G
ENERAL
R
1.16.2
Design Details for Temporary Works
The Contractor shall include the information and details necessary to enable temporary works
construction without reference to any supplemental drawing, calculation sheet, design standard, or
other source document. For falsework, the Contractor shall show all dimensions that control the
design and erection of falsework, including beam lengths, distances between beams, post locations,
distances between posts, vertical distances between connections in diagonal braces, and the heights
of falsework bents (braced frames).
The Contractor shall show the maximum applied dead and live structural loads on each foundation.
Information from the Contractor shall include a drainage plan that describes how work structures will
protect foundations from saturation, erosion, and scouring.
The Contractor shall show anticipated total settlements of falsework and forms, including falsework
footing settlement, joint take-up and elastic deformation. By design, anticipated settlements shall not
exceed 20 mm. Each falsework shall be designed and constructed to elevations that include
anticipated settlement during concrete placement and required camber to compensate for member
deflections during construction.
Temporary waterway bridges shall span the desired water opening and have dimensions that avoid
constricting any stream’s flow while such bridges are in use. To meet basic design criteria, the bridge
system shall be sufficient for a 5-year frequency storm (that is, the worst storm that is anticipated
within any five-year period), with allowance for 150 mm of backwater. The plans shall show the
minimum bridge lengths between abutment piling and the resultant water elevation caused by a five-
year frequency storm. To determine a minimum low superstructure elevation, the Contractor shall
use the given high water elevation and consider local conditions. A temporary work for structure shall
have the minimum roadway width specified in the particular project specifications, as measured
between the faces of the railings or curbs and at right angles to the centreline. Vertical abutments
shall, by design, prevent spilling fill material into the water. Any temporary crossing over sea water
that is subject to boating shall provide horizontal and vertical clearance in accordance with the
appropriate jurisdictional agency.
1.16.3
Materials for Temporary Works
The Contractor shall precisely describe all materials for proposed temporary works, including
materials that are not designated by standard nomenclature (such as AASHTO or ASTM
specifications), based on manufacturer‘s tests and recommended working loads. The Contractor
shall evaluate materials for temporary works and ascertain whether their physical properties and
conditions are sufficient to support the design’s assumed loads.
1.16.4
Concrete Placement for Temporary Works
The Contractor shall provide an outline of the proposed concrete placement operation with a list of
the equipment, labour, and procedures to be used for the duration of each operation. The Contractor
shall include details, such as proposed placement rates and design pressures, etc for each pour.
Information from the Contractor shall include a superstructure placement diagram that shows the
sequence of concrete placements and construction joint locations.
1.16.5
Openings in Temporary Works
The Contract plans shall show the locations of all openings through a falsework that enable public
traffic to pass. The Contract plans shall include all horizontal and vertical clearances and the
locations of temporary railing. For falsework over traffic, the Contract plans shall show the sequence
of falsework erection and removal. The Contractor shall submit separate falsework drawings for each
structure, except for structures with entirely identical falsework designs and details. Construction of
any unit of falsework shall not begin until the project Engineer has reviewed and approved the
drawings for that unit including requirements for height warning structures and locations.