assessment Areas
(which will depend on site
voltage levels
Process Isolator
Process Isolation
Assessment by Process
3
Site Manger/
Supervisor
Site Controller/
Offshore
Installation
Manager
Radiological
Radiological Protection.
Course and written
3
Site Manger/
Protection
examination by external
Site Controller/
Supervisor
trainer
Offshore
Installation
Manager
Fire Watcher
Permit to Work.
Evaluation test and
3
Area Authority
Performing Authority
interview by an Area
Confined Space Entry.
Authority
Permit to work Co-
Permit to Work.
Evaluation test and
3
Area Authority
coordinator
Performing Authority
interview by an Area
Authority
Confined Space Entry.
Energy Isolation.
Task Risk Assessment.
Table 1: Training and Competency Requirements for Authorisation
4 AUTHORISATION PROCESS
Note: No person shall be authorised under this procedure until they have completed
the required training and the competency evaluation detailed in Table 1:
Training and Competency Requirements for Authorisation and where
required a written statement of competency has been received from the
assessor by the authoriser.
4.1 AUTHORISATION ASSESSMENT
For authorization for Isolation Authorities a candidate who successfully meets the
pre-requisite standards, will be assessed further by the Process Supervisor or
Responsible Electrical Person or the Electrical Technical Authority (or nominated
delegate)
For Isolation Authorities-Electrical this part of the assessment will be based on
written, oral and practical demonstration of knowledge.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/10/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Procedure for:
Doc No: UNIF-HSE-PR0-104-C2
Authorisation
Rev No: C2
Page 9 of 14
Dated: October, 2004
Originating Dept: HSE
The candidate will provide written responses to a selection of question relating to
Safe Systems of Work and facility specific information. The site will retain these
responses.
The candidate will also be asked to demonstrate on site appropriate site knowledge,
and how to apply the Safe Systems of Work to an appropriate operational exercise.
The REP will assess competency of Authorized Instrument Persons
(AIP),
Authorized Electrical Persons (AEP) and Competent Isolators (CI). The Electrical
Technical Authority (or delegate) will assess the competency of candidates for the
Senior Authorized Electrical Persons (SAEP) or those persons who will full fill the role
of Responsible Electrical Person (REP).
4.2 LETTER OF AUTHORISATION AND STATEMENT OF COMPETENCY
Authorisation is recognised by a letter to the individual (see Appendix A general
authorization and Appendix B for electrical authorisation), clearly stating the level and
duration of authorisation. If required, the competency assessor shall supply a written
statement of competency to the authorizer
(see Appendix C for electrical
competency).
4.3 AUTHORISATION VALIDITY
Authorisation shall be valid for the maximum duration stated in Table
1 which
corresponds with the refresher training requirements associated with the duties.
Note: Authorisation shall cease if the person moves to a new post, even if the new
post is on the same site.
4.4 AUTHORISATION REGISTER
The Site Manager/ Site Controller/ Offshore Installation Manager shall maintain a
register of all personnel authorised at their facility. This register will be stored on
Documentum and accessed via the Azerbaijan Business Unit web site. This register
shall be available within the facility at the location from where permits are normally
issued.
4.5 RECORDS
The site will retain the assessment record sheet and its attachments. The assessor
will issue Competence Certificates to the candidate and the Site Manager/ Site
Controller/ OIM as appropriate and a copy issued to the successful candidate. The
site will retain the original certificate.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/10/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Procedure for:
Doc No: UNIF-HSE-PR0-104-C2
Authorisation
Rev No: C2
Page 10 of 14
Dated: October, 2004
Originating Dept: HSE
APPENDIX A GENERAL LETTER OF AUTHORISATION
{Date}
Letter of Authorisation Under the Safe Systems of Work Procedures
This letter authorises {full name
} to under take the duties of {postion
} at {site/ facility
}in accordance with the requirements of BP AZBU
(delete as appropriate from the listing of Permit to Work System
(Document No.UNIF-HSE-PRO-103) UNIF-HSE-PRO-106 Energy
Isolation - Electrical; UNIF-HSE-PRO-107 Energy Isolation - Process;
UNIF-HSE-PRO-108 Safe Systems of Work - Confined Space Entry;
UNIF-HSE-PRO-201 Gas Detection Equipment; UNIF-HSE-PRO-205
Radioactive Sources Management. This authorisation is valid for a period
of
{X
} years or until termination of employment in your present
position.
For BP Azerbaijan/Georgia
{Name}
Signature: ………………………….
{Authorizing post holder}
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/10/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Procedure for:
Doc No: UNIF-HSE-PR0-104-C2
Authorisation
Rev No: C2
Page 11 of 14
Dated: October, 2004
Originating Dept: HSE
APPENDIX B ELECTRICAL AUTHORISATION CERTIFICATE
Electrical Authorization
Certificate
Add individuals NAME:
…………………………………………………………………………………………………………
Was found to be competent to operate safely in the following areas
Mechanical isolations for systems of less than 1000V
Control and Instrumentation systems with voltages less than 50V
Electrical circuits with voltages less than 1000V
Electrical distribution systems with voltages less that 1000V
Electrical circuits with voltages less that 33kV
Electrical distribution systems with voltages less than and including 33kV
Electrical distribution systems with voltages of 110KV
Specific equipment type at voltage level See attached training certificate
Role of Responsible Electrical Person for name of site site
Assessor Name……………………………………………………
Date…………………………………………………………………
This certificate authorizes the above name person as a
Competent Isolator (CI)
Authorized Instrument Person (AIP)
Authorized Electrical Person (AEP)
Senior Authorized Electrical Person (SAEP)
For ……………………………………………………………………………………………..……site
For a period
of…………………………………………………………………………………….years
Authorized
By……………………………………………………………………………………………
Date…………………………………………………………………………………………………...….
Accepted
By……………………………………………………………..……………………………….
Date……………………………………………………………………………………………………….
Details of any restrictions to this authorization:
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/10/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Procedure for:
Doc No: UNIF-HSE-PR0-104-C2
Authorisation
Rev No: C2
Page 12 of 14
Dated: October, 2004
Originating Dept: HSE
APPENDIX C ELECTRICAL COMPETENCY CERTIFICATE
Electrical Competency
Certificate
Name;
Role: (AIP, AEP, SEAP, REP)
Site Location;
Experience; (experience in job, formal training, etc)
Site Knowledge; (generation, HV distribution including busbar architecture HV switching procedures, LV switching
arrangements, knowledge of site operating basis, earthing apparatus, battery and UPS systems etc, as appropriate to authorisation
level)
Site Practical; (awareness of electrical risks, switching, earthing apparatus, ICC, PTW, TRA etc)
Electrical Procedures; (questionnaire completed)
Assessment performed by
DATE:
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/10/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Procedure for:
Doc No: UNIF-HSE-PR0-104-C2
Authorisation
Rev No: C2
Page 13 of 14
Dated: October, 2004
Originating Dept: HSE
APPENDIX D
ELECTRICAL TRAINING CERTIFCATE
Competent Isolator
Training Certificate
Name of Trainee;
Site Location;
Equipment trained on: (Specific equipment types Manufacture and Model Number etc)
Operations trained in: (Specific operation that the training has covered, attach any specific operations instructions)
Training assessment; (Assessment of the training which will cover specific knowledge of an equipment hazards or site
procedures covering this equipment)
Assessment performed by
Date
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/10/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Procedure for:
Doc No: UNIF-HSE-PR0-104-C2
Authorisation
Rev No: C2
Page 14 of 14
Dated: October, 2004
Originating Dept: HSE
APPENDIX E
ELECTRICAL ASSESSMENT AREAS
Areas of Assessment
CI
AIP
AEP
SAE
REP
P
Electrical Isolation Standard
X
X
X
X
X
Electrical Safety Guidance
X
X
X
X
X
Safe Systems of Work (ICC, PTW, TRA)
X
X
X
X
X
Appropriate Site Knowledge
X
X
X
X
X
Interpretation of drawings
X
X
X
X
Comp’Ex EX Certificate (for hydrocarbon sites)
X
X
X
X
Isolation of LV supplies up to 50V
X
X
X
X
LV electrical testing up to 50V
X
X
X
X
LV fault finding up to 50V
X
X
X
X
First Aid Certificate covering CPR and electric shock
X
X
X
treatment
Electrical protection
X
X
X
Switching programs
X
X
X
Distribution switching
X
X
X
Isolation of LV supplies
X
X
X
LV electrical testing
X
X
X
LV fault finding
X
X
X
HV switching
X
Isolation of HV supplies
X
HV electrical testing
X
HV fault finding
X
*
Specific equipment training for competent isolators
X
* These areas will be site dependant given the maximum voltage level of the site
The assessment process will consist of both a written and practical assessment elements.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/10/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
AZERBAIJAN BUSINESS UNIT
(AzBU)
Procedure for:
Task Risk Assessment
Issued for
G.Hunt
G.Campbell
C2
09.09.04
G.Stacey
SSoW WG
use
Rev
Date
Reason for
Prepared by
Checked by
Approved by
Endorsed by
Issue
Notes: C2: Updated to
HSE - SAFETY
provide more clarity and detail
Azerbaijan BU Document Reference
Asset Code
Dept Code
Document Type
Sequence No
Revision
Code
UNIF
HSE
PRO
105
C2
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 2 of 41
Dated: September, 2004
Originating Dept: HSE
TABLE OF CONTENTS
1
INTRODUCTION
3
2
ROLES AND RESPONSIBILITIES
5
3
AUDITING AND MONITORING
7
4
COMPETENCY, TRAINING AND AWARENESS
8
5
RISK ASSESSMENT LEVELS
9
6
THE STAGES OF RISK ASSESSMENT
16
7
MANAGEMENT OF RISK
29
APPENDIX A: DEFINITIONS & ABBREVIATIONS
30
APPENDIX B: LEVEL 2 RISK ASSESSMENT - CHECKLISTS
32
APPENDIX C: L2RA FORMS
36
APPENDIX D: HAZARD EFFECT & PROBABILITY TABLES, RISK MATRIX
......................................................................................................................38
APPENDIX E: RISK ASSESSMENT FLOWPATH
40
APPENDIX F: RISK HIERARCHY EXAMPLES
41
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 3 of 41
Dated: September, 2004
Originating Dept: HSE
1
INTRODUCTION
1.1
Purpose
It is a requirement of the Permit to Work procedure employed within BP AzBU that a Task
Risk Assessment is carried out before any permits are issued.
The purpose of this procedure is to describe the Task Risk Assessment process
employed by BP AzBU in support of the Permit to Work System.
It is a requirement of „Getting HSE Right‟ and the „Golden Rules of Safety‟ that the
Hazards associated with BP activities are identified and that the Risks are assessed and
managed.
1.2
Deviations
The procedures are written in sufficient detail that they should be able to be applied
consistently at all sites. There may still be the requirement for some local rules covering
site-specific logistical/administrative arrangements and local variations in responsibilities
to reflect differences in organisational arrangements. These local rules should not deviate
from the core processes within this document. Any form of deviation from this procedure,
including but not limited to local rules, shall be requested and authorised in accordance
with the SSOW Deviations from Regulations and Procedures procedure (Doc. No. UNIF-
HSE-PRO-101)
1.3
Scope
The scope covers defined activities of BP and Contractors at all BP AzBU sites and
installations.
BP AzBU Managed Sites/Installations
A Permit To Work system with supporting Task Risk Assessment process is employed at
all BP AzBU managed sites where hydrocarbons are processed or handled, and at any
other site directly managed by BP AzBU.
When 3rd party/contractor visits a site/installation with a pre-prepared Risk Assessment, it
must be reviewed. The RA must have similar features and ensures identification of
hazards and controls as effectively as the Task Risk Assessment procedures employed
by BP AzBU. In such circumstances, the Risk Assessment process is followed as normal,
with only a new Risk Assessment front-sheet requiring completion.
Third Party Managed Sites/Installations
On sites managed by a third party, e.g., a contracted drilling rig, the contractor‟s permit to
work and Risk Assessment systems may be used provided that they have similar features
and ensures identification of hazards and controls as effectively as the Task Risk
Assessment procedures employed by BP AzBU.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 4 of 41
Dated: September, 2004
Originating Dept: HSE
1.4
Document review
This document will be reviewed on an annual basis when users from the sites will have an
opportunity to propose changes to the existing processes and procedures. The document
Technical Authority will be responsible for coordinating this review.
1.5
SSOW Specific Cross references
This SSOW procedure shall, where appropriate, be used in conjunction with this suite of
AzBU SSOW Procedures referenced below.
Document Number
Title of Procedure
UNIF - HSE- PRO - 101
Deviations from Regulations and Procedures
UNIF - HSE- PRO - 102
Incident Investigation and Reporting
UNIF - HSE- PRO - 103
Permit To Work
UNIF - HSE- PRO - 104
Authorisation
UNIF - HSE- PRO - 105
Task Risk Assessment
UNIF - HSE- PRO - 106
Energy Isolations-Electrical
UNIF - HSE- PRO - 107
Energy Isolations-Process
UNIF - HSE- PRO - 108
Confined Space Entry
UNIF - HSE- PRO - 241
Leak Testing
1.6
BP Golden Rules
Risk Assessment is not an explicit Golden Rule on its own, however it is applicable to
them all. The Golden Rules identify the main areas where Risk Assessment is paramount.
This procedure should be used for all the Golden Rules, being:
Permit To Work
Working at Heights
Energy Isolation
Lifting Operations
Ground Disturbance
Vehicle Safety
Confined Space Entry
Management of Change
1.7
Language Facilitation
Due to the various languages spoken at site, there is a necessity to assist all with “an
ease of understanding”. Therefore, the development and use of information tools are
available.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 5 of 41
Dated: September, 2004
Originating Dept: HSE
2
ROLES AND RESPONSIBILITIES
2.1
Site Manager/OIM/Site Controller
The Site Manager (SM) / Offshore Installation Manager (OIM) / Site Controller (SC) are
responsible for:
 Ensuring that the TRA Process is applied at sites within their area of
responsibility.
 Periodic internal reviews and / or audit of the operations of TRA.
Appointing individuals to act as TRA Team Leaders to facilitate the TRA process.
Site Managers/OIM/Site Controllers are responsible for reviewing all Level
2 Risk
Assessments.
Note: It is incumbent on Site Manager/OIM/Site Controller to request a higher level of
Risk Assessment should they consider that risks have not been fully addressed.
2.2
Area Authority
Area Authorities are responsible for:
 Determining the level of Risk Assessment required to support any Permit to
Work application
 Organising and participating in the Risk Assessment process.
2.3
Performing Authority
Performing Authorities are responsible for taking part in the Risk Assessment process and
disseminating the output from the Risk Assessment process to the personnel who will be
doing the work.
2.4
TRA Team Leader
The main responsibilities of the TRA Team Leader are to:
 Lead the team in performing a Level 2 Risk Assessment
 Ensure the team understands the assessment process
 Take responsibility for maintaining the quality of the TRA
 Ensure that the assessment team includes personnel with all the necessary
experience, knowledge and competence for the task involved
 Ensure that the TRA includes a worksite visit
 Ensure that all members of the TRA team have a full opportunity to contribute
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 6 of 41
Dated: September, 2004
Originating Dept: HSE
and that the details of the assessment are agreed by all team members
 Ensure that the details of the assessment are accurately recorded
2.5
Individual TRA Member
The responsibilities of individual team members are to:
 Actively participate in the TRA process
 Help identify hazards and control measures to reduce the likelihood of an
incident/accident occurring
 Ensure they agree with the overall TRA before approval, ensuring that risks
have been reduced to as low as reasonably practicable
2.6
People carrying out the Work
The responsibilities of the people carrying out the work is to:
 Understand the hazards, risks and controls associated with the task
 Participate and contribute in the Toolbox Talk
 Actively monitor the worksite and surroundings for changes
 Stop the job at any time if they are concerned about safety
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 7 of 41
Dated: September, 2004
Originating Dept: HSE
3
AUDITING AND MONITORING
Each Business Asset shall:
 Undertake internal audits of the operation of the Risk Assessment process as
part of the Safe Systems Of Work at each site.
 Maintain an Audit Register.
 Have in place a system for tracking recommendations
Use of a Standard Audit Checklist is recommended, to allow comparison with external
audit results.
The recommended frequency of Audit is as follows:
 Installation/Site personnel
1 permit per day
 Site Safety Adviser
1 permit per week
 Site Manager/ Controller
1 permit per month
Permit and Risk Assessment audits should be a cross section of activities ongoing.
Where possible, audits should be conducted on all forms of risk assessment:
 Normal (Level 1 and Level 2)
 Isolation Risk Assessment (IRA)
 Operational Risk Assessment (ORA)
 Stand Alone Risk Assessment (SARA)
Installation / Site personnel should carry out audits of individual tasks covering both the
PTW and the Isolation Confirmation Certificate (ICC) on a regular basis.
Offshore Installation Managers / Site Controllers / Site Managers shall carry out regular
internal reviews of the findings of Permit to Work and Risk Assessment Audits, to ensure
that any critical failings in the system, or its manner of implementation, have been
identified and appropriate actions have been, or are being, taken.
The BU HSE Department as part of their annual audit schedule will conduct PTW audits.
Such audits shall examine a cross section of at least 20 Permits, and a number of
relevant ICC‟s. These audits should examine detailed reviews of Risk Assessments, and
check compliance with this procedure and any deviations in place.
The results of the audit shall be discussed with Management and issued for information
and actions allocated to individuals as appropriate.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 8 of 41
Dated: September, 2004
Originating Dept: HSE
4
COMPETENCY, TRAINING AND AWARENESS
4.1
General
All personnel involved in the use of the Risk Assessment process shall be trained and
proven to be competent.
The competency of all relevant personnel shall be established during the planning
process for a particular risk assessment. The Area Authority and/or Line Supervisor shall
ensure that the personnel involved in the activity have the correct competencies through
records or requesting individuals to produce relevant certification.
4.2
Levels of Training
The levels of training are:
First time users: -
Risk Assessment Team Member and Risk Assessment Team Leader level using
classroom based training, with possibly a computer-based Training (CBT) for refreshers.
This also requires a practical assessment to demonstrate that the trainee understands
the Risk Assessment procedure.
Having undergone the appropriate training, RA-Team Members and RA-Team Leaders
can only take on the role when they have been assessed and authorised by the OIM / Site
Manager or Site Controller.
For those considered experienced:
(Regular users)- Refresher training shall be
undertaken, and assessed, at a frequency of not more than 2 years, or if absent from the
site/installation for more than 12 months.
For those transitioning from another Risk Assessment system to this one: -
transition training shall be undertaken with all attendees being assessed for their
competency.
For all BP AzBU employees: - prior to any involvement with the PTW and Risk
Assessment system all employees shall receive awareness training to ensure that they
understand the importance of PTW and how it affects them in the working environment.
Note: The Toolbox Talk is an essential part of the Risk Assessment Process. All users
of SSOW should contribute at this point. Additional information can be found in section
6.9 of this document.
4.3
Records
Records of attendance and competency will be filed for future reference / verification by
Senior Management.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 9 of 41
Dated: September, 2004
Originating Dept: HSE
5
RISK ASSESSMENT LEVELS
5.1
General
The process of Task Risk Assessment (TRA) is a method for systematically examining an
individual work assignment (task), to identify the hazards, evaluate the risks and specify
appropriate controls.
There are two levels of risk assessment defined within the process:
Level 1
 Level 1 is a broad overview of the task by a Competent Person (CP) or persons
(typically the Team Leader, Performing Authority (PA) and Area Authority (AA), to
identify any significant hazards involved and appropriate control measures which
require to be in place to allow the job to proceed.
Level 2
 Level 2 is a formal quantitative assessment, which is required only when the CP(s)
judge that there are greater hazards or complexities associated with the task,
which requires a more rigorous level of assessment. A team of minimum 3
personnel carries out this assessment.
All Risk Assessments require input from those who will be doing the work. In addition,
some Level 2 Risk Assessments may require the input of expertise from outside the
normal site/installation team.
Previously carried out L2 Risk Assessments (L2RA) can be used for repeat tasks.
Note: Whenever a previous L2RA is re-used then it is critical that the details of the TRA
are reviewed to ensure that the scope of the task is still relevant, conditions have
not changed and that the hazards and control measures are still appropriate. A
new L2RA Front-Sheet must be completed, to capture details of the new review
team.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 10 of 41
Dated: September, 2004
Originating Dept: HSE
5.2
Level 1 Risk Assessment Guidance Notes
A Level 1 Risk Assessment is based on section 1 and 2 of the Permit. The Permit Form
provides the prompt list and structured approach for this level of Risk Assessment.
Different Permits have different prompt lists in section 2.
A Level 1 Risk Assessment involves a review of the task by the PA in consultation with
another competent person (CP) (normally the PA, Team leader or AA) to identify the
hazards associated with the task and appropriate control measures required to manage
these hazards. The PA‟s in using their technical competence and task information from
section 1 selects the hazards from a list.
The PA then uses the controls listed in section 2 of the Permit to show how the work will
be controlled.
These hazards and controls are selected from a list from the permit, although the PA
should not be constrained by this and must use his judgement and expertise to identify
any further hazards or controls - there is space on the permit to add additional hazards
and controls.
The CP must decide whether the risks can be controlled adequately by the proposed
means, taking into account the controls required by any relevant local procedure and the
competence of the person in charge. If the CP is not completely assured that the risks will
be adequately controlled by these measures and feels a more rigorous assessment is
required, they must inform the person in charge of the work and request a Level 2 Risk
Assessment. This requirement should ideally be identified at the earliest opportunity. The
Site Manager / Site Controller / Offshore Installation Manager can direct that a Level 2
Risk Assessment shall be undertaken at any time. Earliest communication of the task
requirement and discussion about it will identify the level of Risk Assessment process to
be conducted.
The Area Authority will review with the PA Section 1 and 2 of the permit along with any
documentation. They will visit the worksite to confirm all hazards have been identified and
controlled.
The flow-path that should be followed is provided in Appendix E.
Note: Discussing the job with the workforce involved is an important part of this
process.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 11 of 41
Dated: September, 2004
Originating Dept: HSE
5.3
Level 2 Risk Assessment Guidance Notes
A Level 2 Risk Assessment must be carried out at any stage in the process where the PA,
AA, a member of management or any other personnel believes that significant risks exist
which will not be adequately controlled without a more rigorous assessment and the
application of additional controls. This requirement should ideally be identified when the
planning for the task is first initiated.
The reasons for a Level 2 Risk Assessment might include, for example:
 The task is new and unfamiliar
 It is physically impossible to comply fully with the standards in a relevant local
procedure or other recognised source of guidance
 Previously used controls may not be reasonably practicable in this case
 The task is complex and/or has potential impact on other activities
The decision on when a Level 2 Risk Assessment is required for a task is somewhat
subjective and will depend on the people involved but the following rules should be
applied to ensure a consistent level of assessment is being carried out across the
organisation.
There are four types of Level 2 Risk Assessment:
 Normal
 Operational Risk Assessment (ORA)
 Stand Alone Risk Assessment (SARA)
 Isolation Risk Assessment (IRA)
A Level 2 Risk Assessment is mandatory for any job described in Table 1 and is advised
in Table 2.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 12 of 41
Dated: September, 2004
Originating Dept: HSE
5.3.1 Normal Level 2 Risk Assessment
Tasks identified in this section require a Normal Level 2 TRA to be performed. In the
event a particular task is not listed but the Task has a significant risk (s) then a Line
Supervisor should be consulted. Some sites may have specific activities unique to that
site which they deem as mandatory Level 2 tasks. A Level 2 Risk Assessment must
always be undertaken for any job, which requires:
Table 1 - Mandatory Level 2 Risk Assessment
 Confined Space Entry
 Heavy Lifts
 Work on flare systems
 Diving Operations
 Plugging/sealing
 Simultaneous Operations (SIMOPs)
 Hot / Odd Bolting
 Use of Explosives
 Working with asbestos
 Lifts over live process pipelines or process
plant
 Working at Heights without scaffold or
 Tasks involving Ground Disturbance
structure
(Excavations)
 When minimum standards of Energy
 Where there is a significant potential for
Isolation cannot be achieved
injury to people outside the site boundary
 Unconventional access (e.g., abseiling,
 Hot work within 15m radius of hydrocarbons
crane basket)
 Proof Tests (initial hydro test where no
 When the any approved procedures cannot
design pressure exists)
be followed.
 Pneumatic test (as alternative to hydro
 Task that may have specific hazards
test, up to 110% of design pressure)
associated with Energy Isolation.
 Non-routine venting/draining/cleaning of
 Tasks which are judged to be unusually
equipment containing hazardous chemicals
complex (e.g., due to the number of steps or
interfaces)
 Tasks which are unfamiliar, or which
involve unfamiliar methods or technologies
Table 2 - Advisory Level 2 Risk Assessment
 Any activities involving potential exposure to H2s
 Where multiple protective devices are removed or inhibited from a system
 New activities being carried out for the first time and/or involving personnel or vendors new to
the site
 Where an element of emergency equipment is being removed from service (e.g. fire pump
removal/maintenance)
Some sites will have standing instructions or procedures in place covering standard
precautions for some of these activities. They can act in support of the assessment and
may adequately cover most of the required control measures.
A Level 2 Risk Assessment is carried out against check lists (see Appendix B Risk
Assessment Check Lists).
The flow-path that should be followed is provided in Appendix E.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 13 of 41
Dated: September, 2004
Originating Dept: HSE
5.3.2 Operational Risk Assessment
Operational Risk Assessments (ORAs) are associated with a piece of equipment or plant
as opposed to being associated with a specific task. They involve carrying out a Level 2
Risk Assessment and identifying some control measures that need to be put in place.
Examples of an ORA are:
 Operating a compressor with some instrumentation out of service (e.g. vibration
probe), where some additional controls or monitoring is required to allow continued
operation of the compressor
 Reduction of deluge cover in an area of the Installation where some additional
controls/restriction on work would be applied to that particular area of the plant
 Problem with a lifeboat where some alternative evacuation arrangements are in
place
If a piece of equipment requires an ORA, the procedure would be:
 Create a team as per L2RA procedure (Mandatory Level 2 Risk Assessment)
 Complete a TRA on Front Sheet and Work Sheets
 Authorise ORA - register held by OIM / Site Controller / Site Manager
 Assign controls, and put in-place
Note that an ORA is not a permit, therefore no isolation is available. If any isolation is
required, a permit should be raised.
An Operational Risk Assessment is valid for 28 days and has to be reviewed every 7 days
by the Site Manager/OIM/Site Controller.
5.3.3 Stand-Alone Risk Assessment
SARAs are not task-related but once again require that a Level 2 Risk Assessment be
conducted. A Stand-Alone Risk Assessment involves carrying out a risk assessment,
which may not be associated with either a task or specific piece of equipment. It could for
example involve performing a risk assessment associated with a change in organisation
or responsibilities. It allows direct use of the standard Level 2 Risk Assessment process.
If a SARA is required, the procedure would be:
 Create a team as per L2RA procedure (Mandatory Level 2 Risk Assessment)
 Complete a TRA on Front-Sheet and Work-Sheets
 Authorise SARA - register held by OIM / Site Controller / Site Manager
 Assign controls, and put in-place
Note that a SARA is not a permit. Therefore no isolation is available.
A Stand Alone Risk Assessment has no restriction on validity duration, but should be
reviewed by the Site Manager/OIM/Site Controller every 28 days.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 14 of 41
Dated: September, 2004
Originating Dept: HSE
5.3.4 Isolation Risk Assessment
When an Energy Isolation-Process does not meet the standard as stipulated in procedure
UNIF-HSE-PRO-107 a L2RA is required. The risk assessment should only be on the
isolation element of the task, and not the work task element.
Examples of when an Isolation Risk Assessment (IRA) is required are:
 Sufficient number of valves are not available to achieve the level of isolation
required
 There is an integrity issue (e.g. leaking) of part of an isolation
 An alternative means of isolation must be resourced, i.e. stopple bag, ice-plug
If an isolation requires a risk assessment, the procedure would be:
 Create a team as per L2RA procedure (Mandatory Level 2 Risk Assessment)
 Complete TRA Front Sheet
 The TRA Worksheet should identify controls to allow a safe and suitable isolation
 Authorise IRA - register held by OIM / Site Controller / Site Manager
 Assign controls, and put in-place
An Isolation Risk Assessment is valid indefinitely, however it has to be revalidated after 7
days by the OIM/Site Controller/Site Manager.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 15 of 41
Dated: September, 2004
Originating Dept: HSE
5.4
Level 2 Risk Assessment Team
The objective of the Level 2 Risk Assessment is to assemble a team of persons with
intimate knowledge and expertise of the task and in a structured way, examine all the
hazards associated with that task, and then devise a set of controls which will ensure an
acceptable level of risk is achieved. Where necessary, expertise from elsewhere
(e.g. specialist vendors/contractors) may also be brought into the assessment process.
Where larger jobs or shutdowns are planned, work should be undertaken early on to
identify potential tasks requiring Level 2 Risk Assessments in order to allow adequate time
for the assessment to be undertaken.
The Level 2 Assessment Team should be made up of a minimum of three persons and
consist of persons having intimate knowledge and experience of the task or equipment to
be used. There should also be a fully competent TRA Leader capable of acting as
facilitator and leader of the assessment process.
The TRA Team Leader should make arrangements for the team to work as a group. It is
important to ensure, for example, that there is adequate space for examination of
drawings and that sufficient time is allocated to allow a rational decision to be reached.
It should not normally require more than a team of five persons to carry out an
assessment.
The objective of a Level 2 Risk Assessment is to use local knowledge and specialist
knowledge in a structured way in order to achieve ALARP for any residual risk.
The Risk Assessment team should include:
 the Area Authorities for the areas in which the task will be carried out
 the Performing Authority
 the person who will undertake the task, if not the Performing Authority
 a specialist from inside and external to the operation as required
 an HSE specialist who is responsible for ensuring that the Risk Assessment is
carried out in accordance with this procedure and for recording the results.
Note: a L2RA Team requires at least three members
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 16 of 41
Dated: September, 2004
Originating Dept: HSE
6
THE STAGES OF RISK ASSESSMENT
6.1
Define the Task to be Assessed
The task description detail must provide information on Who, What, Why, How and When
the task will be performed. As the task becomes more complex the level of detail and
supportive documentation required will increase. The level of information provided must
take into account all people taking part in the task.
The Task Risk Assessment team must first ensure that they fully understand the task and
its implications. The overall task may need breaking into steps to facilitate carrying out the
Task Risk Assessment. When defining the task, think about such aspects as provided
below:
Item
Issues to Consider
1. System boundaries
What is the system being worked on? The extent of equipment,
hardware, or software affected by the activity. Will the work be
carried out on isolated or un-isolated systems? Where are the
isolations, or interfaces with other systems?
2. Area or space boundaries
What area is affected by the activity?
What area could be affected in an accident?
3. Work activities included
What do you have to do? What might be the effect of doing it?
Think about isolations, inhibits, etc.
4. People affected
People; in the team, working nearby, who might be passing by,
working on related activities and working on connected systems.
5. Time and duration of work
Will the task take one hour or multiple shifts?
Will the work be done during the day or night or both?
6. Tools and equipment to be
Does the activity require hand tools, power tools, ladders, lifting
used
equipment, etc.? Task-specific PPE
7. Interfaces with adjacent work-
How will your work affect other work going on at the same time?
fronts
How will other work affect you?
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 17 of 41
Dated: September, 2004
Originating Dept: HSE
6.1.1 L1RA Specific
For a L1 Risk Assessment, the Task Description is recorded in box 1.
6.1.2 L2RA Specific
The L2RA Front Sheet should be completed as far as possible. The sections that should
be completed are:
INSTALLATION
DEPARTMENT/SYSTEM/LOCATION -
complete for relevant option
PERMIT No - if known at this point. If not,
TASK DESCRIPTION - be as explicit as
complete when PTW is initiated.
possible, for clarity and future use
REFERENCES AND OTHER RELEVANT
DATE - the date the risk assessment
INFORMATION - enter all relevant
took place
information
TRA Ref No - if registered, enter number
RISK ASSESMENT TEAM - enter names
here. This will be used when Risk
and positions. No signatures required
Assessments are being stored for future
use. Site specific rules will dictate how
this is administered.
TYPE - NORMAL, IRA, SARA or ORA
Any sub task steps should be identified on the L2RA Work-Sheet columns 1 & 2.
Note that the TRA front sheet is not signed as approved initially; this section will only be
signed after worksheets are complete and the SM/SC/OIM accepts the Task Risk
Assessment.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 18 of 41
Dated: September, 2004
Originating Dept: HSE
6.2
Identify the Hazards
A visit to the work site is MANDATORY in order to assess the layout of the area, site
conditions and adjacent plant and activities. Once the members are all familiar with the
scope of the task to be carried out, the team should list all the significant hazards in
column 3 of the TRA worksheet. For a L2RA these are identified on the permit
Checklists are supplied as a guide for reference purposes only. They should not be
considered as being comprehensive. A group brainstorm, with the team leader making
sure that each member is given adequate opportunity to express their views is vital to
maintain a systematic approach to using these checklists.
Hazard Checklist - General
Falling from height
Mental Stress
Noise
Manual Handling
Cold/Heat
Vibration
Lifting operations
Ionising Radiation
Pressure
Falling object
Inert gas
Biological agents
Noise
Chemical hazard
Welding/cutting
Lighting
Flammable gas
Power tools
Fume/dust
Flammable liquid
Static Electricity
Weather
Hand tools
Work on safety systems
Collision
Ignition
Transport by sea/air
Hand tools
Fire
Storage
Machinery
Explosion
Water jetting
Asphyxiation
Structural damage
Grit blasting
Electricity
Personal injury
Potential for ignition
Loss of containment
Barriers/access restrictions
Loss of containment from system
from nearby system
being worked on
Hazard Checklist - Isolations
Type of valves and reliability
H2S
Size of pipe work
Wax
Integrity testing
Sand
Reverse flow
LSA Scale
Pressure build-up
Hydrates
Migration from other systems
Foaming
Inventory behind isolations
Blockage
Duration of isolation
Trapped pressure
Adequacy of pipe supports
Nature of fluid
Fail position of ESD valves/blow down valves
Temperature stability of system and adjacent
systems
Contingency in the event of failure of
Pressure stability of system and adjacent systems
isolations
Environmental impact of spills or emissions
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 19 of 41
Dated: September, 2004
Originating Dept: HSE
Hazard Checklist - Breaking Containment
Note: This checklist should be used in conjunction with Hazard Checklist - Isolations.
Electrical risk of using portable tools
Chemical reactions with cleaning materials
Hazardous substances trapped around bends,
Flammable or toxic vapours arising from
behind baffles, linings etc.
sludge in vessel
Trapped pressure
Chemical reactions with cleaning materials
Environmental impact of spills or emissions
Residual pressure
LSA Scale
Residual heat
Pyrophoric scale
Liquids remaining from flushing
Asbestos gaskets
Inert atmospheres
Chemical hazards
Hazard Checklist - Vessel Entry
Residual gases/vapours
Noise, general
Sludge which may give rise to vapours/gases
Communication difficulties within the vessel
when disturbed
or with the standby man
LSA / NORM scale
Adequacy of lighting within the vessel
Adequacy of ventilation
Temperature effects
Need for air movers during entry.
Oxygen enrichment
Location of rescue kits
Oxygen deficiency
Standby man communication with the CCR
Frequency of gas testing
Ingress of gases/vapours from other nearby
Use of mechanical tools/power
activities or systems
tools/electrical equipment
Competency of standby man
Disposal of vessel cleanings
Slip hazards within the vessel or at the point of
Noise when using power tools
entry
Ionising radiation; nucleonic instrumentation
Visibility within the vessel
Danger of falling into vessel boots or sumps
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 20 of 41
Dated: September, 2004
Originating Dept: HSE
6.3
Identify the Hazard Effects
Note: recording of the Hazard effects is only recorded on a L2RA. However the hazards
effects should be considered on any type of Risk Assessment.
The Team must then identify the Hazard Effects, which will be entered into column 4 of
the L2RA Work-Sheet. Hazard effects are the worst credible possible outcome of the
hazard. As guidance, the team can refer to table the Risk Matrix in the appendices. The
Team should be as explicit as possible in the Hazard Effect details. It is important to
consider property damage and environmental impact and not just personal injury
Examples are shown below:
SUB-TASK ACTIVITY /
HAZARD
EFFECT
DESCRIPTION
Move temporary oil decanting hoses in
Slipping/tripping hazard
sprain, graze
utilities area to new storage cupboard.
Dropped object
broken foot bone
Decant methanol from temporary skid on
Flammable (invisible flame) and
Burns
deck to new storage tanks, use of
Toxic by inhalation &
Fatality
temporary hoses
swallowing.
Welding of new earthing point in live
Fire / explosion in hydrocarbon
Multiple fatality
operational area
area
Long term plant shut down
The table below should be used to determine the hazard effect, rated A - E.
PERSONAL
PROPERTY
ENVIRONMENTAL DAMAGE
EFFECT (E)
INJURY
DAMAGE
RATING
Fatality
Major Loss >$5M
Total Loss of Containment
A
Likely Permanent
Significant Damage
Significant Loss of Containment.
B
Disability
Loss $500k to $5M
100bbl, Limited ability to control
Hospital Stay
Moderate Damage
Significant Loss of Containment
C
Loss $100k to $500k
> 100bbl only Workplace affected
DAFWC / Restricted
Minor Loss $10k to
Minor Loss of Containment
D
Work Case / Medical
$100k
< 100bbl only Workplace affected
Treatment
Simple First Aid
Loss <$10k
Slight Loss of Containment < 1bbl
E
Injury
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 21 of 41
Dated: September, 2004
Originating Dept: HSE
6.4
Existing Control Measures
Note: Existing Control measures are valid for both L1RA and L2RA
When doing a risk assessment, it is normal to assume that no controls are in place. For
many tasks, some controls may be known before the risk assessment, and it is not
realistic to think of the work being done without these controls (e.g. an energy isolation).
So, if experience or normal industry or trade standards dictate, it may be valid to assume
that certain controls are in place, provided that:
 they are stated in column 5 of the L2RA Work-Sheet
 they are demonstrated as part of the task definition (e.g. planned isolations must
have appropriate isolation certificate and marked-up P&IDs); and
 the controls are confirmed to be in place prior to the work being carried out
Controls that may be included in the definition of the task include:
 procedures, operating guides, etc. (supported by a valid risk assessment);
 energy isolations confirmation certificate (including P&IDs)
 entry certificate
 scaffolding request; and
 other risk assessments such as, manual handling, LSA/NORM scale.
Work permits are used for recording the controls for individual work tasks, for controlling
the interfaces between work activities and to gain the correct approvals to start a job.
However, a work permit itself is not a control for an individual work task and should
therefore not be included in the task definition.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 22 of 41
Dated: September, 2004
Originating Dept: HSE
6.5
Evaluate the Risk
Note: recording of the Risk value is only recorded on a L2RA. However the risk factors
should be discussed for a L1RA.
The risks created by each hazard on the list should be evaluated according to:
 The worst credible severity of the hazard effects, should anything go wrong
 The probability of the hazard being realised and resulting in the specified hazard
effect
It is important to consider property damage and environmental impact and not just
personal injury
For each hazard the initial hazard effect and probability are defined based on the hazard
and probability matrix shown:
PERSONAL
PROPERTY
ENVIRONMENTAL DAMAGE
EFFEC
INJURY
DAMAGE
T (E)
RATING
Fatality
Major Loss >$5M
Total Loss of Containment
A
Likely Permanent
Significant Damage
Significant Loss of Containment.
B
Disability
Loss $500k to $5M
>100bbl, Limited ability to control
Hospital Stay
Moderate Damage
Significant Loss of Containment
C
Loss $100k to $500k
> 100bbl only Workplace affected
DAFWC / Restricted
Minor Loss $10k to
Minor Loss of Containment
D
Work Case / Medical
$100k
< 100bbl only Workplace affected
Treatment
Simple First Aid
Loss <$10k
Slight Loss of Containment < 1bbl
E
Injury
PROBABILITY GUIDELINES (P)
RATING
Will occur more than once per quarter
HIGH
OR
(H)
nearly every time
Will occur at least once per year, but less than quarterly
MEDIUM
OR
(M)
sometimes
Will occur less than once per year
LOW
OR
(L)
hardly ever
The hazard effect (E) and probability (P) are then used to determine the risk (R), using the
risk matrix provided. The E, P & R values are written in column 6 of the TRA worksheet.
The initial assessment of risk is to be determined on the basis that no specific control
measures exist. This is in order that the full risk potential may be recognised. The
effectiveness of the assessment will depend entirely on the team‟s ability to identify and
evaluate all significant hazards associated with the task.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 23 of 41
Dated: September, 2004
Originating Dept: HSE
The team should also consider the possibility of the interaction of different hazards,
including those related to:
 Location - Attention should focus on the proximity to other plant or equipment,
e.g., air intakes, shut down systems, control points, vents, drains, sample points
and ignition sources.
 Critical Activities - Critical activities include isolation, flushing, inerting, confined
space entry; work at height, hot work, lifting, use of power tools, temporary
power and air supplies, pressure testing, radiography.
 Simultaneous Activities. - Simultaneous activities should be investigated both
within the task itself and with other unrelated activities taking place nearby.
Risk Matrix (R)
HAZARD EFFECT
A
B
C
D
E
H
15
14
13
9
4
M
12
11
10
5
3
L
8
7
6
2
1
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 24 of 41
Dated: September, 2004
Originating Dept: HSE
6.6
Determine the Additional Controls Required
Note: recording of the Additional Controls is only completed on a L2RA column 7.
Recording of Controls for a L1RA is in section 2 of the permit.
Once the initial Assessment of Risk is complete, the team must work systematically
through the list of Hazards and specify all the Additional Control Measures needed to
mitigate each associated Risk. These are recorded in column 7 of the TRA worksheet.
Note: Controls, which prevent the hazard being realised, should be used in preference to
controls that reduce the effect of a hazard.
The hierarchy of controls is applied in the following order;
1. Eliminate
2. Reduce (substitution, Engineering, Segregation)
3. Manage or Administration (reduce exposure, Procedures)
4. PPE - This must be the last control applied; remember that with PPE you are
inside the hazard zone.
Wherever possible, measures higher in the hierarchy should be used, providing they are
reasonably practicable, and emphasis should be placed upon control at source. A
combination of measures will usually be necessary in order to reduce the level of Risk As
Low As Reasonably Practicable (ALARP). It should also be considered that when
specifying controls, any associated risk that they bring with them needs to be assessed
and controlled.
Typical Control Measures can be placed in the following categories:
Control Measure
Typical Examples
1. Physical
Removal of fuses; Insert spade or blank flange in pipe work; Lock off
valve; Erect mechanical barrier; Use locked enclosure; Keep people at
a distance (e.g., signs, warning tape); Eliminate or substitute toxic
substances; Substitute noisy machinery; Use mechanical handling
equipment.
2. Procedural
Test for pressure build-up or leaks; Examination of flushing fluid; Test
for hazardous chemicals in liquid, solid or gaseous form; Procedure for
control of simultaneous or adjacent work; Prohibition of hot work;
Equipment lock-out; Develop contingency plan,
3. Human
Use of independent specialist personnel; Regular or constant
monitoring of the Task; Use of method statements / detailed
procedures; Clear instructions and warnings to workforce; Clear
definitions of roles and responsibilities during the Task; Adequate
supervision; Ensure competency of personnel for the activity
4. Time
Limit duration of the Task or time of day when the activity occurs; Use
time-saving measures such as hot-bolting, good work-site preparation
and planning for the movement of materials, tools.
5a. Contingency
Emergency shutdown, deluge and blow-down systems, reduction of
(Control)
inventory.
5b. Contingency
Temporary refuge, emergency response system, fire/blast wall, water
(Mitigation)
curtain, provision of PPE, rescue equipment, etc.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 25 of 41
Dated: September, 2004
Originating Dept: HSE
6.7
Allocating Responsibilities for Control Actions
Note: recording of the Responsibilities is completed on a L2RA column 8. Responsibilities
for control actions are not recorded on a L1RA, but can be identified in a method
statement or procedure.
Once the control measures have been identified, each should be allocated to either an
individual or a role. The Risk Assessment may be completed some time before the actual
work task-taking place; therefore the delegated individual/role may change. Where
possible, identify both a role and a specific individual. These are recorded in column 8 of
the L2RA Work Sheet.
Column 11 is for recording the closeout of the actions. Therefore this column should not
be completed until the work is about to commence.
6.8 Re-evaluate the Risks for Acceptability
Note: this is completed on a L2RA column 9. Risk re-evaluations are not recorded on a
L1RA (permit).
The team must then re-evaluate the risk for all those hazards for which controls have
been determined. The new risk level should be determined and the team should consider
whether the risk is now as low as reasonably practicable (ALARP). Column 10 should be
identified with a „Y‟ to confirm the Risk Analysis Team has agreed ALARP.
If the risk is not ALARP, the review team must decide what further safeguards need to be
put in place. The agreed residual E, P and R are recorded in column 9 of the TRA
Worksheet.
The team must finally decide on the acceptability of the overall remaining risk for the task.
Individual hazards with a medium risk may be acceptable provided the overall risk of the
task is considered low. If the team decides that even with the controls in place, there are
too many hazards, which still have a medium risk, this must be recorded and the task in
its present form must be abandoned.
The higher the perceived risk for any particular hazard, the greater should be the
number and/or quality of independent controls, which the team specify as necessary.
Consideration should also be given to the possibility of cumulative effects from the
interaction of several different hazards.
If the team considers that there are insufficient independent controls available, or that the
controls are likely to be ineffective against any particular risk, that risk must be judged to
be unacceptable, and the team leader must record this decision. The task must then be
abandoned or referred to higher management.
The team may also conclude that because of the complexity or degree of the risks
involved, a more detailed engineering assessment is needed. In this case, the task must
be suspended until the assessment is available.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 26 of 41
Dated: September, 2004
Originating Dept: HSE
As a final check, the team should ask itself the following questions about the
proposed task:
 Have all necessary control measures been fully and effectively identified?
 Is there a need for engineering change to eliminate or reduce risk?
 Is there a need to shutdown the plant or process?
 Is the residual risk rating acceptable?
Only at this point can the team judge whether ALARP has been achieved.
Where the residual risk is in the 7 to 11 range should only proceed with utmost
caution.
Where the residual risk >=12, the task may NOT proceed. Either additional controls
must be put in-place, or the task re-engineered.
The table provided provides guidance for residual risk results.
HE
P
R
CONTROL ACTIONS
A
H
15
B
H
14
TASK MAY NOT PROCEED DUE TO SERIOUS LOSS POTENTIAL.
A
M
13
TASK MAY PROCEED ONLY WITH ADDITIONAL CONTROLS IN PLACE TO
AVOID SERIOUS LOSS, AND REDUCE RISK TO <12, THE RESIDUAL RISK
C
H
12
MUST BE ALARP.
D
H
11
B
M
10
TASK MAY PROCEED ONLY WITH THE UTMOST CAUTION.
A
L
9
REVIEW PROCEDURES AND CONTROLS TO REDUCE RISK FURTHER
TO ACHIEVE ALARP
C
M
8
MONITOR CONTINUOUSLY DURING TASK TO ENSURE RISK DOES NOT
B
L
7
INCREASE.
D
M
6
REVIEW PROCEDURES AND CONTROLS TO ENSURE RISK IS REDUCED
TO ALARP.
E
H
5
C
L
4
MONITOR CONTINUOUSLY DURING TASK TO ENSURE RISK DOES NOT
E
M
3
INCREASE.
D
L
2
E
L
1
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 27 of 41
Dated: September, 2004
Originating Dept: HSE
6.9
Implementation of Control Measures
Note: recording of the control implementation is completed on a L2RA column 11.
Implementation of controls is not recorded on a L1RA.
Column 11 is for recording the close-out of the actions. Therefore this column should not
be completed until the work is about to commence.
There are two types of control measures that will be identified from either the Level 1 or
Level 2 TRA process:
 Prerequisite controls are those which must be in place prior to the job starting
 Supplementary controls are those which have to be applied during the job
The prerequisite control measures must be implemented prior to the job going live. This
includes any training and/or special briefing of the PA and work party according to an
agreed plan of action.
The supplementary controls, which will be applied during the job, must be understood fully
by the PA and the work party before work commences.
The AA must satisfy himself that Competent Persons have been allocated the work;
the required controls are in place, any additional paperwork is complete, and that all
the individual risks are reduced to ALARP.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 28 of 41
Dated: September, 2004
Originating Dept: HSE
6.10 Toolbox Talks
Note: Toolbox talks will be carried out for all tasks, whether they are L1RA or L2RA.
This is the process of transferring the methodology and controls to the people who will
carry out the work. It is vital that all persons involved in working on a particular activity are
fully aware of the details of the TRA and all the hazards and controls associated with the
job. Some of them may have been directly involved in the TRA but others may not have
been. This is particularly true of larger jobs (e.g. construction) where the PA who is
probably the Construction Supervisor will have been directly involved in the TRA but the
rest of the work party probably have not.
A Toolbox Talk is a vital part of the process to ensure that the TRA and its associated
documents are reviewed prior to the start of the job and are fully understood by all
persons involved in the task.
Particular emphasis should be placed on those residual risks with a higher rating. It is also
an opportunity for those involved in the work to raise any further concerns about the job
and to identify any hazards not picked up in the TRA process.
Note: If anyone at this stage identifies some additional hazards that have not been
properly assessed or thinks the control measures are inadequate, then the job should not
proceed until the TRA has been re-evaluated and appropriate controls identified to ensure
the job is ALARP.
Keys to success of this step are:
 Communication of the task, the hazards and what must be done to control them to
every person involved in the task.
 Language is critical, especially in complex technical tasks.
 The toolbox talk is held prior to work starting
 Everyone understands everything discussed
 Everyone has the opportunity to voice concerns
Some example topics to cover as part of the Toolbox Talk are:
Issue
Notes
The current weather
Weather
conditions
Sea State
The work party
Competence and experience
Familiarity with the installation and the system being
worked on
Anyone fatigued or distracted
The worksite
Access
Awkward working position
Temperature/humidity
Lighting
The current state of the plant
Physical condition of plant and equipment
and equipment
Current operating status of plant and equipment
The current adjacent work
Can this job affect other work sites
sites
Can other work sites affect this job
The pre-defined precautions
Are they as per written instructions, risk assessments,
and controls
PTW, etc
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 29 of 41
Dated: September, 2004
Originating Dept: HSE
7
MANAGEMENT OF RISK
7.1
Approval
On completion of the Risk Assessment, the Risk Assessment Front & Work Sheets must
be attached to the permit application for the job. It must be reviewed and signed by the
OIM / Site Controller / Site Manager before he approves the associated Permit(s) to Work.
Should the OIM / Site Controller / Site Manager feel that the task presents risks beyond
his level of accountability, he must refer to his Manager for guidance, and if necessary
request a more sophisticated analysis of the risks and mitigation than can be provided by
the method described in this procedure.
7.2
Recording the Risk Assessment
Where a task is likely to be repeated, a record of the Risk Assessment should, at the
permit issuer‟s discretion, be retained for future reference. In any event Risk
Assessments, which include hazards to the health of those, undertaking the task must be
attached to the permit(s) for the job and retained for 12 months.
Where a Risk Assessment form is being re-used, it must be fully reviewed and a new front
sheet created.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 30 of 41
Dated: September, 2004
Originating Dept: HSE
APPENDIX A: DEFINITIONS & ABBREVIATIONS
Confined Space
where there is inadequate ventilation to dispel injurious or
Entry:
flammable fumes, vapour or gas or to provide sufficient oxygen.
Also includes areas where access / egress is restricted.
Controls:
steps taken to reduce either the probability or consequences, or
both of a particular risk.
Hazard:
the potential for human injury or loss of life, damage to the
environment or to material assets or a combination of these.
Hazardous
the result when a hazard is realised.
Consequence:
Inhibition:
The isolation of the executive action of a protective system.
Where practicable, this should not prevent the operation of the
visual / audible warning system.
Isolation:
 Process Isolation involves the closing and locking of valves.
This may include depressurising, flushing and purging, e.g.
single valve isolations.
 Positive Isolation involves the disconnection of plant,
equipment and systems from sources of motive power, liquids
and gases.
 Electrical Isolation - The secure, disconnection and separation
of a circuit, or item of equipment, from every source of
electrical energy. This may involve electrical, instrument and
communication isolations.
 Long Term Isolation - An isolation that remains in place after
permit cancellation, and recorded as “Long Term”.
Isolation
a register maintained in the control room identifying the status of
Certificate
all Isolation Certificates by the Control Room Operator-referenced
Register:
to individual permits.
Permit:
an authorising document approved by management, specifying
the required precautions and conditions under which potentially
hazardous or interacting activities can take place
Permit Display
a board used to display the status of active and suspended
Board:
permits.
Permit
a register maintained in the control room identifying the status of
Register:
all permits.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 31 of 41
Dated: September, 2004
Originating Dept: HSE
Probability:
the chance of occurrence of an event. Probability can be
expressed as a likelihood, frequency, class, rank etc.
Risk:
a combination of the likelihood of a hazardous event and the
severity of the possible consequences of that hazardous event.
Risk
the overall process of risk analysis and risk evaluation.
Assessment:
Risk
the process to support management decisions as to acceptability
Evaluation:
or risk reduction requirements by comparing the estimated risk
against relevant criteria.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 32 of 41
Dated: September, 2004
Originating Dept: HSE
APPENDIX B: LEVEL 2 RISK ASSESSMENT - CHECKLISTS
Note: These checklists are for guidance only. They should not be regarded as
comprehensive in nature and do not replace sound judgment in the
recognition of all hazards associated with any task undergoing assessment.
Several checklists are provided below AS A STARTING POINT FOR LEVEL 2 RISK
ASSESSMENTS. The team should choose the list, which it feels, is the best starting
point for the assessment to be carried out.
The Incident Causation Check List or the General Check List can be used for
guidance on all tasks, in combination with a more specific checklist if appropriate.
Hazard Checklist - General
Falling from height
Noise
Manual Handling
Vibration
Lifting operations
Pressure
Falling object
Biological agents
Noise
Welding/cutting
Lighting
Power tools
Fume/dust
Hand tools
Minimise potential for ignition
Work on safety systems
Collision
Transport by sea/air
Hand tools
Storage
Machinery
Water jetting
Asphyxiation
Grit blasting
Cold/Heat
Loss of containment from nearby system
Mental Stress
Loss of containment from system being worked
on
Ionising Radiation
Ignition
Chemical hazard
Fire
Inert gas
Explosion
Flammable gas
Structural damage
Flammable liquid
Personal injury
Electricity
Barriers/access restrictions
Static Electricity
Weather
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 33 of 41
Dated: September, 2004
Originating Dept: HSE
Hazard Checklist - Isolations
Nature of fluid
Pressure stability of system and adjacent systems
Temperature stability of system and adjacent systems
H2S
Wax
Sand
LSA Scale
Hydrates
Foaming
Blockage
Trapped pressure
Type of valves and reliability
Size of pipe work
Integrity testing
Reverse flow
Pressure build-up
Migration from other systems
Inventory behind isolations
Duration of isolation
Adequacy of pipe supports
Fail position of ESD valves/blow down valves
Contingency in the event of failure of isolations
Environmental impact of spills or emissions
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 34 of 41
Dated: September, 2004
Originating Dept: HSE
Hazard Checklist - Breaking Containment
Note: This checklist should be used in conjunction with Hazard Checklist -
Isolations.
Electrical risk of using portable tools
Flammable or toxic vapours arising from sludge in vessel
Hazardous substances trapped around bends, behind baffles, linings etc.
Chemical reactions with cleaning materials
Environmental impact of spills or emissions
LSA Scale
Pyrophoric scale
Asbestos gaskets
Trapped pressure
Residual pressure
Residual heat
Liquids remaining from flushing
Inert atmospheres
Chemical hazards
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 35 of 41
Dated: September, 2004
Originating Dept: HSE
Hazard Checklist - Vessel Entry
Residual gases/vapours
Sludge which may give rise to vapours/gases when disturbed
LSA scale
Adequacy of ventilation
Need for air movers during entry.
Communication difficulties within the vessel or with the standby man
Standby man communication with the CCR
Ingress of gases/vapours from other nearby activities or systems
Use of mechanical tools/power tools/electrical equipment
Slip hazards within the vessel or at the point of entry
Ionising radiation; nucleonic instrumentation
Danger of falling into vessel boots or sumps
Noise, general
Noise when using power tools
Visibility within the vessel
Adequacy of lighting within the vessel
Temperature effects
Oxygen enrichment
Oxygen deficiency
Frequency of gas testing
Location of rescue kits
Competency of standby man
Disposal of vessel cleanings
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 36 of 41
Dated: September, 2004
Originating Dept: HSE
APPENDIX C: L2RA FORMS
Sheet 1 of __
INSTALLATION :
PERMIT No :
DATE :
TRA REF No :
DEPARTMENT / SYSTEM / LOCATION:
RISK ASSESSMENT TEAM (FIRST NAMED-TRA TEAM LEADER)
NORMAL
IRA
RISK ASSESSMENT TYPE:
SARA
ORA
NAME
POSITION
TASK DESCRIPTION:
REFERENCES AND OTHER RELEVANT INFORMATION :
CONFIRMED ALARP
(e.g. Emergency Provision Required, Competency requirements, Tools & Equipment, additional PPE, P&IDs, Drawings, PTW,
TRA APPROVED BY (OIM/SC/SM):
Procedures, Certificates, other Risk Assessments)
NAME (PRINT) :
SIGNATURE :
POSITION :
DATE :
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 37 of 41
Dated: September, 2004
Originating Dept: HSE
Work-Sheet ___ of ___
TASK DESCRIPTION SUMMARY :
TRA REF No :
6.
9.
INITIAL
RESIDUAL
RISK
2. SUB-TASK
3. HAZARD
4. HAZARD
5. EXISTING
RISK
7. LIST ALL CONTROL MEASURES
ACTIVITY /
DESCRIPTION
EFFECT
CONTROL
REQUIRED
DESCRIPTION
MEASURES
E
P
R
E
P
R
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 38 of 41
Dated: September, 2004
Originating Dept: HSE
APPENDIX D: HAZARD EFFECT & PROBABILITY TABLES, RISK MATRIX
PERSONAL
PROPERTY
ENVIRONMENTAL
HAZARD EFFECT
DAMAGE
(E) RATING
INJURY
DAMAGE
A
Total Loss of
Fatality
Major Loss >$5M
Containment
Likely Permanent
Significant Damage
Significant Loss of
B
Disability
Loss $500k to $5M
Containment
> 100bbl, Limited
ability to control
Moderate Damage
Significant Loss of
C
Hospital Stay
Loss $100k to
Containment
$500k
> 100bbl only
Workplace affected
DAFWC /
Restricted Work
Minor Loss of
D
Case / Medical
Minor Loss $10k to
Containment
Treatment / First
$100k
< 100bbl only
Aid
Workplace affected
E
Simple First Aid
Loss <$10k
Slight Loss of
Injury
Containment < 1bbl
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 39 of 41
Dated: September, 2004
Originating Dept: HSE
PROBABILITY GUIDELINES (P)
RATING
Will occur more than once per quarter
HIGH
OR
(H)
nearly every time
Will occur at least once per year, but less than quarterly
MEDIUM
OR
(M)
sometimes
Will occur less than once per year
LOW
OR
(L)
hardly ever
HAZARD EFFECT
A
B
C
D
E
H
15
14
13
9
4
M
12
11
10
5
3
L
8
7
6
2
1
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 40 of 41
Dated: September, 2004
Originating Dept: HSE
APPENDIX E: RISK ASSESSMENT FLOWPATH
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Task Risk Assessment
Doc No: UNIF-HSE-PRO-105-C2
Procedure
Rev No: C2
Page 41 of 41
Dated: September, 2004
Originating Dept: HSE
APPENDIX F: RISK HIERARCHY EXAMPLES
Examples
1. Elimination / Prohibition
Use of mechanical device instead of manual
handling
Maximum stacking height
Unauthorised personnel
Prohibit smoking, jewellery, mobile phones
2. Substitution
Solvent-based paint with water-based paint
Dusty powders with pastilles or pellets
Electric hand tools with compressed air
Reduction in size or weight of item
3. Engineering Controls
Local exhaust ventilation for e.g.:
-
Welding
-
Soldering
-
Grinding
Mechanical or electrical isolations
Lighting
Enclosure, e.g.:
-
Sealable containers
-
Noise enclosures for turbines or pumps
4. Segregation
Barrier or guard
Separate storage areas
Physical isolations (spade, lock-off)
Access controls
5. Reduction in Personnel or
Job or shift rotation
Time Exposure
Breaks
Hazardous work carried out at low activity
periods such as nights or weekends
Dispense dilute chemical
Increase airflow through work area
Automated feed process instead of manual
6. Personal Protective
Gloves
Equipment
Goggles
Face mask
Boots
Respiratory protective equipment
Chemical suits or gauntlets
Safety harness or inertia reel
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 30/09/2005
Print Date: 24/07/2010
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 2 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 3 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
AZERBAIJAN BUSINESS UNIT
Formatted
(AzBU)
Formatted
Procedure for:
Energy Isolation - Electrical
Issued for
C2
26.08.04
EFWG
Yvonne Hepburn
Simon Rollason
Gary Campbell
use
Rev
Date
Reason for
Prepared by
Checked by
Approved by TA
Endorsed by
Issue
Notes:
HSE - SAFETY
Azerbaijan BU Document Reference
Asset Code
Dept Code
Document Type
Sequence No
Revision Code
UNIF
HSE
PRO
106
C2
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 4 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
TABLE OF CONTENTS
Formatted
Formatted
1
Purpose
4
2
Scope
4
3
Roles and Responsibilities
4
3.1
Electrical Functional Work Group
4
3.2
OIM/Site Manager /Site Controller
4
3.3
Area Authority (AA)
4
3.4
Isolating Authority (IA)
4
3.5
Performing Authority (PA)
4
3.6
Responsible Electrical Person (REP)
5
3.7
Electrical Technical Authority
5
3.8
Senior Authorized Electrical Personnel (SAEP)
5
3.9
Authorized Electrical Personnel (AEP)
5
3.10
Authorized Instrument Personnel (AIP)
5
3.11
Competent Isolator (CI)
5
3.12
Competent Person (CP)
6
Within BP this process is managed using CMAS
6
4
Self-regulation and Audit
6
5
Isolating Authority - Training, Competency and Authorization
6
6
Modification and New Facilities
6
7
Isolation and Planning
7
7.1
Isolation
7
7.2
Isolation Planning
7
7.3
Switching Programmes
8
7.4
Isolation Methods
8
7.5
Isolation Standards
9
7.6
Risk Assessment of Non-compliant Isolations
10
7.7
Live Working
10
7.8
Isolations for Work Near Live Conductor
11
8
Isolation Implementation and Control
11
8.1
Security
11
8.2
Isolation Tagging
11
8.3
Positive Identification of Equipment
12
8.4
Control of Isolations
12
8.5
Operational Locks
12
8.6
Boundary Isolations
13
8.7
Long-term Isolations
13
8.8
Personal Isolations
14
8.9
Testing Isolation Integrity - Proving Dead
14
8.10
Monitoring Isolation Integrity
15
9
De-isolation of Plant
15
10
Flowsheet Electrical Isolations
16
11
Abbreviations and Definitions
17
12
References
17
13
Appendices
18
13.1
Appendix A - Applicable to
18
13.2
Appendix B - Adjacent Working Assessment
19
13.3
Appendix C - Switching Programme
21
13.4
Appendix D - Operational Locking System
22
13.5
Appendix E - Control of Electrical Work
23
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 5 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
1 Introduction
63
Formatted
2 Roles and Responsibilities
63
3 Self-regulation and Audit
96
4 Isolating Authority - Training, Competency and Authorisation
106
5 Modification and New Facilities
107
6 Isolation and Planning
117
7 Isolation Implementation and Control
1712
8 De-isolation of Plant
2517
9 Flow Sheet Electrical Isolations
2618
Appendix A: Abbreviations and Definitions
2919
Appendix B
3120
Appendix C: Adjacent Working Assessment
3221
Appendix D: Switching Programme
3623
Appendix E: Operational Locking System
4024
Appendix F: Control of Electrical Work
4125
Appendix G: Labels
26
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 6 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
1
Introduction
1.1
Purpose
The purpose of this document is to define thea Azerbaijan Business Unit BP Caspian
Formatted
functional standard for the safe isolation of electrical plant or equipment from sources
of electrical energy.
21.2 Scope
Formatted: Bullets and Numbering
This document applies to the electrical isolation of equipment for work. It shall be
Formatted
followed at all Azerbaijan Business UnitBP Caspian operated sites and is applicable
to both onshore and offshore.
Formatted
1.3
SSOW Specific Cross references
Document No
Title of Procedure
Formatted
UNIF-HSE-PRO-104
Procedure for: Authorization
Formatted
UNIF-HSE-GLN-106
Guideline for: Electrical Safety
UNIF-HSE-PRO-103
BU PTW Process
Risk Assessments (Level 2 risk assessment)
UNIF-HSE-PRO-105
Work Site Risk Assessment
UNIF-HSE-PRO-107
Energy Isolation-Process
32
Roles and Responsibilities
Formatted: Bullets and Numbering
3.12.1 Electrical Functional Work Group
Formatted: Bullets and Numbering
The Electrical Functional Work Group
(EFWG) has produced this document to
Formatted
support the safe system of work. The Document Technical Authority will issue any
new revisions of the document for approval.
2.2
3.2OIM / Site Manager / Site Controller
Formatted: Bullets and Numbering
The OIM / Site Manager / Site Controller is responsible for ensuring that those
Formatted
performing the roles of Area Authority, Responsible Electrical Person, Isolation
Authority and Performing Authority are competent to do so. The OIM / Site Manager
/ Site Controller is responsible for authorizing any deviations from the isolation
standard through the risk assessment process. In doing so, he/she may choose to
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 7 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
defer or not to carry out the activity and seek further technical guidance if the residual
risk is perceived to be excessive.
The OIM / Site Manager / Site Controller is also responsible for ensuring that plant
and equipment isolations are subject to the appropriate level of self-regulation and
audit.
2.3
3.3Area Authority (AA)
Formatted: Bullets and Numbering
The Area Authority is responsible for approving the isolation design, providing
Formatted
assurance that the design achieves the highest quality of isolation reasonably
practicable. He/she can delegate the detailed isolation design to an appropriately
competent or authorized person. The Area Authority is then responsible for
authorizing the work to proceed under appropriate controls. This includes approval
of any preparatory work and, on completion of the task, the work required to
complete reinstatement.
2.4
3.4Isolating Authority (IA)
Formatted: Bullets and Numbering
The Isolating Authority is responsible for design of an electrical isolation when
Formatted
requested
by
the
Area Authority. He/she is then responsible for safely isolating a specific section of
plant
or
items
of equipment to the highest quality and security of isolation, which is reasonably
practicable.
The Isolating Authority is also responsible for demonstrating the integrity of the
isolation to the Performing Authority. The Isolating Authority will be authorized to the
maximum voltage level required for the isolation.
2.5
3.5Performing Authority (PA)
Formatted: Bullets and Numbering
The Performing Authority is the person charged with the responsibility of carrying out
Formatted
the work and has the right to request demonstration of the integrity of any isolation.
The Performing Authority will be a competent person. The Performing Authority will
ensure that they have witnessed, at the point of work, that the conductors are dead.
The Performing Authority may complete this task themselves if suitably authorized.
2.6
3.6Responsible Electrical Person (REP)
Formatted: Bullets and Numbering
This is a role under the safe system of work or permit to work system to clearly
Formatted
identify which authorized person, has the responsibility for the electrical system, the
REP is nominated by the OIM / Site Manager / Site Controller from the those persons
having the highest level of authorization required for that site.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 8 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
The REP will :
 Approve any switching programs
 Countersign permits with electrical content where the Area Authority isn‟t
electrically competent, ensuring that the isolation has been correctly designed
and the Isolating Authority has the appropriate authorization level for the work
AThe REP will assess and recommend site personnel for authorization to
AEP, AIP, CI
At any one time there can be only one REP on site. The REP may also be the
Formatted
isolating authority.
2.7
3.7Electrical Technical Authority (ETA)
Formatted: Bullets and Numbering
The Electrical Technical Authority is an Electrical Engineer who is recognized by
Formatted
management as the site technical authority. The technical authority or their delegate
assesses and recommends site personnel for authorization to SAEP and will assess
and recommend personnel for the role of REP.
2.8
3.8Senior Authorized Electrical Personnel (SAEP)
Formatted: Bullets and Numbering
Electrical personnel who have been formally assessed by the site Electrical
Formatted
Technical Authority and authorized by the OIM / Site Manager / Site Controller to
switch, isolate and test electrical equipment with voltage levels up to and greater than
1000V,. cCan act as an isolating authority under the safe systems of work for
electrical systems with voltage levels up to and greater than 1000V.
2.9
3.9Authorized Electrical Personnel (AEP)
Formatted: Bullets and Numbering
Electrical personnel who have been formally assessed by the site REP and
Formatted
authorized by the OIM / Site Manager / Site Controller to switch, isolate and test
electrical equipment with voltage levels less than 1000V,. Ccan act as an isolating
authority under the safe systems of work for electrical systems with voltage levels
less than 1000V.
3.102.10
Authorized Instrument Personnel (AIP)
Formatted: Bullets and Numbering
Instrument personnel who have been formally assessed by the site REP and
Formatted
authorized by the OIM / Site Manager / Site Controller to switch, isolate and test
control, instrument and telecom equipment with voltage levels less than 50V.
, cCan
act as an isolating authority under the safe systems of work for control, instrument
and telecom systems with voltage levels less than 50V phase to earth.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 9 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
2.11
3.11Competent Isolator (CI)
Formatted: Bullets and Numbering
In special circumstances individuals can be assessed as competent isolators by the
Formatted
site REP and authorized by the OIM / Site Manager / Site Controller for specific items
of equipment providing that they have completed the formal training and have been
assessed as competent.
2.12
3.12Competent Person (CP)
Formatted: Bullets and Numbering
An essential requirement for persons undertaking electrical work is that they are
Formatted
competent, this established bye virtue of training and or experience. A competent
person is capable of recognising danger and knows when to seek guidance when the
work falls outside their area of competence.
The employing company will certify competency of the employee and will supply BP
with copies of their competence assessment as required. The
Within Azerbaijan Business UnitBP certifies the competence of its own employees
using this process is managed using CMAS.
3
Self - regulation and Audit
Formatted
Formatted
Formatted
4Self-regulation and Audit
Formatted: Bullets and Numbering
Business Units shall periodically review isolation related activities, including review of
Formatted
individual isolations and review of overall isolation processes. Such reviews may
also include:
 General compliance with this document and any local procedures
 The assessment of non-compliant isolations and the extent of any approved
deviations
 Registers of competent and authorized persons
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 10 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
54
Isolating Authority - Training, Competency and Authoriszation
Formatted
The Isolating Authority will be authorized by OIM / Site Manager / Site Controller
Formatted
based on the following criteria.
Formatted: Bullets and Numbering
Formatted
The Isolating Authority will be:
 Familiar with the site
 Have Electrical First Aid Training
 Will be EX certified, when working on Hydrocarbon Plants
 Where appropriate, will have HV operational training
 Will have been formally and practically assessed for electrical isolations and
recognised as authorized at a specific voltage level for the work site
 The Authorisation levels on site will be as follows:
 Authorised Instrument Person (AIP) authorised to isolate instrument circuits up to
50Vac
 Authorised Electrical Person (AEP) authorised to isolate electrical circuits up to
1000V
 Senior Authorised Electrical Person
(SAEP) authorised to isolate electrical
systems above 1000v and prepare and carry out switching operations
In special circumstances individuals can be assessed as Competent Isolators (CIs)
Formatted
for specific items of equipment providing that they have completed the formal training
and have been assessed as competent on the specific tasks. Site management is
responsible for ensuring that this is recorded so that it is clear which tasks these
individuals are competent to undertake.
5
Modification and New Facilities
Formatted
6Modification and New Facilities
Formatted: Bullets and Numbering
In relation to existing Installations and sites:
Formatted
 The design of all modification and new facilities shall include a review of the
provision of means of isolation for maintenance to ensure compliance with this
document
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 11 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
 Such reviews shall address both isolations within the modified/new facilities and
any opportunities to upgrade existing isolation facilities where these are
inadequate
New isolators supplied as part of a modification or as a replacement shall be
Formatted
provided with a facility to be locked off.
76
Isolation and Planning
Formatted: Bullets and Numbering
Formatted
7.16.1 Isolation
Formatted: Bullets and Numbering
The highest quality and security of isolations, which is reasonably practicable in the
Formatted
prevailing circumstances, shall always be used. This document sets out the
minimum recommended isolation standard to be used in the Azerbaijan Business
Unit.Caspian
Any isolation, which does not meet the Minimum Recommended Isolation Standard
as defined in section 76.5, including the application of the Mandatory Safeguards,
Formatted
must be assessed using the Level 2 Risk Assessment Process before the isolation is
approved. Should any non-compliant isolation have to be repeatedly justified by risk
assessment, consideration shall be given to a permanently engineered solution.
All key participants in the implementation of the BP Isolations Policy shall be trained
and assessed as competent to the appropriate level in the Electrical Isolation
Standard.
An audit programme shall be established by the OIM / Site Manager / Site Controller
at each site to ensure that regular checks are made on isolations to provide
assurance that the isolations policy and standards are being applied and that lessons
learned are communicated effectively.
6.2
7.2Isolation Planning
Formatted: Bullets and Numbering
Isolation of any piece of equipment shall be planned to minimize risk to personnel,
Formatted
production and property. To achieve this the following information will be required:
 A clear description of the work, ensuring that if the activity includes electrical work
that this is clearly identified
 A clear description of the equipment which needs to be isolated, this will include
the Plant Tag Number and the Plant Tag Description
 A drawing identifying the isolation, earth and disconnection points where this is not
obvious
 Tag references of all the switching and isolation points
 Locks and Labels for securing the isolation points
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 12 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
 Test equipment for proving effectiveness of the isolation
 Switching program detailing the sequence of switching required to achieve the
isolation where the equipment is fed from more than one source or at the REP‟s
discretion.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 13 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
7.36.3 Switching Programmes
Formatted: Bullets and Numbering
Where main distribution equipment is to be switched it is essential that the equipment
Formatted
isbe
switched
in
the correct sequence. To achieve this, a switching programme will be required,
detailing the switching sequence. This will be accompanied by a marked up single
line drawing. The switching programme will be prepared by an SAEP and checked
by the REP. Where the REP is alone on site, the site electrical technical authority
will check the switching program. Technical advice will be sought as required.
See Appendix DC for a blank Switching Programme. The Switching Programme
Formatted
does
not
replace
an ICC.
7.46.4 Isolation Methods
Formatted: Bullets and Numbering
The highest quality of isolation, which is reasonably practicable, shall be applied to
Formatted
every individual isolation point. The methods of isolation normally available are
detailed below; listed in decreasing descending order of security and effectiveness.
Key to all of these isolations is the positive identification of the equipment to be
isolated, to this end all equipment and isolation points on a site will be uniquely
identified and clearly labeledlabelled, a secondary check could be to use the cable
numbers which connect the isolator to the equipment. If there is any doubt about the
correct identification of the equipment to be isolated and the isolation point then the
work should be suspended and clarification sought.
(a)
Isolate Circuit, Prove Dead, Disconnect, Lock, Label and Earth
This is a positive isolation of the main phase conductors with an isolator and
Formatted
disconnection of the main phase and neutral conductors by removal of fuses,
links or withdrawal of a circuit breaker or some other means of disconnection. In
addition, tThe circuit is earthed proven dead to ensure that the circuit is
discharged and isis earthed to prevent recharging maintained at earth potential.
Locks and labels are applied to all points of isolation and earthing
Note: When the isolation requires switching of main distribution equipment, a
Switching Program is also required.
(b)
Isolate Circuit, Prove Dead, Disconnect, Lock and Label
Formatted
This is a positive isolation of the main phase conductors with an isolator and
Formatted
disconnection of the main phase and neutral conductors by removal of fuses,
links or withdrawal of a circuit breaker or some other means of disconnection.
The circuit is proven dead to ensure that the circuit is discharged. Locks and
labels are applied to all points of isolation.
Note: Where the isolation switch meets the minimum standard for
Formatted
disconnection, as defined in IEC 60947, and it includes all phases and
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 14 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
neutral then no further disconnection is necessary if the risk of physical
disconnection outweighs the advantage. However, this is a minimum
standard and it is expected that if fuses or links are part of the circuit that
they will be removed.
(c)
Isolate, Lock and Label
Formatted
Formatted
This is a positive isolation of the main phase conductors with an isolator; the
isolator type will be of such construction that it breaks the main phase
conductors when open. Locks and labels are applied to all points of isolation.
Note: Isolation by auxiliary control circuits only is not acceptable for isolation
Formatted
purposes.
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 15 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
7.56.5 Isolation Standards
Formatted: Bullets and Numbering
Operating Voltages
Isolation requirements for
<50V
>50V < 1000V
>1000V
Non-electrical work only
N/A
Is+LL
Is+LL
Electrical work on single circuit
Is+P+D+Label
Is+P+D+LL
Is+P+D+LL+E
Electrical work on distribution
system
N/A
SP+Is+P+D+LL
SP+Is+P+D+LL+E
Note 1: If any work requires Proving Dead in a Hazardous Area, a gas monitor will be
required with a Hot Work 2 (Spark Potential) Permit.
Note 2: If any work is done adjacent to live conductors then this must be considered
when providing the isolation.
Is - Isolation of the main phase conductors with an isolator
LL - Lock and labeledlabelled
D - Main phase and neutral conductors disconnected
P - Prove dead with an approved voltage tester which is proved before and after testing
E - Earth the isolated conductors
SP - Authorized Switching Programme
Precautions
<50V
>50V < 1000V
>1000V
SAEP or AEP
under direct
Authorisation level required to
AIP, AEP,
supervision of
perform the isolation
SAEP
AEP, SAEP
SAEP
Accompanied for proving dead,
AEP, SAEP
distribution switching, testing,
based on Risk
fault finding
No
assessment
SAEP
Communications link
Yes
Yes
Yes
Nomex gloves or leather
gauntlets
No
Yes
Yes
Note 3: If work is to be accompanied there must be a clear understanding between the
Isolating Authority and the accompanying person identifying what the
accompanying person will do in the event of an emergency.
Table 1 Minimum Recommended Isolations Standard
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 16 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
7.66.6 Risk Assessment of Non-compliant Isolations
Formatted: Bullets and Numbering
In the event that the Minimum Recommended Isolation Standard cannot be
Formatted
achieved, a Risk Assessment shall be carried out in accordance with SSOW
guidelines
The assessment team, including the REP shall specify appropriate safeguards, which
may
replace
or
be
in
addition
to
those listed in Table 1. The team shall be satisfied that these safeguards shall
reduce the risks to an acceptable level before the task requiring isolation is permitted
to proceed.
The OIM / Site Manager / Site Controller must authorize all level 2 risk assessments
prior to any work proceeding.
7.76.7 Live Working
Formatted: Bullets and Numbering
Live working is defined as work on or in close proximity to live conductors; this
Formatted
includes
testing.
All conductors will be assumed live unless proven dead.
(See section 8.9 for
guidelines
for
proving dead.)
Live work will not be a normal activity and will not be carried out unless there is no
other reasonably practicable method available. Where it is not possible to avoid live
work, an appropriate level of risk assessment shall be carried out before work
commences.
Is the live working justified? Consider:
 If the work could be done when equipment is isolated (an example of work which
must be done live would be work on battery systems)
 If isolating the equipment introduces other greater safety risks
When Iidentifyingication theof Rrisks consider? Consider:
Formatted: Bullets and Numbering
 Voltage level working on
 Fault level of the equipment and the arc energy if a fault develops while working
 Working environment (wet, dusty, noisy, vibration, at height etc)
 What exposed voltage levels will be adjacent to the worksite
 What could go wrong
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 17 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
Can adequate precautions be taken to reduce risk to an acceptable level? Some
Formatted
precautions whichprecautions, which should be considered:
 Competent people with training and experience
 Insulated tools and test equipment
 Accompanied work - /Accompanying person to be First Aid Trained /Itand it should
be clear what is expected of the accompanying person to ensure that they are
competent to accomplish this expectation
Insulated barriers, mats, grab hooks
Formatted: Bullets and Numbering
Work site control (ege.g. cordoning off area, limiting access)
Formatted: Bullets and Numbering
Additional and / or specialist personal protective equipment
Formatted: Bullets and Numbering
Reference to any specific safety rules or guidance
Formatted: Bullets and Numbering
See Appendix EF for a flowchart covering the Control of Electrical Work.
Formatted: Bullets and Numbering
Formatted: Bullets and Numbering
7.86.8 Isolations for Work Near Live Conductor
Frequently, work inside of complex control equipment means that although the circuit
Formatted
to be worked on is isolated, there may be other circuits that are still energised. It is a
requirement that the risk from these adjacent conductors is assessed and
appropriate precautions taken to reduce the risk.
See Appendix CB for an adjacent working assessment form.
Formatted
87
Isolation Implementation and Control
Formatted: Bullets and Numbering
8.17.1 Security
Formatted: Bullets and Numbering
Any isolation must effectively disconnect the worksite from all sources of energy.
Formatted
Locks must be used to prevent unauthorized de-isolation; to this end unique locking
devices must be used. Keys to any locks used for isolation purposes must be
effectively controlled via the Area Authority and the Permit to Work
- Isolation
Confirmation Certificate (ICC). Only when the ICC allows should the Area Authority
make the key available to remove a lock.
The locks should be a high security type which are tamper proof.
See appendix E
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23
Title: Energy Isolation -
Doc No: UNIF-HSE-PRO-106-C2
Formatted
Electrical
Rev No: C2
Page 18 of 45
Formatted
Dated: August, 2004
Originating Dept: HSE
Formatted
CASPIAN REGION: Electrical Isolation Standard
Formatted
UNIF-HSE-PRC-001
Formatted
Formatted
7.2
Isolation Labelling
Formatted
8.2Isolation Tagging
Formatted: Bullets and Numbering
All isolation points shall be clearly identified, tagged and recorded on the ICC.
Where
not
obvious,
a drawing should be attached to the ICC showing the location of each isolation and
earth
point
(where applied).
At the isolation point there should be a Yellow Isolation Label with the following
clearly identified:
ICC number
Formatted: Bullets and Numbering
ICC point number
 The Tag number of the isolation point
 Reason for isolation
 Isolation Authority name and signature
 Date
 At the Earth point there should be a Green Earth Label with the following clearly
identified:
ICC number
Formatted: Bullets and Numbering
ICC point number
 The Tag number of the isolation point
 Reason for isolation
 Isolation Authority name and signature
 Date
Adjacent live circuits will be identified with a Red Danger notice, e.g. live bus bar
Formatted
shutters when work is to be carried on the circuit.
See Appendix G for labels
Formatted
The controlled version of this document can be found at: http://baku.bpweb.bp.com/dep/hse/safe/
Next Revision Date: 01/12/2005
Print Date: 24/07/201015/11/2004
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING
Created on 04/02/2004 14:05
Page 15 of 23

 

 

 

 

 

 

 

Content      ..     4      5      6      7     ..