Military reference books and manuals (2009-2023, Volume 4) - page 40

 

  Index      Manuals     Military reference books and manuals (2009-2023, Volume 4)

 

Search            copyright infringement  

 

   

 

   

 

Content      ..     38      39      40      41     ..

 

 

 

Military reference books and manuals (2009-2023, Volume 4) - page 40

 

 

Procedure for Hydrogen Sulphide
Page 2 of 14
TABLE OF CONTENTS
1.
PURPOSE / SCOPE
3
1.1
PURPOSE
3
1.2
SCOPE
3
2.
DEFINITIONS
3
3.
GENERAL REQUIREMENTS
4
3.1
BP AZSPU REQUIREMENTS
4
3.2
LEGISLATION & STANDARDS
4
3.3
STOPPING UNSAFE WORK
4
3.4
DEVIATIONS
4
3.5
LANGUAGE FACILITATION
5
4.
RESPONSIBILITIES
5
4.1
SITE MANAGER (SM) / SITE CONTROLER (SC) / OFFSHORE INSTALLATION MANAGER (OIM)
5
4.2
AREA AUTHORITY (AA)
5
4.3
HSE MANAGER
5
4.4
HS&E ADVISORS
5
5.
HYDROGEN SULPHIDE HEALTH & SAFETY REQUIREMENTS
6
5.1
HYDROGEN SULPHIDE DESCRIPTION
6
5.1.1
Where Hydrogen Sulphide Can Occur
6
5.1.2
Properties and Characteristics of Hydrogen Sulphide
6
5.1.3
Toxicity
6
5.1.4
Corrosiveness
7
5.1.5
Pyrophoric Scale
7
5.2
SHYDROGEN SULPHIDE DETECTION KNOWN H2S AREAS
8
5.2.1
Known H2S Areas
8
5.2.2
Hydrogen Sulphide Fixed Detection System
8
5.2.3
Hydrogen Sulphide Portable Detection Equipment
8
5.2.4
Areas Not Currently Producing H2S
9
5.2.5
Other Areas
9
5.3
HYDROGEN SULPHIDE PRECAUTIONS
9
5.3.1
Classification of H2S Risk Areas
9
Warning: Notices warning of the presence of H2S and stipulating access requirements must be posted at
the perimeter of medium and high-risk areas, and at every access point
9
5.3.2
Breathing Apparatus Training
10
5.3.3
Contingency Planning
10
5.3.4
Planning for a Hydrogen Sulphide Release
11
5.3.5
Training of Personnel
11
5.3.6
Monitoring the Presence of H2S
12
5.4
HYDROGEN SULPHIDE FIRST AID
12
6.
DOCUMENTS REFERENCES
12
APPENDIX A: CLASSIFICATION OF PHYSIOLOGICAL RESPONSES TO HYDROGEN
SULPHIDE
13
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 3 of 14
1.
PURPOSE / SCOPE
1.1
PURPOSE
This Safe System of Work contains the information and guidelines necessary to assist in
reducing the risks encountered when working with Hydrogen Sulphide to as low as
reasonably practicable.
1.2
SCOPE
The contents of this procedure are applicable to all BP owned and managed sites /
installations in Azerbaijan and Georgia. Contractors working on BP owned or managed
sites / installations are also responsible for alignment with this procedure.
This document does not replace the procedures prepared and adopted by specialist
contractors. Neither does it supersede any national regulatory requirements.
This procedure contributes to compliance with Group Control of Work (CoW) standard that
the Hazards associated with BP activities are identified and that the risks are assessed and
managed.
All guidelines contained shall be regarded as the minimum requirements for BP owned or
managed sites / installations in Azerbaijan and Georgia.
The scope covers defined activities of BP and Contractors at all BP AzSPU sites and
installations.
For detailed procedures to be followed during drilling, well testing and well servicing
operations, refer to the BP Drilling Operations Guidelines (EUR-D-001), Hydrogen Sulphide
(H2S) Procedures.1120/GEN.
2.
DEFINITIONS
Refer to document AzSPU-HSSE-DOC-00021-2 HSE Definitions for definitions common to
this Procedure. Definitions specific to the Procedure are included below.
SM
Site Manager
SC
Site Controller
OIM
Offshore Installation Manager
AA
Area Authority
PA
Performing authority
TRA
Task Risk Assessment
H2S
Hydrogen Sulphide
PSA
Production Sharing Agreement
ALARP
As Low as Reasonably Practicable
CoW
Control of Work
UTG
Upstream Technology Group
SRB
Sulphate Reducing Bacteria
PPM
Parts Per Million
Mg/l
Milligrams Per Litre
LEL
Lower Explosive Limit
AGT
Authorised Gas Tester
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 4 of 14
ERT
Emergency Response Team
OES
Occupational Exposure Standard
LTEL
Long Term Exposure Limit
STEL
Short Term Exposure Limit
TWA
Time Weighted Average
3.
GENERAL REQUIREMENTS
3.1
BP AZSPU REQUIREMENTS
It is a company requirement that all tasks are subjected to an assessment of risk to
demonstrate that risks have been reduced to as low a level as reasonably practicable
(ALARP). This can be achieved by complying with the BP existing standards. Where
compliance with BP standards cannot reasonably be achieved, a formal level 2 Risk
Assessment will be undertaken to identify any additional controls and demonstrate that
risks remain as low as reasonably practicable, whether by compliance with BP Standards
or through level 2 Risk Assessment.
- Operating Management System OMS Essentials 3.2.1 and 4.5.1
3.2
LEGISLATION & STANDARDS
This procedure complies with applicable national law. Applicable national law is national law
as amended by project specific agreements, e.g. the ACG Production Sharing Agreement
(PSA), and relevant International Conventions, if any, in force in Azerbaijan or Georgia, as
applicable.
In the absence of national legislation, or where national legislation is inconsistent with the
requirements of project specific agreements, BP Group Standards or applicable
requirements from UK or US legislation will be complied with.
Where requirements conflict, legal advice has been obtained and a defendable compliance
position adopted.
The standards and practices contained in this procedure are consistent with those
internationally recognized within the petroleum industry.
3.3
STOPPING UNSAFE WORK
To stop the continuation of potentially unsafe work at the earliest possible stage, the
Control of Work (CoW) Policy and this procedure for Hydrogen Sulphide make it very clear
that all personnel are obliged and have the authority to “STOP” the work that they consider
to be unsafe.
3.4
DEVIATIONS
This procedure is written in sufficient detail that it should be able to be applied consistently
at all sites / installations. There may still be the requirement for some local rules covering
site
/ installation specific logistical/administrative arrangements and local variations in
responsibilities to reflect differences in organisational arrangements. These local rules
should not deviate from the core processes within this document. Any form of deviation
from this procedure, including but not limited to local rules, shall be requested and
authorised in accordance with SSOW, Deviations from Regulations and Procedures (Doc.
No: AZSPU-HSSE-DOC-00011-2).
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 5 of 14
3.5
LANGUAGE FACILITATION
Due to the various languages spoken at sites / installations, there is a necessity to assist all
with “an ease of understanding”.
4.
RESPONSIBILITIES
4.1
SITE MANAGER (SM) / SITE CONTROLER (SC) / OFFSHORE INSTALLATION MANAGER
(OIM)
The Site Manager / Site Controller / Offshore Installation Manager shall be responsible and
accountable for the application of this procedure in his area of responsibility. He shall
ensure:
 That adequate number of Competent responsible persons are appointed to manage
and maintain the requirements of this procedure
 The assessment and management of health risks on the site / installation
 Review of Risk Assessment findings and recommendations
 Systems are in place to implement and track the actions resulting from the Risk
Assessment
 Sufficient monitoring systems and equipment is in place and there is adequate
equipment available on site e.g. BA.
 Such mechanisms are in place to communicate the findings, recommendations and
requirements of the Hydrogen Sulphide Risk Assessment to all relevant personnel
(including contractors, visitors, etc).
4.2
AREA AUTHORITY (AA)
Area Authorities shall ensure that:
 Hydrogen Sulphide Risk Assessments are carried out before any related tasks are
undertaken or begun where H2S may be present
 Personnel working under their supervision are aware of the risks involving Hydrogen
Sulphide and are aware of the necessary precautions.
 Personnel working under their supervision are trained in the use of monitoring
devices and other protective systems.
4.3
HSE MANAGER
The HSE Manager is responsible for:
 Maintaining this Safe System of Work
 Ensuring Company training programmes comply with the requirements of this Safe
System of Work
4.4
HS&E ADVISORS
HS&E Advisors are responsible for providing technical support, guidance and advice,
whenever required.
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 6 of 14
5.
HYDROGEN SULPHIDE HEALTH & SAFETY REQUIREMENTS
5.1
HYDROGEN SULPHIDE DESCRIPTION
5.1.1 Where Hydrogen Sulphide Can Occur
Hydrogen Sulphide can occur naturally:
 In crude oil and gas
 During the decomposition of organic materials, including sewage
 In de-oxygenated seawater, which encourages the growth of Sulphate Reducing
Bacteria (SRB)
In addition, Hydrogen Sulphide can be produced as a by-product:
 While processing hydrocarbons that contain Sulphur
 From the chemical action of acids on metallic sulphides; for example, during the
chemical cleaning of equipment containing Iron Sulphide deposits.
H2S is generated by bacteria in seawater, which thrives in conditions of oxygen deficiency
and, together with organic materials as a nutrient, reduces the sulphate in seawater to
hydrogen sulphide
5.1.2 Properties and Characteristics of Hydrogen Sulphide
Principle characteristics of H2S are:
 Highly toxic, colourless, flammable gas which, in relatively low concentrations, can
quickly cause unconsciousness
 Approximately 20% denser than air and therefore can accumulate in depressions
around an area where the gas is present
 Has an auto-ignition temperature of 260o C, is flammable in the range of 4.3% to
45% volume in air and burns with a blue flame to produce sulphur dioxide, which is
also toxic
 Is highly corrosive to certain metals. In particular, materials containing copper should
never be used due to the possibility of an explosive reaction with H2S
 In air, concentrations are measured in parts per million (ppm) on a volume-to-volume
basis. In water, concentrations are measured in milligrams per litre (mg/I)
5.1.3 Toxicity
Warning: Hydrogen Sulphide is highly toxic and can cause unconsciousness and
death at quite low concentrations.
Hydrogen Sulphide is an irritant and an extremely toxic gas, between five and six times as
toxic as Carbon Monoxide. After exposure to Hydrogen Sulphide, symptoms usually begin
immediately:
Lower level exposure causes irritation of the eyes, nose and throat
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 7 of 14
Moderate exposure levels can cause headaches, dizziness, nausea and vomiting
as well as coughing spasms and breathing difficulties within 15 minutes
Higher exposure levels can cause shock, convulsions, coma, and damage to the
heart, brain damage and death.
Very low concentrations of Hydrogen Sulphide can be detected by the offensive odour of
rotten eggs. However, personnel working in areas where Hydrogen Sulphide is present
may become accustomed to the smell because prolonged and repeated exposure will
cause the sense of smell to tire (not being able to smell it, may mean that concentration of
H2S has increased, not decreased). Higher concentrations of Hydrogen Sulphide can
paralyse the sense of smell immediately and cause rapid loss of consciousness. Death
may result within minutes unless the casualty is moved to fresh air and resuscitated.
5.1.4 Corrosiveness
Hydrogen Sulphide is highly corrosive, especially in association with moisture or oxidizing
gases such as Oxygen and Carbon Monoxide. Iron and steel are particularly vulnerable.
Corrosion mechanisms associated with Hydrogen Sulphide include:
 General corrosion
 Pitting
 Crevice corrosion, including Sulphide Stress Corrosion Cracking which can lead to
sudden and catastrophic failure
 Hydrogen induced cracking, also known as hydrogen embrittlement
Any equipment likely to be exposed to Hydrogen Sulphide must be made of appropriate
materials, constructed and operated to take account of these corrosion problems.
5.1.5 Pyrophoric Scale
Carbon steel lines and equipment that carry gas or liquids containing hydrogen sulphide
may develop a layer of pyrophoric scale (iron sulphide) on their internal surfaces. When
these lines or equipment are opened up to atmosphere, oxygen from the atmosphere will
react with the pyrophoric scale to produce spontaneous burning. If hydrocarbons or other
combustible substances are present during this reaction, an explosion may result.
Warning: A by-product of this oxidising process is Sulphur Dioxide, which is also
toxic.
Whenever such lines and equipment are opened up to atmosphere, their internal surfaces
should be doused thoroughly with water or blanketed by steam in order that any pyrophoric
scale is rendered harmless.
Warning: Equipment and pipe work that has been on sour-gas duty (i.e. contains
more than 0.5% by weight of H2S) should only be opened in one place at
a time unless the pyrophoric scale has been thoroughly wetted. Opening
the system in more than one place can cause through drafts capable of
igniting the scale.
If the introduction of water is not permissible, either due to corrosion potential or the risk of
freezing, a nitrogen purge followed by a further purge with a mixture of 5% oxygen in
nitrogen will allow controlled oxidation.
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 8 of 14
Pyrophoric scale that has been removed from lines and equipment shall be placed in a
drum and immediately covered with water. It must then be disposed of by:
 Burying or burning in a suitable area as determined by legislation
(onshore
situations)
 Slurrying with water and storing in sealed drums, clearly marked „PYROPHORIC
SCALE‟, and manifested as dangerous goods and sent onshore (offshore situations).
Apart from the hazards to personnel, H2S also poses a risk of sulphide corrosion and
hydrogen embrittlement to metals. Protection methods for metals are detailed in BP
Hydrogen Sulphide Technical Safety Aspects Guidance Note GN 91/30 (refer to BP
Engineering Standard GS 136-1.
5.2
SHYDROGEN SULPHIDE DETECTION KNOWN H2S AREAS
5.2.1 Known H2S Areas
In cases where H2S is known to be present or may be present in well fluids, appropriate
measures shall be provided to prevent exposure of personnel to this hazard.
Procedures, especially those relating to breaking of containment, confined space entry and
gas testing, shall be the principle means of protecting personnel. Portable instruments may
be used together with procedures to monitor potential hazards in which personnel are
present.
The personnel using and relying on the detection equipment shall be trained in its use.
5.2.2 Hydrogen Sulphide Fixed Detection System
Note: It is BP policy that the protection of site personnel is primarily achieved by
the safe working practices defined in this document, not by the use of fixed
detectors. However, fixed detection methods may be installed for other
reasons.
Areas where an accumulation of H2S is possible may be monitored by use of fixed
detectors that react to H2S and give early warning of its presence. However, these should
not be relied on to prove the area is clear of an H2S hazard. Personnel should not approach
an area where such a suspected release has taken place unless they are wearing self-
contained breathing apparatus.
Warning: There may also be a risk of ignition and explosion in such a scenario; if the lower
explosive limit (LEL) for H2S or the LEL of other process gases has been reached or
exceeded, then personnel should not approach the area. Isolations should be applied
remotely.
5.2.3 Hydrogen Sulphide Portable Detection Equipment
Where a specific risk of H2S has been identified, personnel are recommended to use
portable detectors or wear personal electronic detectors that alarm when H2S level
reaches 5 PPM.
Portable Hydrogen Sulphide monitors must be provided so that in the event of a Hydrogen
Sulphide escape, the extent of the danger can be established.
Chemical sampling methods of Hydrogen Sulphide detection are preferred, because they
are much more reliable than instruments. It is important to ensure that the detector tubes
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 9 of 14
used to monitor Hydrogen Sulphide are always within the test expiry date.
Note: Chemical sampling methods are not suitable in certain circumstances; for
example, for confirming that clean air has been reached when escaping
from a Hydrogen Sulphide hazard.
5.2.4 Areas Not Currently Producing H2S
In cases of producing sites, which at present do not have H2S in their well fluids, sampling
shall be undertaken at defined intervals in order that any onset of H2S is established early.
5.2.5 Other Areas
Appropriate measures shall be provided for non-process systems/areas, which have the
potential to produce H2S. These measures shall be determined by suitable risk
assessment.
5.3
HYDROGEN SULPHIDE PRECAUTIONS
5.3.1 Classification of H2S Risk Areas
Warning: Notices warning of the presence of H2S and stipulating access requirements
must be posted at the perimeter of medium and high-risk areas, and at every
access point.
5.3.1.1 High Risk Areas
High risk areas are those areas where Hydrogen Sulphide is likely to be continually present
above the 8 hour Time Weighted Average Long Term Exposure Limit of 5 PPM (see
Appendix A) for long periods during normal operations and where routine monitoring is
mandatory.
Note: It is usual BP practice to paint pipe work and vessels containing hazardous
concentrations of Hydrogen Sulphide yellow, or with yellow bands.
In areas where H2S is likely to be encountered, sufficient self-contained (positive pressure)
breathing apparatus sets (working sets) shall be kept for all persons normally working in
that area. Two full spare air cylinders for each set shall be held in reserve in an open-air
safe area. Adequate numbers of 10-minute duration escape sets shall also be provided.)
If the presence of H2S in the air is suspected or an alarm is activated, personnel must leave
the area immediately, if possible heading first 90 degrees to the current wind direction then
head upwind to a safe area.
Entry into such areas shall be permitted only under a planned entry procedure and a work
permit. Personnel, working in pairs, must wear self-contained positive pressure breathing
apparatus or an airline. A standby rescue team must be in attendance.
Consideration should be given to the installation of wind direction indicators (windsocks or
flags) in high-risk areas, to aid direction of escape upwind/across wind.
5.3.1.2 Medium Risk Areas
Medium risk areas are those areas where Hydrogen Sulphide may occur during certain
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 10 of 14
planned operations and maintenance activities and where monitoring is carried out during
these operations.
Only authorized persons should enter these areas. Work shall be carried out under permit
to work procedures that must list precautions to be taken. The area should be monitored
with portable Hydrogen Sulphide detection equipment during these activities.
In both the above cases, it is vital that the source of any H2S is clearly identified and an
assessment made of any potential for deterioration.
5.3.1.3 Low Risk Areas
Low risk areas are those areas where Hydrogen Sulphide is not likely to occur in normal
operations, and if it does occur it will exist only for a short time, e.g. system malfunction.
Personnel entering low risk areas must be made aware of the possibility of the presence of
Hydrogen Sulphide and the emergency arrangements in force at the site.
5.3.2 Breathing Apparatus Training
All personnel who are likely to work in an environment where there could be potential
exposure to Hydrogen Sulphide shall be given positive pressure breathing apparatus
training (self-contained and air-line sets). Only fully trained personnel shall be permitted to
wear breathing apparatus and they must receive local refresher training every six months.
Personnel should be trained where and when to remove breathing apparatus after
completing a job since there may still be Hydrogen Sulphide present. They should either
remove the set at a remote location or test the atmosphere adjacent to the job first.
Personnel‟s medical evaluation and fit test requirements must be taken into account and
met.
Training shall also be given in mouth-to-mouth resuscitation and the use of resuscitation
equipment.
On plant where high concentrations of Hydrogen Sulphide are likely, consideration should
be given to the use of escape breathing apparatus sets or H2S respirators. These can
either be carried by personnel or located at various parts of the plant.
5.3.3 Contingency Planning
It is not feasible to provide a single plan for every contingency at every site. Plans must be
prepared on a site by site basis, and should cover:
 Planning for a Hydrogen Sulphide release
 Personnel training
 Hydrogen Sulphide monitoring.
In addition, sites that have a Hydrogen Sulphide risk must have an alarm system that is
understood by all personnel.
If the presence of H2S in the air is suspected, personnel must leave the area immediately.
The Area Authority, following Risk Assessment
(AZSPU-HSSE-DOC-00063-2),
accompanied by one other person trained to AGT Level 1 shall don breathing apparatus
and investigate, by using suitable test equipment, the concentrations of H2S in the air.
Upon recognition of an H2S gas hazard, (e.g. by smell) or on activation of personnel H2S
detectors, as a minimum, the following steps should be incorporated into any response to a
H2S release:
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 11 of 14
1. Evacuate the area, moving upwind/across wind if possible.
2. If necessary, don an emergency BA escape set to effect safe escape.
3. Do not attempt to rescue other personnel from the H2S area unless equipped with a
full duration BA set (leave it to the rescue team).
4. A person outside the H2S risk area should oversee personnel working in an H2S
atmosphere or on equipment where H2S is present.
Reference should be made to Appendix B, for what to do on discovery of an H2S leak or
finding a victim of H2S exposure. (Any accidents/incidents shall be reported in accordance
with AZSPU-HSSE-DOC-00054-2, Accident and Incident Investigation and Reporting
Procedure).
5.3.4 Planning for a Hydrogen Sulphide Release
A site action plan should be prepared showing the location of safe areas according to
prevailing wind conditions. For onshore sites usually three safe Areas will be defined:
 Two areas will be in the open air on opposite sides of the site (so that at least one
will be up wind of any incident). These areas shall be used for mustering essential
personnel.
 The third area (at a remote off-site location) will be used to muster all non-essential
personnel.
On offshore Installations, there should be one suitable Temporary Safe Refuge (TSR)
where personnel can withdraw to in the event of a release of H2S. This area of the facility
should have shutoff dampers on the Heating, Ventilation and Air Conditioning (HVAC)
system to prevent the ingress of H2S.
Protective / emergency equipment should be stored or located near to the two Safe
Areas used for essential personnel. In addition, in areas where H2S is likely to be
encountered, sufficient self contained positive pressure breathing apparatus sets shall be
kept for all persons normally working in that area. Two full spare air cylinders for each set
shall be held in reserve in an open-air safe area. Adequate numbers of escape sets shall
also be provided.
Where operations are being carried out in a known Hydrogen Sulphide area, and where
personnel may be required to wear breathing apparatus, it should be ascertained that
personnel have no obvious medical conditions that might endanger their health or
performance prior to breathing apparatus training.
5.3.5 Training of Personnel
All personnel shall be informed of the hazards relating to Hydrogen Sulphide and they shall
receive instruction in the correct use of any personal safety equipment, Hydrogen Sulphide
detectors, warning systems and evacuation procedures.
Information relating to Hydrogen Sulphide safety measures shall be prominently displayed
at strategic points around the site / installation.
All personnel working in the crew and rescue team should be instructed in basic first aid
procedures applicable to victims of Hydrogen Sulphide exposure.
An Emergency Response Team shall be established. All ERT and rescue team members
should be instructed in basic first aid procedures applicable to victims of H2S exposure.
Training exercises and drills must be carried out on a regular basis.
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 12 of 14
5.3.6 Monitoring the Presence of H2S
Portable H2S monitors must be provided so that, in the event on an H2S escape, the extent
of the danger area can be established.
H2S monitors should be set to current occupational exposure limits, i.e. 5PPM.
5.4
HYDROGEN SULPHIDE FIRST AID
Symptoms of acute Hydrogen Sulphide poisoning reduce rapidly when inhalation of the gas
ceases. It is therefore vital to get casualties into fresh air and to summon medical aid
immediately.
Casualties should be kept at rest. If their breathing is slow, laboured or impaired, artificial
resuscitation
(mouth to mouth or by the use of a mechanical resuscitator) may be
necessary.
Note: Before commencing mouth-to-mouth resuscitation, any gas in the casualty‟s lungs
should be first expelled by pressing down on the chest.
6.
DOCUMENTS REFERENCES
This procedure shall, where appropriate, be used in conjunction with this suite of AzSPU
Procedures referenced below.
Document Number
Title of Procedure
AZSPU-HSSE-DOC-00011-2
Procedure for Deviations
AZSPU-HSSE-DOC-00060-2
Procedure for Permit To Work
AZSPU-HSSE-DOC-00063-2
Procedure for Task Risk Assessment
AZSPU-HSSE-DOC-00013-2
Procedure for Confined Space Entry
AZSPU-HSSE-DOC-00054-2
Procedure for Incident Investigation
AzSPU-HSSE-DOC-00021-2
HSSE Definitions
AZSPU-HSSE-DOC- 00002-2
Procedure for Control of Work
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 13 of 14
APPENDIX A: CLASSIFICATION OF PHYSIOLOGICAL RESPONSES TO
HYDROGEN SULPHIDE
Revision/Review Log
Revision Date
Authority
Custodian
Revision Details
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Hydrogen Sulphide
Page 14 of 14
12 October 2004
CHSSE Manager
Central Safety TL
Initial Issue
30 May 2008
Alan McNulty,
Abbas Islamov,
General:
AzSPU Central H&S
Central Safety TL
Through the Procedure the document
Manager
numbering for referred procedures has been
changed from UNIF to AzSPU.
Section 1. Introduction
The following are new inclusions to Section 1.
Legislation and Standards
Company Requirements
Stopping Unsafe Work
Deviations
Document Review
SSOW Cross Referrence
Language Facilitation
Considerable changes were made to paragraph
1.2 Scope.
Section 3. Roles & Responsibilities
3.1 One point added to SM/SC/OIM
responsibilities.
The recommended personnel’s behavior if H2S
is found to be in presence in air is strengthened
and made more precise - paragraph 6.1
In addition to Appendix A, new appendix is
add as follows:
Appendix B - Feedback & Improvements
Suggestions.
05 December 2008
Yuliy Zaytsev
Adalat Mamedov,
Authority position/name and custodian name
AzSPU Safety &
Central Safety TL
have changed to reflect org changes in
Compliance Systems
HSE&TD.
Manager
14 August 2009
Yuliy Zaytsev
Niyaz Mamedov
Appendix A - Change of terminology from
AzSPU Safety &
HSE Systems /
OES (Occupational Exposure Standards) to
Compliance Systems
CoW Adviser
WEL (Workplace Exposure Limits)
Manager
The procedure’s numbering is structurally
changed in accordance with Standardized
Document Control Procedure Template
requirements.
25 January 2011
Yuliy Zaytsev
Elman
Section 1 General Requirements
AzSPU Safety &
Shikhkerimov
Removed reference to Getting HSE right,
Compliance Systems
Safety
Golden Rules and replaced with OMS,
Manager
Systems/CoW Lead
Group requirements
Control Tier:
<<2>>
Revision Date: 25 January 2011
Document Number: << AZSPU-HSSE-DOC-00066-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 1 of 23
Procedure
For Leak Testing of In-Service Equipment
AZSPU-HSSE-DOC-00055-2
This document supersedes UNIF-HSE-PRO-241-C2
Authority:
AzSPU Safety & Compliance
Custodian:
HSE Systems - Control of Work Advisor
Systems Manager
Niyaz Mamedov
Yuliy Zaytsev
Scope:
AzSPU
Document
Administrator:
Document Asset Technician
Issue Date:
09 September 2004
Issuing Dept:
Safety & Compliance Systems
Revision Date:
23 April 2009
Control Tier:
2
Next Review
23 October 2010
Date:
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 2 of 23
TABLE OF CONTENTS
1 INTRODUCTION
4
1.1
PURPOSE
4
1.2
SCOPE
4
1.3
LEGISLATION & STANDARDS
4
1.4
COMPANY REQUIREMENTS
5
1.5
STOPPING UNSAFE WORK
5
1.6
DEVIATIONS
5
1.8
NORMATIVE REFERENCES
5
1.9
LANGUAGE FACILITATION
6
2 ROLES AND RESPONSIBILITIES
6
2.1
OFFSHORE INSTALLATION MANAGER / SITE MANAGER / SITE CONTROLLER
6
2.2
AREA AUTHORITY
6
2.3
PERFORMING AUTHORITY
7
2.4
EMPLOYEES
7
3 COMPETENCY, TRAINING AND AWARENESS
7
3.1
COMPETENCY
7
3.2
UNDERSTANDING
8
3.3
AWARENESS
8
3.4
NEW INDIVIDUALS
8
4 SELECTION OF TEST TYPE
8
4.1
GENERAL
8
4.2
HYDRAULIC
9
4.3
NITROGEN
9
4.4
LIQUID FILL AND NITROGEN SQUEEZE
9
4.5
NITROGEN - HELIUM
9
4.6
SERVICE
10
4.7 POST-TEST INTEGRITY CHECKS
10
5 LEAK TESTING GUIDELINES
11
5.1
COMMUNICATION
11
5.2
TEST AREA ACCESS
11
5.3
TEST EQUIPMENT
11
5.4
TEST BOUNDARY
11
5.5
ISOLATIONS
12
5.6
VENTS AND SAFETY VALVES
12
5.7
APPLYING THE TEST
12
5.8
MONITORING AND INSPECTION
13
5.9
DEPRESSURISING AND RETURN TO SERVICE
13
5.10
REPAIRS OR ADDITIONS AFTER LEAK TESTING
13
5.11
SAFETY CONSIDERATIONS IN NITROGEN LEAK TESTING
14
6 RECORDS (CERTIFICATION)
15
7 REGISTERS
15
8 CONTRACTORS
15
9 AUDIT AND REVIEW
15
APPENDIX A - LIST OF DEFINITIONS
16
APPENDIX B - LEAK TESTING CHECKLIST
18
APPENDIX C - GUIDANCE NOTES
20
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 3 of 23
REVISION/REVIEW LOG
22
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 4 of 23
1
INTRODUCTION
1.1
PURPOSE
The purpose of this document is to provide:
Guidelines for assessing the risks and establishing the precautions to be taken
when carrying out leak testing of in-service equipment.
Information that may be used as the basis for producing formal instructions for
specific pressure and leak testing activities.
Prior to re-instatement of plant or equipment, any leak testing operations shall
be conducted in accordance with this procedure.
A leak test (hydraulic where practicable) is performed to prove the pressure tightness (i.e.
fitness for service) of joints, seals and glands etc, whenever the integrity of containment
systems has been broken, either at hook-up/commissioning or post-operations phase. The
prevention of even minor leaks is vitally important where flammable or toxic fluids are
concerned.
Leak testing is carried out at a pressure of 110% of the maximum operating pressure
(MOP), or 95% PSV set pressure if PSV is provided in the system.
1.2
SCOPE
This applies to all leak testing operations carried out on BP owned and managed sites and
installations in AzSPU. This procedure does not include standard strength tests which are
conducted on individual items of equipment/systems. These tests are carried out to
separate item design codal requirements, and are completed before the items are installed
as part of the overall pressure retaining system. e.g. pressure vessels, valves etc.
Contractors working on BP owned or managed sites / installations are also responsible for
alignment with this procedure.
This procedure contributes to compliance with the “HSE expectations” contained in “getting
HSE right”, the „Golden Rules of Safety‟ and the Control of Work (CoW) standard that the
Hazards associated with BP activities are identified and that the risks are assessed and
managed.
All guidelines contained shall be regarded as the minimum requirements for BP owned or
managed sites / installations in Azerbaijan and Georgia.
The scope covers defined activities of BP and Contractors at all BP AzSPU sites and
installations.
1.3
LEGISLATION & STANDARDS
The aim of this Safe System of Work is to achieve ”no accidents”, “no harm to people” and
“no damage to the environment”. To achieve this aim, this SSOW complies with National
Legislation, the terms of the Production Sharing Agreement (PSA) and mandatory BP
Standards.
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 5 of 23
The best International Oil Industry practice has been adopted to reduce the level of risk to
ALARP.
In the absence of local regulations, BP Group Standards will apply. In addition, appropriate
UK and US regulations and industry best practice have been considered in setting suitable
goals and targets.
1.4
COMPANY REQUIREMENTS
It is a company requirement that all tasks are subjected to an assessment of risk to
demonstrate that risks have been reduced to as low a level as reasonably practicable
(ALARP). This can be achieved by complying with the Company‟s existing standards.
Where compliance with Company standards cannot reasonably be achieved, a formal Level
2 Risk Assessment will be undertaken to identify any additional controls and demonstrate
that risks remain as low as reasonably practicable. Whether by compliance with Company
Standards or through Level 2 Risk Assessment, the Company‟s Golden Rules of Safety
must be complied with. Golden Rules are non-negotiable.
1.5
STOPPING UNSAFE WORK
To stop the continuation of potentially unsafe work at the earliest possible stage, the
Control of Work (CoW) Policy and this procedure for Leak Testing make it very clear that all
personnel are obliged and have the authority to “STOP” the work that they consider to be
unsafe.
1.6
DEVIATIONS
This procedure is written in sufficient detail that it should be able to be applied consistently
at all sites / installations. There may still be the requirement for some local rules covering
site
/ installation specific logistical/administrative arrangements and local variations in
responsibilities to reflect differences in organisational arrangements. These local rules
should not deviate from the core processes within this document. Any form of deviation
from this procedure, including but not limited to local rules, shall be requested and
authorised in accordance with SSOW, Deviations from Regulations and Procedures (Doc.
No: AZSPU-HSSE-DOC-00011-2).
1.8
NORMATIVE REFERENCES
The following normative documents contain requirements that, through reference in this
text, constitute requirements of this procedure. For undated references, the latest edition of
the normative document referred to applies.
American Society of Mechanical Engineers (ASME)
ASME B1.20.1
Pipe Threads, General Purpose
2006
ASME B31.3
Process Piping
2006
ASME B31.4
PIPELINE TRANSPORTATION SYSTEMS FOR
LIQUID HYDROCARBONS AND OTHER LIQUIDS
2007
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 6 of 23
In addition, this procedure shall, where appropriate, be used in conjunction with the suite of
BP AzSPU SSOW Procedures referenced below.
Document Number
Title of Procedure
AZSPU-HSSE-DOC-00011-2
Deviations from Regulations and Procedures
AZSPU-HSSE-DOC-00054-2
Incident Investigation and Reporting
AZSPU-HSSE-DOC-00060-2
Permit To Work
AZSPU-HSSE-DOC-00012-2
Authorisation
AZSPU-HSSE-DOC-00063-2
Task Risk Assessment
AZSPU-HSSE-DOC-00048-2
Energy Isolations-Electrical
AZSPU-HSSE-DOC-00049-2
Energy Isolations-Process
AZSPU-HSSE-DOC-00013-2
Confined Space Entry
AZSPU ENG STP 36-101-01
Bolted Joint Integrity Management
1.9
LANGUAGE FACILITATION
Due to the various languages spoken at site, there is a necessity to assist all with “an ease
of understanding”. Therefore, the development and use of information tools are available.
2
ROLES AND RESPONSIBILITIES
2.1
OFFSHORE INSTALLATION MANAGER / SITE MANAGER / SITE CONTROLLER
The Site Manager / Site Controller / Offshore Installation Manager shall be responsible and
accountable for the application of this procedure in their area of responsibility. They shall
ensure:
 That adequate numbers of Competent responsible persons are appointed to manage
and maintain the requirements of this procedure
 That only competent and authorised personnel are involved in pressure testing
activities
 That this procedure is strictly adhered to for all occasions when it is identified that
leak testing activities are to take place.
 That formal records of all risk assessments are maintained in accordance with this
procedure
 That only suitably qualified and experienced personnel are appointed to the roles of
Performing Authority, responsible engineer / person in charge of leak testing
 That formal records of all pressure tests and leak tests are maintained in accordance
with this procedure
2.2
AREA AUTHORITY
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 7 of 23
The Area Authority shall:
 Be responsible for ensuring that the requirements of this procedure are adhered to
for all work involving leak testing activities in his area of responsibility
 Ensure that leak testing operations comply with the guidelines within this document
and/or ensure that any deviations from those guidelines are documented and
authorised
2.3
PERFORMING AUTHORITY
The Performing Authority shall ensure:
 Have such practical experience and theoretical knowledge of the equipment to be
tested so that he will be able to detect defects or weaknesses highlighted by the test
and assess their importance to the integrity and function of the equipment. The
Performing Authority must be qualified and trained to a standard sufficient to meet
any applicable regulations.
 Ensure that leak testing operations comply with the guidelines within this document
and/or ensure that any inability to comply with the conditions of the Permit result in a
re-assessment of the task
 The compliance of all personnel under their supervision with this procedure when
involved in leak testing activities
 That a risk assessment has been performed and a toolbox talk conducted
 That all personnel are informed of, and understand, the risks associated with the task
they are performing, and any associated works that may affect their work activity
 That the activity is executed in accordance with this procedure
 That leak testing activities are halted if an unsafe situation occurs
 That good housekeeping practices are implemented at all work areas
 That work activities have been reviewed and pertinent information exchanged with all
other affected parties
2.4
EMPLOYEES
ALL EMPLOYEES SHALL BE RESPONSIBLE FOR:
 Compliance with this procedure when involved in leak testing activities
 Implementing good housekeeping practices at the work site
 Informing their immediate Supervisor should any unsafe situation occurs
Awareness of other personnel and ongoing works in their area
3
COMPETENCY, TRAINING AND AWARENESS
3.1
COMPETENCY
BP‟s employees, and those of it‟s Contractors must provide adequate training for all
personnel likely to be involved in Leak Testing, to ensure that they possess the correct
levels of competency.
All individuals shall be able to and be prepared to demonstrate their levels of competency to
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 8 of 23
the Performing Authority, Supervisor and / or Leak Test Supervisor
This shall be demonstrated through individuals understanding, knowledge and the skills
necessary to safely perform their assigned duties together with certifiable evidence of their
competency.
3.2
UNDERSTANDING
All individuals shall be fully conversant with the:
 Scope of work and the potential hazards associated within their scope of work to
ensure that they understand the hazards of the task in hand and all associated
controls
 Safe systems of work (SSOW) elements associated with their scope of work,
including but not limited to: PTW, Energy Isolations., purging and / or ventilation
procedures
 Relevant scope of work task risk assessments
3.3
AWARENESS
All individuals shall be fully aware of:
 What they need to do in the event of an emergency on site
 What they need to do in the event of an incident related to their scope of work
 How to use the relevant communications equipment
 Self rescue
 How to use continuous gas monitoring equipment
 All aspects of the proposed Leak Test activities with focus on their particular duties
3.4
NEW INDIVIDUALS
New individuals shall not be assigned to the above tasks, unless under training and
accompanied by a competent person (maximum 2 new starts to 1 supervisor) who is
familiar with the hazards of Leak Testing.
4
SELECTION OF TEST TYPE
4.1
GENERAL
A liquid medium (hydraulic) is the preferred means of testing and shall be used for leak
testing wherever possible, in order to minimise the stored energy.
The preferred liquid medium is water. However, the effect of the water, and any additives,
on the metallurgy of the pressure envelope, and the effect of any residual water/additives
on the process (eg formation of hydrates), shall be considered (eg when testing austenitic
stainless steels, the water should be distilled or demineralised and contain <30ppm of
chloride ions).
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 9 of 23
Selection of liquids other than water should take account of:
 The possibility of explosion resulting from the „diesel‟ effect
 The boiling point relative to the test temperature
The flammability of the liquid, the flash point of which should not be less than 65°C, and at
least 10°C above the maximum test temperature.
4.2
HYDRAULIC
 Weight must be considered, particularly in context of equipment support e.g. pipe
hangers, foundations
 Care must be taken with draining the test fluid on completion - in some cases the
equipment may require flushing and/or drying.
 Some test fluids, typically water, may be incompatible with equipment materials
 Generally considered to be a “safe” test medium due to low levels of stored energy
 Internal leakage, e.g. through valves at the boundary, may require continuous
pressuring of the equipment. In severe cases this can prevent a successful test
 Detection of leakage is typically by observation of fluids leaking to atmosphere at
joints/connections under test. In cases where joints/connections are not visible then
pressure drop off can be used as an indicator.
4.3
NITROGEN
Note! Pneumatic leak-testing should not be carried out before the integrity of the equipment
has been confirmed by a standard pressure test.
 Relatively high levels of stored energy
 Large volumes may require supply of bulk nitrogen
 Considerable time may be needed to pressurize and/or vent
 Vent location(s) must be carefully selected so as to avoid any risk of asphyxiation to
personnel
 Detection of leakage is typically by means of bubble test at joints/connections.
4.4
LIQUID FILL AND NITROGEN SQUEEZE
Combination of both sets of attributes mentioned in sub sections 4.2 and 4.3.
4.5
NITROGEN - HELIUM
 Addition of a small proportion of helium (known as a tracer) enhances the searching
qualities of nitrogen. Normally 99% nitrogen, 1% helium.
 Typically supplied in bulk by a specialist contractor. Usually used for large-volume
tests e.g. post shutdown
 Detection - Requires specialist detection equipment - can give a quantitative output
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 10 of 23
4.6
SERVICE
For process hydrocarbon systems, although it is not the preferred means of testing, under
certain conditions it may be considered appropriate to carry out testing with the service fluid
(ie liquid or gas) rather than with water, nitrogen or some other medium. This should only be
considered where it can be clearly demonstrated that it is impractical to carry out leak testing
due to the configuration of the system and that the hazards associated with the introduction of
high-pressure testing equipment etc would be greater than the hazards associated with the
service testing.
Where this method is proposed, a written justification must be recorded on a Level 2 Risk
Assessment.
The following criteria and precautions should be considered as the minimum in support of
carrying out service tests on hydrocarbon system;
 The number of joints that have been broken shall be small to guarantee the ability to
control and monitor the test.
 A competent technician shall have witnessed the joints being re-made in accordance
with the Guidance on Certification (GOC) Procedure for Critical Joint Installation.
Pressurisation should be controlled via a designated pressurisation route where
possible, e.g. a small bore line fitted with a globe valve.
Pressurisation shall be in small incremental steps (5.bar max) where possible.
Depressurisation routes shall be specified and if possible both local/manual
depressurisation and remote depressurisation from the control room shall be designed
into the leak boundaries.
 The boundary isolation valves for the service test shall be controlled under the ISSOW
isolation control.
Once it has been decided to carry out a service test, a formal procedure shall be developed
including marked-up P & ID‟s defining the service test and detailing compliance with the
above criteria.
4.7 POST-TEST INTEGRITY CHECKS
After hydrocarbons or hazardous utilities have been introduced, an initial visual check of
joint integrity shall be made for all broken joints and any other joints that may have been
disturbed. Further checks shall be carried out every 12 hours until the plant has reached its
normal operating pressure and temperature. Checks shall be carried out for at least 2 days.
Note: Where a service test has been completed on a hydrocarbon system, these
post-test integrity checks must be repeated at each pressure increase of 5 barg
above the original service test pressure.
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 11 of 23
5
LEAK TESTING GUIDELINES
5.1
COMMUNICATION
 Effective communication must be established between sites whenever the test
envelope extends beyond one site, for example, pipelines.
5.2
TEST AREA ACCESS
Access to the test area shall be limited to essential personnel only. In particular, before the
test commences compliance is required with the following points:
The area shall be cordoned off (using tape, shields or barriers, etc) at an adequate
distance from the equipment to be tested,
Warning signs and barriers shall be posted at access ways, at other strategic
positions, and on the equipment to be tested (including the doors of test workshops
or other designated areas.
Wherever possible, warnings of an imminent pressure test shall be broadcast.
When testing, the test area boundaries shall be patrolled to ensure that no
unauthorised personnel enter the area.
5.3
TEST EQUIPMENT
Pressuring equipment shall be provided with suitably calibrated pressure control /
regulator devices.
Suitably calibrated pressure indicating device(s) shall be provided in a location
clearly visible to the person controlling the pressure. Account should be taken of
pressure variation caused by elevation changes inside the envelope.
Pressuring equipment and plant/equipment shall not be left unattended at any time
during the test.
Pressuring equipment shall be isolated from the equipment under test and where
practicable disconnected, when the test pressure has been reached. The
pressurising valve should be locked in the closed position.
All hoses are fully secured with tie-down devices capable of withstanding the forces
used in the test. Each hose end is to be fitted with whip check cables.
5.4
TEST BOUNDARY
A Competent Person shall inspect the equipment to be tested, prior to testing, to
ensure the equipment is free from any obvious flaws
Within the test boundary, there should be an accessible and operable means of
quickly and safely de-pressuring the test in the event of equipment failure etc.
Prior to any hydraulic pressure test taking place it must be established that the
foundation and supports of the equipment under test are rated and capable of
withstanding the combined weight of the equipment and the liquid required to fill it.
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 12 of 23
The volume of equipment under test must be kept as small as possible so to
minimise the stored energy within the pressurised system.
Hazard and risk identification shall, as a minimum, consider:
o the stability of components such as expansion joints and spring hangers
o any interfaces with lower pressure systems or equipment (including heat exchangers,
gauges, instruments etc) and must ensure measures are in place to ensure that such
systems cannot be over-pressurised
o any connected high pressure equipment such as pulsation dampers and
accumulators.
5.5
ISOLATIONS
Blanking devices such as spades, blinds and screwed plugs, etc. shall conform to
the equipment specification. All plugs must have a minimum thread engagement
length as per ASME B1.20.1.
Where testing is carried out against closed valves it must be assumed that the
valves leak, and downstream equipment must be protected against subsequent over
pressuring. This should be done by opening of suitable vents or by monitoring of
downstream pressures
5.6
VENTS AND SAFETY VALVES
Where the source pressure of the pressurising medium is greater than the test
pressure, a safety valve should be fitted to the equipment/system being tested, set
to relieve at a pressure that will prevent over pressurisation.
Sufficient venting / draining points shall be provided in order to prevent trapping of
pressurising medium behind non-return valves, check valves, between isolation
valves, or within dead legs of the pressure envelope.
When filling equipment/plant, adequate venting must take place at all high points or
dead ends to release entrapped gas.
5.7
APPLYING THE TEST
Pressure must be increased gradually to the final pressure, and sufficient time
should be allowed for equipment and test medium to reach equilibrium.
o Raise pressure to 25% test pressure and allow to settle.
o Increase to 50% test pressure.
o Increase to 75% test pressure.
o Final increase to the full test pressure.
The pressure should be maintained sufficiently long for an Inspection Engineer to
examine the entire system, and for any defects to have time to manifest themselves.
Equipment must not be subjected to any form of shock loading during testing.
When any equipment/plant is left under pressure for decay or leak observation,
consideration must be given to the ambient temperature changes, particularly in
respect to thermal expansion of liquids in a closed system.
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 13 of 23
5.8
MONITORING AND INSPECTION
Pressure monitoring shall extend to any adjacent systems that are not positively
isolated.
Close examination of equipment at above design pressure shall not take place until
the pressure has been held for 30 minutes. In any event, extreme care should be
exercised until the pressure has been reduced to the design pressure.
If an inspection is required within the hold period, then pressure should be reduced
to the Design Pressure.
5.9
DEPRESSURISING AND RETURN TO SERVICE
Extreme care shall be taken to ensure that all pressure has been relieved before
opening any system that has been subject to pressure or leak test.
On completion of the test, the pressure shall be reduced gradually and under
controlled conditions until approximately atmospheric pressure is reached. More
rapid draining of the test fluid can then take place.
When draining equipment, adequate vents at the highest point must be opened to
prevent drawing a vacuum. The drainage system must be capable of handling the
flow from the pressurized equipment/plant without itself over pressuring.
Consideration must be given to the possibility of test fluids being trapped behind
non-return valves; it may often be necessary to vent or drain the test fluid from more
than one point.
Special consideration should be given to test fluid which may be contaminated with
oil or contain corrosion inhibitor or other chemical. The method of disposal of test
fluid must be included in Work Permit.
Clamps or bolts on flanges shall not be loosened while the system is still under
pressure. Clamps shall only be removed by competent personnel who have been
trained in such procedures.
Depending upon the test medium used, the return of equipment/plant back into
service may produce additional hazards. In particular:
o Residual water after draining may contaminate the product, or cause problems if the
equipment is on high or low temperature service.
o Systems containing air need to be inert prior to the introduction of process fluids.
o Inert gas must be vented to an area where personnel cannot be affected by it.
Consideration must be given to the flushing and preserving of systems that are not
being taken back into re-use immediately.
5.10 REPAIRS OR ADDITIONS AFTER LEAK TESTING
If repairs or additions are made following the leak test, the affected piping shall be retested,
except that for minor repairs or additions, the retest requirements may be waived when
precautionary measures are taken to assure sound construction. (B31-345-2.6)
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 14 of 23
5.11 SAFETY CONSIDERATIONS IN NITROGEN LEAK TESTING
Nitrogen can asphyxiate, therefore great care should be taken to avoid gross leakage of
nitrogen or nitrogen/helium. Particular care should be taken when opening up vessels that
have been nitrogen purged or when the venting of nitrogen is taking place.
Pressure shall be introduced gradually into the system allowing adequate time for
temperature equalisation; in this respect special attention is drawn to the cooling Joule-
Thompson effect which occurs when letting down high-pressure nitrogen into the system to
be tested. Nitrogen leak testing is performed with gases at high pressure. Therefore
attention is drawn to the hazards of a possible release, with explosive force, of energy
stored in the system. Systems under test shall be depressurised prior to bolt re-tightening,
tensioning or other remedial action to improve leaks, the only exceptions to this being valve
glands, which may be adjusted but not re-packed whilst the system is still pressurised.
The possibility of brittle fracture shall be considered when conducting a nitrogen leak test at
metal temperatures near the ductile/brittle transition temperature of the steel. It is
recommended that nitrogen leak testing should not be carried out when the ambient
temperature is below 7°C on equipment and piping constructed from non-impact tested
carbon steel materials with nominal thickness of >3/4in (19mm), (ie API 5L, A 106, A 105, A
216, etc). For non-impact tested carbon steel materials with nominal thickness >3/4in, a
Competent Person shall specify the minimum metal temperatures for leak testing, based on
requirements of either RP 42-1 or BS 5500. Sites are advised to identify any systems
containing non-impact tested carbon steel and prepare the appropriate local test
procedures.
Introducing nitrogen to a system introduces a large energy source, far greater than the
energy stored in an equivalent liquid leak test. To minimise this stored energy, vessels
which normally operate with a liquid level should be water filled (ensure water filling of the
vessel is acceptable with respect to corrosion and scaling) prior to pressurising with
nitrogen.
When a specialist contractor is contracted to carry out nitrogen leak testing rather than leak
testing with nitrogen quads or low volume pumps the following additional measures apply:
 There will be a Pump Operator who will be in radio contact with the Leak Test
Supervisor who will monitor system pressure. The pumping unit will be manually
shut down on the instruction of the Leak Test Supervisor. The leak test crew should
have a written procedure for radio protocol
 There will be an automatic pump trip (Overpressure Protection Device (OPPD)) that
will shut down the pumping unit. The OPPD will be located close to the injection
point so that it can monitor the highest pressure that will be seen in the Installation
system
 Full flow (of test medium injection rate) pressure relief will be available via Pressure
Safety Valves
(PSVs). It is acceptable and appropriate for the PSVs on the
Installation system/plant to be used for this purpose. However, if full flow pressure
relief is not available via a plant system, then Full flow pressure relief will be
available via Pressure Safety Valves (PSVs). It is acceptable and appropriate for the
PSVs on the Installation system/plant to be used for this purpose. However, if full
flow pressure relief is not available via a plant system, then consideration should be
given to the use of temporary PSVs supplied by the leak test contractor. Any system
PSV‟s used for this purpose shall be within their re-certification date. Any contractor
supplied PSV‟s shall be certified and calibrated, with certification available for
examination at site. If full flow pressure relief is not provided, then a Level 2 Risk
Assessment should be completed and assurance gained that there is sufficient
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 15 of 23
control in place to manage the HP/LP interface
 If it has been identified that the leak test contractor will have to supply PSVs,
consideration should be given to the location that these PSVs would vent to in an
emergency. The vent location should be surveyed and approved by the Installation
Area Authority with guidance from the leak test contractor on expected nitrogen
plume
 Contractor Method Statement shall be thoroughly examined and approved
6
RECORDS (CERTIFICATION)
All pressure / leak test results shall be formally certificated and recorded where necessary
and all certificates included with the relevant equipment records.
7
REGISTERS
A register will be held on site of all personnel deemed competent for all the roles
associated with Leak testing, and will be managed by the Site Manager / Site Controller /
Offshore Installation Manager.
8
CONTRACTORS
In cases where leak testing is contracted to a specialist third party, the contract shall, as a
minimum, specify the need to observe the requirements of this procedure and in addition
the:
Roles and responsibilities of the relevant BP and contractor personnel
Authority for approval of procedures
Required competency of the contractor personnel and the means of controlling
compliance
Keeping of test records
Means of monitoring the contractor‟s safety management system.
9
AUDIT AND REVIEW
Business Units shall periodically review pressure and leak testing activities to verify general
compliance with this procedure and with any local procedures. Such reviews shall include
checks to verify compliance with any statutory requirements for periodic strength tests of
equipment to demonstrate its continued fitness for service.
Independent audit of pressure / leak testing procedures and records shall be undertaken
periodically at the request of the Site Manager / Site Controller / Offshore Installation
Manager.
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 16 of 23
APPENDIX A - LIST OF DEFINITIONS
In-Service
Equipment installed as part of a system, the individual components of
Equipment
which have been subject to Codal Pressure/Strength Testing. This applies
to equipment included in systems where the integrity of containment has
been broken, either at hook-up/commissioning or post-operations phase.
Blank /
Installation of a piping specification rated device such as a blind flange,
Blanking:
spade or spectacle blind for the purpose of achieving positive isolation.
Boundary
Isolations that define the boundaries of a discrete pressure envelope.
isolations:
Competent
A person having such practical experience and theoretical knowledge of
Person:
the equipment to be pressure tested so that he will be able to detect
defects or weaknesses highlighted by the pressure test and assess their
importance to the strength and function of the equipment.
Competent Persons must be qualified and trained to a standard sufficient
to meet any applicable regulations.
Design Pressure
The maximum pressure at which the system is designed to operate at.
This is usually the maximum operating pressure plus a small margin
(typically 10%).
Application of pressure to a system in which the integrity of individual
Leak test:
components has already been proven by a pressure test so as to identify
leakage and leakage rates from component connections, valves etc. Leak
testing is carried out at a pressure of 110% of the maximum operating
pressure (MOP), or 95% PSV set pressure if PSV is provided in the
system.
Local
Site specific or Business Unit specific procedures that address the
procedures:
arrangements in place for the implementation of recommended and
statutory practices.
Maximum
The maximum pressure expected during normal systems operation.
Operating
Pressure (MOP)
Maximum
The maximum pressure which a component can safely withstand. Note
Allowable
that this is often greater than the design pressure, due to components
Working
being manufactured from thicker material than that required for the design
Pressure
pressure.
Pressure/
A test involving the application of pressure to a system so as to apply a
Strength test:
load greater than the maximum load generated in service but less than
would cause physical damage. The test provides evidence that the system
can safely withstand the service pressure. Test pressures may vary
between individual components within the same system due to differing
codal design requirements.
Initial Service
A leak test undertaken when a system is brought into normal service,
leak test:
completed at operating pressure for Category D fluids only (refer to ASME
B31.3 para 300.2).
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 17 of 23
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 18 of 23
APPENDIX B - LEAK TESTING CHECKLIST
A checklist to be used when planning leak tests is provided in Figure 1 below as a guide.
Note: This checklist in this appendix is provided as an aide memoir only, and is not intended for use
as an approved test certificate or an official document:
Leak/Pressure Testing Checklist
1.TYPE OF TEST:
STANDARD PRESSURE TEST:
LEAK PRESSURE TEST:
2.TESTING MEDIUM:
HYDRAULIC:
PNEUMATIC:
3.EQUIPMENT TO BE TESTED:
Codal Test Pressure (strength test)
Proposed Test Pressure:
Maximum Operating Pressure (leak test)
Incremental steps (%):
Duration each step:
Duration of Test Pressure:
Written procedure
YES
NO
provided:
All threaded connectors, plugs, and caps secure and tight:
YES
NO
All attachments unable to withstand Test pressure removed or isolated:
YES
NO
Quality:
Temperature:
4. TEST ENVELOPE INSPECTION:
Visual
YES
NO
MPI:
YES
NO
Radiography:
YES
NO
Other (specify):
YES
NO
5. EQUIPMENT ISOLATED AT:
and at:
6. PRE-TEST PREPARATIONS:
Equipment vented for filling at:
and at:
Check facilities for venting trapped pressure from NRVs or between isolation valves
YES
NO
Vents now SHUT
YES
NO
Safety valves set to prevent test pressure being exceeded
YES
NO
Calibrated test pressure gauge(s) fitted and visible to operator
YES
NO
Any pipe support / expansion joints fitted with temporary restraints
YES
NO
Pressuring equipment fitted with regulator and relief valve and is in sound condition
YES
NO
Methods for upstream and downstream monitoring are in place
YES
NO
Warning signs posted, barriers erected, and sentries in place
YES
NO
PA announcement of proposed test has been organised / made
YES
NO
7. ON COMPLETION OF TEST:
Vents are open for slow depressurisation at:
and at:
Drains are open for draining of test medium at:
and at:
8. EQUIPMENT HAS BEEN RETURNED TO PRE-TEST EXCEPT FOR:
and:
YES
NO
9. CHECKLIST COMPLETED BY:
Name:
Signature:
Title:
Date:
Control Tier:
<<2>>
COMPETENT PERSON
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 19 of 23
Test Plan / Programme
 If any pipeline or plant configuration changes then a MoC and relevant TA approval are required
 Design Pressure or Maximum Operating Pressure (MOP) defined
 Test Pressure defined
 Marked up P&ID‟s produced showing test boundaries
 Written test procedure developed
 Test medium selected (hydraulic considered rather than pneumatic)
 If pneumatic test planned, consider reducing the volume by water filling vessels
 Emergency depressurisation route identified
 Pressurisation / depressurisation procedures take account of the position of non-return valves
 Pressurisation procedure specifies hold points (25%, 50%, 75% of the test pressure)
Pre-test Preparation and Equipment Checks
 All threaded connections, plugs and caps are secure
 All attachments unable to withstand test pressure are removed/ isolated
 Facilities have been checked for means of venting trapped pressure
 Safety valve set to prevent test pressure being exceeded
 Calibrated test pressure gauge(s) fitted and visible to operator
 Any pipe supports/expansion joints fitted with restraints
 Pressure equipment is fitted with regulator and relief valve and is in sound condition
 Methods of upstream and downstream monitoring are in place
 Warning signs and barriers erected
 PA announcement of proposed test has been organised
 Contingencies for leakage have been made
 Overpressure protection device in place for specialist contractor nitrogen testing
 Pumping unit connected to ESD system where required
Post-test Checks
 Vents to be opened at high points during liquid depressurisation
 Pressure to be released gradually
 Inert gases vented to flare or alternatively to a safe area
 Confirm that there is no trapped pressure within test envelope
Figure 1. Leak Testing Checklist
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 20 of 23
APPENDIX C - GUIDANCE NOTES
Leak Testing Acceptance Criteria
This section defines the allowable leak rates for different test medium and equipment type
and duty.
Acceptance Criteria for Hydraulic Testing
For hydraulic testing using water the test should be conducted for a minimum of
30 minutes. A test should be deemed successful if no significant reduction in pressure is
observed over the test period and all joints and connections have been visually inspected
for leakage. In some cases it may not be possible to maintain a constant test pressure due
to trapped air in the system or passing valves. In this case the visual inspection is vital in
confirming an acceptable test.
Acceptance Criteria for Nitrogen Testing
For nitrogen testing, depending on the scope of the test, there are two primary means of
confirming an acceptable test. These are:
 Bubble testing
 Leak rate measurement using a helium tracer
Helium tracer testing is normally used for large scale testing of plant or the installation of
new equipment involving a specialist contractor. Bubble testing is normally applicable when
carrying out smaller scale testing using nitrogen quads.
Bubble Testing Criteria for Hydrocarbons
Bubble Testing Method
Acceptance Criteria
Method
1 involves the application of a leak
No presence of continuous bubble growth
detection fluid e.g „Snoop‟ to the joint and monitoring
detected in 60 seconds for flanges up to
for surface bubbles. For all large diameter flanges
and including 4in NB and 90 seconds for
(>6” NB), the joint should be taped and the leak
flanges above 4in NB.
detection fluid applied to a pin hole in the tape.
Method 2 involves taping the joint and inserting a
5 bubbles/min.
1/4in diameter tube from the flange into a water
bucket and monitoring the number of bubbles
released.
Note:
5 bubbles/min approximates to 15scf/year from a 1/4in tube.
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 21 of 23
Helium Tracer Testing
Leak rate measurement in the case of helium tracer testing involves taping of individual
flanges and measurement of leakage using a measurement probe. The following leakage
criteria apply:
Leakage Rates (scf/yr)
Helium Tracer Testing Method
Acceptance Criteria (scf/year)
Target
Maximum
Closed Module
Open Module
Oil
100
200
400
Gas <50barg
50
100
200
Gas >50barg
20
40
100
Acceptance of leak rates in the range between target and maximum allowable leakage is by
exception only and review by the appropriate Technical Authority. The review shall take into
account fluid type, location of joint and ventilation and subsequent monitoring programme.
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 22 of 23
REVISION/REVIEW LOG
Revision Date
Authority
Custodian
Revision Details
9 September 2004
Alan McNulty
Esmira Akhundova
Initial Issue
08 April 2008
Alan McNulty
Abbas Islamov
General.
(AzSPU CH&S
(Central Safety TL)
Section 1. Introduction.
Manager)
Four new paragraphs are added to
Section 1:
1.3
Legislation & Standards
1.4
Company Requirements
1.5
Stopping Unsafe Work
1.6
Deviations
SSOW Specific Cross References
paragraph 1.5 is now Normative
References 1.8
Section 2. Roles and Responsibilities.
New paragraph is added 2.4 Employees
Section 4. Responsibilities. New
paragraph is added 4.7 Post-Test
Integrity Checks
Section 5. Leak Testing Guidelines.
New paragraph is added 5.10 Repairs or
additions after leak testing.
Appendix D. New appendix provides
opportunity for quick feedbacks and/or
improvement suggestions.
05 December 2008
Yuliy Zaytsev
Adalat Mamedov
Authority position/name and custodian
Safety & Compliance
Central Safety TL
name have changed to reflect org
Systems Manager
changes in HSE&TD.
23 April 2009
Yuliy Zaytsev
Niyaz Mamedov
Additional alteration made to Paragraph
Safety & Compliance
HSE Systems -
1.1 in regard to the maximum operating
Systems Manager
Control of Work
pressure
(MOP) and PSV. The same
Advisor
issue is accordingly reflected in
Appendix A - List of Definitions.
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Leak Testing of In-Service Equipment
Page 23 of 23
Control Tier:
<<2>>
Revision Date: 23 April 2009
Document Number: << AZSPU-HSSE-DOC-00055-2>>
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Lifting Operations
Page 1 of 55
Procedure for Lifting Operations
AZSPU-HSSE-DOC-00056-2
This number supersedes UNIF-HSE-PRO-109-C1
AzSPU Engineering
AzSPU Lifting Operations
Authority:
Custodian:
Authority
Technical Authority
Document
Scope:
AzSPU
Administrato
Document Asset Technician
r:
Issue Date:
06 July 2004
Issuing Dept:
Engineering
Revision
05 August 2010
Control Tier:
2
Date:
Next Review
30 December 2010
Date:
Control Tier:
<<2>>
Revision Date: 05 August 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Lifting Operations
Page 2 of 55
TABLE OF CONTENTS
1
INTRODUCTION
Document Purpose
Document Scope
Legislation & Standards
Stopping Unsafe Work
Medical
Deviations
Document Review
SSOW Specific Cross References
Lifting Operations Golden Rules of Safety
Language Facilitation
Procedure Summary
2
DEFINITIONS & ABBREVIATIONS
3
LIFTING EQUIPMENT
3.1
Category 1: Portable Lifting Equipment (Lifting Appliances)
3.2
Category 2: Fixed Lifting Equipment
3.3
Category 3: Mobile Equipment
3.4
Category 4: Cargo Carrying Units
3.5
Category 5: Transit Slings
4
EXAMINATION PHILOSOPHY
4.1
Examination of Portable Lifting Equipment
4.2
Examination of Fixed Lifting Equipment
4.3
Examination of Transit Slings
4.4
Examination of CCUs
4.5
Examination of Mobile Lifting Equipment
5
REPORTS / RECORDS
5.1
Strategy
5.2
Storage & Availability of Records
6
CONTROL PROCESSES
6.1
Rigging Loft (Storage Area)
6.2
Colour Coding
6.3
Control of Portable Lifting Equipment
6.4
Control of Fixed Lifting Equipment
6.5
Control of Transit Slings
6.6
Control of Cargo carrying Units (CCUs)
6.7
Control of Mobile Lifting Equipment
6.8
Control of Third Party Contractor Lifting Equipment
6.9
Control of Uncertified Structural Components
1.10
Control of Webbing & Round Slings
Control Tier:
<<2>>
Revision Date: 05 August 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED
VERSION OF THIS DOCUMENT CAN BE FOUND AT http://docs.bpweb.bp.com/dkazspu/component/hssesms
Procedure for Lifting Operations
Page 3 of 55
7
COMPETENCY
7.1
Competencies and Training of Personnel
8
ROLES and RESPONSIBILITIES
8.1
Site Manager / Site Controller / Offshore Installation Manager
8.2
Area Authority
8.3
Banksman
8.4
Rigger / Slinger
8.5
Crane Operator
8.6
Forklift Driver
8.7
Site Competent Person
8.8
Lifting Inspector
8.9
Site Lifting Coordinator
8.10
Mechanical Handling Contractor‟s (MHC) Technical Support Engineer
8.11
Lifting Technical Authority (LTA)
8.12
Senior Technical Authority (STA)
9
COMMUNICATIONS
10
RISK ASSESSMENT & PLANNING of LIFTING OPERATIONS
10.1 Strategy
10.2 Spheres of Responsibility
10.3 Planning Process
Appendix A: Glossary of Terms
Appendix B: Inspection & Certification of Temporary or New Cranes
Appendix C: References
Appendix D: Examples of Lifting Plans
Appendix E: Checklist for Pre-use - Mobile Crane Inspection Form
Appendix F: BP North Sea Lifting Rules
Appendix G: BP AzSPU References for Selection, Application & Control of Man Made Fiber
Slings for lifting Operations
Appendix H: Wind Force Scale
Appendix I: Procedure Summary
Appendix J: Feedback & Improvement Suggestions
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 4 of 55
1
INTRODUCTION
1.1
Document Purpose
This document is based on the UK Lifting Operations and Lifting Equipment Regulations
1998 and SI 1998/2307 (LOLER). It presents the BP standards applicable to the safe use of
lifting equipment in Azerbaijan Strategic Performance Unit.
LOLER implements the lifting provisions of the Amending Directive to the Use of Work
Equipment Directive (AUWED, 95/63/EC) and build upon the requirements of the Provision
and Use of Work Equipment Regulations 1998 (PUWER).
It is important to note that all work equipment, including that deemed to be „lifting‟ under
LOLER, shall require to be maintained in an efficient state, in effective working order and in
good repair, LOLER Regulation 5.
This document satisfies the requirements of lifting operations in the BP Golden Rules of
Safety. The BP North Sea Lifting Rules and other references are cited in Appendix C.
1.2
Document Scope
The contents of this procedure are applicable to all BP owned and managed sites /
installations in Azerbaijan and Georgia. Contractors working on BP owned or managed sites
/ installations are also responsible for alignment with this procedure.
This document does not replace the procedures prepared and adopted by specialist
contractors. Neither does it supersede any national and local regulatory requirements.
This procedure complies with the „HSE expectations‟ contained in „getting HSE right‟, the
Golden Rules of Safety, and the Control of Work
(CoW) standard that the hazards
associated with BP activities are identified and that the risks are assessed and managed.
All guidelines contained in this document shall be regarded as the minimum requirements for
BP owned or managed sites / installations in Azerbaijan and Georgia.
The scope covers defined activities of BP and Contractors at all BP AzSPU sites and
installations.
The contents of this document apply to work carried out by or on behalf of the AzSPU.
The scope of this document incorporates mechanisms to ensure:
¾ All items of work equipment covered by AzSPU identified as lifting equipment are
operated and maintained in a safe and fit for purpose condition
¾ Lifting operations are carried out in a safe manner
¾ Risks to plant equipment and personnel involved in lifting operations are identified,
appropriately assessed and mitigated to ensure that these are at all times as low as
reasonably practicable
¾ Equipment, procedures, and standards of competency etc. are identified and
managed in a safe manner
¾ Roles and responsibilities for all lifting operations and activities are clearly defined
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 5 of 55
1.3
Legislation and Standards
The aim of this Safe System of Work is to achieve no accidents, no harm to people, and no
damage to the environment. To achieve this aim, this SSOW complies with Azerbaijani
legislation, terms of the Production Sharing Agreement (PSA) and mandatory BP Standards.
The best international oil industry practice and relevant goal setting legislation have been
adopted to reduce the level of risk to as low as reasonably practicable and therefore well
below that mandated by applicable statutory laws and regulations.
In the absence of local regulations, BP Group Standards will apply. In addition, appropriate
UK and US regulations and industry best practice have been considered in setting suitable
goals and targets.
1.4
Stopping Unsafe Work
To stop the continuation of potentially unsafe work at the earliest possible stage, the Control
of Work policy and this Lifting Operations procedure make it very clear that all personnel are
obliged and have the authority to STOP the work that they consider to be unsafe.
1.5
Medical
All operators of lifting machines i.e. cranes, forklifts, MEWPs etc must be medically fit to the
requirements of AZSPU-HSSE-DOC-00007-2 and section 4 of the Scope and Frequency
document.
1.6
Deviations
This procedure is written in sufficient detail that it can be applied consistently at all sites /
installations. There may still be the requirement for some local rules covering site
/
installation specific logistical
/ administrative arrangements and local variations in
responsibilities to reflect differences in organizational arrangements. These local rules
should not deviate from the core processes within this document. Any form of deviation from
this procedure, including but not limited to local rules, shall be requested and authorized in
accordance with SSOW, Deviations from Regulations and Procedures procedure (Doc. No.
AZSPU-HSSE-DOC-00011-2).
1.7
Document Review
This document will be reviewed on an annual basis when users from the sites / installations
will have an opportunity to propose changes to the existing processes and procedures. The
document Technical Authority will be responsible for coordinating this review.
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 6 of 55
1.8
SSOW Specific Cross References
This procedure shall be used where appropriate in conjunction with the suite of AzSPU
Procedures referenced below.
Document Number
Title of Procedure
AZSPU-HSSE-DOC-00011-2
Deviations from Regulations and Procedures
AZSPU-HSSE-DOC-00054-2
Incident Investigation and Reporting
AZSPU-HSSE-DOC-00060-2
Permit To Work
AZSPU-HSSE-DOC-00012-2
Authorization
AZSPU-HSSE-DOC-00063-2
Task Risk Assessment
AZSPU-HSSE-DOC-00059-2
Man Riding Operations
AZSPU-HSSE-DOC- 0002-2
Control of Work Standards
1.9
Lifting Operations Golden Rules of Safety
Lifting Operations is one of BP‟s Golden Rules of Safety and states:
Lifting operations over „live‟ equipment may only be undertaken if all other options have been
considered and ruled out. Lifts utilizing cranes, hoists, or other mechanical lifting devices will
not commence unless:
¾ An assessment of the lift has been completed and the lift method and equipment has
been determined by a responsible person
¾ Operators of powered lifting devices are trained and certified for that equipment
¾ Rigging of the load and supervision of the lift is carried out by a competent person
¾ Lifting devices and equipment have been verified fit for use within the last 12 months
(as a minimum)
¾ Load does not exceed dynamic and / or static capacities of the lifting equipment
¾ All safety devices installed on lifting equipment are operational
¾ All lifting devices and equipment have been visually examined before each lift by a
competent person
¾ Non-essential personnel are out of any area where they might be injured by a falling or
shifting load
1.10 Language Facilitation
Due to the various languages spoken at different sites and installations, there is a necessity
to assist all with an ease of understanding. Therefore, the development and use of
information tools are available.
1.10 Procedure Summary
A Procedure Summary has been developed in a form of a leaflet, which can be carried by
line supervisors while conducting their day-to-day work tasks. The leaflet summarizes the
contents of this Lifting Operations procedure. The procedure summary can also be used as
a guideline for line supervisors to deliver their daily toolbox talk.
(See Appendix I)
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 7 of 55
2
DEFINITIONS & ABBREVIATIONS
ASNT: American Society of
ACO: Approved Code of Practice for LOLER
Non-Destructive Testing
AzSPU: Azerbaijan Strategic Performance
CITB: Construction Industry Training Board
Unit
EMTA: Engineering and Machines
CCU: Cargo Carrying Unit
Training Association.
ECITB: Engineering and Construction
IMR: Inspection maintenance routine
Industry Training Board.
LOLER: Lifting Operations and Lifting
MHC: Mechanical Handling Contractor
Equipment Regulations 1998, S.I. 2307
NDT: Non-Destructive Testing
NVQ: National Vocational Qualification
OPITO: Offshore Production Industry
PCN: Personnel certification in NDT
Training Organization.
PMR: Planned Maintenance Routine
PPE: Personal Protective Equipment
PUWER: Provision and Use of Work
PU: Performance Unit
Equipment regulations 1998, S.I. 2306
RACI: A document describing positions or
people who are Responsible, Accountable,
RTITB: Road Transport Industry Training.
Consulted, and Informed for actions.
SI: Statutory Instrument
SSOW: Safe System of Work
SVQ: Scottish Vocational Qualification
SWL: Safe Working Load
3
LIFTING EQUIPMENT
All lifting equipment shall be marked with a unique identifier, safe working load and portable
lifting equipment shall be colour-coded.
Lifting equipment and mechanical handling aids can be divided into four main categories,
which reflect different purposes, different re-certification methods and different areas of
responsibility.
These categories can be summarized as follows:
3.1
Category 1: Portable Lifting Equipment (Lifting Appliances, Accessories)
Portable lifting appliances are generally defined as:
Any mechanical device capable of raising or lowering a load e.g. chain blocks, pull lifts, Tirfor
machines, powered hoists, beam clamps, sheave blocks.
Portable lifting accessories are defined as:
Any below the hook device which is used to connect a load to a lifting appliance e.g.
shackles, wire rope slings, chain slings, sling sets, swivels, turnbuckles, plate clamps etc. A
suitably trained competent person shall examine and document portable lifting equipment at
six month intervals.
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 8 of 55
Clarification on four leg sling sets: Four leg sling sets must be fitted to a quad link assembly
and not four sling legs onto one link. The safety factor of the wire must be 5:1.
This equipment will be stored and issued from a designated storage area. This is generally
a cargo container modified for the purpose of storing lifting equipment, generally referred to
as a rigging loft.
Portable lifting equipment appliances will be supplied via the rigging loft and subjected to the
relevant site specific lifting controls and procedures.
3.2
Category 2: Fixed Lifting Equipment
Fixed lifting equipment are those items of lifting equipment permanently installed at the site
such as overhead cranes, hoists trolley beams, pad eyes, davits, swing jibs, man riding
winches, tugger winches, etc.
Maintenance schedules and records of inspection and testing shall be maintained through
Maintenance Management System (MMS) via the Planned Maintenance Routine (PMR)
schedules and Written Schemes of Examination (WSE) or appropriate auditable method.
3.3
Category 3: Mobile Equipment
Equipment mounted on wheels or tracks and is self propelled or specifically designed to be
attached to or pulled by a vehicle are defined as mobile equipment.
This category of lifting equipment includes but is not limited to:
¾ Mobile cranes
¾ Mobile forklifts
¾ Mobile working platforms
¾ Mobile knuckle boom cranes / hiabs
¾ Cargo handling equipment (fitted with load indicator)
3.4
Category 4: Cargo Carrying Units
Offshore Containers: Portable units for use in the transportation of goods or equivalent,
handled in open seas, to and from fixed and / or floating installations.
Units designed to the BS/EN
12079 standard are suitable for shipment to offshore
installations.
Units that do not comply with the EN 12079 should be examined in accordance with the BP
check list and if fit for purpose a technical deviation shall be applied for before shipment.
Examples of offshore Cargo Carrying Units (CCUs) are containers, lifting baskets, waste
skips, skids, and power packs etc.
Onshore Containers: Portable units for repeated use in the transportation of goods or
equivalent, handled via crane or forklift on shore based yards or in harbour areas (not lifted
to offshore installations).
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 9 of 55
Units used onshore or loaded onto boats in harbour areas do not need to conform to the
BS/EN 12079 standard but must be suitably fit for purpose and subject to a two yearly load
test and six monthly visual examinations as per industry standards.
CCUs permanently held onshore include rigging lofts, paint stores, temporary office units
etc.
Freight Containers - Units generally supplied with materials via coastal ports and fitted with
ISO corner casting lifting points.
Units fitted with ISO corner casting lifting points are not suitable for lifts to and from offshore
installations with a four or five leg sling arrangement.
As per the standard BS 3951-2 unit types A, B, C are not designed to be lifted by sling sets,
see BS 3951 - 2 section 6.3.1.
Onshore - Units weighing less than five metric tons (gross) maybe lifted with a four or five
leg sling arrangement, if fit for purpose and the original manufactures data plate is intact.
Shore based units over five metric tons (gross) should be lifted with a suitable spreader
beam to ensure only vertical loadings are applied on the main structure or a lower twist lock
spreader beam arrangement my be used, if fit for purpose and the original manufactures
data plate is intact.
Offshore - Under controlled and planned conditions, an approved lifting frame may be used
with a technical deviation.
Onshore - Single Point Lifts
CCUs or skids with single point lifts are not acceptable offshore in open seas form supply
boat to platform. CCUs or skids that are properly certified with correct centre of gravity for
an even lift may be lifted onshore or onto boats in harbour areas.
All CCUs must be regularly inspected, tested and a valid certificate to be in place prior to
use.
3.5
Category 5: Transit Slings
Lifting equipment accessories such as slings and shackles referred to as „transit slings‟ are
generally used on offshore facilities for general cargo handling and transportation duties.
Transit slings are used for cargo handling, boat transfer, and transportation duties and must
not be used for general lifting operations.
Due to the particular duty and environmental conditions to which this category of equipment
is subjected, i.e. shock loading and corrosive atmosphere, transit slings shall be used once
and then quarantined for back load and destroyed and replaced when returned onshore.
Transit slings shall not be reused for a return trip. Demonstrable management and
adherence to the one time use policy is to be asset specific.
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 10 of 55
Transit slings shall only be used for lifting loads during delivery to an offshore facility or back
loaded to shore. Unbundled drill pipe or tubulars shall be fitted with new slings / bulldogs /
tie wraps for the return journey.
4
EXAMINATION PHILOSOPHY
A statutory examination known as a Thorough Examination will be carried out as per specific
requirements defined in this section.
An Authorized Lifting Equipment Inspector shall perform all Thorough Examinations (as
defined in Appendix A) of lifting equipment within AzSPU.
4.1
Examination of Portable Lifting Equipment
A Thorough Examination of all portable lifting equipment shall be conducted and
documented every six months. An Authorized Lifting Equipment Inspector must approve
inspection, testing, and maintenance procedures.
All portable lifting equipment must have original certificate (birth certificate). Where the
original or an approved copy is not available or out of date, re-certification will be necessary.
A competent person must inspect portable lifting equipment prior to issue and use.
The rigging loft keeper or responsible person shall implement the six monthly thorough
examination and colour coding of equipment, control of equipment, control quarantine area
and pre use examinations of all equipment signed out from his control.
4.2
Examination of Fixed Lifting Equipment
All fixed lifting equipment (excluding offshore pedestal cranes) is subject to a six monthly
thorough examination and colour coding performed by authorized lifting equipment
inspector.
All fixed lifting equipment must be registered in Computerized Maintenance Management
System (CMMS) or equivalent complete with inspection and maintenance intervals (including
six month thorough examination).
It is responsibility of an Authorized Lifting Equipment Inspector to develop inspection /
maintenance / certification program based on regulations, established best practices and
history information (excluding offshore pedestal cranes).
A BP approved inspection and maintenance program for offshore pedestal cranes should be
developed and performed by company responsible for crane management through CMMS or
equivalent.
4.3
Examination of Transit Slings
A competent person must examine all transit slings prior to use.
Transit Slings shall not be used offshore for any other purpose than a single transit or
delivery to or from a facility.
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 11 of 55
Due to the particular duty and environmental conditions to which this category of equipment
is subjected, i.e. shock loading and corrosive atmosphere, it shall be destroyed immediately
following its return onshore.
4.4
Examination of CCUs
All CCUs with pad-eyes must be regularly inspected, tested, and recertified.
Offshore - CCUs must be manufactured to EN 12079, 2006 standard as a minimum and
inspected every six months and load tested every two years.
It is important to note that the lifting assembly fitted to CCUs are deemed to be accessories
for lifting and shall therefore be subjected to a six monthly thorough examination.
Units that do not comply with the EN 12079 should be examined in accordance with the BP
check list and if fit for purpose a technical deviation shall be obtained before shipment.
Onshore - CCUs permanently held on site, which are lifted on a regular basis or otherwise
in service, will be subject to a two yearly load test and six monthly visual examinations as
per industry standards.
CCUs permanently held onshore include rigging lofts, paint stores, temporary office units
etc.
Freight Containers - Units fitted with ISO corner casting lifting points shall comply with BS
3951.
Records of examinations of these units shall be kept with the Site Controller and a register
detailing the location and the next examination due dates maintained.
All CCUs must be appropriately checked prior to use.
4.5
Examination of Mobile Lifting Equipment
All mobile lifting equipment must be supplied, maintained, inspected, certified as per
manufacturer recommendations and relevant standards
(BS
7121, ASME B30.5 or
equivalent, see references in appendix C). Ensure that certification can be located for all
ropes, hook blocks, wedge sockets, crane accessories and calibration or verification
certificates for the load indicator.
Temporary or new cranes, forklifts, cherry pickers, hiabs and load cargo handling equipment
to sites must be checked and fully inspected prior to use by a registered or approved
competent person, additionally all certification should be reviewed to ensure items meet
required standards (Standard check list Appendix E).
Daily checks should be made on mobile / crawler cranes, forklifts and cherry pickers by
operator and recorded on a check sheet; these check sheets should be issued to the
maintenance department to form part of the Maintenance Management System and Planned
Maintenance Routine schedules and Written Schemes of Examination or appropriate
auditable method. (Standard check list Appendix E)
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 12 of 55
5
REPORTS / RECORDS
5.1
Strategy
Each site must have a complete register of all lifting equipment.
Hard copies of all the lifting equipments original certification, all Thorough Examination
certificates shall be kept on site with the Site Lifting Coordinator or Superintendent.
A register of lifting and rigging loft equipment including the information below should be
maintained.
¾ Unique Identification Number
¾ Safe Working Load or Working Load Limit
¾ Description sufficient to identify the item
¾ Location
¾ Original test certificate details
¾ Date of last Thorough Examination and certificate number
¾ Name of inspector carrying out examination
¾ Name of company carrying out examination
¾ Date of additional thorough Examinations and certificate numbers
¾ Date of next Thorough Examination
¾ Any remedial work or areas not inspected (internal parts)
¾ Quarantined / defect report number if applicable
The lifting equipment register must accurately describe all lifting equipment on site.
Third party Thorough Examination reports shall be held on the asset, by the relevant
supervisor, until such times as the equipment is returned to the supplier.
The register shall be regularly audited. It shall be the responsibility of the competent person,
to check the relevant lifting equipment register to confirm the current status of the equipment
prior to use.
5.2
Storage and Availability of Records
The Site Manager / Site Controller / Offshore Installation Manager shall ensure that the
records are properly maintained and are in order.
6
CONTROL PROCESSES
6.1
Rigging Loft
A rigging loft concept shall be used for pre use inspection, management, and control of
portable lifting equipment appropriate to the work site.
The rigging loft will consist of a secure controlled storage area providing the following:
¾ Storage of new equipment
¾ Quarantine of defective equipment
¾ Inspection area / Document control
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 13 of 55
Any items are released form the rigging loft must undergo a pre use inspection by a suitably
trained competent person.
A competently trained responsible person will become the Rigging Loft Controller and will
hold the key for the rigging loft for each shift.
Lifting equipment issue will be recorded by the rigging loft controller in the equipment issue
section of the „Register and Control Document‟ spreadsheet, detailing the date issued, pre
use inspection has been carried out, equipment plant number and description, location or job
site, signature of person, name and company of personnel using the item, date returned and
return inspection comments.
All items of equipment including slings, shackles, and eyebolts will be registered.
All returned items shall be subject to a receiving inspection by the rigging loft controller prior
to release into the rigging loft stock.
Items awaiting inspection will be held in the designated inspection area of the rigging loft.
The rigging loft keeper is also responsible for the control and management of the quarantine
area.
For BP operations sites this process is detailed in document OPSB-OPS-PRC-063.
Contractor sites must operate under an approved controlled operational procedure for
rigging lofts.
6.2
Colour Coding
All portable lifting equipment shall be colour coded to give visual indication of its certification
status prior to use. Some fixed lifting equipment may be colour coded.
The colour code system denotes a thorough examination within the past six months and that
a valid examination report exists. Conduct a visual examination prior to use, as colour
coding does not guarantee that equipment is in serviceable condition.
Incorrectly coloured portable lifting equipment shall not be used under any
circumstances.
The valid colour codes boards shall be visibly evident at all sites.
Colour coding, listed in section 6.3, is an established industry practice. Any other coding
convention must be discontinued.
All sites shall adopt a strict colour code system for lifting and rigging equipment. An
approved site specific procedure must be in place.
Each colour code shall be valid for a period of six months.
A suitably trained and competent person i.e. third party testing company should carry out
colour coding.
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF
Procedure for Lifting Operations
Page 14 of 55
6.3
Control of Portable Lifting Equipment
On BP controlled sites / installations the following colour code cycle will be used on portable
lifting equipment of categories 1 and 2 to indicate that they have been examined and fit for
use for a six-month period:
Green
(October 2008 to April 2009)
Blue
(April 2009 to October 2009)
Yellow
(October 2009 to April 2010)
Then back to Green
NOTE: Clearly identified colour codes for the six month period shall be posted in Permit
offices and security entrances to the site or facility.
NOTE: Colour Coding shall be clearly demonstrated against black backg2round
Portable and fixed lifting equipment and accessories that have been rejected on post use
examinations must be stored in the quarantined area of the rigging loft and will have the
colour coding painted over with white paint and tagged „Do Not Use‟ until such time that
the item is returned to the supplier for repair or replacement.
The Rigging loft concept shall be used for management and control of portable lifting
equipment appropriate to the work site.
The rigging loft will consist of a secure controlled storage area providing the following:
¾ Storage of new equipment
¾ Quarantine of defective equipment
¾ Inspection area / document control
6.4
Control of Fixed Lifting Equipment
All Fixed Lifting Equipment shall have a unique visible identification number or reference
number entered into CMMS or equivalent.
All fixed lifting equipment approved for personnel transfer (manriding) must be properly
identified.
6.5
Control of Transit Slings
All transit slings will be colour coded as shown below. This will ensure that all lifting
equipment is easily identified and kept separate from the transit slings. The control and
recertification of unused transit slings shall be the responsibility of the Site Manager, Site
Controller, or Offshore Installation Manager.
Brown
(April to October)
Purple
(October to April)
Control Tier:
<<2>>
Revision Date: 27 April 2010
Document Number: << AZSPU-HSSE-DOC-00056-2>>
Print Date: 2/1/2011
PAPER COPIES ARE UNCONTROLLED. THIS COPY VALID ONLY AT THE TIME OF PRINTING. THE CONTROLLED VERSION OF

 

 

 

 

 

 

 

Content      ..     38      39      40      41     ..