Instruction Manual for Single Stage 350, 500, and 700 Frame Steam Turbines - page 2

 

  Главная      Manuals     Instruction Manual for Single Stage 350, 500, and 700 Frame Steam Turbines

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..      1      2      3      ..

 

 

 

Instruction Manual for Single Stage 350, 500, and 700 Frame Steam Turbines - page 2

 

 

WARNINGS
If the turbine is supplied with oil mist lubrication oil mist could escape
from the bearing housing vents or constant level oiler. If there is the
possibility that these could be ignited by equipment of processes in
the proximity of the turbine they should be piped to a safe area.
Lighting must be installed in the installation area to insure that
operators can see the turbine and its controls.
Do not install the turbine where ambient temperature could be -20°
F or less unless this was specified in the original order and LOW
TEMPERATURE materials have been provided. Refer to Section F,
Lubrication System, for ambient temperature limits based on
lubrication.
Proper installation of the turbine and driven equipment is vital for successful
operation of the system. It is for this reason that competent, experienced personnel
should be employed during installation. Before installing turbine refer to the
certified drawings in Appendix A of this manual.
Dresser-Rand recommends that API Recommended Practice RP-686 be consulted
for additional guidance in regard to the installation of the turbine and driven
equipment package. It provides recommended procedures, practices and quality
assurance checklists covering the installation and de-commissioning of turbines,
compressors, fans, motors, gear reducers and pumps for use in petroleum,
chemical, gas industry and other facilities.
The following subsections, C.2 through C.11, provide basic installation and
decommissioning procedures. Follow them in the indicated sequence for complete
and correct installation. These recommendations and instructions are provided to
assist the purchaser and/or his contractor. Fully qualified labor, including qualified
supervision, is required for proper installation, start-up, and subsequent operation
of the equipment. The services of a Dresser-Rand serviceman are recommended for
the final on site installation review and the initial commissioning and start-up of the
turbine.
As a minimum the following steps must be carried out in sequence to achieve
satisfactory operation.
64
Speed Control System
WARNINGS
NEVER CONNECT the steam turbine to inlet or exhaust
sources of UNKNOWN PRESSURE OR TEMPERATURE, or to
sources whose pressure or temperature EXCEED limits stated
on the NAMEPLATE.
Misalignment with driven equipment or overload due to driven
equipment could result in excessive wear and bearing failure.
This could create sparks or hot surfaces could ignite lubricant
or flammable gasses.
a.
Refer to the certified drawings in Appendix A and carefully read all
installation notes, piping connection details, dimensions and clearances, and
any other special data.
b.
Provide a proper and adequate foundation for the turbine.
c.
Provide a proper piping installation, in accordance with NEMA SM23, that
will accommodate pressure forces and thermal growth without imposing
excessive force on the turbine.
d.
Remove all protective coatings and foreign matter from the turbine and all
piping. If the turbine was prepared for long-term storage, reinstall the matched
carbon ring sets, springs and washers into the turbine gland housings.
e.
Refer to coupling alignment instructions supplied by the coupling
manufacturer, as well as those supplied in this manual.
f.
Perform an accurate cold alignment.
g.
Grout the base-plate or sole plate to the foundation, as required.
h.
Carefully check hot alignment at operating temperature and adjust it, if
necessary, to establish accurate alignment.
i.
Dowel turbine and driven machine in place to maintain proper alignment.
C.2
Foundation
WARNING
65
If the turbine is installed in a location where there is the
possibility of an earthquake this must be considered in the
design of the piping and foundation.
The foundation is one of the most influential factors governing overall reliability of
a turbine. A foundation must maintain alignment under all normal and abnormal
conditions. This includes the way a foundation is supported on the soil and/or
superstructure, soil settling, soil resonances, thermal distortion, piping forces, and
vacuum pull or pressure forces in expansion joints.
The turbine, gear reducer (if used), and driven equipment should all be mounted on
a common foundation.
Sufficient space should be provided around and above the foundation to allow for
proper installation and maintenance.
The foundation must minimize vibration by being as heavy as possible and non-
resonant. It is important that the turbine be isolated from external vibration. Neither
the foundation nor related support structure should be resonant within the operating
range of the turbine.
Vibration transmissions may occur from the unit to the surroundings, or vice versa;
vibration may also be aggravated by resonance at transmission frequencies. Piping,
stairways, and ducts may also transmit vibration, which should be prevented by
proper isolation.
A certified outline drawing is furnished with each Dresser-Rand turbine and is
included in this manual in Appendix A. This drawing includes dimensions for
locating anchor bolts, equipment weights, and general information required for
determining foundation dimensions and design.
A generous safety factor should be used when determining foundation thickness.
The foundation length and width should extend at least 6 inches (152 mm) beyond
the anchor bolts.
Anchor bolts must be positioned accurately and provided with sleeves. The sleeve
bore diameter should be approximately twice the bolt diameter, but should provide
not less than 1/2” (13 mm) clearance all around the bolt.
Carefully constructed templates are required to hold bolts and sleeves in position
while the foundation is cast. Templates are usually made of wood and secured to
the foundation forms. Experienced workers should be able to set anchor bolts to a
tolerance of 1/8” (3 mm) by locating and drilling holes in the template after they
have been secured to the braced forms.
66
Speed Control System
Anchor bolts should be threaded at both ends and be of sufficient length to extend
one-and-a-half to twice the bolt diameter above the top of securing holes in the
base plate or the sole plate. The lower end of each bolt is enclosed in a sleeve and
passes through an anchor plate, where it is secured by a nut to which it is welded.
Anchor plates can be either washers or plates of cast iron or steel. They should
have a diameter or side dimensions of approximately twice to two-and-a-half the
outside diameter of the sleeves.
Notes:
1.
Templates must be rigid enough to prevent bolts from shifting while the
concrete is being poured.
2.
After concrete has been poured and before it has hardened, recheck positions
of the anchor bolts.
3.
Allow a 1-1/2” (38 mm) gap above the top of the foundation surface for
grouting under edges of the base plate or sole plates.
C.3
Piping
WARNING
Improperly designed or installed piping can lead to turbine
misalignment and failure of the turbine or driven equipment. It
is the user/installers responsibility to insure that the piping
system is properly designed, installed and that it meets local
codes and regulations. All references to piping design in this
section are for reference only.
67
WARNING
If the turbine is installed in a location where there is the
possibility of an earthquake this must be considered in the
design of the piping and foundation.
Proper piping of a steam turbine is essential. Correctly designed and installed
piping contributes to safe, trouble-free operation and can improve ease of turbine
operation and maintenance.
Before installing any piping, installation personnel should read and become
thoroughly familiar with this section.
The effects of possible earthquakes should be taken into account when designing
the inlet and exhaust piping systems.
C.3.1
Piping Forces
Any pipe connected to the steam turbine casing, valves, gland housing, or bearing
housings can exert forces and/or moments on the turbine. This can misalign the
turbine with its driven equipment or distort the turbine casing, resulting in internal
misalignment of the turbine shaft with bearings, seals, and other components. Such
misalignment can cause vibration, premature wear or failure of bearings, seals,
couplings and shafts, and casing leaks.
Steam supply (inlet) and exhaust piping, being relatively large and subjected to
higher temperatures and pressures, can, if improperly installed, exert relatively
large forces and moments on a steam turbine. Leak-off, drain, lube, cooling water
and gland seal piping does not normally transmit significant piping forces.
To prevent excessive piping forces or moments, the customer must ensure that the
piping is designed and installed so as to comply with NEMA SM-23, Section 8,
Allowable Forces and Moments on Steam Turbines. The maximum allowable
forces and moments are a function of inlet and exhaust flange sizes. Flange sizes
are tabulated on the Certified Drawing appearing in Appendix A.
Piping forces can be reduced or eliminated with proper piping design, the use of
expansion joints, and correct piping support systems. Figure C-1, Suggested Steam
Inlet and Exhaust Piping Arrangement, suggests inlet and exhaust piping systems,
showing typical expansion joints, piping loops, and spring supports in the piping
system.
68
Speed Control System
Optional constructions, which include third-party throttle and/or over-speed trip
valves or other equipment configurations, may require the use of additional supports.
Refer to the certified drawings in the Appendix A.
Refer to a separate sketch in Appendix A for the estimated thermal movement of the
inlet flange and exhaust flange. The estimated thermal movements of the inlet and
exhaust flanges are used in the design and analysis of the piping support system.
Figure C-1. Suggested Steam Inlet and Exhaust Piping Arrangement
C.3.2
Isolating Valves
69
Inlet and exhaust lines to a turbine must be provided with isolating valves. The
purpose of these valves is to isolate the turbine from inlet and exhaust systems,
allowing the turbine to be shut down, along with sealing inlet and exhaust lines if
the turbine is to be moved or serviced.
DANGER
NEVER DISCONNECT inlet or exhaust piping of the turbine
without first CLOSING and TAGGING the ISOLATING VALVES
and then OPENING DRAIN VALVES SLOWLY to relieve any
pressure within the turbine. Failure to do so may expose
PERSONNEL to SERIOUS INJURY if steam was to be
introduced into the piping or captured in the turbine. As an
added precaution, always install blank flanges on inlet and
exhaust lines after removing the turbine.
The inlet piping isolating valve should be installed immediately upstream of the
turbine. Refer to Figure C-1, Suggested Steam Inlet and Exhaust Piping
Arrangement.
The exhaust piping isolating valve should be installed immediately downstream of
the full flow relief valve. Refer to Figure C-1, Suggested Steam Inlet and Exhaust
Piping Arrangement.
C.3.3
Full Flow Relief Valve
An atmospheric relief valve must be installed between the turbine exhaust flange
and the first exhaust line shut-off valve (Refer to Figure C-1, Suggested Steam Inlet
and Exhaust Piping Arrangement). The purpose of this relief valve is to protect the
turbine casing from excessive exhaust pressure. The relief valve must be of ample
size to pass the maximum quantity of steam flowing through the turbine at the
maximum inlet temperature and pressure steam conditions without allowing the
turbine casing pressure to exceed the limit defined below. It is the user’s
responsibility to install the relief valve in the piping.
The full flow relief valve shall begin to open at 10% or 10 PSIG (69 kPag) above
maximum exhaust pressure, whichever is greater, for non-condensing turbines; and
at not more than 10 PSIG (60 kPag) for condensing turbines. The valve shall be
fully open with an additional rise in pressure not to exceed 10%. Refer to NEMA-
23, Steam Turbines for Mechanical Drive Service, for further details.
70
Speed Control System
WARNINGS
It is the USER’S RESPONSIBILITY to INSTALL A FULL-FLOW
RELIEF VALVE in the exhaust line between the turbine exhaust
casing and the first shut-off valve. This relief valve should be
sized to relieve the FULL AMOUNT OF STEAM THAT THE
TURBINE WILL PASS, in the event that the exhaust line is
blocked.
The optional SENTINEL WARNING VALVE, located on the
turbine casing, DOES NOT SERVE as a RELIEF VALVE. The
sentinel warning valve WILL NOT PASS SUFFICIENT STEAM
FLOW to relieve the turbine casing of EXCESSIVE EXHAUST
PRESSURE. The purpose of the sentinel warning valve is to
warn visually and audibly that excessive pressure is building in
the turbine exhaust casing.
C.3.4
Inlet Piping
As shown in Figure C-1, Suggested Steam Inlet and Exhaust Piping Arrangement,
inlet piping should come off the top of the steam header and form an expansion
relieving loop or other strain relieving device, before coming down to the turbine.
A valved condensate drain should be installed in the inlet line upstream of the
isolating valve, allowing condensate to drain prior to opening the isolating valve
and feeding steam to the turbine. Piping must be supported in such a manner as to
allow thermal growth of the turbine and piping, without imposing excessive forces
and moments on the inlet flange. Properly installed piping should mate squarely to
the turbine inlet flange, without any need to force flanges by twisting them into
alignment when connecting them.
The inlet line should be well lagged to prevent heat loss and to avoid burns.
Pipe sizes should be large enough to maintain rated steam pressure at the turbine
inlet flange under maximum load conditions. In determining pipe size, proper
allowance should be made for pressure drop due to long sections of pipe, elbows,
valves, or other fittings between the boiler and the turbine.
If wet or saturated steam is used, it is very important that piping be arranged so that
condensate cannot be carried over into the turbine. A steam separator of the proper
size, with a trap of ample capacity, should be installed before the turbine inlet. All
horizontal runs must be sloped up in the direction of steam flow, with drains at the
low points.
71
The importance of protecting the turbine against slugs of water cannot be
overemphasized. The issue is not “wetness” of the steam, but with condensate,
which is separated out as water. The harmful effects of water are:
1. Rapid erosion of blading and valves.
2. In the case of turbine wheels with inserted blades, water may have a hammer-
blow effect, tearing out the blades and destroying the rotor.
3. Governing is adversely affected.
4.
The rotor may be permanently distorted and/or the turbine may be seriously
damaged.
5.
A danger of thrust bearing failure and consequent destruction of the turbine.
C.3.5
Exhaust Piping
Figure C-1, Suggested Steam Inlet and Exhaust Piping Arrangement, shows
exhaust piping together with the full flow relief valve and support system. Note that
the exhaust line should slope down toward the header or create an overhead loop,
to prevent condensate at the header from flowing back toward the turbine. Valved
drains should be installed before and after the exhaust-isolating valve.
On each installation, the length of run, elbows, valves, and other fittings in the pipe
must be considered, together with all factors, which may cause back-pressure on
non-condensing turbines or reduced vacuum on condensing turbines, and a final
decision on piping size made accordingly. On non-condensing turbines, back-
pressure which is higher than what the turbine was designed for will cause
reduction of power and an increase in steam consumption. It may also cause gland
leakage, and in extreme cases, can rupture the turbine casing. On condensing
turbines, decreased vacuum will have an even greater effect on capacity and
economy.
The exhaust pipe must be installed and anchored so that no excessive stress is
placed on the turbine from either the weight of the pipe or its expansion and
contraction. In cases where such an arrangement cannot be made with certainty, an
expansion joint near the turbine can be useful in low pressure lines and is usually
required on large pipe sizes. The use of an expansion joint does not of itself avoid
undue stress. It is not as flexible as many people assume and when installed, it must
be properly aligned and not indiscriminately exposed to shear or torsion. In the
majority of applications, axial thrust created on the cross-sectional area of the
largest bellows, by internal pressure, must be restricted by the use of tie rods. They
are most effective when the expansion joint is used in shear, instead of tension or
compression. When used in either a vacuum or a pressure line, tie rods must be
72
Speed Control System
arranged accordingly. They are useless where a joint moves under tension or
compression, as they bypass the joint and transmit pipe forces directly to the
turbine. Provision must be made to anchor the piping in such a way that excessive
forces will not be transmitted to the turbine during shutdown and operational
running. Connection to a header must be made at the top, never from the bottom or
side, and great care must be taken to avoid draining water back into the turbine. All
horizontal runs must be sloped away from the turbine exhaust connection.
Properly installed piping should mate squarely to the turbine exhaust flange,
without any need to force flanges by twisting them into alignment when connecting
them. The exhaust line should be well lagged to prevent heat loss and avoid burns.
C.3.6
Piping Blow Down
Newly constructed steam piping should be blown-down to remove scale, weld slag
and any other foreign material. Such material can cause severe damage if it enters
the steam turbine.
After inlet piping has been installed, but before connecting it to the turbine, steam
should be blown through the line and into the exhaust line to remove welding slag
and debris.
Refer to NEMA SM-23, Steam Turbines for Mechanical Drive Service or a reliable
piping contractor for a blow-down procedure.
CAUTION
INLET STEAM LINES MUST BE BLOWN DOWN PRIOR TO
CONNECTING them to the turbine. Debris and welding slag
can cause serious damage to valves, nozzles, and turbine
blading if allowed to enter the turbine.
C.3.7
Steam Strainer
Standard SST Dresser-Rand turbines are provided with integral inlet steam
strainers to prevent entry of foreign material into the turbine. Part of the throttle
valve is located in the same chamber with the steam strainer. The steam strainer
will allow small debris particles to pass through the turbine and does not preclude
the need for inlet piping blow-down prior to connecting the turbine. The steam
strainer should be removed and cleaned at least once a year and replaced at least
every three years or as needed.
When a turbine is supplied without an integral or separate y-type strainer, the
purchaser must install an appropriate steam strainer in the inlet steam piping.
73
C.3.8
Check Valve
Where a turbine exhausts or bleeds steam into another system, and a check valve
(commonly referred to as a non-return valve) is installed for prevention of reverse
flow to the turbine, adequate bracing must be installed to absorb any forces created
by water hammer effects occurring in the exhaust line downstream and acting on
the check valve. The maximum relief valve settings are found on the turbine data
sheets. The sentinel relief valve on the turbine case is a warning valve only.
C.3.9
Expansion Joints
Low pressure and vacuum lines are usually large and relatively stiff. It is common
practice to use an expansion joint in these lines to provide flexibility. If an
expansion joint is improperly used, it may cause a pipe reaction greater than the
one that it is supposed to eliminate. An expansion joint will cause an axial thrust
equal to the area of the largest corrugation multiplied by the internal pressure. The
force necessary to compress or elongate an expansion joint can be quite large, and
either of these forces may be greater than the limits for the exhaust flange. In order
to have the lowest reaction; it is best to avoid absorbing pipeline expansion by axial
compression or elongation. If it is found that expansion joints are required, it is
essential that they be properly located and their foundation rigid. Refer to NEMA
SM-23, Steam Turbines for Mechanical Drive Service or a reliable piping
contractor for steam piping system design and installation guidance.
See Figure C-2 Unrestrained Expansion Joint (not recommended).
Figure C-2. Unrestrained Expansion Joint (Not Recommended)
The axial thrust from the expansion joint tends to separate the turbine and the
elbow. To prevent this, the elbow must have an anchor to keep it from moving. The
turbine must also absorb this thrust, and in so doing, it becomes an anchor. This
force on the turbine case may be greater than the allowable force. In general, this
method should be discouraged.
74
Speed Control System
Figure C-3 Expansion Joint with Tie Rods (Acceptable) below shows the same
piping arrangement as in the previous figure, except for the addition of tie rods on
the expansion joint.
Figure C-3. Expansion Joint with Tie Rods (Acceptable)
The tie rods limit elongation of the joint and take the axial thrust created by the
internal pressure so it is not transmitted to the turbine flange. The tie rods eliminate
any axial flexibility, but the joint is still flexible in shear, meaning that the flanges
may move in parallel planes. The location of this type of joint in the piping should
be such that movement of the pipe puts the expansion joint in shear instead of
tension or compression.
Figure C-4 Expansion Joint with Tie Rods for Non-condensing Operation
(Preferred) below is an arrangement frequently used, with tie rods as indicated.
Figure C-4. Expansion Joint w/ Tie Rods Non-Condensing Operation (Preferred)
This arrangement will prevent any thrust, due to internal pressure, from being
transmitted to the exhaust flange. It retains the axial flexibility of the joint and may
be used for either vacuum or pressure service.
75
Figure C-5. Expansion Joint w/ Tie Rods Condensing Operation
(Preferred)
Figure C-5 shows a suggested arrangement for a condensing turbine with an up exhaust. This
arrangement is recommended and frequently used. Due to the large exhaust pipe size normally
encountered on condensing turbines, the exhaust piping will be relatively stiff and an
expansion joint must be used at some point to take care of thermal expansion. An
unrestricted expansion joint placed at the exhaust flange of the turbine will exert an upward
or lifting force on the turbine flange, which in many cases is excessive. Figure C-5
provides the necessary flexibility to take care of thermal expansion without imposing a
lifting force on the turbine. The expansion joint is in shear, which is the preferred use. The
relatively small vertical expansion will compress one joint and elongate the other, which
causes a small reaction only and will be well within the turbine flange limits.
On smaller and high-pressure exhaust lines it is frequently better to rely on the flexibility of
the piping than on an expansion joint. Only after a careful analysis of the piping shows the
need for an expansion joint should they be used.
In order to have flexibility in piping, short direct runs must be avoided. By arranging the
piping in more than one plane, torsional flexibility may be effectively used to decrease the
forces.
76
Speed Control System
Figure C-6. Short Runs to Exhaust Header
Figure C-6 shows a short direct run to an exhaust header. If the header is free to float in
a horizontal plane, thermal expansion of the exhaust line will put very little direct
thrust on the exhaust flange. If the header is fixed, the thermal expansion will tend to cause
either the turbine or header to move and may cause damage. If thermal expansion causes
the header to move in an axial direction it will transmit a force and moment to the exhaust
flange. Figure C-6 is not recommended, as it is difficult to prevent excessive forces
from being transmitted to the exhaust flange.
C.3.10
Leak-Off Piping
WARNINGS
Leak-off and drain connections of turbines operated on
flammable or noxious gas must be piped to a safe location to
avoid the possibility of ignition of the gas or poisoning of
operating personnel.
LEAK-OFF AND DRAIN LINES MUST NOT BE
INTERCONNECTED. A leak-off from a high pressure upstream
location connected to a steam chest drain or throttle valve leak-
off/drain could supply sufficient steam TO ALLOW THE
TRIPPED TURBINE TO CONTINUE RUNNING, since such an
interconnection would bypass the overspeed trip valve.
77
LEAK-OFF PIPES that are left UNCONNECTED will allow the
escape of HIGH TEMPERTURE STEAM that could cause
PERSONAL INJURY or contamination of lubricating oil.
Standard SST Dresser-Rand turbines are supplied with leak-off connections at the
gland housings, throttle valve, and overspeed trip valve. Leak-offs are piping
connections that allow steam leaking past seals to be carried away to a safe area.
Shaft and valve stem seals depend on some leakage for lubrication and to minimize
wear. Leakage is therefore acceptable and necessary.
The leak-offs must be pitched down and away from the turbine and connected to
open, unrestricted, separate, non-manifolded drain lines, which discharge to a safe
and visible area. There should not be any valves on leak-off lines. Leak-off piping
should be arranged to insure that no pressure build-up occurs in the system,
avoiding any low points where condensate could accumulate and may be connected
to a gland condenser, eductor or ejector. No vertical upward pipe runs are to be
included in leak-off piping. Unavoidable low points should be trapped.
On gas operated turbines, leak-offs must be piped to a safe area away from the
turbine site.
Locations and sizes of leak-off connections are shown on the certified drawing in
Appendix A.
Gland housings on turbines operating with vacuum exhaust or at high back pressure
require special Gland Seal leak-off systems.
For turbines operating with vacuum exhaust refer to Section C.3.11 Gland Seal
Leak-Off Piping-Vacuum Exhaust
Turbines operating with high back pressure may have intermediate leak-off
connections on their gland housings. Refer to Section C.3.12 Gland Seal
Intermediate Leak-Off Piping - High Back pressure Exhaust.
C.3.11
Gland Seal Leak-Off Piping - Vacuum Exhaust
On turbines exhausting to a vacuum, sealing steam at 5 to 10 PSIG (34 to 69 kPag)
pressures must be furnished through the carbon ring glands to prevent air from
entering the exhaust casing.
78
Speed Control System
Figure C-7. Typical Gland Sealing System without Gland Condenser
If gland seal piping is not furnished with the turbine, sealing steam connections
should be piped via a common connection to the user’s steam supply. A
recommended piping diagram for gland seal piping is shown in Figure C-6 Gland
Seal Leak-Off Piping - Vacuum Exhaust.
Frame
Relief
Gauge
Customer’s
Gauge
Angle Control Valve
Composition
Valve
Valve
Connection
Ashcroft
Kunkle
No. 1009
1/2” pipe 12.7 mm
Cat.
KGSC
Max. Press. 600
Vogt No. 1971 3/8”
Range 30”
Vogt No
Fig. No.
lbs. 750F 42.18
All Sizes
600 lbs. Steel 9.52 mm
to 30 lbs.
9871
40R
Kg/Cm2 399C
272 Kg.
760 mm to
Stainless
2.109
Steel
Kg/Cm2
Table C-1. Gland Intermediate Leak-Off Piping—High Back Pressure
Exhaust
79
Turbines to be operated with high back pressure may have intermediate gland leak-
offs that must be piped to a steam header with a pressure not less than 35 PSIG
(241 kPag) and not exceeding 70 PSIG (483 kPag). This intermediate leak-off
piping must include, for start up purposes, an atmospheric vent with a shut off
valve near the turbine and a check valve installed between the vent and the steam
header to prevent back-flow. Do not connect the intermediate leak-off piping with
other leak-off connections. Refer to Figure C-8 Gland Seal Int. Leak-Off Piping
High Back Pressure Exhaust.
Figure C-8. Gland Seal Intermediate Leak-Off Piping-High Back Pressure
Exhaust
C.3.12 Gland Seal Intermediate Leak-Off Piping—High Back Pressure Exhaust
In certain turbines with a high exhaust back pressure, a gland leak-off system is used. Figure 8
shows a typical system using gland ejectors connected to the leak-off piping of both packing
cases. The ejectors maintain a constant vacuum in the gland packing case leak-off lines. When
the ejectors are shipped separate from the turbine, the piping leak-off connections from the
turbine are shown on the outline drawing, Appendix A. If gland ejectors are required for your
turbine, the specific part number is listed on the Appendix A contents sheet. On certain designs,
a drip drain connection is located adjacent to gland leak-off on each packing case. These drain
connections must be plugged.
For leak-off systems that use a gland condenser, a system schematic diagram with operating
instructions is included in Appendix A, along with a description of the major components that
comprise the system.
80
Speed Control System
Figure C-9. Gland Leakage Ejector System
C.3.13
Drain Piping
WARNING
DRAIN PIPING flanges and valves must be SELECTED AND
INSTALLED BY EXPERIENCED PERSONNEL, taking into
account the MAXIMUM OPERATING STEAM PRESSURE
AND TEMPERATURE. Improperly designed or installed drain
systems could FREEZE, become PLUGGED AND RUPTURE,
causing serious personal injury or equipment damage.
81
Leak-off and drain connections of turbines operated on
flammable or noxious gas must be piped to a safe location to
avoid the possibility of ignition of the gas or poisoning of
operating personnel.
LEAK-OFF AND DRAIN LINES MUST NOT BE
INTERCONNECTED. A leak-off from a high pressure
upstream location connected to a steam chest drain or throttle
valve leak-off/drain could supply sufficient steam TO ALLOW
THE TRIPPED TURBINE TO CONTINUE RUNNING, since
such an interconnection would bypass the over-speed trip
valve.
Drains are low-point piping connections at valves and casings that allow release of
condensed water. Drains are opened before starting the turbine, to allow any
accumulated water to escape. They are left open during the start-up cycle to allow
water condensing in the cold casings to exit. Once the turbine reaches normal
operating temperature, drains should be closed.
The user must install drain valves when not supplied by Dresser-Rand.
Drains can be automated with properly sized steam traps, if desired. Refer to C-10
Suggested Steam Inlet, Exhaust and Drain Piping, Manual Start and Figure C-11
Suggested Inlet, Exhaust and Drain Piping, - Auto Start.
Sizes and locations of drains are shown on the certified drawing in the
Supplemental Documentation section, supplied at the end of this manual.
C.3.14
Water Cooling Piping to Bearing Housing Water Jackets
Depending on service conditions and the type of lubrication system supplied with
the turbine, bearing housings may require water cooling to maintain an acceptable
bearing oil temperature.
Refer to Section F, Lubrication, for cooling water application requirements,
suggested piping, water flow, pressure and temperature requirements, and oil sump
temperature.
82
Speed Control System
Figure C-10. Suggested Steam Inlet, Exhaust and Drain Piping, Manual Start
Figure C-11. Suggested Steam Inlet, Exhaust and Drain Piping, Auto-Start
83
C.4
Alignment Requirements
Many problems experienced with turbines, gears, and driven equipment is due to
misalignment. Units must be properly supported and their alignment accurately and
permanently established if the installation is to be successful.
WARNING
Misalignment with driven equipment or overload due to driven
equipment could result in excessive wear and bearing failure.
This could create sparks or hot surfaces could ignite lubricant
or flammable gasses.
CAUTIONS
ALIGNMENTS performed by the factory on turbines with gears
or other driven equipment mounted on base plates MAY SHIFT
during rigging or shipment. These alignments must be
RECHECKED before startup.
Never put a steam turbine into service without first carefully
ALIGNING it to the driven equipment under cold conditions and
then again at operating temperature. Failure to do so may
result in premature FAILURE of both TURBINE and DRIVEN
EQUIPMENT components.
Excessive vibration, bearing edge loading, and high shaft loads can result from
incorrect alignment. Factors affecting alignment can be settling of the foundation,
growth in shaft heights due to temperature changes, machine movement of either
unit with respect to the foundation due to vibration, worn bearings, or distortion of
the casing due to loads from connecting structures (such as piping). A dependable
turbine drive system requires that all of these factors be given proper attention prior
to and during alignment.
The turbine and driven equipment should always be aligned cold, checked later at
operating temperature, and re-aligned if necessary. Both shafts should be parallel
and their axes concentric so that there is no offset at operating temperature.
Two types of misalignment must be identified and corrected (if necessary) to be
within defined limits.
84
Speed Control System
Angular misalignment occurs when shaft centerlines intersect at an angle.
Figure C-12 Coupling Misalignment Limits
Parallel misalignment occurs when shaft centerlines are parallel to each other, but
do not intersect.
85
As previously noted, alignment is influenced by the thermal growth of both the
turbine and the driven equipment. This must be compensated for during cold
alignment by calculating the growth of each machine and intentionally creating a
parallel offset that will disappear when the equipment is hot.
C.5
Couplings
WARNING
A coupling guard must be installed at the coupling between the
turbine and driven equipment.
When the coupling guard is to be installed, refer to the coupling
guard manufacturer’s instructions to insure that it does not
contact the running shaft or coupling which could cause a spark
that could ignite hazardous gasses in the environment in which
the turbine is installed.
CAUTION
Coupling weights should not exceed the allowable limits on the
coupling drawing without approval from Dresser-Rand. A
heavier than allowed coupling could create a lower critical
speed, which could cause excessive vibration within the
operating range of the turbine.
A flexible coupling is required to connect the turbine to the driven machine.
Couplings should be selected based on power, speed, and characteristics of the
driven machine, using selection and balancing guidelines established by the
coupling manufacturer.
Correct installation of the coupling hubs is vital to proper operation of the turbine
and driven unit; great care must be exercised in assembling hubs onto shafts.
Before mounting a coupling, check the coupling bore and shaft diameter with a
micrometer to determine that the interference fit is as specified by the coupling
manufacturer. Also, inspect the key and keyways, making sure that the key is a
drive fit into the shaft keyway and a push fit into the coupling hub keyway. The
86
Speed Control System
key should also sit positively on the bottom of the shaft keyway, with clearance on
the top of the key to allow expansion within the hub keyway.
If the shaft key extends beyond the back of the coupling hub, the key should fill the
entire keyway. The exposed portion of the key must be removed so that it is flush
with the coupling back face and must be profiled flush to the circumference of the
shaft so that only the keyway in the shaft is filled, maintaining shaft balance. When
installing coupling hubs on shafts, it is important to heat them uniformly, taking
great care to avoid overheating. A recommended method is to use an oil bath with a
temperature control or an induction heater.
When fitting the coupling onto the shaft, it is helpful to have a chamfer on the sides
and top of the key, making alignment easy with the hub keyway. Also, a temporary
block should be used, to prevent the hub from sliding too far onto the shaft.
Do not use hammers to drive coupling hubs onto the shaft, as this would damage
the coupling, shaft, or bearings. As coupling hubs are frequently used for reference
in alignment, runout or eccentricity of hubs, which may be caused by damage to the
shaft, hubs, or badly fitted keys, must be avoided.
CAUTION
DO NOT drive the coupling on or off the shaft with a HAMMER.
The force of the hammer will damage the rotor locating bearing,
resulting in internal turbine damage.
NOTE
Axial clearance between the coupling hubs and shaft end faces
should be in accordance with recommendations of the coupling
manufacturer, when shafts are in their normal running
condition.
Lubricate the coupling as required, by following the coupling manufacturer’s
instructions.
C.6
Preparation for Alignment
Use the following procedure:
87
a.
Clean turbine mating support surfaces and mount turbine on the foundation.
b.
Do not connect the turbine to inlet and exhaust piping.
c.
Disconnect the coupling by removing the coupling spacer (if provided) and
pulling coupling sleeves away from the hub.
d.
Insert suitable shim packs between supporting surfaces of the turbine and/or
driven equipment and their respective mounting surfaces. It is important to
insert sufficient shims under the equipment so that shims can be removed to
lower either piece of equipment if required during hot final alignment. A
minimum of 1/16 inch (1.6 mm) is recommended.
e.
Level and square the turbine with respect to the driven equipment.
f.
Check for base distortion and improper shimming by placing dial indicators in
vertical and horizontal planes on the driven equipment, with the indicators
detecting turbine shaft movement. Each turbine foot anchor bolt should then be
loosened and tightened, while observing the dial indicator reading. Readings
should not exceed 0.003 in. (0.075 mm); if they are exceeded, the cause must
be determined. Repeat this procedure for driven equipment.
g.
Check that all anchor bolts (i.e., turbine, driven equipment and supports) are
tightened.
h.
Check coupling hub face runout using the following procedure:
1. Install dial indicator
(refer to Figure C-13, Alignment Using Dial
Indicators) to read a point nearest to the outside circumference on the face
of one hub.
2.
Rotate the shaft and hub on which the dial indicator is touching and record
the maximum and minimum indicator readings. Axial runout is the
difference between the two readings.
3. Re-position the dial indicator to read on the external outside diameter of
the same hub as in step 1 and measure coupling hub diametral runout, as
shown in Figure C-13, Alignment Using Dial Indicators.
4.
Rotate hub and record the maximum and minimum indicator readings.
Lateral runout is 1/2 of the difference between the two readings.
5.
Repeat steps 1 through 4 for the other coupling hub.
88
Speed Control System
6.
Any runout exceeding 0.0015 inch (0.038 mm) should be corrected by
reinstallation of the hub and keys or their replacement.
7. Hub runout values should be subtracted from the desired alignment
setting.
Figure C-13. Alignment Using Dial Indicators
C.7
Compensation for Thermal Movement
During initial alignment, allowances must be made for thermal expansion of the
turbine and driven equipment. The shaft centerline of each unit will rise when they
reach operating temperature. Therefore, the difference between the two anticipated
growths must be incorporated into the cold alignments so that the shafts will come
into alignment when operating temperature is attained.
CAUTION
89
Thermal movement varies significantly with inlet temperature,
load, ambient conditions and time. Final hot alignment of the
turbine to the driven equipment must be based on actual
measured shaft rise under steady state conditions (after at least
a two hour run time).
Figure C-14. Centerline Height VS Centerline Rise per Ambient
Temperatures
On steam turbines, steam temperatures and insulation of the turbine case, proximity
of packing leak-off lines to the supports and type of lagging enclosure affect the
support temperatures. The average support temperatures may vary from 130F to
160 F (approximate oil drain temperatures). Judgment will have to be exercised in
estimating the support temperature for the initial cold alignment. The curves in
figure C-14 may be useful for checking and also for telling the effect of an error in
the estimate of support temperature. Refer to the certified drawings in Appendix A
for the estimated thermal movement of the turbine shaft extension.
90
Speed Control System
Thermal growth of the driven equipment, or its temperature change, must be
obtained from the driven equipment manufacturer.
The unit with the greater thermal growth must be set lower than the other unit, by
the difference between their thermal growths. Normally, the turbine has the greater
thermal growth.
CAUTION
The initial alignment established with this estimated thermal
growth is only approximate. An actual hot alignment must be
performed prior to putting the turbine into service.
C.8
Cold Alignment Check
Cold alignment must be completed at ambient temperature (turbine and driven
machine in cold condition) and in the proper sequence, with angular misalignment
corrected first, followed by correction of parallel misalignment.
C.8.1
Angular Alignment
Use the following procedure:
a. Clamp a dial indicator to one coupling hub and place the finger (contact point)
against the finished face of the other hub, as shown in Figure C-13, Alignment
Using Dial Indicators.
b. Scribe a reference mark on the coupling hub at the point where the finger
touches the hub face.
c. Rotate both shafts simultaneously (in the direction they were designed to
operate), keeping the finger against the reference mark on the coupling hub.
Note the dial indicator reading at each one-quarter revolution.
d. Angular misalignment of the shafts must not exceed the coupling
manufacturer’s recommendations or a total indicator reading of 0.001 inch
(0.025 mm) for each radial inch of the coupling hub.
e. When the distance between coupling hubs does not permit the use of dial
indicators, angular misalignment can be established using one of the two
following methods:
91
1.
Use feeler gauges to determine the gap between coupling faces at four
locations, 90 apart. Adjust the turbine or driven equipment to obtain
equal clearance within 0.001 inch (0.025 mm) between coupling faces at
each 90 location.
2.
Use a dial indicator mounted on a flexible arm to measure run-out on the
back surface of the coupling hub, as shown in Figure C-13, Alignment
Using Dial Indicators.
C.8.2
Parallel Alignment
Use the following procedure:
a.
Mark both hub rims so that their relative positions can be maintained at all
times during the alignment check.
b.
Mount the dial indicator on one of the coupling hubs and position the indicator
finger on the rim of the opposite coupling hub, as shown in Figure C-13,
Alignment Using Dial Indicators.
c.
Scribe a reference mark on the machined diameter of the coupling hub at the
point of indicator finger contact, or align match marks on the hub rims.
d.
Rotate both shafts at the same time, while retaining the indicator finger at the
reference mark and the two match points aligned.
e.
Note indicator readings at 90 locations (90, 180, 270, 360). Remember to
zero the indicator at the starting point.
f.
Repeat steps d and e two or three times to verify accuracy of readings.
In installations where there is excessive coupling gap (when a coupling spacer
is used), it may be necessary to make a reading correction when determining
vertical parallel misalignment.
g.
Parallel misalignment must not exceed the coupling manufacturer’s
recommendations or a total indicator reading of 0.002 inch (0.051 mm).
When parallel alignment is complete, connect inlet and exhaust piping, and recheck
angular and parallel alignment thoroughly.
C.8.3
If using laser alignment tooling such as Rotalign, you can eliminate Section C.B.1
and C.B.2. Follow recommended instructions included in the laser alignment
tooling.
92
Speed Control System
C.9
Grouting
When cold alignment is satisfactory (the turbine has been leveled, and the coupling
alignment has been checked), grout the base plate or sole plate to the foundation
using the guidelines specified below. (Epoxy grout procedures may differ--follow
manufacturer’s instructions.)
Mix a test batch of ready-to-use grouting material to verify that the material
overcomes settlement and drying shrinkage. This type of material is normally used
for clearances less than one inch in thickness, and where the size and shape of the
space make placement difficult.
Coarse aggregate is normally used for clearances over one inch
(2.5 cm) in
thickness, where free passage of the grout will not be obstructed. One part of pea
gravel or pea stone may be added to two parts of the ready-to-use grouting material
to form coarse aggregate grout.
CAUTION
Do not disturb alignment by removing shims or wedges under
the base plate or sole plate.
Grouting must be done with all steam and exhaust piping disconnected from the
turbine.
When prepared grout mixes are used, follow the manufacturer’s instructions and
applicable safety precautions. Be sure that there are no air pockets in the grouting.
A suitable form should be built around the base-plate or sole plate before grout is
applied.
With either of the above-described mixes, use the minimum amount of water
required to create a flowable grout that completely fills the required space.
Excessive water causes segregation and bleeding.
Apply grout quickly and continuously to avoid the undesirable effects from
overworking.
Once the grout has acquired its initial set, all exposed edges should be cut off
vertically to coincide with the base-plate. Paint the grout with waterproof paint
after the grout has thoroughly dried, or apply plaster with Portland cement-sand
mortar.
Do not connect the piping before the grout is thoroughly dry and
alignment has been rechecked.
93
C.10
Hot Alignment Check
After installation is complete, the grout is fully set, and the tightness of all hold-
down bolts have been checked, bring the turbine and driven machine up to
operating temperature (this normally takes about two hours run time), shut down
the unit, and make a careful and final check of the alignment using the procedure
outlined in Section C.8. This should be done as soon as possible after shut down, to
avoid erroneous readings due to cooling. Final adjustments should be made so that
both shafts are parallel and their axes concentric, resulting in zero offset at
operating temperature, consistent with the coupling manufacturer’s limits.
If the alignment is not satisfactory, check the following for possible causes:
a. Pipe strains distorting or shifting machines due to thermal growth (disconnect
piping and re-check alignment).
b. Springing of the base-plate or sole-plates by heat from the turbine, from a heat
source close to the turbine, or due to soft shims or partial shims.
c. Loose hold-down bolts.
d. Shifting of the entire structure due to variable loading, a change in the
foundation due to concrete curing, or improper grouting causing non-continuous
support.
When final alignment is satisfactory, dowel the turbine and driven equipment in
place to maintain proper alignment.
C.11
Fire Protection
All possible precautions should be exercised to avoid fire hazard to operating
personnel and equipment, particularly to the oil system. To guard against the event
of a serious fire around the turbine, the following protective features should be
provided at an accessible location near the unit.
Fire Extinguishing Equipment Type Best Suited for Oil Fires
Examples: Carbon Dioxide Multi-purpose Dry Chemical
Provision for emptying oil reservoir quickly by draining oil to waste or distant
storage.
A shut-off valve in the steam inlet line and in the steam inlet line to the turbo
auxiliary oil pump (if supplied).
94
Speed Control System
C.12
Decommissioning
WARNING
Prior to commencing the decommissioning operation, ensure
that the inlet and exhaust stop valve are shut, locked out and
tagged to eliminate the possibility of inadvertent start-up during
the decommissioning operation.
The decommissioning procedure is as follows:
1.
Remove bolts from the inlet and exhaust flanges.
2.
Disconnect all turbine piping from permanently installed piping.
3.
Drain oil from the bearing housings and the governor. Dispose of the oil
in an environmentally responsible manner.
4.
Drain cooling water from the cooling system and bearing housings.
5.
Remove carbon rings, springs and stops from the gland housings.
6.
Remove coupling guard.
7.
Disconnect drive half coupling from driven half coupling. Remove
spacer coupling if one is installed.
8.
Remove hold down bolts/nuts from the base-plate.
9.
Sling the turbine and move it to a position where the inlet and exhaust
are exposed.
10.
Spray the internals with a rust preventative through all available
openings.
11.
Coat the non-painted machined surfaces with a water-soluble rust
preventative.
Seal all flanged connections with a rubber gasket, steel plate and through-bolts and
nuts.
Move the turbine to the selected storage location suitable for this type of
machinery.
95
Speed Control System
Section D
Speed Control System
D.1
General
Your Dresser-Rand turbine has been designed to produce the rated power, at its
rated speed, under the specified steam conditions. This information can be found on
the turbine nameplate, on the turbine data sheet at the beginning of this manual, or
on the certified drawings in the Appendix A.
When the turbine has been provided with a droop-type governor (WOODWARD
TG-13 governor or similar), and the load created by the driven equipment is less
than the rated power, the turbine would tend to run faster than the rated speed.
When the load is greater than the rated power, the turbine would tend to run slower
than the rated speed. Regulating the amount of steam admitted to the turbine can
counteract these tendencies. The governor and throttle valve provide this function.
The governor senses the speed, at which the turbine is running and opens or closes
the throttle valve; accordingly to maintain the turbine at its predetermined (set)
speed.
WARNING
Never operate the turbine with the governor or governor system
disabled.
D.2
Standard Governor
The basic hydraulic governor is the Woodward TG mechanical-hydraulic speed
control governor. The governor is attached to the governor mounting housing and
couples to the turbine shaft via a flexible coupling. The governor linkage connects
the governor to the throttle valve.
96
Speed Control System
WOODWARD
PG, UG OR 3161
GOVERNOR
SHAFT
OVERSPEED
COUPLING
GOVERNOR CUP
Figure D-1.
Throttle Valve Features
97
Speed Control System
BREATHER
SPEED ADJUSTING
SCREW
OIL LEVEL
INDICATOR
OUTPUT SHAFT
INPUT
SHAFT
DRAIN
Figure D-2. Woodward Oil Relay Governor Features
The instruction manual for the standard or optional governor is found in Appendix
B.
Figure D-2 shows external features of the Woodward TG Governor.
Breather--this is a vent for the oil reservoir and also serves as a plug for the oil
filler hole.
Oil Level Indicator--a sight gauge on the side of the Governor for checking the oil
level.
Speed Adjusting Screw--this screw, located on the rear of the Governor, increases
the turbine speed setpoint when turned clockwise.
Output Shaft--opens and closes the Throttle Valve via the throttle linkage.
Input Shaft--is connected to turbine shaft, sensing turbine speed.
Drain Plug--oil drain on the bottom of the Governor.
98
Speed Control System
D.3
Lubrication and Maintenance
The hydraulic governor has a self-contained, 1.75 quart oil reservoir. Oil level can
be checked by viewing the oil level indicator on the side of the Governor.
The turbine is shipped with the governor reservoir filled with oil. Oil level should
be checked before starting the turbine and should be maintained at the proper level.
Oil should be changed according to recommendations in the Woodward manual,
included with this manual. If oil should become contaminated, quality
turbomachinery oil is recommended. Refer to Section F, Lubrication System, for oil
selection guidelines.
WARNING
Operating the GOVERNOR with DIRTY OIL or with a LOW OIL
LEVEL can cause the Governor to MALFUNCTION, resulting in
damage to the governor and possible overspeed causing
damage to the turbine and personal injury.
Refer to the governor manual for governor oil selection guidelines and for any
additional maintenance information.
D.4
Speed Range and Droop Adjustment
The hydraulic governor speed range is preset at the factory, with the purchaser’s
specified turbine rated speed within that range. The user, within the allowable
range of the supplied governor, may vary the speed set point by turning the speed
adjusting screw on the rear of the Governor. Clockwise rotation of the speed
adjusting screw increases turbine speed.
Droop, the variation in speed from no load to full load, can affect speed stability
and may need adjustment if the turbine hunts or surges. Refer to the governor
manual for details on droop adjustment.
D.5
Optional Governors
Dresser-Rand turbines can be supplied with a variety of optional governors,
depending on customer needs. If your turbine is equipped with an optional
governor, refer to the appropriate vendor manual in the Appendix B.
WARNING
99
Speed Control System
NEVER attempt to START the steam TURBINE without first
reading about and UNDERSTANDING the GOVERNOR
CONTROLS.
D.6
Throttle / Governor Valve
The SST throttle/governor valve (refer to Figure D-1, Throttle Valve Features)
consists of a balanced Venturi valve sliding in a cage contained within the valve
body. The valve stem extends through the valve bonnet, which contains a set of
hardened bushings. The bushings are captured in the cover, which is provided with
a leak-off to direct any steam that escapes past the stem bushings away from the
valve. Drain holes at the bottom of the steam chest are used to connect piping,
which drains condensate from the valve. The turbine is shipped with pipe plugs in
the drain holes. Refer to Section C.3.10, C.3.11, C.3.12 and C.3.13, for leak-off and
drain piping recommendations.
The throttle/governor valve needs no regular maintenance other than replacement
of the stem bushings if leakage becomes excessive. Valve stem freedom of
movement should be checked prior to starting a turbine that has been out of service
for any significant length of time.
The steam strainer screen, surrounding the throttle valve cage, prevents
foreign matter from entering the turbine. If foreign matter does appear in the steam
chest, turbine nozzles exhaust casing, or if blading is damaged, then the steam
strainer may be defective. Foreign matter that gets past an intact steam strainer
generally has a small particle size, or it could come from within the turbine itself.
Optional construction may include separate throttle and/or over-speed trip valves or
other equipment configurations. Refer to the certified drawings in Appendix A.
When a turbine is supplied without an integral or separate Y-type strainer, the
purchaser must install an appropriate steam strainer in the inlet steam piping.
100
Speed Control System
Figure D-3. Governor Valve and Emergency Trip Valve
101
Speed Control System
Figure D-4. Woodward Governor Valve Linkage
D.7
Governor Linkage
The linkage between the governor and the throttle/governor valve needs no
lubrication or maintenance. However, it should be checked periodically for
freedom of movement and for worn parts.
D.8
Hand Valves
The steam turbine may be equipped with one or two optional hand-valves, located
on the steam chest. The purpose of the hand-valves is to allow the operator to open
or close passages to one or more of the turbine nozzles. Since the turbine is more
efficient when operating at the highest possible steam chest pressure, it is advised
to operate the turbine with the throttle/governor valve open as wide as possible,
while regulating power with the hand-valves. If operating at lower power is
necessary, this is accomplished by closing hand-valves one at a time until the
governor and throttle/governor valve are no longer capable of maintaining speed
(throttle/governor valve is wide open), and then opening one hand-valve. If the load
should increase while operating in this mode (more power is required), it will be
necessary to open additional hand-valves to maintain speed.
102
Speed Control System
WHEEL
NOZZLE
RING
HAND VALVE
(OPEN POSITION)
Figure D-5. Hand Valve Arrangement
Hand-valves must be fully open or fully closed. Operation with a partially open
hand-valve is equivalent to throttling, meaning that efficiency is lower. It will also
cause steam cutting damage to the valve seats.
When closing hand-valves, close the valve furthest from the inlet flange first. Open
hand-valves using the opposite sequence. This will prevent interrupted flow from
nozzles to the blades, which will subject blades to unnecessary stress cycles and
could reduce turbine efficiency.
103
Lubrication System
Section E
Overspeed Trip System
E.1
General
In the event of an overspeed condition, caused by a sudden loss of load or failure
of the speed control system, the supply of steam to the turbine must be quickly and
positively interrupted, preventing damage to or destruction of the turbine or driven
equipment and possible personal injury. The turbine has a fixed amount of stored
energy in the steam or gas already downstream of the trip valve at the time that the
trip valve is closed. The turbine converts that energy to rotating mechanical
energy and transmits it to the driven machine. As it does so, with no additional
energy entering the turbine, the turbine slows down and comes to a stop.
An overspeed trip valve, activated by the over-speed governor cup assembly and/or
electronic trip system, performs this function.
Per NEMA SM23, Steam Turbines For Mechanical Drive Service, normal turbine
trip speed is 15% over maximum continuous speed for NEMA A (Woodward TG)
governors and 10% over maximum continuous speed for NEMA D governors.
Maximum continuous speed is 5% over rated speed; therefore, trip speed is 16%
(NEMA D) or 21% (NEMA A) over rated speed. Occasionally the trip speed set
point may be lower or higher than normal due to a customer request and/or
technical reason. The factory trip setting speed appears on the turbine nameplate.
Standard SST turbines are supplied with an overspeed governor cup assembly
(refer to Figure E-2, Overspeed Governor Cup Assembly), located within the
mounting housing on the steam end of the turbine shaft, which contains a spring-
loaded weight, within which resides a speed-adjusting set-screw. The weight,
spring, and setscrew are selected and set at the factory so that the weight snaps out
of the bushing at a predetermined trip speed. This trip speed is recorded on the
turbine data sheet and the turbine nameplate.
When the weight snaps out of the overspeed governor cup assembly (refer to
Figures E-2, Trip System), it strikes the trip paddle, which in turn releases the trip
linkage, causing the trip valve to close. As turbine speed decreases, the weight is
pulled back into the bushing by spring action. The trip valve can then be manually
105
reset to the open position under full inlet pressure by first closing the throttle valve
and then latching the trip linkage using the reset handle.
Pressing down the manual trip lever, which protrudes from the bearing case, can
also trip the turbine.
SOLENOID
DUMP VALVE
(OPTIONAL)
LOW OIL TRIP AND
ALARM SWITCH
(OPTIONAL)
LUBE OIL
OR AIR
TO TURBINE
NOZZLES
Figure E-1. Typical Trip System Arrangement Diagram
106
Lubrication System
E.2
Warnings
CAUTION
If the KW load on a turbine-generator cannot be reduced in the
normal manner, it indicates the possibility of unacceptable
deposits on the control valve components.
STUCK CONTROL VALVES ARE A DANGER SIGNAL THAT THE
TRIP VALVE MAY ALSO BE STUCK. UNDER THESE
CONDITIONS IT IS IMPERATIVE THAT THE GENERATOR LOAD
NOT BE REMOVED UNTIL THE TRIP VALVE IS CLOSED.
If the trip valve cannot be closed by normal means, then other valves in
the steam system must be used to cut off the steam supply to the
turbine.
THE UNIT CIRCUIT BREAKER SHOULD NEVER BE OPENED
WHILE LOAD IS ON THE UNIT AND TRIP AND THROTTLE /
GOVERNOR VALVES ARE INOPERABLE. FAILURE TO
FOLLOW THESE PRECAUTIONS COULD CAUSE A SEVERE
OVERSPEED WITH EXTREME DANGER TO THE TURBINE
AND OPERATING PERSONNEL.
DANGER
NEVER BLOCK OR DISABLE THE TURBINE TRIP SYSTEM
OR ATTEMPT TO ADJUST OR REPAIR IT WHILE THE
TURBINE IS OPERATING.
107
WARNINGS
TESTING, REPAIR AND MAINTENANCE of overspeed trip
systems must be performed only by trained and
EXPERIENCED PERSONNEL.
The OVERSPEED TRIP SYSTEM must always be TESTED
and adjusted, if necessary, when STARTING the steam
turbine.
The OVERSPEED TRIP SYSTEM must be TESTED WEEKLY
on turbines that operate continuously. This prevents build-up
of foreign material in the trip linkage and alerts the operator to
deterioration that may affect trip system performance.
The TRIP SYSTEM utilizes HEAVY SPRINGS; use CAUTION
when assembling or disassembling the mechanism.
The TRIP LINKAGE MOVES RAPIDLY WITH GREAT FORCE
when the turbine trips. Use CAUTION when ADJUSTING the
TRIP SYSTEM, MAINTAINING the turbine, or when
WORKING IN THE VICINITY of the OPERATING TURBINE.
WARNINGS
Always determine and CORRECT the cause of an
OVERSPEED TRIP BEFORE RESETTING THE VALVE AND
MECHANISM.
108
Lubrication System
DO NOT SET THE OVERSPEED TRIP SYSTEM to a speed
HIGHER than the factory setting without first consulting the
factory.
E.3
Description and Function
E.3.1
Overspeed Governor Cup Assembly
The overspeed governor cup assembly (Figure E-2) consists of the following parts.
Legend:
90. Cup - Governor
94. Spring
91. Screw - Adjusting
95. Bushing - Weight
92. Set Screw
96. Ring - Retaining-Open type
93. Weight
97. Ring - Retaining-External type
Figure E-2. Emergency Governor Cup Assembly
The weight (93), which is contained via retaining rings (96 and 97) within the
emergency governor cup (90), is installed within a lateral hole in the emergency
governor cup body (90). The emergency governor cup assembly is installed on the
109
turbine shaft via key and set screw. The weight is heavy at the adjusting screw end
(upper part of Figure E-2, Emergency Governor Cup Assembly). As the shaft and
cup assembly rotates, centrifugal force tends to move the weight out of the cup,
compressing the spring (94). When turbine speed reaches the trip speed, centrifugal
force at the weight exceeds spring retention force, causing the weight to snap out,
tripping the trip linkage.
The speed at which the weight trips the linkage is a function of the weight (93),
bushing (95) shape and material, the spring rate of the weight spring (94), and the
position of the adjusting screw (91). The factory based on the desired trip speed
selects these components. In the field, trip speed is adjusted by changing the
position of adjusting screw (91). It is imperative that the setscrew (92) be tightly
turned into and locking the adjusting screw (91) from any movement. Refer to
Section E.5, Adjustment of Trip Speed, for adjustment and maintenance
instructions.
WARNING
Weight (93), spring (94), adjusting screw (91) and setscrew
(92) are a FACTORY-CONFIGURED SET, selected to obtain
the proper trip speed for a specific turbine. DO NOT MIX OR
INTERCHANGE THESE PARTS with similar parts from other
turbines or attempt to modify these components. Consult your
local Dresser-Rand manufacturer’s representative or the
factory if replacement parts are needed.
E.3.2
Trip Valve
The standard SST turbine trip valve (Figure E-3, Trip Valve, E-4 Trip System) is a
positive shut-off, force-actuated, sliding trip valve that is spring-loaded to ensure
fast action.
When the turbine is running, the trip valve is fully open, held in place by the trip
linkage (valve linkage lever (444), latch (445) and trip lever (490)), which is in
turn held by trip lever (583) action against the trip finger (584).
110
Lubrication System
Figure E-3. Trip Valve
424
Washer
425
Retainer
111
426
Seat
427
Roll Pin
428
Valve
429
Stem
430
Cover
431
Cap Screw
432
Lock Washer
433
Plug
436
Bushing
437
Link
438
Set Screw
439
Packing
440
Gland Follower
441
Valve Spindle
444
Lever
1000
Valve Body
The trip linkage operates as follows:
Refer to Figures E-1, Typical Trip System Arrangement Drawing, E-2, Emergency
Governor Cup Assembly, E-3 Trip Valve and E-4, Trip System.
During trip valve reset, as the valve (428) approaches the fully open position, reset
handle (434) rotates trip lever and latch (444 and 445) into place with the knife
edge of the latch (445) into position into the slot on the trip lever (490). The trip
pin (577) then engages the trip lever (583), holding the valve in the open position.
There is a torsion spring, operating in the valve closing direction, applies tension to
trip pin (577). There is also a linear acting spring (510) that is pulling against lever
(444). This tension is transferred to the knife-edge, holding the linkage in the open
position. With the valve in the open position, inlet steam can now flow into the
turbine.
The trip valve can then be tripped, either manually or by an overspeed condition. If
overspeed occurs, the weight (93) will snap out of the weight bushing (95), striking
the trip lever (584), causing it to release trip lever (490). The trip shaft (441) is
rotated by retraction of torsion spring (510), extending the linkage, closing the trip
valve via stem (429) and link (437). The force of the longitudinal spring (510)
ensures positive closing of the trip valve.
When the system is tripped, a spring acting on pin (577) retracts, rotating lever
(490), thus allowing lever (444) and latch (445) to be pulled by spring (510) into
the closed position via the trip linkage, isolating the turbine from the steam supply.
112
Lubrication System
DANGER
Under no circumstances should the TRIP VALVE be blocked or
held open to render the trip system inoperative. Overriding the
trip system, and allowing the turbine to exceed the rated
(nameplate) trip speed, may result in FATAL INJURY to
personnel and extensive turbine damage. In the event the trip
system malfunctions, immediately SHUT DOWN the turbine
and remedy the cause.
Refer to Sections C.3.10, C.3.11, C.3.12 and C.3.13 for recommended drain and
leak-off piping configurations.
Optional construction may include a separate overspeed trip valve. Refer to the
certified drawings in Appendix A.
E.3.3
Trip Linkage
The standard SST turbine trip linkage, set in motion by movement of the weight
(93) in the governor cup assembly (90) Fig. E-2 controls the closing of the trip
valve. The linkage also allows the valve to be opened and latched in the open
position via reset handle (434), Fig. E-4. The design clearance at the end of the
governor controlled steam valve(s) and trip or trip and throttle valve stems are required
to minimize steam leakage from the turbine.
WARNING
NEVER OPEN A CLOSED TRIP VALVE without first preparing
the turbine and driven equipment for operation.
E.4
Trip System Operation
For SST turbines supplied with the standard trip linkage, if the overspeed trip valve
is tripped shut and the turbine stopped, either from an overspeed trip condition or
manual activation of the trip lever, the trip valve must be reset manually, as
described below.
E.4.1
Manual Reset
Use the following procedure to manually reset the over-speed trip valve:
113
a. Close shut-off valve in inlet steam line as soon as possible after the turbine
trips.
b. Determine cause of the trip condition. It may be due to loss of the driven
machine load, a turbine fault, or a governor problem. Remedy the cause using
procedures detailed in Section K, Troubleshooting.
c. If the turbine is not at a complete stop, listen for weight retraction into the
weight bushing, or wait for turbine speed to drop to 75% of its rated value to
ensure resetting of the trip weight.
d. Lift reset handle (434 in Figure E-4) slightly (approximately 10-15 angular
degrees) to open trip valve (428 in Figure E-3).
e. When pressure in the valve body has bled off, continue lifting the reset handle
using minimal force, until the trip valve opens and the trip lever (490 in figure
E-4) latches on latch (445 in Figure E-4).
CAUTION
DO NOT try to FORCE or jerk open the TRIP VALVE.
g. Gradually open shut-off valve in inlet steam line to bring turbine up to normal
operating speed, allowing the governor to take control. Then open shut-off
valve to full open position and back off one-quarter turn.
114
Lubrication System
Figure E-4. Trip System
115
E.5
Adjustment of Trip Speed
E.5.1
Trip Speed Setting
It may become necessary to change the factory speed setting of the trip system due
to a change in the normal operating speed of the turbine.
Refer to the following figures:
Figure E-1, Typical Trip System Arrangement Diagram
Figure E-2, Emergency Governor Cup Assembly
Figure E-3, Trip Valve
Figure E-4, Trip System
Figure M-2, Governor, Mounting Housing, and Trip Components
Figure L-15, Governor Valve Travel Setting, Woodward TG Governor
For SST turbines supplied with the standard emergency governor cup assembly,
adjusting the position of the adjusting-screw (91) inside the governor cup (90) can
change this setting. Use the following procedure to set turbine trip speed:
a. Test the over-speed trip system per the Overspeed Trip Test Procedure specified
in Section E.6.2. Record the speed at which the weight triggers the over-speed trip
valve, stopping the turbine. Close isolating valve in inlet steam line to prevent
accidental restart.
b. For turbines with a Woodward governor with overspeed test device (type TG,
PG-PL and PG-D) remove test device cover located on top or end of the governor
(refer to Woodward instructions in Appendix B.)
c. Slide the end of the operating rod into its socket and turn it slowly. The turbine
speed will increase to tripping, and the turbine will trip out. For type UG
governors, the over-speed pin is located adjacent to the “Woodward” logo. Raise
up on this pin to over speed the turbine.
d. Turbines with Woodward governors without the over-speed device: Pry open
the governor valve, being careful not to damage the linkage. When trip speed is
reached, the turbine will trip out.
e. Turbines with electronic governors (Tri-Sen, CCC, and Woodward) -- refer to
the instruction manuals located in Appendix B for correct operating and testing
procedures.
116
Lubrication System
WARNING
FIELD CONFIGURABLE GOVERNOR
Any change to the control limits, such as (but not limited to)
speed, over-speed trip, control logic, other than “tuning” (see
governor manual) requires the prior written approval of
Dresser-Rand Company to assure that safe operating limits are
not exceeded. Failure to comply may result in damage to
property, serious injury or death to personnel.
The new trip setting should be approximately 21% above the rated speed for a
NEMA A (Woodward TG) governor and 16% above the rated speed for a NEMA
D governor.
f. Open inlet isolating valve and test turbine tripping several times after final
adjustment. If the trip speed is not repeatable within 2%, or if erratic operation
occurs, investigate and correct the problem before placing the turbine in normal
service.
If possible, carry out a daily check of the tripping mechanism during the first week
after adjustment, by over-speeding the turbine.
Optional construction may include an electronic overspeed trip system. Refer to
the certified drawings and the appropriate vendor instruction manual in Appendix
A and Appendix B for instruction on how to adjust the trip speed set point.
E.5.2
Magnetic Pickup Clearances
When supplied, maintaining the proper clearance between the magnetic pickups
(located on the turbine mounting housing) and the turbine shaft mounted signal
gear/device is crucial to the operation of the turbine electronic trip systems and
electronic governor systems. Refer to Figure E-5.
Prior to initial start up of the turbine, the clearances must be checked, adjusted and
the pickups locked into position.
117
As a part of the routine checking and testing of the turbine, the magnetic pickups
should be visually checked for damage and the clearances verified to be within
tolerance.
Figure E-5. Air Gap Between Signal Gear and Magnetic Pickup
E.6
Testing the Overspeed Trip Mechanism
E.6.1
General
Before testing the overspeed trip system, the turbine must be visually inspected for
defects. Pay particular attention to governor and overspeed trip components and
correct the defects prior to initiating any tests.
Exercising of the governor-controlled valves may be performed choking the trip or trip
and throttle valve. At the same time, the trip or trip and throttle valve is exercised.
WARNING
RAPID CLOSING OF VALVES SUPPLIED WITH THE
TURBINE IS ESSENTIAL TO PROTECT AGAINST
OVERSPEED AND POSSIBLE OTHER MECHANICAL
PROBLEMS.
DANGER
118
Lubrication System
NEVER BLOCK OR DISABLE THE TURBINE TRIP SYSTEM
OR ATTEMPT TO ADJUST OR REPAIR IT WHILE THE
TURBINE IS OPERATING.
WARNING
The overspeed trip system may malfunction during testing. Use
caution when testing and be prepared to shut the turbine down
quickly with the inlet-isolating valve.
The overspeed trip system should be tested weekly to verify its operation, to
prevent build-up of foreign material on the trip linkage, and to alert the operator to
deterioration that may affect trip system performance.
Dresser-Rand recommends incorporation of testing into the plant
operating/maintenance program and the keeping of a log to record tests.
Any malfunction of the trip system should be investigated and corrected prior to
returning the turbine to service.
E.6.2
Overspeed Trip Test Procedure
Before testing of the overspeed trip system, the turbine must be visually inspected
for defects. Pay particular attention to governor and overspeed trip components and
correct any defect prior to initiating any tests.
Use the following procedure to test the SST Turbine over-speed trip system:
a. Start up the turbine per Section I.4.2, Initial Start-Up Procedure.
b. Manually trip the turbine by pressing on the trip lever (434). The over-speed
trip valve should close, shutting off the turbine steam supply and bringing it to
a stop. This confirms operation of the linkage and valve, but not the
emergency governor cup assembly. If the valve does not close, refer to Section
K, Troubleshooting. Otherwise, proceed to Step c.
WARNING
119
The TRIP LINKAGE MOVES VERY RAPIDLY and abruptly
through its full travel when the turbine is TRIPPED. To guard
against serious hazards to operating personnel, they must
STAY CLEAR OF THE LEVER.
c. Open and latch the overspeed trip valve according to Section E.4, Trip System
Operation.
d. Increase turbine speed using the governor speed adjusting screw or knob on
the governor until trip speed is reached. The turbine should trip within 2% of
the trip speed setting on the turbine nameplate, and come to a complete stop.
e. If the turbine fails to trip at a speed 5% greater than the trip speed setting,
manually trip the turbine by pressing down on the trip lever. Refer to Section
K, Troubleshooting, to determine why the turbine fails to trip properly.
Optional construction may include an electronic overspeed trip system. Refer to
the certified drawings and the appropriate vendor instruction manual for
instructions on how to test the overspeed trip system.
Section F
Lubrication System
120
Lubrication System
F.1
General
Proper lubrication of turbine bearings and the governor is essential for long,
trouble-free service. Turbine oil must be clean, of the proper viscosity and
quantity, and maintained at the proper temperature. Oil levels should be checked
before starting the turbine and on a daily basis for turbines running continuously.
WARNING
Lack of lubricant or contaminated lubricant could result in
bearing failure. This could create sparks or hot surfaces, which
could ignite lubricant or flammable gasses.
CAUTIONS
Overloading the turbine drive shaft will cause the turbine to
slow down - possibly resulting in insufficient lubrication and/or
reduced function and damage to the driven equipment.
If the ambient temperature exceeds 110° F (43° C), cooling
water must be provided to the bearing housings to limit the
maximum temperature of the lubricating oil to 180° F (82°C). If
the ambient temperature falls below freezing a means must be
provided to maintain the lubricating oil in the bearing housings
to a minimum temperature of 130°F (54°C) and to prevent
cooling water from freezing and possibly cracking the bearing
housings.
Without immediate and constant oil feed, the heat generated by the shaft in the
turbine bearings, unless properly dissipated, can cause bearing failure. Oil ring
lubricated bearings receive immediate lubrication as the shaft begins to turn, so
long as the proper oil level is maintained in the bearing housings. With pressure
lubricated bearings, the lubrication system must be arranged such that oil fills the
supply lines and feeds the bearings when the shaft begins to turn.
121
F.2
Lubrication Requirements
Lubrication requirements are a function of the turbine type, exhaust temperature
and required operating speed range. In many cases, several lubrication options are
feasible at a given set of operating conditions with the selected method determined
by the user.
Major oil companies produce satisfactory oil for turbine use. It is advisable to consult
with your oil supplier for specific recommendations. As a minimum, the selected oil
should meet the following:
(a) Properly refined highly filtered mineral oil.
(b) Maximum metal wetting ability and ability to prevent the formation of rust on
metal parts bathed in oil. High stability toward oxidation and corrosion resistance may be
accomplished by the use of rust and oxidation inhibitors, or as a result of a particular
refining process.
(c) Free from acid or alkali.
(d) Best possible ability to separate rapidly from water.
(e) Minimum tendency to oxidize or form sludge when agitated at actual operating
temperatures when mixed with air and water.
(f) Minimum tendency to emulsify or foam when agitated with water and/or air.
(g) High viscosity index. A fluid with a high viscosity index can be expected to
undergo very little change in viscosity with temperature extremes and is
considered to have a stable viscosity.
CAUTIONS
CLEANLINESS is ESSENTIAL for long and trouble free service
from BEARINGS and GOVERNOR. Care must be taken to
ensure that no foreign material enters bearing housings, the
governor, and constant level oilers or oil reservoirs when
performing maintenance, checking oil, adding oil or making
adjustments.
122
Lubrication System
Overloading the turbine drive shaft will cause the turbine to
slow down - possibly resulting in insufficient lubrication and/or
reduced function and damage to the driven equipment.
The bearings are made to precision limits on a production basis. When bearing
clearances become excessive, new bearings must be installed. Bearing clearances
may be considered excessive when they become approximately 0.004”/0.101mm over
the normal maximum clearance. (Refer to the turbine data sheets for normal running
clearance of your turbine.) The bearings are longitudinally split to permit their removal
and replacement with the shaft in place. Procedures for replacements are given in
Section L-6.
The recommended bearing temperature limits are as follows:
Metal Temp. Oil Temp.
°F / °C
°F / °C
Maximum Normal - Pressure Lube
Operating
220/104
180/82
Alarm
230/110
185/86
Shutdown
250/121
195/90.5
Maximum Normal - Ring Oiled
Operating
220/104
180/82
Alarm
265/129
185/86
Shutdown
270/132
195/90.5
Table F-1 Bearing Temperature Limits
F.3
Oil Ring Lubrication
The basic method of lubrication for SST turbines is oil ring lubrication. Carbon
steel oil rings running on the turbine shaft pick up oil from reservoirs in the
bearing housings. As the shaft and oil rings rotate together, oil flows from oil rings
onto the shaft, ultimately flowing into the bearings, providing lubrication. The
thrust bearing, located inside the shell of the steam end main bearing, receives its
lubricating oil from this same action. The oil level within bearing housings must
be maintained at a sufficient level to allow the oil rings to run in the oil. An oil
level that is too high results in oil leakage past the shaft seals. Oil rings cease to
rotate sufficiently when the shaft runs below
950 RPM, no longer providing
adequate lubrication. Therefore, the turbine should not be run at minimum
governor speeds less than 950 RPM unless for slow roll speeds of 500 RPM for
warm-up purposes.
SST frame turbines must have simple bearing cases, the ambient temperatures must
be below 110°F (43°C) and the cooling water supply must not exceed 100°F
123

 

 

 

 

 

 

 

Content      ..      1      2      3      ..