Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 32

 

  Главная      Manuals     Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10)

 

Search            copyright infringement  

 

 

 

 

 

 

 

 

 

 

 

Content      ..     30      31      32      33     ..

 

 

 

Standard Specifications for Road, Bridge, and Municipal Construction 2020 (M 41-10) - page 32

 

 

Page 6-56 

Concrete Structures

6-02.3(17)B 

Allowable Design Stresses and Deflections

The maximum allowable stresses listed in this section are based on the use of identifiable, 
undamaged, high-quality materials. Stresses shall be appropriately reduced if lesser quality 
materials are to be used.

These maximum allowable stresses include all adjustment factors, such as the short-term 
load duration factor. The maximum allowable stresses and deflections used in the design 
of the falsework and formwork shall be as follows:

6-02.3(17)B1 Deflection

Deflection resulting from dead load and concrete pressure for exposed visible surfaces 
shall not exceed

 1/360 of the span.

Deflection resulting from dead load and concrete pressure for unexposed non-visible 
surfaces, including the bottom of the deck slab between girders shall not exceed 

1/270 

of 

the span.

In the foregoing, the span length shall be the center line to center line distance between 
supports for simple and continuous spans, and from the center line of support to the 
end of the member for cantilever spans. For plywood supported on members wider than 
1½ inches, the span length shall be taken as the clear span plus 1½ inches. Also, dead load 
shall include the weight of all successive placements of concrete, reinforcing steel, forms 
and falsework self weight. Only the self weight of falsework girders may be excluded from 
the calculation of the above deflections provided that the falsework girder deflection is 
compensated for by the installation of camber strips.

Where successive placements of concrete are to act compositely in the completed 
Structure, deflection control becomes extremely critical. Maximum deflection of 
supporting members shall not exceed

 1/500 of the span for members constructed in 

several successive placements (such as concrete box girder and concrete T-beam girder 
Structures). Falsework components shall be sized, positioned, and/or supported to 
minimize progressive increases in deflection of the Structure which would preload the 
concrete or reinforcing steel before it becomes fully composite.

Concrete Structures 

6-02

6-02.3(17)B2 Timber

Each species and grade of timber/lumber used in constructing falsework and formwork 
shall be identified in the drawings. The allowable stresses and loads shall not exceed the 
lesser of stresses and loads given in the table below or factored stresses for designated 
species and grade in Table 7.3 of the Timber Construction Manual, latest edition, by the 
American Institute of Timber Construction.

Compression perpendicular to the grain reduced to 300 psi for use when 

moisture content is 19 percent or more (areas exposed to rain, concrete curing 

water, green lumber).

450 psi

Compression parallel to the grain but not to exceed 1,500 psi.

480,000 psi 

(L/d)

2

Flexural stress for members with a nominal depth greater than 8 inches.

1,800 psi

Flexural stress psi for members with a nominal depth of 8 inches or less.

1,500 psi

The maximum horizontal shear.

140 psi

AXIAL tension.

1,200 psi

The maximum modulus of elasticity (E) for timber.

1,600,000 psi

Where:

is the unsupported length; and

is the least dimension of a square or rectangular column, or the width of a square of 

equivalent cross-sectional area for round columns.

The allowable stress for compression perpendicular to the grain, and for horizontal 
shear shall not be increased by any factors such as short duration loading. Additional 
requirements are found in other parts of 

Section 6-02.3(17)

. Criteria for the design of 

lumber and timber connections are found in 

Section 6-02.3(17)I.

Plywood for formwork shall be designed in accordance with the methods and stresses 
allowed in the APA Design/Construction Guide for Concrete Forming as published by the 
American Plywood Association, Tacoma, Washington. As concrete forming is a special 
application for plywood, wet stresses shall be used and then adjusted for forming 
conditions such as duration of load, and experience factors. Concrete pour pressures shall 
be in accordance with 

Section 6-02.3(17)J

.

6-02.3(17)B3 Steel

For identified grades of steel, design stresses shall not exceed those specified in the 
Steel Construction Manual, latest edition, by the American Institute of Steel Construction, 
except as follows:

Compression, flexural but not to exceed 0.6F

y

12,000,000 psi 

Ld/bt

The modulus of elasticity (E) shall be

29,000,000 psi

When the grade of steel cannot be positively identified as with salvaged steel and if rivets 
are present, design stresses shall not exceed the following:

Page 6-58 

Concrete Structures

Yield point f

y

30,000 psi

Tension, axial, and flexural

16,000 psi

Compression, axial except L/r shall not exceed 120

14,150 - 0.37(KL/r)

2

 psi

Shear on gross section of the web of rolled shapes

9,500 psi

Web crippling for rolled shapes

22,500 psi

Compression, flexural but not to exceed 16,000 psi and L/b not greater 

than 39

16,000 - 5.2(L/b)

2

 psi

The modulus of elasticity (E) shall be

29,000,000 psi

Where:

is the unsupported length; 

is the least dimension of rectangular columns, or the width of a square of equivalent 

cross-sectional area for round columns, or the depth of beams; 

is the flange width; 

is the thickness of the compression flange;

is the radius of gyration of the compression flange about the weak axis of the member; 

and 

F

y

 

is the specified minimum yield stress, psi, for the grade of steel used.

All dimensions are expressed in inches.

6-02.3(17)C 

Falsework and Formwork at Special Locations

In addition to the minimum requirements specified in Sections

 6-02.3(17)A

 and 

6-02.3(17)B

, falsework towers or posts supporting beams directly over Roadways or 

railroads which are open to traffic or the public shall be designed and constructed 
so that the falsework will be stable if subjected to impact by vehicles. The use of 
damaged materials, unidentifiable material, salvaged steel or steel with burned holes or 
questionable weldments shall not be used for falsework described in this section. For 
the purposes of this Specification the following public or private facilities shall also be 
considered as “Roadways”: pedestrian pathways and other Structures such as bridges, 
walls, and buildings.

The dimensions of the clear openings to be provided through the falsework for Roadways, 
railroads, or pedestrian pathways shall be as specified in the Contract.

Falsework posts or shoring tower systems which support members that cross over a 
Roadway or railroad shall be considered as adjacent to Roadways or railroads. Other 
falsework posts or shoring towers shall be considered as adjacent to Roadways or 
railroads only if the following conditions apply:
1.  Located in the row of falsework posts or shoring towers nearest to the Roadway or 

railroad; and

2.  Horizontal distance from the traffic side of the falsework to the edge of pavement is 

less than the total height of the falsework and forms; or

3.  The total height of the falsework and forms is greater than the horizontal clear 

distance between the base of the falsework and a point 10 feet from the centerline 
of track.

Concrete Structures 

6-02

The Contractor shall provide any additional features for the Work needed to ensure that 
the falsework will be stable for impact by vehicles; providing adequate safeguards, safety 
devices, protective equipment, and any other needed actions to protect property and 
the life, health, and safety of the public; and shall comply with the provisions in Sections 

1-07.23

 and 

6-02.3(17)M

The falsework design at special locations, shall incorporate 

the minimum requirements detailed in this section, even if protected by concrete median 
barrier.

The vertical load used for the design of falsework posts and towers which support the 
portion of the falsework over openings, shall be the greater of the following:
1.  150 percent of the design load calculated in accordance with 

Section 6-02.3(17)B

but not including any increased or redistributed loads caused by the post-tensioning 
forces; or

2.  100 percent of the design load plus the increased or redistributed loads caused by 

the post-tensioning forces.

Each falsework post or each shoring tower leg adjacent to Roadways or railroads shall 
consist of either steel with a minimum section modulus about each axis of 9.5 inches 
cubed or sound timbers with a minimum section modulus about each axis of 250 inches 
cubed.

Each falsework post or shoring tower leg adjacent to Roadways or railroads shall be 
mechanically connected to its supporting footing at its base, or otherwise laterally 
restrained, to withstand a force of not less than 2,000 pounds applied at the base of 
the post or tower leg in any direction except toward the Roadway or railroad track. 
Posts or tower legs shall be connected to the falsework cap and stringer by mechanical 
connections capable of resisting a load in any horizontal direction of not less than 
1,000 pounds.

For falsework spans over Roadways and railroads, all falsework stringers shall be 
mechanically connected to the falsework cap or framing. The mechanical connections 
shall be capable of resisting a load in any direction, including uplift on the stringer, of 
not less than 500 pounds. All associated connections shall be installed before traffic is 
allowed to pass beneath the span.

When timber members are used to brace falsework bents which are located adjacent to 

Roadways or railroads, all connections shall be bolted through the members using ⅝-inch 

diameter or larger bolts.

Concrete traffic barrier shall be used to protect all falsework adjacent to traveled 
Roadways. The falsework shall be located so that falsework footings, mudsills, or piles are 
at least 2 feet clear of the traffic barrier and all other falsework members shall also be at 
least 2 feet clear of the traffic barrier. Traffic barrier used to protect falsework shall not 
be fastened, guyed, or blocked to any falsework but shall be fastened to the pavement 
according to details shown in the Plans. The installation of concrete traffic barrier shall be 
completed before falsework erection is begun. The traffic barrier at the falsework shall 
not be removed until allowed by the Engineer. Falsework openings which are provided 
for the Contractor’s own use (not for public use) shall also use concrete traffic barrier 

Page 6-60 

Concrete Structures

to protect the falsework, except the minimum clear distance between the barrier and 
falsework footings, mudsills, piles, or other falsework members shall be at least 3 inches.

Falsework bents within 20 feet of the center line of a railroad track shall be braced to 
resist the required horizontal load or 2,000 pounds whichever is greater.

Pedestrian openings through falsework shall be paved or surfaced with full width 
continuous wood walks which shall be wheel chair accessible and shall be kept clear. 
Pedestrians shall be protected from falling objects and water falling from construction 
above. Overhead protection for pedestrians shall extend at least 4 feet beyond the edge 
of the bridge deck. Plans and details of the overhead protection and pathway shall be 
submitted with the falsework Working Drawings. Pedestrian openings through falsework 
shall be illuminated by temporary lighting, constructed and maintained by the Contractor. 
The temporary lighting shall be constructed in accordance with local electrical code 
requirements. The temporary lighting shall be steady burning 60-watt, 120-volt lamps 
with molded waterproof lamp holders spaced at 25-foot centers maximum. All costs 
relating to pedestrian pathway paving, wood walks, overhead protection, maintenance, 
operating costs, and temporary pedestrian lighting shall be incidental to applicable 
adjacent items of Work.

6-02.3(17)D  Falsework Support Systems: Foundations, Manufactured Shoring 

Towers, Caps, and Posts

Foundations for falsework shall be designed for conditions stated in this Section using 
methods shown in the AASHTO Standard Specifications for Highway Bridges Seventeenth 
Edition – 2002 for allowable stress design, the AASHTO LRFD Bridge Design Specifications 
for load and resistance factor design or the AASHTO Guide Design Specifications for Bridge 
Temporary Works
. Allowable stresses for materials shall not exceed stresses and conditions 
allowed by Section 6-02.3(17)B.

6-02.3(17)D1 Vacant

6-02.3(17)D2 Vacant

6-02.3(17)D3  Bents, Shoring Towers, Piling, Posts, and Caps

Plans for falsework bents or shoring tower systems, including manufactured tower 
systems shall have plan, cross-section, and elevation view scale drawings showing all 
geometry. Show in the falsework plans the proximity of falsework to utilities or any 
nearby Structures including underground Structures. The ground elevation, cross-slopes, 
relation of stringers to one another, and dimensions to posts or piling shall be shown in 
the falsework plans. Column, pile, or tower heights shall be indicated. Member sizes, wall 
thickness and diameter of steel pipe columns or piles shall be shown in the falsework 
plans. Location of wedges, minimum bearing area and type of wedge material shall be 
identified in the falsework plans. Bracing size, location, material and all connections shall 
be described in the falsework plans.

Concrete Structures 

6-02

The relationship of the falsework bents or shoring tower systems to the permanent 
Structure’s pier and footing shall be shown. Load paths shall be as direct as possible. 
Loads shall be applied through the shear centers of all members to avoid torsion and 
buckling conditions. Where loads cause twisting, biaxial bending, or axial loading with 
bending, the affected members shall be designed for combined stresses and stability.

Posts or columns shall be constructed plumb with tops and bottoms carefully cut to 
provide full end bearing. Caps shall be installed at all bents supported by posts or piling 
unless the falsework Working Drawings specifically permit otherwise. Caps shall be 
fastened to the piling or posts. The falsework shall be capable of supporting non uniform 
or localized loading without adverse effect. For example, the loading of cantilevered ends 
of stringers or caps shall not cause a condition of instability in the adjacent unloaded 
members.

Timber posts and piling shall be fastened to the caps and mudsills by through-bolted 
connections, drift pins, or other accepted connections. The minimum diameter of round 
timber posts shall be shown in the falsework plans. Timber caps and timber mudsills shall 
be checked for crushing from columns or piling under maximum load.

Steel posts and piling shall be welded or bolted to the caps, and shall be bolted or welded 
to the foundation. Steel members shall be checked for buckling, web yielding, and web 
crippling.

Wedges shall be used to permit formwork to be taken up and released uniformly. Wedges 
shall be oak or close-grained Douglas fir. Cedar wedges or shims shall not be used 
anywhere in a falsework or forming system. Wedges shall be used at the top or bottom of 
shores, but not at both top and bottom. After the final adjustment of the shore elevation 
is complete, the wedges shall be fastened securely to the sill or cap beam. Only one set 
of wedges (with one optional block) shall be used at one location. Screw jacks (or other 
allowed devices) shall be used under arches to allow incremental release of the falsework.

Sand jacks may be used to support falsework and are used for falsework lowering only. 
Sand jacks shall be constructed of steel with snug fitting steel or concrete pistons. Sand 
jacks shall be filled with dry sand and the jack protected from moisture throughout its use. 
They shall be designed and installed in such a way to prevent the unintentional migration 
or loss of sand. All sand jacks shall be tested in accordance with 

Section 6-02.3(17)G

.

When falsework is over or adjacent to Roadways or railroads, all details of the falsework 
system which contribute to the horizontal stability and resistance to impact shall be 
installed at the time each element of the falsework is erected and shall remain in place 
until the falsework is removed. For other requirements see 

Section 6-02.3(17)C

.

Transverse construction joints in the Superstructure shall be supported by falsework at 
the joint location. The falsework shall be constructed in such a manner that subsequent 
pours will not produce additional stresses in the concrete already in place.

Page 6-62 

Concrete Structures

6-02.3(17)D4  Manufactured Shoring Tower Systems and Devices

Manufactured proprietary shoring tower systems shall be identified in the falsework plans 
by make and model and safe working load capacity per leg. The safe working load for 
shoring tower systems shall be based upon a minimum 2½ to 1 factor of safety.

The safe working load capacity, anticipated deflection (or settlement), make and model 
shall be identified in the falsework plans for manufactured devices such as: single shores, 
overhang brackets, support bracket and jack assemblies, friction collars and clamps, 
hangers, saddles, and sand jacks. The safe working load for shop manufactured devices 
shall be based on a minimum ultimate strength safety factor of 2 to 1. The safe working 
load for field fabricated devices and all single shores shall be based on a minimum 
ultimate strength safety factor of 3 to 1.

The safe working load of all devices shall not be exceeded. The design loads shall be as 
defined by 

Section 6-02.3(17)A

The maximum allowable free end deflection of deck 

overhang brackets under working loads applied shall not exceed 3/16 inch measured at the 

edge of the concrete slab regardless of the fact that the deflection may be compensated 
for by pre-cambering or of setting the elevations high. The Contractor shall comply with 
all manufacturer’s Specifications; including those relating to bolt torque, placing washers 
under nuts and bolt heads, cleaning and oiling of parts, and the reuse of material. Devices 
which are deteriorated, bent, warped, or have poorly fitted connections or welds, shall not 
be installed.

Shoring tower or device capacity as shown in catalogs or brochures published by the 
manufacturer shall be considered as the maximum load which the shoring is able to safely 
support under ideal conditions. These maximum values shall be reduced for adverse 
loading conditions; such as horizontal loads, eccentricity due to unbalanced spans or 
placing sequence, and uneven foundation settlement.

Copies of catalog data and/or other technical data shall be furnished with the falsework 
plans to verify the load-carrying capacity, deflection, and manufacturers installation 
requirements of any manufactured product or device proposed for use. Upon request 
by the Engineer, the Contractor shall furnish manufacturer certified test reports and 
results showing load capacity, deflection, test installation conditions, and identify 
associated components and hardware for shoring tower systems or other devices. In 
addition to manufacturer’s requirements, the criteria shown in the following sections 
for manufactured proprietary shoring tower systems and devices shall be complied with 
when preparing falsework plans, calculations, and installing these shoring tower systems 
and devices as falsework.

Alternative criteria and/or systems shall be submitted as a Type 2 Working Drawing 
consisting of a written statement on the manufacturer’s letterhead, signed by the shoring 
or device manufacturer (not signed by a material supplier or the Contractor) addressing 
the following:
1.  Identity of the specific Contract on which the alternative criteria and/or system will 

apply;

Concrete Structures 

6-02

2.  Description of the alternative criteria and/or system;
3.  Technical data and test reports;
4.  The conditions under which the particular alternative criteria may be followed; and
5.  That a design based on the alternative criteria will not overstress or over deflect any 

shoring component or device nor reduce the required safety factor.

In any case where the falsework drawings detail a manufactured product and the 
manufacturer’s safe working load, load versus deflection curves, factor of safety, and 
installation requirements cannot be found in any catalog, the Engineer may require load 
testing in accordance with 

Section 6-02.3(17)G

 to verify the safe working load and 

deflection characteristics.

Tower leg loads shall not exceed the limiting values under any loading condition or 
sequence. Frame extensions and any reduced capacity shall be shown in the falsework 
plans. Screw jacks shall fit tight in the leg assemblies without wobble. Screw jacks shall be 
plumb and straight. Shoring towers shall be installed plumb, and load distribution beams 
shall be arranged such that vertical loads are distributed to all legs for all successive 
concrete placements. There shall be no eccentric loads on shoring tower heads unless 
the heads have been designed for such loading. Shoring towers shall remain square or 
rectangular in plan view and shall not be skewed. There shall be no interchanging of parts 
from one manufactured shoring system to another. Bent or faulty components shall not 
be used.

For manufactured shoring towers that allow ganging of frames, the number of ganged 
frames shall be limited to one frame per opposing side of a tower, and the total number 
of legs per ganged tower shall not exceed eight legs. Ganged frames shall be installed 
in accordance with the manufacturer’s published standards using the manufacturer’s 
components. Other gang arrangements shall not be used.

For manufactured steel shoring tower systems, the Contractor shall have bracing 
designed and installed for horizontal loads and falsework overturning in accordance with 

Section 6-02.3(17)A

. Minimum bracing criteria and allowable leg loads are described in 

the following paragraphs.

All shoring tower systems and bracing shall be thoroughly inspected by the Contractor 
for plumb vertical support members, secure connections, and straight bracing members 
immediately prior to, at intervals during, and immediately after every concrete placement. 
For manufactured shoring tower systems, the maximum allowable deviation from the 

vertical is ⅛ inch in 3 feet. If this tolerance is exceeded, concrete shall not be placed until 

adjustments have brought the shoring towers within the acceptable tolerance.

Page 6-64 

Concrete Structures

6-02.3(17)E 

Stringers, Beams, Joists, Bridge Deck Support, and Deck 

Overhangs

All stringers, beams, joists, and bridge deck support shall be designed for the design loads, 
deflections, and allowable stresses described in the preceding 

Section 6-02.3(17)A

B

, and 

C

 and for the following conditions.

At points of support, stringers, beams, joists, and trusses shall be restrained against 
rotation about their longitudinal axis. The effect of biaxial bending shall be investigated in 
all cases where falsework beams are not set plumb and the Structure cross-slope exceeds 
3 percent.

For box girder and T-beam bridges, the centerline of falsework beams or stringers shall be 
located within 2 feet of the bridge girder stems and preferably directly under the stems or 
webs. Stringers supporting formwork for concrete box girder and T-beam slab overhangs 
shall be stiff enough so that the differential deflection due to the placement of bridge 

deck concrete is no more than 3/16 inch between the outside edge of the bridge deck and 

the exterior web even if camber strips can compensate for the deflection.

Friction shall not be relied upon for lateral stability of beams or stringers. If the 
compression flange of a beam is not laterally restrained, the allowable bending stress 
shall be reduced to prevent flange buckling. If flange restraint is provided and since it is 
impossible to predict the direction in which a compression flange will buckle, positive 
restraint shall be provided in both directions. Flange restraint shall be designed for a 
minimum load of 2 percent of the calculated compression force in the beam flange at the 
point under consideration.

Camber strips shall be used to compensate for falsework take-up and deflection, 
vertical alignment, and the anticipated Structure dead load deflection shown in the 
camber diagram in the Contract Plans. Camber is the adjustment to the profile of a load-
supporting beam or stringer so that the completed Structure will have the lines and 
grades shown in the Plans. The dead load camber diagram shown in the Contract Plans is 
the predicted Structure dead load deflection due to self mass. This dead load camber shall 
be increased by:
1.  Amount of anticipated falsework take up,
2.  Anticipated deflection of the falsework beam or stringer under the actual load 

imposed, and

3.  Any vertical curve compensation.

Camber strips shall be fastened by nailing to the top of wood members, or by clamping 
or banding in the case of steel members. Camber strips shall have sufficient contact 
bearing area to prevent crushing under total load. Camber strips are required when the 
total camber adjustment exceeds ¼ inch for exterior falsework stringers and ½ inch for 
interior stringers.

Concrete Structures 

6-02

On concrete box girder Structures, the forms supporting the bridge deck shall rest on 
ledgers or similar supports and shall not be supported from the bottom slab except as 
provided below. The form supports shall be fastened within 18 inches of the top of the 
web walls, producing a clear span between web walls. The bridge deck forms may be 
supported or posted from the bottom slab if the following conditions are met:
1.  Permanent access, shown in the Contract Plans, is provided to the cells, and the 

centerline to centerline distance between web walls is greater than 10 feet;

2.  Falsework stringers designed for total load, stresses and deflections in accordance 

with 

Section 6-02.3(17)A

 and 

B

 are located directly below each row of posts;

3.  Posts have adequate lateral restraint; and
4.  All forms (including the bridge deck forms), posts, and bracing are completely 

removed.

The falsework and forms on concrete box girder Structures supporting a sloping web 
and deck overhang shall consist of a lateral support system which is designed to resist all 
rotational forces acting on the stem, including those caused by the placement of bridge 
deck concrete, bridge deck formwork mass, finishing machine, and other live loads. 
Stem reinforcing steel shall not be stressed by the construction of the bridge deck slab 
placement. Overhang brackets shall not be used for the support of bridge deck forms 
from sloping web concrete box girder bridges.

Deck slab forms between girders or webs shall be constructed such that there is no 
differential settlement relative to the girders. The support systems for form panels 
supporting concrete deck slabs and overhangs on girder bridges (such as steel plate 
girders and prestressed girders) shall be designed as falsework. Falsework supporting deck 
slabs and overhangs on girder bridges shall be supported directly by the girders so that 
there will be no differential settlement between the girders and the deck forms during 
placement of deck concrete.

6-02.3(17)F Bracing

All falsework bracing systems shall be designed to resist the horizontal design load in 
all directions with the falsework in either the loaded or unloaded condition. All bracing, 
connection details, specific locations of connections, and hardware used shall be shown 
in the falsework plans. Falsework diagonal bracing shall be thoroughly analyzed with 
particular attention given to the connections. The allowable stresses in the diagonal 
braces may be controlled by the joint strength or the compression stability of the 
diagonal. Timber bracing for timber falsework bents shall have connections designed in 
accordance with 

Section 6-02.3(17)I

Any damaged cross-bracing, such as split timber 

members shall be replaced. Steel strapping shall avoid making sharp angles or right-
angle bends. A means of preventing accidental loss of tension shall be provided for steel 
strapping. See Sections 

6-02.3(17)A

B

, and 

C

 for design loads and allowable stresses.

Bracing shall not be attached to concrete traffic barrier, guardrail posts, or guardrail.

Page 6-66 

Concrete Structures

To prevent falsework beam or stringer compression flange buckling, cross-bracing 
members and connections shall be designed to carry tension as well as compression. All 
components, connection details and specific locations shall be shown in the falsework 
plans. Bracing, blocking, struts, and ties required for positive lateral restraint of beam 
flanges shall be installed at right angles to the beam in plan view. If possible, bracing in 
adjacent bays shall be set in the same transverse plane. However, if because of skew 
or other considerations, it is necessary to offset the bracing in adjacent bays, the offset 
distance shall not exceed twice the depth of the beam.

All falsework and bracing shall be inspected by the Contractor for plumbness of vertical 
support members, secure connections, tight cables, and straight bracing members 
immediately prior to, during, and immediately after every concrete placement.

Bracing shall be provided to withstand all imposed loads during erection of the falsework 
and all phases of construction for falsework adjacent to any Roadway, sidewalk, or 
railroad track which is open to the public. All details of the falsework system which 
contribute to horizontal stability and resistance to impact, including the bolts in bracing, 
shall be installed at the time each element of the falsework is erected and shall remain in 
place until the falsework is removed. The falsework plans shall show provisions for any 
supplemental bracing or methods to be used to conform to this requirement during each 
phase of erection and removal. Wind loads shall be included in the design of such bracing 
or methods. Loads, connections, and materials for falsework adjacent to Roadways, shall 
also be in accordance with 

Section 6-02.3(17)C

.

6-02.3(17)F1  Cable or Tension Bracing Systems

When cables, wire rope, steel rod, or other types of tension bracing members are used 
as external bracing to resist horizontal forces, or as temporary bracing to support bents 
while falsework is being erected or removed adjacent to traffic, all elements of the 
bracing system shall be shown in the falsework plans. Bracing shall not be attached to 
concrete traffic barrier, guardrail posts, or guardrail. Any damaged bracing, such as frayed 
and kinked guying systems shall be replaced. Wire rope shall avoid making sharp angles or 
right-angle bends and a means of preventing accidental loss of tension shall be provided. 
The following information shall be submitted as a Type 2 Working Drawing:
1.  Cable diameter, rod, or tension member size, and allowable working load.
2.  Location and method of attaching the cable, rod, or tension member to the 

falsework. The connecting device shall be designed to transfer both horizontal and 
vertical forces to the cable without overstressing any falsework component.

3.  The type of cable connectors or fastening devices (such as U-bolt clips, plate clamps, 

etc.) to be used and the efficiency factor for each type. If cables are to be spliced, the 
splicing method shall be shown.

4.  Method of tightening cables, rods, or tension members after installation if tightening 

is necessary to ensure their effectiveness. Method of preventing accidental 
loosening.

Concrete Structures 

6-02

5.  Anchorage details, including the size and mass of concrete anchor blocks, the 

assumed coefficient of friction for surface anchorages, and the assumed lateral soil 
bearing capacity for buried anchorages.

6.  Method of pre-stretching or preloading cable or tension members.
7.  Determination of the potential stretch or elongation of the tension member under 

the design load and if the resulting lateral deflection will cause excessive secondary 
stresses in the falsework.

Copies of manufacturer’s catalog or brochure showing technical data pertaining to the 
type of cable to be used shall be furnished with the falsework plans. Technical data 
shall include the cable diameter, the number of strands and the number of wires per 
strand, ultimate breaking strength or recommended safe working strength, and any other 
information as may be needed to identify the cable.

In the absence of sufficient technical data to identify the cable, or if it is old and obviously 
worn, the Contractor shall perform cable breaking tests to establish the safe working load 
for each reel of cable furnished. For static guy cable the minimum factor of safety shall be 
3 to 1. The Contractor shall provide the Engineer an opportunity to witness these tests.

When cable bracing is used to prevent the overturning of heavy-duty shoring, attention 
shall be given to the connections by which forces are transferred from the shoring to the 
cables. Cable restraint shall be designed to act through the cap system to prevent the 
inadvertent application of forces which the shoring is not designed to withstand. Cables 
shall not be attached to any tower component.

Cable splices made by lapping and clipping with “Crosby” type clamps shall not be used. 
Other splicing methods may be used; however, at each location where the cable is spliced, 
cable strength shall be verified by a load test.

When cables are used as external bracing to resist overturning of a falsework system, the 
horizontal load to be carried by the cables shall be calculated as follows:
1.  When used with heavy-duty shoring systems, cables shall be designed to resist the 

difference between 1.25 times the total overturning moment and the resistance to 
overturning provided by the individual falsework towers.

2.  When used with pipe-frame shoring systems where supplemental bracing is 

required, cables shall be designed to resist the difference between 1.25 times the 
total overturning moment and the resistance to overturning provided by the shoring 
system as a whole.

3.  When used as external bracing to prevent overturning of all other types of falsework, 

including temporary support during erection and removal of falsework at traffic 
openings, cables shall be designed to resist 1.25 times the total overturning moment.

Page 6-68 

Concrete Structures

The maximum allowable cable design load shall be determined using the following 
criteria:
1.  If the cable is new, or is in uniformly good condition, and if it can be identified by 

reference to a manufacturer’s catalog or other technical publication, the allowable 
load shall be the ultimate strength of the cable as specified by the manufacturer, 
multiplied by the efficiency of the cable connector, and divided by a safety factor of 
3 (i.e., safe working load = breaking strength × connector efficiency/safety factor).

2.  If the cable is used but still in serviceable condition, or is new or nearly new but 

cannot be found in a manufacturer’s catalog, the Contractor shall perform load 
breaking tests. In this case, the cable design load shall not exceed the breaking 
strength, as determined by the load test, multiplied by the connector efficiency 
factor, and divided by a safety factor of 3.

3.  If the cable is used and still in serviceable condition, or is a new or nearly new cable 

which cannot be identified, and if load breaking tests are not performed, the cable 
design load shall not exceed the safe working load shown in the wire rope capacities 
table multiplied by the cable connector efficiency.

 

Cable connectors shall be designed in accordance with criteria shown in the 
following tables “Efficiency of Wire Rope Connections” and “Applying Wire Rope 
Clips”. Cable safe working loads are provided in table “Wire Rope Capacities”.

Efficiency of Wire Rope Connections 

(As compared to Safe Loads on Wire Rope)

Type of Connection

Connector Efficiency

Wire Rope

100%

Sockets – Zink Type

100%

Wedge Sockets

70%

Clips – Crosby Type With Thimble

80%

Knot and Clip (Contractors Knot)

50%

Plate Clamp – 3 Bolt Type With Thimble

80%

Spliced Eye and Thimble:

¼″ and smaller

100%

⅜″ to ¾″

95%

⅞″ to 1″

88%

1⅛″ to 1½″

82%

1⅝″ to 2″

75%

2⅛″ and larger

70%

Concrete Structures 

6-02

Wire Rope Capacities  

Safe Load in Pounds for New Plow Steel Hoisting Rope  

6 Strands of 19-Wires, Hemp Center (Safety Factor of 6)

Diameter inches

Weight Lbs./Ft.

Safe Load Lbs.

¼

0.10

1,050

5

/

16

0.16

1,500

0.23

2,250

7⁄16

0.31

3,070

½

0.40

4,030

9⁄16

0.51

4,840

0.63

6,330

¾

0.95

7,930

1.29

10,730

1

1.60

15,000

1⅛

2.03

18,600

2.50

23,000

1⅜

3.03

25,900

3.60

30,700

1⅝

4.23

35,700

4.90

41,300

6-02.3(17)F2  Applying Wire Rope Clips

The only correct method of attaching U-bolt wire rope clips to rope ends is to place the 
base (saddle) of the clip against the live end of the rope, while the “U” of the bolt presses 
against the dead end.

The clips are usually spaced about six rope diameters apart to give adequate holding 
power. A wire-rope thimble shall be used in the loop eye to prevent kinking when 
wire rope clips are used. The correct number of clips for safe application, and spacing 
distances, are shown below:

Number of Clips and Spacing for Safe Application

Improved Plow Steel 

Rope Diameter inches

Number of Clips

Minimum

Drop Forged

Other Material

Spacing (Inches)

2

3

3

½

3

4

3

4

4

¾

4

5

4

5

1

5

6

6

1⅛

6

6

6

7

1⅜

7

7

7

8

9

Page 6-70 

Concrete Structures

6-02.3(17)F3  Anchor Blocks

Concrete anchor blocks and connections used to resist forces from external bracing shall 
be shown in the falsework plans. Concrete anchor blocks shall be proportioned to resist 
both sliding and overturning. When designing anchor block stability, the mass of the 
anchor block shall be reduced by the vertical component of the cable or brace tension 
to obtain the net or effective mass to be used in the anchorage computations. The 
coefficient of friction assumed in the design shall not exceed the following:

Friction Coefficient

Anchor block set on sand

0.40

Anchor block set on clay

0.50

Anchor block set on gravel

0.60

Anchor block set on pavement

0.60

Multiply the friction coefficient by 0.67 if it is likely the supporting material 
is wet or will become wet during the construction period.

The method of connecting the cable or brace to the anchor block is part of the 
anchor block design. The connection shall be designed to resist both horizontal and 
vertical forces.

6-02.3(17)F4  Temporary Bracing for Bridge Girders During Erection

Steel girders shall be braced in accordance with 

Section 6-03.3(7)A

.

Prestressed concrete girders shall be braced sequentially during girder erection. The 
bracing shall be designed and detailed by the Contractor and shall be shown in the 
falsework/formwork Working Drawings. The Contractor shall furnish, install, and remove 
the bracing at no additional cost to the Contracting Agency.

At a minimum, the Contractor shall brace girders at each end and at midspan to prevent 
lateral movement or rotation. This bracing shall be placed prior to the release of each 
girder from the erection equipment. If the bridge is constructed with cast-in-place 
concrete diaphragms, the bracing may be removed once the concrete in the diaphragms 
has been placed and cured for a minimum of 24 hours.

Concrete Structures 

6-02

6-02.3(17)F5  Temporary Bracing for Bridge Girders During Diaphragm 

and Bridge Deck Concrete Placement

Prestressed concrete girders shall be braced to resist forces that would cause rotation or 
torsion in the girders caused by the placing of precast concrete deck panels and concrete 
for the bridge deck.

Bracing shall be designed and detailed by the Contractor and shall be shown in the 
falsework/formwork Working Drawings. These braces shall be furnished, installed, 
and removed by the Contractor at no additional cost to the Contracting Agency. The 
Contractor may consider the bracing effects of the diaphragms in developing the 
falsework/formwork plans. The Contractor shall account for the added load from concrete 
finishing machines and other construction loadings in the design of the bracing.

Falsework support brackets and braces shall not be welded to structural steel bridge 
members or to steel reinforcing bars.

6-02.3(17)G  Testing Falsework Devices

The Contractor shall establish the load capacity and deflection (or settlement) of all 
friction collars and clamps, brackets, hangers, saddles, sand jacks, and similar devices 
utilizing a recognized independent testing Laboratory accepted by the Engineer. 
Laboratory tests shall use the same materials and design that will be used on the 
project. Test loads shall be applied to the device in the same manner that the device will 
experience loading on the project. Any bolts or threaded rods used with the device shall 
be identified as to diameter, length, type, grade, and torque. Any wedges, blocks, or shims 
used with the device on the project shall also be tested with the device. Any adjustable 
jack system used as a part of a device shall be tested with the device and shall have its 
maximum safe working extended height identified. Devices shall not be tested in contact 
with the permanent Structure. Independent members with the same properties as the 
permanent Structure shall be used to test device connections.

At least 14 days prior to the test, the Contractor shall submit a Type 2 Working Drawing 
consisting of the test procedure and scale drawing showing how the device will be tested 
and how data will be collected. The Contractor shall provide the Engineer an opportunity 
to witness these tests.

The independent testing Laboratory shall provide a certified test report which shall 
be signed and dated. The test report shall clearly identify the device tested including 
trademarks and model numbers; identify all parts and materials used, including grade 
of steel, or lumber, member section dimensions; location, size, and the maximum tested 
extended height of any adjustable jacks; indicate condition of materials used in the 
device; indicate the size, length and location of all welds; indicate how much torque 
was used with all bolts and threaded rods. The report shall describe how the device was 
tested, report the results of the test, provide a scale drawing of the device showing the 
location(s) of where deflections or settlements were measured, and show where load was 
applied. Deflections or settlements shall be measured at load increments and the results 
shall be clearly graphed and labeled. Prior to installation of falsework devices named 

 

 

 

 

 

 

 

Content      ..     30      31      32      33     ..